CHART - STRUCTURAL WORKS SG.

BULOH SERDANG - PUTRAJAYA (SSP) MSPR202C SUPERSTRUCTURE DATE: 20 SEPTEMBER 2020


GROUND LEVEL - LEVEL 1

TNB AREA

ZONE A ZONE B

ZONE D ZONE C

Unit Total Quantity Cum. Last Week Qty. This Week Cum. This Week Balance of Work Legend
Ground Beam m 1060 491 59 550 510
Slab m2 2151 929 92 1021 1130 In-progress
Column Nos 55 0 17 17 38
Wall 1 m 145 80 30 110 35 Complete