Engineer completes a con-
crete test to ensure that the
previous day's pour has
q achieved the required
strength .
With the engineer's
permission the Tun-
nelform is struck,
cleaned, oiled and
repositioned
Once all of the pack-
ages are in position
slab reinforcement
and insertion of con-
duits can begin.
Concrete pouring
commences. This
usually takes be-
tween 2 and 3
hours
After pouring, the curtains are closed and
heaters are inserted. Heating, when re-
quired, is used to kick start the curing
process. This whole exercise is re-
peated at 07:00 the next day