NOTE:

1) KEMAJUAN KERJA DENGAN KEMAJUAN KEWANGAN TAK SEIRING


2) PHK NO.1 – 1.8 JUTA

SAFETY BRIEFING

1) 17/9/2020 – AUDIT SHASSIC


2) SAFETY – 94 %
3) TEAM BRIDGE – 8 ORANG
4) AKTIF DALAM 30 ORANG
5) BARRIER – KENE IMPROVE

ON SITE

1) KELUARKAN SEMUA BARANG YANG XPAKAI YG BERADA DALAM RIZAB JALAN – 3 HARI
2) PASTIKAN KEBERSIHAN DI TAPAK KERANA DENGGI KAT JOHOR TINGGI

TMP
1) KELULUSAN DARIPADA RSA – PERSIMPANGAN BERJAYA
2) PERBENTANGAN DENGAN MBJB DAN JKR
3) SEKALIKAN DENGAN PERSIMPANGAN KEMPAS UTAMA
4) JANGKAAN NAK BUAT LENCONGAN – BULAN 11
5) DISCUSSION DENGAN MBJB, RSA DGN JKR
6) KEMALANGAN – KENDERAAN AWAM LANGGAR PLASTIC BARRIER SBB HUJAN LEBAT, TIADA
KECEDERAAN,
7) PINDAHKAN BARRIER YANG XAKTIF KE TEMPAT2 YANG AKTIF
8) TOTAL KEMALANGAN – 12 (TIADA KEMATIAN)
9) PENGURUSAN TRAFIK UNTUK KAWASAN JAMBATAN – 3 HARI

SEBELOM

74 –JADUAL

71 – SEBENAR

3 – VARIAN

SELEPAS

80 – JADUAL

76 – SEBENAR

4- VARIAN

LEWAT – 40 HARI

AMARAN PERTAMA – KELEWATAN LEBIH 30 HARI


1) KERJA-KERJA RETAINING WALL – ASAL KAT STARHILL TP PINDAHKAN KE KAWASAN
JAMBATAN
2) SELEPAS KERJA SUBSTRUKTUR SIAP
3) KERJA DRAINAGE – MASALAH SUBCON
4) KERJA-KERJA PAVEMENT – UTK ROAD DIVERSION MASUK KAT TMP..BUKAN DEKAT
PAVEMENT.
5) ROAD FURNITURE – SEKALI DENGAN DRAINAGE
6) NJB – MOULD DAH SMPAI – START BULAN 15/10/2020
7) KERJA-KERJA BRIDGE – KERJA-KERJA PILING DAH SIAP,,SKANG TGH BUAT ABUTMENT B
8) PERBEZAAN KEWANGAN DENGAN FIZIKAL
9) TNB – KERJA DAH START – 13 DRUM
10) TM – KERJA-KERJA INFRA DAH SIAP.. TINGAL PART TM
11) SUKAN PARA SUKMA BULAN 3
12) SURAT KE JKR UNTUK STATUS KERJA YANG DAH SIAP

SURAT KE IRDA – PEROBOHAN SIGNBOARD