Professional Documents
Culture Documents
SAES-A-114
SAES-A-114 30 September 2014
Excavation and Backfill
Document Responsibility:
Responsibility: Geotechnical Standards
Standards Committee
Committee
1 Scope............................................................ . 2
3 References.................................................... . 2
4 Definitions..................................................... . 4
5 General......................................................... . 6
7 Excavation.................................................. . 21
1 Scope
This Engineering Standard defines the requirements for excavation, plac ement,
compaction, inspection, and management of earth and rock materials during
construction and/or maintenance.
2.1 Any conflicts between this Specification and other applicable Saudi Aramco
Materials System Specifications (SAMSSs), Engineering Standards (SAESs),
Standard Drawings (SASDs) or industry standards, codes, and forms shall be
resolved in writing by Saudi Aramco through the Manager, Consulting Services
Department.
2.2 Direct all requests to deviate from this Specification in writing to the Company
Representative, who shall follow internal company procedure SAEP-302
procedure SAEP-302 and
forward such requests to the Manager, Consulting Services Department of Saudi
Aramco, Dhahran.
3 References
The selection of material and equipment, and the design, construction, maintenance, and
repair of equipment and facilities covered by this Stand ard shall comply with the latest
edition of the references listed below, unless otherwise noted.
Page 2 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
Page 3 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
4 Definitions
Brackish Water: Water with Total Dissolved Solids of 10,000 ppm or more.
Clean Sand: Soil meeting the following gradation containing less than 3% weight of
organic material or clay:
Page 4 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
Contractor: The party responsible for performing excavation and backfill, including
work executed through the use of sub-contractors
General Fill Material: Inorganic soil or rock meeting the requirements in Section 6.1.1.
Hard Rock: Rock that cannot be excavated using typical excavation equipment.
See Rock Excavation, Section 7.5.
Marl: is a wide variety of calcareous soil materials found in Saudi Arabia which may
vary from clay to gravel sizes and often include cobble and boulder sized pieces.
Rock: “Rock ” may refer to anything from boulder-size individual pieces to hard, intact
bedrock. See section 7.5 for classification of rock by excavation methods.
Select Fill Material: Gravel, sand, clay, or silt, or a mixture of these constituents
meeting the requirements in Section 6.1.2.
Soft Rock: Weak and fractured rock formations that can be excavated using typical
excavation equipment. See Normal Excavation, Section 7.5.
Stable Rock: Natural solid mineral matter that can be excavated with vertical sides and
remain intact while exposed. It is usually identified by a rock name such as limestone
or sandstone.
Page 5 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
5 General
The Contractor shall institute a quality control program that will verify or ens ure
that the work performed under the Contract me ets the requirements of this
Standard and the Contract Documents. Saudi Aramco shall have access to all
facilities and records of the Contractor for the purpose of conducting
performance inspection/audits. During the audit, any inspection, test reports,
and/or engineering analyses and calculations associated with the scope of work
shall be furnished upon request.
5.1.2 All required laboratory and field acceptance tests required in Section 6.4
and all seismic refraction testing required in Section 7.5 shall be
performed by a Saudi Aramco-approved independent testing agency.
5.1.3 If testing and/or inspection is done by Saudi Aramco, this does not
relieve the Contractor of the responsibility to meet all requirements of
this Standard. Should it be later found that some work has been
completed not in compliance with this Standard, it shall remain the
Contractor's responsibility to repair or reconstruct deficient work until
specifications are met at no cost to Saudi Aramco.
5.2 Submittals
5.2.1 Compaction Test Reports, including all laboratory and field test logs and
comments. Field test reports shall include density and moisture content
test logs indicating location by coordinates and elevation as per
SAES-A-100. Reports shall be submitted as follows:
Page 6 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
5.2.2 Fill Materials and Water Test Reports. Sources and test results of all fill
materials and compaction water shall be submitted for approv al prior to
beginning fill operations. Compaction water shall be tested for Total
-
Dissolved Solids, Chloride (Cl ) and Sulfate (SO4) contents according to
SAES-Q-001.
5.2.3 Controlled Low Strength Material (CLSM) mix design and 28-day
compressive strength shall be submitted for approval prior to use o n the
site.
Page 7 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
5.3 Environmental
The Contractor shall ensure that all slopes and o ther areas subject to
erosion shall be maintained using temporary erosion and sediment
control measures during construction or until relieved by the S audi
Aramco Company Representative or until permanent measures are
completed and functioning in a satisfactory manner.
5.4.1 All temporary drainage and dewatering methods and disposal of water
are subject to approval by Saudi Aramco.
Page 8 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
5.4.5 All diverted and pumped water shall flow to specified collection areas
and shall be disposed of as directed by the Saudi Aramco Company
Representative. Excavations for foundations and other underground
installations shall not be used as temporary drainage ditches.
The Contractor shall place and maintain in good condition temporary fences,
guardrails, barricades, lights, shoring, bracing, and other protective measures
required for the safety of personnel and the premises as described in the Saudi
Aramco Construction Safety Manual.
5.5.1.2 All rock blasting shall follow the procedures in the Saudi
Aramco Blasting Manual.
Page 9 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
Commentary Note:
Page 10 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
5.5.6 Clean Up
5.5.6.1 Soil that is spilled or washed onto paved areas or streets shall
be removed daily or as directed by the Saudi Aramco
Company Representative.
Page 11 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
Fill and backfill materials shall conform to the criteria in sections 6.1.1, 6.1.2,
6.1.3 and 6.1.4 below or as recommended by a geotechnical report as per
SAES-A-113.
Stockpiles shall be placed, graded, and shaped for proper drainage. Storage or
stockpiling of material shall not be permitted on a completed subgrade.
Stockpiles of cohesive soil shall be protected from freezing.
6.1.2.2 The portion of Select Fill material passing the No. 40 sieve
shall have a maximum liquid limit of 35 and a maximum
plasticity index of 12 per ASTM D4318. Liquid limit and
plastic limit tests are not required for select fill material with
less than 15% passing the No. 200 sieve.
Commentary Notes:
Clean sand and dune sand may be used as Fill or Select Fill Material.
If sand is used as fill material, see Paragraphs 6.3.3.5 and 6.3.8.
Page 12 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
6.1.4 Other fill materials (e.g., rock fill, lean concrete, etc.) may be used with
the approval of the Chairman, Geotechnical Standards Committee.
Page 13 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
Commentary Note:
6.2.2 Proper drainage shall be maintained at all time so that the site is free of
standing water. Any soil that becomes saturated shall be removed
completely or as specified by the Company Representative.
6.2.3 Areas, in horizontal plane or side slope, shall be prepared for fill or
loading as follows:
6.2.3.1 The site shall be proof-rolled and inspected for soft spots or
loose zones. Proof roll may be defined as crossing the area
with a heavy (minimum 10-ton weight) rubber-tire or steel-
wheel roller.
6.2.3.2 All observed soft spots or loose zones shall be compacted in-
place or excavated to firm soil and replaced with fill material
compacted to the specifications in Section 6.2.3.2.
Page 14 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
6.3.2 Before placement of fill, the area to receive the fill shall be prepared in
accordance with Section 6.2. In addition:
Page 15 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
beyond the design edge of the slope and then trimming back
to achieve the final slope dimensions.
6.3.3 Fill material shall be placed in uniform loose lifts not exceeding the
following criteria, provided that the specified compaction is a chieved for
the full depth.
6.3.3.3 General Fill Material and Select Fill Material shall be placed
in lifts of 100 mm maximum in loose depth for hand-operated
compaction equipment.
6.3.3.5 If clean sand or dune sand is used for fill, the compacted sand
shall be kept wet until the next layer is placed.
Commentary Note:
Sand that has been allowed to dry out will uncompact under
vehicle or pedestrian traffic. Continuous watering is required
to maintain compaction until the next lift is in-place.
6.3.4 Compacting shall begin only after the fill or backfill has been properly
placed and the material to be compacted is at the proper moisture content.
Page 16 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
6.3.6 Fill and backfill layers shall be uniformly compacted in accordance with
the following density requirements:
6.3.6.1 All Select Fill Material and any fill beneath and/or adjacent to
foundations, grade beams, mats, buildings, lined slopes o r
drainage channels, and process areas:
Page 17 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
Page 18 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
6.3.7 Compacted surfaces of fill and backfill shall be finish graded to the cross
sections, lines, grades, and elevations as indicated on the drawings.
Commentary Note:
Page 19 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
Page 20 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
7 Excavation
Structural excavation shall include excavations for footings, grade beams, pits,
Page 21 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
basements, retaining walls, man holes, catch basins, pipeline thrust anchors, etc.
Earthen structures include permanent work items such as ponds, canals, ditches,
etc. Excavation for such work shall be made to the lines, grades, and cross
sections as shown on the drawings.
7.3.1 Side slopes of excavations shall be cut true and straight and shall be
graded to the design cross section. Unstable soil in the slopes shall be
removed and the slopes properly prepared as described in Section 6.3.2.
The bottoms of excavations shall be graded to the elevations and
configurations as shown on the drawings.
7.4 Trenching
Reinstatement of roads and pavements after trenching shall comply with shall
comply with SAES-Q-006 and GI-1021.000, Street and Road Closure:
Excavation, Reinstatement and Traffic Controls.
Seismic velocities will be the sole factor in determining the app ropriate category
for the excavation of rock. Excavation of rock will fall into the following
categories, based on the excavation type and the seismic compression (P) wave
Page 22 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
Where:
All excavated materials that are unsatisfactory for use as fill or backfill or that
are surplus to that needed for backfilling shall immediately be disposed of at a
location designated by the Saudi Aramco Company Representative.
Revision Summary
30 September 2014 Major revision to revise compaction water requirements, add CSLM as a fill material,
revise requirements for fill placement and compaction, and revise testing requirements.
Added a summary table of fill placement and compaction requirements as an Appendix.
Reorganized entire document for clarity.
Page 23 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
APPENDIX
Summary of Fill Placement and Compaction Requirements
Site preparation of areas to The density of the top 150 mm in these areas Site preparation
receive fill, pavement or loads. shall not be less than: Areas shall be free of organic material, trash
or other unsu itable material.
90% of the maximum Modified Proctor density
(ASTM D1557) Proper drainage so that the site is free of
or standing water all the time.
70% relative density (ASTM D4253 and In-situ soil proof rolled and inspected for soft
ASTM D4254) for cohesionless free draining spots or loose zones. Proof roll may be
soil defined as crossing the area with a heavy
(minimum 10-ton weight) rubber-tire or
steel-wheel roller.
All observed soft spots or loose zones shall
be compacted in-place or excavated to firm
soil and replaced with p roperly compacted
fill.
Top 6 inches (150 mm) scarified and
recompacted.
All Select Fill Material or any Compacted to at least: Fill material shall be placed in uniform loose
fill beneath and/or adjacent to lifts not exceeding the following criteria,
grade beams, mats, buildings, 90% of the maximum Modified Proctor density provided that the specified compaction is
lined slopes or drainage (ASTM D1557) achieved for the full depth.
channels, and process areas. or Select Fill Material shall be placed in lifts of
70% Relative Density (ASTM D4253 and 200 mm maximum in loose depth.
ASTM D4254) for cohesionless granular soils
that do not exhibit well-defined moisture General Fill Material shall be placed in lifts
density relationship. of 300 mm maximum in loose depth.
General Fill Material and Select Fill Material
shall be placed in lifts of 100 mm maximum
Select Fill Material beneath Compacted to at least: in loose depth for hand -operated compaction
and/or adjacent to foundations equipment.
with static loads over 320 kPa 95% of the maximum Modified Proctor density Other lift thicknesses may be approved by the
and foundations for vibrating or (ASTM D1557). appropriate Saudi Aramco Inspection
heavy machinery. or Representative based on a field test section
85% relative density (ASTM D4253 and using the intended compaction equipment.
Asphalt and concrete pavement ASTM D4254) for cohesionless granular soils (Impact rollers can compact soils in lifts
subgrades (roads & parking that do not exhibit well-defined moisture exceeding 1 m).
areas). density relationship.
Page 24 of 25
Document Responsibility: Geotechnical Standards Committee SAES-A-114
Issue Date: 30 September 2014
Next Planned Update: 30 September 2019 Excavation and Backfill
Working platforms for A 500 mm thick layer of fill material placed Working platforms for compaction on subkha
compaction on subkha deposits. directly on the subkha compacted as well as deposits shall be compacted as necessary to
possible is usually sufficient. Stripping of the achieve a stable base. Subkha working
subkha “crust” prior to fill placement is not platforms must be indicated as such and
recommended. A geotextile layer between the accounted for in the design.
subkha and the working platform provides a
capillary break and improves both short-term Compaction to the required densities indicated
(construction) and long-term performance of in Section 6.3 are virtually impossible to
the engineered fill. achieve in the first layer p laced directly on
subkha and similar very weak soils. A working
Compaction testing of working platforms is not platform to provide a stable base is often
required. required.
Pavement Reconstruction after Reinstatement of roads and pavements after Controlled Low Strength Material (CLSM), a
Trenching trenching shall comply with shall comply with flowable, self-compacting fill, is recommended
SAES-Q-006 and GI-1021.000. for backfill of trenches crossing roads and
pavements.
Page 25 of 25