Professional Documents
Culture Documents
Proposal 117&118 Lake Circus (South Face)
Proposal 117&118 Lake Circus (South Face)
LAND OWNER
Page 1 of 12
18th Dec, 2018
To,
Md. Mofejul, Gong
Plot: Baw bazaar khilbarir tak , Shahjadpur.
Dhaka.
We the GREEN BAY DEVELOPMENTS LTD. would like to express our gratitude and thank
you for giving us opportunity to introduce ourselves and to discuss on the development of
your precious land. With reference to our discussion, we are placing this proposal to you for
your consideration.
Subsequent to our discussions, we have thoroughly analyzed the merit and demerits of the
proposed construction work and have chalked out a program for your kind consideration.
In this proposal you will find that GBDL always specific regarding each and every issues with
the land owner, specially you will see in the specifications where we have mentioned brand
as far as possible to make your understanding clear.
After going through this proposal you may have lot of queries, moreover you may need
clarification on different areas of the proposal. In this regard GBDL wants to make sure that
all your queries are answered properly up to your satisfaction for your final decision-making.
Please allow us any time convenient to you for detailed discussion.
Finally, GBDL is ready to undertake the total responsibility with heart and soul to turn your
idea of developing your land into reality.
Thank you once again and looking forward for your early response.
Sincerely yours,
Page 2 of 12
CONTENTS
Title
2.0 Annexure
Annexure
Page 3 of 12
EXECUTIVE SUMMARY
Total measured land12 Katha (approx.).
There will be 1(one) building with common facilities.
It takes about 5/6 (five/six) months time for project planning. The job in planning stage
includes; preliminary design, finalization of design by the Management considering land
owner’s views & observations, sub-soil test, approval from different regulatory bodies e.g.
DESA/DESCO,WASA, Titas Gas, CITY CORPOATION & RAJUK, etc.
Legal procedures are followed strictly in adherence to the pertinent provisions of the law
of the land.
Complex will be equipped with all modern amenities, standard specifications & facilities.
ANNEXURE
FAR: Non Restricted i.e. 60% land use maximum in each floor
Build-up Area= 60% Land 12 k. x 720sft. X 012 floor = 8640 sft (Approx.)
Type-A
Type-B
h
Nort
Size-1,225 sft(Aprx.)
Size-1,225 sft(Aprx.)
18’
Lift & Stair
Note: This proposal prepared as per present RAJUK plan approval rules.
Page 4 of 12
PROJECT OUTLINE
The Developer proposes to design and construct a 09 (Nine) storied (As per
RAJUK rules) Residential complex consisting of parking and Reception Floor at
ground level plus 09 (nine) Apartment floors above.
There will theoretically be a total of 4200 sft. in each floor with common space.
Total project duration will be 48 (Forty eight) months with grace period
from the date of handing over the physical vacant possession of the land
by the Land Owner or approval of plan from RAJUK which occurs later
on. Plan preparation and approval may take 5-6 months. Some
modifications requested by the Landowner and or the other commercial
space owners may lead to minor extension of the completion time.
Page 5 of 12
CONSIDERATION OF THE LAND OWNER
Following benefits will be provided to land owner in return to there more or less 12 katha
lands (Aprx.):
Note: 1. The land Owner will get the sale value of the existing structure.
2. Utility cost of land owners spaces shall be borne by the developer.
*Total built up area & Sizes of floors subject to change as per RAJUK rules and approval.
Entitlement in Car-Parking:
- Total Number of car parking will be 014 Nos.
- The Landowner will get 50.00% i.e. 04 Nos. Car-parking space from Ground Floor.
(Per floor will get 01 car parking spaces.)
Financial Consideration:
* This offer is valid for next three months from submission date.
Page 6 of 12
LEGAL PROCEDURE
Ownership of the land will remain with the Land Owners up to the completion of the
project.
Legal Tools:
The Developer will hold necessary sub-soil test and site survey of the project land,
prepare plan & working design and obtain approval thereof from all regulatory bodies
& RAJUK at the cost & expenses of the Developer.
The land owner will sign plan. Design, drawing, formal application and related papers/
documents to the appropriate Govt. authorities for taking approvals and installation of
utility lines for the project. All related cost and expenses for obtaining such approval and
sanctions from the competent authorities will be paid by the Developer.
Status of the project land:
The Land Owner shall make payment of all rents, taxes and utility bills till the date of
handing over of the project land of the Developer by the land owners and the Developer
shall make payment of such bills during construction period.
Page 7 of 12
ANNEXURE "A'
Building Entrance
Decorative Prestigious Main Gate (MS) with Lampposts as per the elevation &
perspective of the building.
Security provision through guardroom to control incoming and out going persons,
vehicles and goods.
Comfortable & functional internal driveway made of concrete with Best Quality
designed pavement blocks/floor tiles (Mirpur Ceramic/Unique approved quality).
Designed boundary walls all around of at least 8 height with necessary security
protections to prevent unauthorized entrance.
Project Name with address and logo of the developer in brass on an attractive
polished Marble /Granite base as per design of the Architect.
Reception Lobby
Reception desk with Marble Top.
Mirror Polished 16”x16” tiles floor in the reception area.
Lift
02/03 International standard 6(eight) passengers Lift (LG Otis / Mitsubishi
/Hyundai or Equivalent)
Fast & Reliable service in all floors.
Intercom line & Emergency Alarm provision
Adequate lighting & Fan provision.
Will maximize advantages especially in relation to the daylight and outside view.
Cable TV Provision:
Provision for telephone connection & satellite channel connection from the cable
TV operator.
Roof Top:
Protective parapet wall.
Generator
International Standard Generator (SDMO, France / FG. Wilson, Uk / Parkins or
Equivalent)
KVA capacity to cover Lift, Pumps, Common Lights and shopping area.
Full back up
Water Pump
04(four) Unit
European Origin pedrollo or Saer or Equivalent.
Bath Rooms
Good quality RAK/equivalent Sanitary Wares in all Bathrooms except servants toilet.
Matching RAK/equivalent floor tiles in all Bathrooms
Mirrors in all Bathrooms with overhead Lamps
Good Quality foreign Chrome plated Fittings.
Cabinet Basin with Marble top.
Provision for exhaust fan in all bath rooms.
Concealed hot water lines in Master bathroom.
Page 9 of 12
Electrical
Walls
Outside walls are plastered 0'-5" standard brickwork. (1 st class) as per Architect
design
All interior walls are also plastered 5" brickwork. (1st class)
Walls below ground are water proof RCC
Door
10mm Glass doors, handle with security Lock.
All Bathroom doors are Waterproof laminated door.
Windows
Total building will be glass covered as per Architectural Design of the Building with
OPTIONAL FEATURES
Various interior designing and additional fittings and fixtures as per choice of Land
Owners/allottee may be arranged at cost basis upon approval of GBDL.
Utility Lines
Electricity supply will be of individual Meter and connection for the project.
Water Supply and Sewerage will have common meter connection for the project.
GAS supply will be of individual Double Burnet Connection.
Connection cost will be borne by the Developer for the Landowner’s Spaces.
Note: Items specified in this Annexure will be supplied as per market availability. In case of
non-availability or shortage of supply of any specified item(s), equivalent item (in terms of
price and quality) will be used as per Green Bay Developments Ltd .’s selection in
consultation with the Land-Owners.
Page 10 of 12
STRUCTURAL & GENERAL ENGINEERING FEATURES
The building will be planned & designed by reputed professional architects and
structural design engineers.
Structural design parameters will be based on American Concrete Institute (ACI)
and American Standard of Testing Material (ASTM) codes, as well as Bangladesh
National Building Code (BNBC).
Developer will arrange necessary soil tests of the building site and analysis of the
relevant soil samples by the BUET laboratories. Design of foundation and super
structures of the building will be based on the soil test report.
The building will comprise of foundation, columns and beams made of heavily
Reinforced Cement Concrete (RCC) with good quality crushed stones and floor slabs
will be brick chips & 100% sylhet sand of ratio 1:2:4.
Systematic structural combination of steel reinforced concrete frames and shear
wall core will be employed using modern design concept/methodology (Computer
Software). All parts of the structure will be interconnected by Ties & Beams with
shear core wall.
Water proofing material shall be used in correct proportion in the foundation for
better protection of structure/concrete from dampness.
Structural design will cater for earthquakes up to 8 Richter scale and wind intensity
up to 210 kilometer per hour as per Bangladesh National Building Code (BNBC).
Comprehensive & systematic checking and testing of all concrete & steel
reinforcements at every stage and other completed work samples will be conducted
by professional Design & Supervising engineers of the Developer and relevant
samples will be analyzed from BUET laboratory to ensure highest quality of
workmanship.
Landowner or his representatives will have the right to get involved in these
checks/tests.
All materials including Steel, Cement, Bricks, Stone Chips, Sylhet Sand & other
finishing materials etc. will be of highest standard and screened for quality.
All underground sanitary & sewerage pipes will be good quality UPVC pipes of
designed thicknesses & sizes.
All underground water pipes will be good quality GI/ UPVC pipes (Adamjee-
National/ Equivalent) of designed thicknesses & sizes.
All construction site equipments/tools e.g. vibro-hammers, vibrators, vibromax,
mechanical rollers, steel cutting & bending equipments, welding equipments,
concrete mixers, concrete vibrators, water pumps, material handling equipment,
leveling instruments, hand tools etc will be arranged by the developer.
Ground Floor Level (Plinth) will be higher than the highest previous flood level of
1988/1998/2004.
The building site will be given appropriate Termite Protection & Pest Control
Treatment by the relevant experts / professionals.
Page 11 of 12
MAJOR STRUCTURAL MATERIALS
Steel
60 Grade Deformed Bar
Manufactured by
i. Bangladesh Steel & Re-Rolling Mills Ltd. (BSRM)
ii. KSRM.
iii. SS Steel Ltd.
iv. Other Equivalent High Standard Steel Mills Ltd.
Cement
Cemex Cement
Lafarge Cement
King Brand Cement
Fresh Cement
Holcim cement
Other Equivalent High Standard Manufacturer
Aggregates
Stone Chips for all columns, beams, foundations & other will be Brick chips.
High strength Brick Chips.
Bricks
First Class Bricks of approved quality
Sand
2.5 FM Coarse Sand
1.5 FM Medium
After Sales service
Preparation of Bye-Laws and formation of Apartment Owners Association
6(Six) months free repair & maintenance of technical problems.
Supervision of Complex and repair/ rectification of technical defect by an Engineer
for 2 (two) months.