TNB AREA
ZONE A ZONE B
ZONE D ZONE C
Unit Total Quantity Cum. Last Week Qty. This Week Cum. This Week Balance of Work Legend
Ground Beam m 1060 491 59 550 510
Slab m2 2151 929 92 1021 1130 In-progress
Column Nos 55 0 17 17 38
Wall 1 m 145 80 30 110 35 Complete