ID Task Name Duration Start Finish Predecessors

1 House project 36 days Wed 8/12/15 Wed 9/30/15


2 Planning 4 days Wed 8/12/15 Mon 8/17/15
3 Elicit customer requirements 1 day Wed 8/12/15 Wed 8/12/15
4 Prepare draft blue print 2 days Thu 8/13/15 Fri 8/14/15 3
5 Customer review iterations 1 day Mon 8/17/15 Mon 8/17/15 4
6 Blue print approval 0 days Mon 8/17/15 Mon 8/17/15 5
7 Design 12 days Wed 8/12/15 Thu 8/27/15
8 Wiring diagrams 4 days Tue 8/18/15 Fri 8/21/15 6
9 Structural design 4 days Wed 8/12/15 Mon 8/17/15
10 Water pipeline layout 4 days Tue 8/18/15 Fri 8/21/15 6;9
11 Sewage pipeline layout 4 days Mon 8/24/15 Thu 8/27/15 6;9;10
12 Construction 36 days Wed 8/12/15 Wed 9/30/15
13 Concrete work 30 days Tue 8/18/15 Mon 9/28/15
14 Foundation 27 days Tue 8/18/15 Wed 9/23/15
15 Chip and size stones 1 day Tue 8/18/15 Tue 8/18/15
16 Digging 20 days Tue 8/25/15 Mon 9/21/15 6;9;15SS+5 days
17 Place stone and concrete1 day Tue 9/22/15 Tue 9/22/15 16
18 Curing 1 day Wed 9/23/15 Wed 9/23/15 17
19 Wall construction 1 day Thu 9/24/15 Thu 9/24/15
20 Wall 1 1 day Thu 9/24/15 Thu 9/24/15 18
21 Wall 2 1 day Thu 9/24/15 Thu 9/24/15 18
22 Wall 3 1 day Thu 9/24/15 Thu 9/24/15 18
23 Wall 4 1 day Thu 9/24/15 Thu 9/24/15 18
24 Wall 5 1 day Thu 9/24/15 Thu 9/24/15 18
25 Wall 6 1 day Thu 9/24/15 Thu 9/24/15 18
26 Wall 7 1 day Thu 9/24/15 Thu 9/24/15 18
27 Wall 8 1 day Thu 9/24/15 Thu 9/24/15 18
28 Wall 9 1 day Thu 9/24/15 Thu 9/24/15 18
29 Wall 10 1 day Thu 9/24/15 Thu 9/24/15 18
30 Wall 11 1 day Thu 9/24/15 Thu 9/24/15 18
31 Wall 12 1 day Thu 9/24/15 Thu 9/24/15 18
32 Wall plastering 1 day Fri 9/25/15 Fri 9/25/15
33 Wall 1 1 day Fri 9/25/15 Fri 9/25/15 20;75FF;83FF
34 Wall 2 1 day Fri 9/25/15 Fri 9/25/15 21;75FF;83FF
35 Wall 3 1 day Fri 9/25/15 Fri 9/25/15 22;75FF;83FF
36 Wall 4 1 day Fri 9/25/15 Fri 9/25/15 23;75FF;83FF
37 Wall 5 1 day Fri 9/25/15 Fri 9/25/15 24;75FF;83FF
38 Wall 6 1 day Fri 9/25/15 Fri 9/25/15 25;75FF;83FF
39 Wall 7 1 day Fri 9/25/15 Fri 9/25/15 26;75FF;83FF
40 Wall 8 1 day Fri 9/25/15 Fri 9/25/15 27;75FF;83FF
41 Wall 9 1 day Fri 9/25/15 Fri 9/25/15 28;75FF;83FF
42 Wall 10 1 day Fri 9/25/15 Fri 9/25/15 29;75FF;83FF
43 Wall 11 1 day Fri 9/25/15 Fri 9/25/15 30;75FF;83FF
44 Wall 12 1 day Fri 9/25/15 Fri 9/25/15 31;75FF;83FF
45 RCC 21 days Mon 8/31/15 Mon 9/28/15 90
46 Bend bars 1 day Mon 8/31/15 Mon 8/31/15 6
47 Lay concrete roof 1 day Mon 9/28/15 Mon 9/28/15 6;32;46
48 Carpentary work 1 day Tue 9/29/15 Tue 9/29/15 86
49 Doors 1 day Tue 9/29/15 Tue 9/29/15 6;45
50 Windows 1 day Tue 9/29/15 Tue 9/29/15 6;45
51 Cupboards 1 day Tue 9/29/15 Tue 9/29/15 6;45
52 Painting 1 day Tue 9/29/15 Tue 9/29/15 45;92
53 Apply primers to inner walls 1 day Tue 9/29/15 Tue 9/29/15
54 Apply paint to inner walls 1 day Tue 9/29/15 Tue 9/29/15
55 Apply primers to outer walls 1 day Tue 9/29/15 Tue 9/29/15
56 Apply paint to outer walls 1 day Tue 9/29/15 Tue 9/29/15
57 Paint the wood work 1 day Tue 9/29/15 Tue 9/29/15
58 Flooring 2 days Tue 9/29/15 Wed 9/30/15 91
59 Lay tiles 1 day Tue 9/29/15 Tue 9/29/15 6;45
60 Room 1 1 day Tue 9/29/15 Tue 9/29/15
61 Room 2 1 day Tue 9/29/15 Tue 9/29/15
62 Room 3 1 day Tue 9/29/15 Tue 9/29/15
63 Room 4 1 day Tue 9/29/15 Tue 9/29/15
64 Room 5 1 day Tue 9/29/15 Tue 9/29/15
65 Room 6 1 day Tue 9/29/15 Tue 9/29/15
66 Polish tiles 1 day Wed 9/30/15 Wed 9/30/15 52;59
67 Room 1 1 day Wed 9/30/15 Wed 9/30/15
68 Room 2 1 day Wed 9/30/15 Wed 9/30/15
69 Room 3 1 day Wed 9/30/15 Wed 9/30/15
70 Room 4 1 day Wed 9/30/15 Wed 9/30/15
71 Room 5 1 day Wed 9/30/15 Wed 9/30/15
72 Room 6 1 day Wed 9/30/15 Wed 9/30/15
73 Electrical work 3 days Thu 9/24/15 Mon 9/28/15 88
74 Embed PVC pipes in the wa1 day Thu 9/24/15 Thu 9/24/15 19SS
75 Run wires within the pipes 1 day Fri 9/25/15 Fri 9/25/15 74;19SS
76 Install switches 1 day Mon 9/28/15 Mon 9/28/15 32;75
77 Install lights 1 day Mon 9/28/15 Mon 9/28/15 32;75
78 Install fans 1 day Mon 9/28/15 Mon 9/28/15 32;75
79 Install other equipments 1 day Mon 9/28/15 Mon 9/28/15 32;75
80 Water and sewage works 3 days Thu 9/24/15 Mon 9/28/15 89
81 Dig sewage chambers 1 day Thu 9/24/15 Thu 9/24/15 14
82 Lay sewage pipes 1 day Fri 9/25/15 Fri 9/25/15 81;89
83 Lay water pipes 1 day Thu 9/24/15 Thu 9/24/15 89;19SS
84 Install taps, shower and oth 1 day Mon 9/28/15 Mon 9/28/15 32;83
85 Procurements 13 days Wed 8/12/15 Fri 8/28/15
86 Procure raw wood 1 day Fri 8/28/15 Fri 8/28/15 7
87 Procure construction materi 1 day Fri 8/28/15 Fri 8/28/15 7
88 Procure Wires and fixtures 1 day Fri 8/28/15 Fri 8/28/15 7
89 Procure pipes and fixtures 1 day Fri 8/28/15 Fri 8/28/15 7
90 Procure Iron rods 1 day Fri 8/28/15 Fri 8/28/15 7
91 Procure Tiles 1 day Fri 8/28/15 Fri 8/28/15 7
92 Procure paints 1 day Fri 8/28/15 Fri 8/28/15 7
93 1 day Wed 8/12/15 Wed 8/12/15
Resource Names
ID Resource name Type Material label Initials Group Max.Units
Unassigned
1 Ar Work A 100%
2 Architect Work A 100%
3 Customer Work C 100%
4 ES Work E 100%
5 PS Work P 100%
6 L1 Work L 100%
7 L2 Work L 100%
8 L3 Work L 100%
9 L4 Work L 100%
10 L5 Work L 100%
11 L6 Work L 100%
12 L7 Work L 100%
13 L8 Work L 100%
Std.Rate Ovt.Rate Cost/Use Accrue At Base Calendar Code

$10.00/hr $15.00/hr $0.00 Prorated Standard


$10.00/hr $15.00/hr $0.00 Prorated Standard
$10.00/hr $15.00/hr $0.00 Prorated Standard
$10.00/hr $15.00/hr $0.00 Prorated Standard
$10.00/hr $15.00/hr $0.00 Prorated Standard
$10.00/hr $15.00/hr $0.00 Prorated Standard
$10.00/hr $15.00/hr $0.00 Prorated Standard
$10.00/hr $15.00/hr $0.00 Prorated Standard
$10.00/hr $15.00/hr $0.00 Prorated Standard
$10.00/hr $15.00/hr $0.00 Prorated Standard
$10.00/hr $15.00/hr $0.00 Prorated Standard
$10.00/hr $15.00/hr $0.00 Prorated Standard
$10.00/hr $15.00/hr $0.00 Prorated Standard
Uid Task name Resource name Work Duration