You are on page 1of 17

Document Number: ECS 05-9542

Version: 2.0
Date: 21/09/2018

THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE
ENGINEERING CONSTRUCTION STANDARD

ECS 05-9542

REMSDAQ CALLISTO NX CONFIGURATION PROCEDURE

Network(s): EPN, LPN, SPN

Summary: Configuration procedure for the Remsdaq Callisto NX, Type E RTU

Author: James Ford Date: 21/09/2018

Approver: Paul Williams Date: 05/11/2018

This document forms part of the Company’s Integrated Business System and its requirements are mandatory throughout UK
Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset
Management. If you have any queries about this document please contact the author or owner of the current issue.

Applicable To
UK Power Networks External
☒ Asset Management ☒ G81 Website
☒ Capital Programme ☒ UK Power Networks Services
☒ Connections ☒ Contractors
☒ Health & Safety ☒ ICPs/IDNOs
☐ Legal ☐ Meter Operators
☒ Network Operations
☒ Procurement
☐ Strategy & Regulation
☒ Technical Training
Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

Revision Record

Version 2.0 Review Date 05/11/2023


Date 21/09/2019 Author James Ford
Reason for update: Periodic review
What has changed: Reference to PAKNET removed and to include details of the use of the Type E
RTU with multi panel switchgear and as a retrofit RTU. Updated screenshots.
Version 1.0 Review Date 19/05/2018
Date 27/04/2017 Author James Ford
New document detailing the configuration procedure for the Remsdaq Callisto NX Type E RTU

© UK Power Networks 2018 All rights reserved 2 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

Contents

1 Introduction ............................................................................................................. 4
2 Scope ....................................................................................................................... 4
3 Glossary and Abbreviations ................................................................................... 5
4 Description............................................................................................................... 6
5 Comms Device Installation ..................................................................................... 9
6 CallistoNX Configuration ........................................................................................ 10
7 References ............................................................................................................. 16
8 Dependent Documents.......................................................................................... 16
Appendix A – RTU Firmware Update ............................................................................... 17

Figures

Figure 1 – CallistoNX RTU Cabinet Layout ............................................................................. 6


Figure 2 – Switch 1 and Switch 2 FPI CT Connections ........................................................ 7
Figure 3 – Sockets on Underside of RTU .............................................................................. 8
Figure 4 – Comms Device DIN Rail Installation .................................................................... 9
Figure 5 – Comms Device Installed...................................................................................... 9
Figure 6 – RTU Selection page .......................................................................................... 11
Figure 7 – RTU General information page.......................................................................... 12
Figure 8 – RTU Modbus connected device page................................................................ 13
Figure 9 – RTU switch configuration page including EFPI/FPI ........................................... 14
Figure 10 – RTU configuration upload page ....................................................................... 15

© UK Power Networks 2018 All rights reserved 3 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

1 Introduction
1.1 This procedure details the configuration procedures to set up a Remsdaq CallistoNX
RTU for use in secondary substations.

1.2 This procedure shall be carried out by the Commissioning Engineer or their appointed
representative, who shall be an Authorised Person having appropriate training and
experience.

1.3 This procedure shall be carried out in accordance with the requirements of the
Distribution Safety Rules.

1.4 This procedure shall be carried out having regard to the requirements and
recommendations of the manufacturer. If conflict exists between the requirements of
the manufacturer and those of UK Power Networks the matter shall be referred to
Asset Management.

1.5 This procedure assumes that the unit has been installed in accordance with the
appropriate procedures.

2 Scope
2.1 This procedure applies to the configuration of the Remsdaq CallistoNX RTU. The
CallistoNX is used to provide remote control of all UK Power Networks approved
secondary RMUs.

2.2 The Type E RTU can be used to monitor and control secondary substation multi
panel switchgear. Specific details regarding the connection to and use of the Type E
RTU with the multi panel switchgear is contained within a separate document, see
references section.

2.3 The Type E RTUs can be used as a retrofit RTU with old specification RMUs. Specific
details regarding the connection to and use of the Type E RTU as a retrofit is detailed
within a separate document, see references section.

2.4 The commissioning procedure for the secondary substation is contained in the
relevant substation commissioning document, see references section.

© UK Power Networks 2018 All rights reserved 4 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

3 Glossary and Abbreviations

Term Definition

ADSL Asynchronous Digital Subscriber Line


APN Access Point Name (secure access to mobile comms networks)
CT Current Transformer
DNP3 Distributed Network Protocol
PowerOn Electricity Network Management and Control
ESN Electronic Serial Number
EFPI Earth Fault Passage Indicator
FPI Fault Passage Indicator
GPRS/3G/4G Mobile Comms Networks (Vodafone and O2)
HMI Human Machine Interface
RMU Ring Main Unit
RTU Remote Terminal Unit
SHDSL Symmetrical High-Speed Digital Subscriber Line

© UK Power Networks 2018 All rights reserved 5 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

4 Description
4.1 An overview of the main components of the Remsdaq CallistoNX is shown Figure 1.

Figure 1 – CallistoNX RTU Cabinet Layout


4.2 For use with RMUs, the CallistoNX has remote control and monitoring facilities for up
to four switches or circuit-breakers (or a mixture of both). Each switch/circuit breaker
to be controlled and / or monitored needs an umbilical cable connection between the
equipment and the CallistoNX.

4.3 For use with multi panel switchgear, the Type E RTU has control facilities for up to
four switches or circuit-breakers and monitoring (open/close) of up to eight switches
or circuit-breakers (including the four controlled). To monitor six or more switches or
circuit-breakers, an additional DI module must be installed in the RTU.

4.4 Local control and monitoring is provided using the touch screen HMI.

4.5 The CallistoNX is mains powered with a battery back-up and is self-monitoring.

4.6 The CallistoNX uses the DNP3 IP protocol to provide communication with PowerOn
network management system for remote control and monitoring. Any appropriate IP
compliant comms system can be used, such as:

 O2 or Vodafone GPRS/3G/4G networks via the dedicated UK Power Networks


APNs.
 Rented ADSL circuits.
 UKPN SHDSL circuits.
 UKPN Geostationary Satellite.
 Fibre.

© UK Power Networks 2018 All rights reserved 6 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

4.7 The IP comms networks will also provide remote configuration and monitoring
capability from UKPN offices.

4.8 The CallistoNX is capable of providing two internal fault passage indicators (FPI) on
the FPM module, driven via the 3 phase RMU FPI CT inputs (where available). These
are directly wired to RTU switch 1 and RTU switch 2.

4.9 Where RMU CT inputs cannot be provided to the RTU (old LPN spec RMUs for
instance), or where additional FPIs are required, these can be facilitated using
external FPI units connected to the RTU via the RMU marshalling box.

Figure 2 – Switch 1 and Switch 2 FPI CT Connections

© UK Power Networks 2018 All rights reserved 7 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

4.10 Connections to plant and equipment are made using the sockets provided on the
bottom of the RTU, see Figure 3.

Figure 3 – Sockets on Underside of RTU

© UK Power Networks 2018 All rights reserved 8 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

5 Comms Device Installation


5.1 Ensure the Comms Device mounting DIN rail is installed in the appropriate position
for the Comms Device to be installed as shown in Figure 4. Note, the DIN rail may
need to be repositioned depending on the Comms Device being fitted.

Figure 4 – Comms Device DIN Rail Installation

5.2 Mount the Comms Device on the DIN rail as shown in Figure 5.

Figure 5 – Comms Device Installed


5.3 Connect the Comms Device power lead to the Comms Device and connector TB15,
terminals 1 and 2 of the RTU.

5.4 If using GPRS/3G/4G Comms: Connect the ethernet patch lead to Port A of the
System Bus module and to the comms device Ethernet port.

5.5 If a risk assessment of the location allows, the aerial should be mounted outdoors,
however if not the aerial should be mounted as high as possible within the substation.

5.6 If the substation is underground, every effort should be made to place the aerial at
street level, or as close as reasonably practicable.

5.7 If using GPRS/3G/4G Comms: The Aerial feeder should be passed through one of
the stuffing glands already installed on the RTU. The aerial feeder cable may need
to be packed out (with insulating tape or something suitable) to ensure the stuffing
gland can be tightened to form a good seal around the feeder cable.

© UK Power Networks 2018 All rights reserved 9 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

6 CallistoNX Configuration
6.1 Please note, the process and screenshots may vary slightly from the actual screens
shown during configuration, but the principles and process is the same. This is
because new functions and features may be added to the RTU between document
updates.

6.2 The Callisto NX RTU is pre-configured for the ‘hardwired’ I/O points and only requires
configuration for the additional options that may be installed on a site by site basis,
and the site specific RTU address.

6.3 The Callisto NX Configuration Tool software is used to configure the RTU, set up
the DNP3 address and IP addresses, etc, and to check the status of the RTU.

6.4 Ensure the Laptop is to set to obtain an IP address automatically (DHCP Client).

6.5 Connect a laptop PC to RJ 45 Config Port on the touch screen swing frame using a
suitable Ethernet Patch cable. If the Laptop supports auto-crossover a standard
Ethernet Patch Cable may be used to connect a laptop PC to the CallistoNX for
configuration, if not a crossover Ethernet cable is required. DO NOT connect to the
RJ 45 port on the touch screen itself.

6.6 Open the Callisto NX Configuration Tool on the laptop.

6.7 The box at the top of the Config Tool page displays the Commissioning Tool, Base
Config and Firmware version numbers, make sure the Config and Firmware are the
latest versions as available on Alfresco. If any of these are older versions, please
refer to Appendix A to upgrade them. Please note, the same Firmware/Software
versions are used for both RMUs and multi panel switchgear, however, different
configs are used.

6.8 The Config Tool will search for any connected RTU and display the details on the
screen. If more than one RTU is displayed, ensure you select the correct one (The
RTU name should match the Power-On name).

6.9 Select the desired RTU, type the following username and password into the relevant
boxes. Username ukpn, password <deliberately not shown in this document>
and select Connect.

Note: do not click the Switch to Remote Access Logon button.

© UK Power Networks 2018 All rights reserved 10 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

Figure 6 – RTU Selection page

6.10 The Config Tool will then connect to the selected RTU, this may take a couple of
minutes.

© UK Power Networks 2018 All rights reserved 11 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

6.11 The following screen will be displayed.

Figure 7 – RTU General information page

6.12 Step 1: Input the required RTU Name into the appropriate box. (site name specified
by Power-On commissioning engineer).

6.12.1 Select the Required Network.

6.12.2 Input the required DNP3 Address.

6.12.3 Check the RTU IP Address, RTU Subnet Mask, Gateway IP Address and Router
Sharing – RTU Number are all set to:

RTU IP Address: 192.168.1.11

RTU Subnet Mask: 255.255.255.0

Gateway IP Address: 192.168.1.1

Router Sharing – RTU Number: 1 (assuming only one RTU is connected to the
Router). If more than one RTU is connected to the Router this will need to be
incremented.

Up to 4 RTUs can be connected to a single Router. Please note, each RTU must
have a DIFFERENT sharing number. If in doubt, check the other RTUs connected to
the router (Lucy Gemini 3 RTUs will have the IP address as detailed below):

RTU Sharing – RTU Number 1 = RTU IP Address 192.168.1.11


RTU Sharing – RTU Number 2 = RTU IP Address 192.168.1.12
RTU Sharing – RTU Number 3 = RTU IP Address 192.168.1.13
RTU Sharing – RTU Number 4 = RTU IP Address 192.168.1.14

© UK Power Networks 2018 All rights reserved 12 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

6.12.4 RTU Switch 1 is always enabled by default. If RTU Switch 2, 3 or 4 are to be utilised
they must be enabled by selecting the relevant tick boxes as required.

6.12.5 If PLTU functionality is required, tick the box to enable the PLTU functionality. If the
PLTU functionality is enabled, ensure the correct RTU switch is selected, so the
correct circuit breaker is tripped.

6.12.6 Ensure the boxes for the Optional 6I and Optional DI modules are not ticked.

6.13 Select Next.

6.14 The following screen will be displayed:

Figure 8 – RTU Modbus connected device page

6.15 Select any equipment connected via the RS485/Modbus comms bus (such as a
Power Meters or Protection relays). If none is connected, select None.

6.16 Please note, the Modbus address of the devices installed on the comms bus must
match the Modbus address detailed in the configuration tool.

6.17 Select Next.

6.18 The following screen will be displayed:

© UK Power Networks 2018 All rights reserved 13 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

Figure 9 – RTU switch configuration page including EFPI/FPI

6.19 Step 3: Set up RTU Switch 1 (Do not change RTU Switch Name).

6.19.1 Select what RMU type the switch or circuit breaker is connected to.

6.19.2 Select whether the Actuator Disabled Alarm is fitted.

6.19.3 Select whether an FPI/EFPI is fitted, and if so what type


(Internal/External/Directional).

6.19.4 If an internal FPI/EFPI is being used, set up the detection parameters.

Please note, the standard FPI settings for use with the Type E RTU internal FPIs for EPN,
LPN and SPN are: Phase Fault 600A 50ms and Earth Fault 90A 50ms. These values can
be overwritten if site specific values have been calculated.

Internal FPI/EFPI functionality is only available on RTU switch 1 and RTU switch 2.

Select Next.

6.20 Repeat for all configured RTU switches.

6.21 The following screen will be displayed:

© UK Power Networks 2018 All rights reserved 14 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

Figure 10 – RTU configuration upload page

6.22 Click Upload Configuration to write the configuration to the RTU. The RTU will
restart, green ticks will be shown against the items in the Progress list.

6.23 When the RTU has been configured and rebooted, the following date/time will be
shown on the RTU LCD panel (not the touch screen): Sat Jan 1 2000 00:00:00 until
the RTU has connected into Power-On and the clock automatically set to the correct
time. The RTU has approximately 3 minute delay before connecting to Power-On to
enable it to collect all of the relevant data first.

6.24 A message will be displayed stating “Operation complete; RTU Name=”site


name”; RTU Config version=x.xxx; Firmware version=x.x.x.xx”.

6.25 Check the Config and Frimware versions are correct.

6.26 Select Close to exit the Config Tool.

© UK Power Networks 2018 All rights reserved 15 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

7 References
EAS 05-9016 Remsdaq Callisto NX RTU
EOS 05-9306 Remsdaq Callisto NX RTU
ECS 05-9543 Type E RTU Retrofit Installation Procedure
ECS 05-9544 Type E RTU with Multi Panel Switchgear
EDS 05-9005 RTU Type E Ground Mounted Switchgear Interface
ECP 11-0501 Secondary Ground Mount Substation Commissioning Procedures
ECP 11-0601 GPRS/3G/4G Comms Device Commissioning Procedure
ECS 05-9540 Type E RTU and Ancillary Items Installation Procedure
UK Power Networks Distribution Safety Rules
Remsdaq CallistoNX Installation, Operation and Maintenance User Manual

8 Dependent Documents
The documents below are dependent on the content of this document and may be affected
by any changes.

EDS 06-0014 Secondary Substation Earthing Design

ECP 11-0501 Secondary Commissioning Procedures


EDS 05-9005 RTU Type E Ground Mounted Switchgear Interface.
ECS 05-9540 Type E RTU and Ancillary Items Installation Procedure
ECS 05-9543 Type E RTU Retrofit Installation Procedure
ECS 05-9544 Type E RTU with Multi Panel Switchgear

© UK Power Networks 2018 All rights reserved 16 of 17


Remsdaq Callisto NX Configuration Procedure Document Number: ECS 05-9542
Version: 2.0
Date: 21/09/2018

Appendix A – RTU Firmware Update


The CallistoNX software is upgraded using CallistoNX Configuration Tool as follows:

1. Follow the procedure detailed in 6.3 to 6.9 to start the config tool and connect to the RTU.
2. Select Import New Version Files.
3. Navigate to where the relevant file is stored on the Laptop.
4. Select the file and select Open.
5. A message will be displayed to tell you the file has been successfully imported.
6. Repeat the process for any files than need to be upgraded.

Once imported, the Config Tool holds the RTU Firmware and Config versions. If the versions
in the individual RTUs are incorrect (as displayed in the lower box next to the relevant RTUs,
see Figure 6 on page 11), the Config Tool will update them with the version in the Config Tool
during the configuration process.

© UK Power Networks 2018 All rights reserved 17 of 17

You might also like