1. .

At Lawas (BV-106)

1. Low pressure Gauge (0-10 Bar) will be provided at PG-2911 by opening LW-P-007.
Ensure HV-2912 is closed.
2. Once 2.0 Bar is reached at Lawas, inform KMS control room and at all BV station
persons and Mobile team leader.
3. Start Venting of Gas from Lawas till Hydrocarbon detection is reached >95%.
4. Once 95% is reached , stop venting.
5. Take all PG, PT and TT in line.
6. Start leak checking, any leakage, isolate and take corrective action accordingly.
7. Inform KMS control room to increase pressure.
8. Leak check at 5.0 Bar and 10.0 Bar. If any leakage found, take corrective action
accordingly.
9. Action for pressurization of next section of P/L i.e. Lawas to Long Lama