Engineer completes a con- crete test to ensure that the previous day's pour has q achieved the required strength . With the engineer's permission the Tun- nelform is struck, cleaned, oiled and repositioned Once all of the pack- ages are in position slab reinforcement and insertion of con- duits can begin. Concrete pouring commences. This usually takes be- tween 2 and 3 hours After pouring, the curtains are closed and heaters are inserted. Heating, when re- quired, is used to kick start the curing process. This whole exercise is re- peated at 07:00 the next day =j|| Outinord FEB Ei Cm International Ltd