Professional Documents
Culture Documents
SERIES NG 300
FENCING
Contents
March 2003 1
Volume 2 Series NG 300
Notes for Guidance on the Specification for Road Fencing
Works
FENCING
NG 301 Not Used repetitive use when the need arises. The high
standard should encourage the immediate
provision of permanent fencing, although this
NG 302 Requirements for is not always practical because of the
Temporary and Permanent Fences possibility of damage to the permanent
fencing during the progress of the Works.
1 Clause 302 sets out the action to be
taken by the Contractor, drawing 3 The height of the fence in the range selected
particular attention to the requirements may have to be increased or, it may be
for temporary fencing in all situations considered excessive for the purpose it has to
where he does not provide permanent perform. Any further requirements or
fencing immediately. relaxation should be described on the
Drawings.
2 There may be specific temporary
fencing requirements for a particular
location during the construction period, NG 304 Timber Quality
eg. to isolate a semi-permanent
diversion of a public right of way or a 1 Stress grading rules are based on rectangular
Statutory Undertaker’s works or sections but it is permissible to process
Apparatus. Such fencing should be trapezoidal sections for fencing, without re-
shown on the Drawings. The grading, from rectangular sections, as long as
Contractor is obliged to provide all the processing does not remove more than
temporary fences required for safety 10% of the cross-sectional area. Alternatively
and security as a result of his particular the trapezoidal section may be machine
method of working, and maintain such graded using machine settings applicable to
temporary fencing during the period of the thickness and largest width dimension of
the Works. the trapezoid.
March 2003 2
Volume 2 Series NG 300
Notes for Guidance on the Specification for Road Fencing
Works
2 The types of fence in the RCD (b) two lower wires, barbed or plain as
should be sufficient to meet all described, one below the bottom rail
environmental and amenity factors and and the other between that rail and the
the chosen design which should be next above; alternatively, a fifth timber
decided after consultation with the rail may be provided as shown in the
Overseeing Organisation should fit RCD
visually into each distinctive stretch of
country, each situation having its (ii) Dropper Pattern Fence
appropriate type of fence. Wherever a
change of fence type is made, the (a) one barbed wire fixed, with tie
transition point should be carefully wires every 450 mm, to the top
selected to coincide with a convenient wire of the 1.35 m fence;
feature which will give a logical reason
for the change in fence design. (b) one barbed wire fixed as in (a) to
the third from top wire of the 1.35
3 Where a motorway is bordered by m fence;
farm land, (the Overseeing
Organisation in Malta) undertakes in (c) provision of a 1.80 m fence when
the fencing covenant to provide and there is a possibility of there being
maintain a sufficient fence or wall, to deer on adjacent land but;
provide cattle and sheep(including
lambs) and, at the request of the (d) provision of a 2.10 m fence when
vendor, horses and pigs, from straying deer are on adjacent land in large
on the motorway. Although motorway numbers.
fences are sited on Road land it is not
always possible to carry out the However, the views of the landowner should
erection within the boundary. be sought before deciding on the position of
Consideration should be given to barbed wire because practice varies over the
obtaining an easement so that the country.
erector can encroach on the adjoining
land both for initial erection and any If horses are being contained it may not be
subsequent maintenance, including the satisfactory to fix barbed wire at a low level.
maintenance of mesh provided for the
security of animals such as badgers. 5 The requirement for spacing straining posts
at intervals not exceeding 300 m and
4 Where additional stock proofing is intermediate posts at 7.5 m centers for
required; the following options should dropper pattern fences should be waived in the
be considered; following circumstances:
line is straight but varies in 6 Wire dropper fencing will often have been
level, straining posts should be chosen because of its capacity to blend into
provided at the summits and the landscape, and so plastic coated wire and
valleys of the slopes and the posts have been chosen as the standard. The
requirement for these additional fittings should also be unobtrusive; preferred
straining posts should be stated fittings are included in the RCD.
in Appendix 3/1 or on the
Drawings. In choosing the fittings required the following
points should be noted and where appropriate
When the ground is uneven under the included in Appendix 3/1:
line of the fence it is suggested that the
ground be trimmed, particularly if the (i) The fittings on intermediate posts
fence is desired to be shockproof, and should allow the strained wires to be
that this requirement be included in free running.
Appendix 3/1.
(ii) The size of the holes drilled in the posts
(ii) Horizontal alignment. When the should be to the appropriate dimensions
alignment of the carriageway is for the fittings chosen and surplus holes
on a horizontal curve, the curve should be filled with grommets.
cannot be followed with dropper
pattern fencing. In such cases (iii) Plastic coated wire which has exposed
the distance between the galvanizing should be painted with
straining posts should be divided plastic paint.
into a series of straights,
depending on the sharpness of (iv) External ratchets, droppers and other
curvature, and turning posts fittings should be coated with plastic
should be erected at each change paint.
of direction. For instance with
the desired minimum radius of (v) Breaks in straining wires can be repaired
1020 m it is suggested that 3 by untensioning, fixing a wire vice
turning posts be included fitting, as shown on the RCD, and
between straining posts at 75 m retensioning.
centres. The angle of change of
direction at a turning post should 7 The Drawings should show where fencing is
not be more than 135°. required, and the position, length and height
for each type of fence. Appendix 3/1 should
The land take should reflect the need to include any further details required.
erect this type of fence in a series of
straights. 8 Foundations to posts for wooden post and
rail fences can be either rammed backfill or
(iii) Sharp change of direction. It is concrete mix ST 2, unless otherwise specified
recommended that two straining in Appendix 1/15 or Appendix 3/1 (see RCD
posts be provided instead of Drawings H3 and H15).
using one
9 Where fencing for the protection of planted
areas is required, the type of fence may be
March 2003 4
Volume 2 Series NG 300
Notes for Guidance on the Specification for Road Fencing
Works
EN 351-1 by defining the penetration and freshsawn timber should be cut to the required
retention of the preservative in the treated sizes and open-stacked, preferably under
wood and the sampling system that must cover, for a period that will depend on
be used to demonstrate compliance. climate, weather and timber species.
Alternatively, the timber can be kiln dried.
2 Inspection of the timber before
preservative treatment is of the utmost 4 If timber moisture content is to be assessed,
importance and arrangements should the moisture meter offers a quick practical and
be made for this to be carried out for convenient method (see prEN 13183-2).
each scheme. The extent of permitted Electrical resistance-type moisture meters
defects generally is defined in the should always be used in accordance with the
relevant British and European manufacturer’s instructions. Meters should be
Standards indicated in Clause 304. suitably calibrated before each use against a
Rejection of timber due to defects calibrated meter or oven-dried sample.
affected by moisture content, ie.
‘checks’ and ‘splits’ can only be 5 The moisture meter test results can be
enforced when the timber is within the confirmed by oven-drying tests (see prEN
specified moisture content range. This 13183-1). This is particularly desirable in any
is only certain before preservation case where there is the possibility of dispute.
treatment and before the timber is However, the non-destructive method of
subjected to the uncontrolled sampling (moisture meter method) should
conditions on Site. It is not satisfactory normally be used.
to inspect the material for quality
control on delivery to Site except in 6 Quality control at all stages of the process is
respect of physical defects which are essential. Clause 7 of MSA EN 351-1 contains
unaffected by moisture content. recommendations on suitable factory
production control procedures. Normally,
3 Since the level of protection afforded direct testing shall be used to check
by preservative treatment is now compliance with penetration and retention
defined by required levels of retention specifications. MSA EN 351-1 includes
and penetration in the treated timber, it definitions of permeable and resistant timbers,
is no longer necessary to include enabling the AQL to be established. MSA EN
methods of treatment in the 351-2 includes guidance on the sampling
specification. However, it is scheme and the penetration pass/fail criteria
anticipated that vacuum/high pressure for different AQLs. To demonstrate that the
methods of treatment will be required specified sapwood retention has been
to achieve the retentions and achieved, the analytical zones (i.e complete
penetration specified. Equally, the sapwood portion) of all the borings taken to
moisture content of the timber can be determine penetration should be combined
critical when attempting to treat timber and converted to an appropriate homogeneous
in this way to the specified form for chemical analysis. For all penetration
requirements. It is, therefore, advisable and retention determinations suitable methods
to ensure that the timber is at a of analysis are required.
moisture content of 28% or less before
preservative treatment is carried out. 7 If a CCA preservative has been applied, a
To achieve this moisture content, spray reagent (described in BS 5666 : Part 2)
March 2003 6
Volume 2 Series NG 300
Notes for Guidance on the Specification for Road Fencing
Works
can be used to detect its presence and another scheme. In such cases, suitable
to reveal the extent of the penetration arrangements should be made regarding
in the samples taken for this purpose. inspection of the subsequent batch destined
Suitable methods of analysis to for the initial scheme.
determine the retention of CCA
preservatives are described in BS 5666 10 Timber should not be dispatched to site
: Part 3. If creosote has been applied, until it is at least surface dry. When “wet”
its dark colour provides the necessary timber is received on site, it should be stacked
indicator of its presence and on cross-bearers, with crossbearers between
penetration. A method of analysis to bundles and not used within seven days of
determine retention is described in EN being treated. Treatment with a water-borne
12490. For other preservatives, preservative saturates and swells the timber. If
suitable methods of analysis should be subsequent drying is carried out too rapidly,
obtained from the preservative extensive splitting can occur. To prevent this,
manufacturer. slow drying, preferably under controlled
8 If the manufacturer has conditions, is essential. The degree of
demonstrated to the satisfaction of the necessary drying is largely dependent on the
specified that a safe relationship exists local prevailing weather conditions.
between the achievement of the
required penetration and retention and 11 If there is any doubt over the quality of
measurable features of the treatment preservation in a treated batch supported by
process, the manufacturer can use indirect testing, the direct testing system can
these measurable features to be applied.
demonstrate compliance. In MSA EN
351-1 this is referred to as the indirect
method. However, if this approach is NG 312 Painting of Timber Fences,
established, the manufacturer shall Gates, Stiles and Posts
demonstrate the correctness of the
relationship to the specified during 1 Appendix 1/15 should contain the details of
random, unannounced checks initiated accommodation works required in the
by the specified. Contract and should include the type and
colour of paint required for fencing and gates.
9 If the indirect testing approach is If preservation treatment is not required this
established and the treatment process should also be stated.
parameters are used to demonstrate
compliance, the only way to ensure 2 Requirements for the use of water borne
that each treatment process has been acrylic paints or alkyd-acrylic paint instead of
carried out as required is to witness the oil based paints should be given in Appendix
treatment. If exceptionally this is not 3/1.
done, it is necessary to accept the
assurance of the treated, embodied in a 3 Paint containing non-toxic constituents
certificate of treatment that should be should be specified for use where the painted
provided with each batch. It may be surfaces are accessible to animals.
that a batch of inspected timber,
because of variations in the
Contractor’s programme, is sent to
March 2003 7
Volume 2 Series NG 300
Notes for Guidance on the Specification for Road Fencing
Works
1 Temporary Fencing
(i) Requirements for temporary fencing if different from requirements of sub- Clause 302.1 and
303.1.
2 Timber Quality
(i) Requirements for timber if different from the requirements of sub-Clause 304.2.
3 Fittings
(i) Requirements for bolts, screws and nuts if different from the requirements of sub-Clause 305.1.
4 Permanent Fencing: Wooden Fencing, Gates and Stiles including Planting Works Fencing
(i) Flowing alignment and trimming ground to regular level on fence line.
[Location. Only included when necessary.]
(ii) Requirements for joining permanent fencing to existing hedges, fences and
to other structures if different from the requirements of sub-Clause 306.1.
(iv) Details of painting required [Only included when the compiler wishes to specify painting
specifically.]
(v) Concrete surround to base of posts. [Location. Included when the compiler
wishes to specify concrete footings for post and rail fencing as shown on RCD drawing no. H3
March 2003 8
Volume 2 Series NG 300
Notes for Guidance on the Specification for Road Fencing
Works
and H15.]
(vii) Details of security treatment below wildlife mesh. [Location and details]
(i) Flowing alignment and trimming ground to regular level on fence line. [Location. Only
included when necessary.]
(ii) Requirements for joining permanent fencing to existing hedges, fences and
to other structures if different from the requirements of sub-Clause 306.1.
(iv) Requirements for painting with plastic paint in accordance with sub-Clause 306.3.
(v) Zinc coated wire only. [Only included when departing from standard zinc and plastic coating]
(vi) Details of fittings required. [Preference is for hidden ratchet and wire vice an droppers and
other fittings painted with plastic paint.]
(i) Details of wire mesh attachments to fencing including the appropriate side of an existing fence
to which the mesh is fixed. [Location and details]
7 Badger Gates
(i) Details of requirements for badger gates including whether two-way gates are required.
[Location and details]
March 2003 9
Volume 2 Series NG 300
Notes for Guidance on the Specification for Road Fencing
Works
(i) Details of requirements for fenced tree guards. [Location and details]
9 Preservation of Timber
(i) Details of preservative to be used if different from sub-Clause 311.2(i). [Location and
details]
10 Other
March 2003 10