You are on page 1of 5

Condition Based Maintenance

Byron A. Ellis

Consultant and Executive Director of The Jethro Project, (TJP), email: ellis@jethroproject.com.

Abstract

A well-implemented condition based maintenance (CBM) regime requires management support, data
analysis to determine cost-effective monitoring points, and a knowledgeable and disciplined maintenance
organization. The main objective of CBM is to ensure that assets fulfill their mission in the most cost-
effectively manner.

Keywords: Condition based maintenance, reliability centered maintained, preventive maintenance, failure
mode, computerized maintenance management system.

Introduction opposed to costly time-based (fixed


intervals) repairs or emergency
Condition based maintenance (CBM) is a breakdowns. In some instances, however,
management philosophy that posits repair CBM might not be cost-effective or data
or replacement decisions on the current or might not exist to justify its introduction.
future condition of assets (Raheja, Llinas,
Nagi, & Romanowski, 2006); it Raheja, Llinas, & Nagi (2000), on the
recognizes that change in condition other hand, argued that current
and/or performance of an asset is the approaches to CBM system design are
main reason for executing maintenance extremely specific and that a generic
(Horner, El-Haram, & Munns, 1997). architecture for CBM is missing. Thus,
Thus, Horner et al. noted that the optimal they claimed that each domain area has
time to perform maintenance is its own interpretation of CBM that may
determined from actual monitoring of the not be compatible with the requirements
asset, its subcomponent, or part. They of other applications. However, CBM is
also noted that condition assessment not applicable to all maintenance assets
varies from simple visual inspections to and should only be applied to instances
elaborate automated inspections using a where condition-monitoring techniques
variety of condition monitoring tools and are available and cost-effective (Horner et
techniques. al., 1997).

The objective of CBM is to minimize the CBM requires robust analysis of


total cost of inspection and repairs by reliability and financial maintenance data
collecting and interpreting intermittent or (Crespo Márquez & Sánchez Herguedas,
a continuous data related to the operating 2004). Furthermore, it requires an
condition of critical components of an unambiguous understanding of failure
asset (Knapp and Wang, 1992). Knapp, modes and rates, asset criticality, and
Javadpour, and Wang (2000) argued that potential payoffs associated with different
monitoring, where cost-effective, could maintenance strategies. Moubray (2001)
provide adequate notice on pending cited studies done on civil aircraft
failures, which would allow for planned describing patterns of failure that
repairs based on asset degradation, as contradicted the belief of a relationship

www.jethroproject.com, TJP, November 10, 2008, pp. 1-5 Condition Based Maintenance
Copyright  2008 TJP. All rights reserved. 1 Byron A. Ellis
between reliability and operating age. He Maintenance Strategies
noted that this belief led to the idea that
frequent overhaul of an asset would Coetzee (1999) observed that
increase its reliability. maintenance management often
implement some highly publicized
According to Moubray (2001), unless strategy towards increasing the efficiency
there is a dominant age-related failure of the maintenance function, such as
mode, time-based overhauls do not reliability centered maintenance (RCM),
improve the reliability of complex items. total productive maintenance (TPM),
He further noted that it is highly possible condition based maintenance (CBM),
that time-based overhauls would computerized maintenance management
introduce infant mortality failures in systems (CMMS), auditing systems and
otherwise stable systems. so on. However, most managers do not
know what the right regime for
The Benefit of Monitoring Asset optimizing maintenance is. As a result,
Performance most efforts do not materialize.

Wood (1999), as well as Moubray (2001), Intervention strategies are not only
argued that time-based preventive technical in nature; they are also a matter
maintenance (PM) often failed to of art (Heckscher, Eisenstat, & Rice,
maximize the service life of each 1994). According to Hecksher et al. most
component; in many instances the best practice strategies fail within a year
components were being replaced with or so. They labeled this phenomenon as
many hours of useful life remaining. PM successful failure, which results from
tasks, based on hard time intervals, waste limited know-how within the
a lot of resources (Tsang, 1995); that is, organization: few internal members
often the plant or building is over- understanding what they are moving
maintained (Mann, Saxena, & Knapp, towards when they start an
1995). implementation process (Heckscher, et
al.).
Bloch and Geitner (1983), noted that
certain signs, conditions, or indications As a result, Coetzee (1999) argued for a
precede 99% of all machine failures. holistic approach within the maintenance
Therefore, by monitoring an asset, action function to implement CBM. A holistic
can be taken prior to it having a serious approach would include the evaluation of
effect on the performance of the the maintenance assets, including
organization. Thus, condition-based building structures. Shonet (2003) argued
monitoring offers an alternative to the that effective implementation of CBM
PM assumption of age-related failure requires the development of performance
mode. Moreover, with condition-based indicators for building components and
monitoring, managers can focus on just- systems. He noted that the evaluation of
in-time (JIT) replacement. According to building components should assess (1)
Wood, JIT replacement maximizes the the physical performance of building
life of each component and is facilitated systems, (2) frequency of failures of
by building automation systems (BAS) or building systems, and (3) actual
intelligent buildings. preventive maintenance (PM) carried out
on the systems.

www.jethroproject.com, TJP, November 10, 2008, pp. 1-5 Condition Based Maintenance
Copyright  2008 TJP. All rights reserved. 2 Byron A. Ellis
contents in oil, and so on. Sensors
Likewise, a holistic approach should also capable of detecting pre-failure signals
include performance measurement can provide alerts and alarms notifying
systems as a tool for delivering strategic the asset operator of the potential of an
objectives, such as the implementation of impending failure. For other assets,
a balanced scorecard process(Letza, failure (hard faults) may occur
1996); the evaluation of breakdown (BD) instantaneously and cannot be predicted;
maintenance, where the run to failure generally these failures are exogenously
philosophy prevails; the evaluation of generated.
planned schedule maintenance, where
planning and scheduling methodologies CBM is a non-intrusive technique and the
are rigorously applied; and the evaluation actual preventive action (repair) is taken
of CBM, where critical and costly assets at the incipient failure level (Tsang,
are monitored for degradation (Amari and 1995). Tsang noted that hidden failures
McLaughlin, 2004). Degradation is a are often present in standby units,
process where system parameters protective devices, or infrequently used
gradually worsen. assets. Hidden failures are not evident
until the time when the proper function of
The application of CBM requires the use the item is needed.
of certain analytical tools, such as failure
mode, effect, and criticality analysis Thus, a CBM regime on standby units,
(FMECA) and RCM to determine the such as protective devices, or
likelihood of failure and how failure infrequently used assets would not be
would occur; as well as a reliable effective, since upon startup hidden
information tool (i.e., CMMS) to capture failures could occur. However, to
and track repairs and associated costs of counteract, hidden failures Tsang (1995)
the assets under consideration. recommended faultfinding (FF) tasks. FF
tasks are performed at scheduled intervals
FMECA is a systematic process for to check the state of assets or items with
identifying all possible ways in which dormant functions. A typical example is
failures of an element can occur and an emergency generator that is generally
RCM is an approach for identifying the idle until needed.
most applicable and cost effective
maintenance task for asset elements (El- According to Sherwin and Al-Najjar
Haram & Horner, 2002). Thus, El-Haram (1999) if downtime is very expensive,
and Horner noted that the RCM process inspection and condition monitoring are
evaluates each failure to determine its not the best overall maintenance policies
consequences, if any, as well as each unless the combined age to failure
consequence to determine applicable and distribution of the various failure modes
cost effective maintenance tasks. of an asset, or component, has a large
variance such that the standard deviation
Failure is when an asset, component or is greater than or (nearly) equal to the
element cannot fulfill its mission. For mean.
many assets, however, certain symptoms
(soft faults) often occur prior to total Determining CBM Failure Point
failure, such as excessive vibration,
abnormal heat (Knapp et al., 2000), solid

www.jethroproject.com, TJP, November 10, 2008, pp. 1-5 Condition Based Maintenance
Copyright  2008 TJP. All rights reserved. 3 Byron A. Ellis
Determining when a failure mode has The introduction of CBM without
been initiated and predicting the time managerial support at all levels,
remaining for complete failure requires appropriate data and analysis, a
reliable data and effective algorithms. disciplined and knowledgeable
Moreover, making decisions on the maintenance staff is unlikely to achieve
appropriate maintenance response to desired results.
CBM alerts or alarms requires a
disciplined maintenance organization.

Many maintenance organizations


equipped with CBM do not effectively Copyright of TJP is the property of
respond to alerts and alarms. However, The Jethro Project and its contents
some CBM systems are integrated into may not be copied or emailed to
the CMMS, so that a work order is multiple sites or posted to a listserver
automatically generated when signals without the copyright holder's express
from a monitored point trigger alerts or written permission. User, however,
alarms. This is particularly suited for may print, download, or email articles
continuous process plants where failure for individuals use.
and downtime can be extremely costly.

False Alarms

A key requirement for successful


implementation of CBM is a low
incidence of false alarms and quick and
reliable detection of faults (Buswell &
Wright, 2004). Buswell and Wright noted
that an International Energy Agency
(IEA) project indicated that abrupt faults
could be easily detected; degradation
faults, on the other hand, had to be quite
large before detection was unambiguous.
The study also noted that it is possible to
balance robustness and sensitivity.
Increasing sensitivity results in early
warning of faults, but may increase the
incident of false alarms (Knapp,
Javadpour, & Wang, 2000). However,
condition-based monitoring industry
leaders have applied quality control type
techniques in the detection of machine
faults; thus, providing increased
protection from false alarms, as well as
from missed faults (Mann et al., 1995).

Conclusion

www.jethroproject.com, TJP, November 10, 2008, pp. 1-5 Condition Based Maintenance
Copyright  2008 TJP. All rights reserved. 4 Byron A. Ellis
References Knapp, G.M., Javadpour, R., and Wang,
H.P. (2000), An ARTMAP neural
Amari, S.V & McLaughlin, L. (2004). network-based machine condition
Optimal design of condition based monitoring system. Journal of
maintenance Model. IEEE. Quality in Maintenance
Brian W. (1999). Intelligent building Engineering, Vol. 6 No. 2, 2000,
care, Facilities, Volume 17 · pp. 86-105.
Number 5/6 , pp. 189–194. Stephen R. Letza (1996). The design and
Buswell, R. A., & Wright, J. A. (2004). implementation of the balanced
Uncertainty in model-based business scorecard. Business
conditioning monitoring. Building Process Re-engineering &
Services Engineering Res. Management Journal Vol. 2 No.
Technol, 25 (1), 65-75. 3, 54-76.
Coetzee, J.L. (1999). A holistic approach Moubray, J (2001). Reliability-Centered
to the maintenance ``problem.'' Maintenance. NY: NY Industrial
Journal of Quality in Press Inc.
Maintenance Engineering, Vol. 5 Raheja, D., Llinas, J., Nagi, R. &
No. 3, pp. 276-280. Romanowski, C. (2000). A
El-Haram, M.A., and Horner, R.M.W. holistic view of condition based
(2002). Journal of Quality in maintenance. Working Paper,
Maintenance Engineering, Vol. December 2000 (Center for
85 No.2, pp. 135-143. Multisource Information Fusion
Heckscher, C., Eisenstat, R. A., & Rice, (CMIF), SUNY.
T. J. (1994). Transformational Raheja, D., Llinas, J., Nagi, R. &
processes. In C. Heckscher and A. Romanowski, C. (2006). Data
Donnellon (Eds.), The post- fusion/data mining based on
bureaucratic organization: New architecture for condition based
perspectives on organizational maintenance. International
change (pp. 129-177). Thousand Journal of Production Research,
Oaks, CA: Sage Publications. Shonet, I.M. (2003). Building evaluation
Horner, R.M.W., El-Haram, M.A., and methodology for setting
A.K. Munns (1997). Building maintenance priorities in hospital
maintenance strategy: a new buildings. Construction
management approach, Journal of Management and Economics
Quality in Maintenance Tsang, A. C. (1995). Condition based
Engineering, Vol. 3 No. 4, pp. maintenance: Tools and decision
273-280. making. Journal of Quality in
Knapp, G.M. and Wang, H.P. (1992), Maintenance Engineering, 1(3),
``Machine fault classification: a 1-17.
neural network approach,''
International Journal of
Production Research, Vol. 30 No.
4, pp. 811-23.

www.jethroproject.com, TJP, November 10, 2008, pp. 1-5 Condition Based Maintenance
Copyright  2008 TJP. All rights reserved. 5 Byron A. Ellis

You might also like