You are on page 1of 13

DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA

BIAYA
No. URAIAN KO HP KAP. HARGA SEWA KET.
DE ALAT ALAT/JAM
(di luar PPN)

1 ASPHALT MIXING PLANT E01 150.0 40.0 T/Jam 1,005,000,000 5,800,498.77


2 ASPHALT FINISHER E02 50.0 5.0 Ton 1,140,000,000 447,673.09
3 ASPHALT SPRAYER E03 4.0 800.0 Liter 260,000,000 104,004.52
4 BULLDOZER 100-150 HP E04 140.0 - - 1,191,000,000 705,344.49
5 COMPRESSOR 4000-6500 L\M E05 60.0 5,000.0 CPM/(L/m) 45,000,000 216,570.67
6 CONCRETE MIXER 0.3-0.6 M3 E06 15.0 500.0 Liter 10,000,000 72,142.93
7 CRANE 10-15 TON E07 120.0 15.0 Ton 900,000,000,000 582,187.69
8 DUMP TRUCK 3-4 M3 E08 100.0 6.0 Ton 600,000,000 457,104.17
9 DUMP TRUCK 10 TON E09 120.0 10.0 Ton 240,000,000 440,895.95
10 EXCAVATOR 80-140 HP E10 80.0 0.5 M3 1,425,000,000 572,858.83
11 FLAT BED TRUCK 3-4 M3 E11 125.0 4.0 ton 250,000,000 449,331.81
12 GENERATOR SET E12 180.0 180.0 KVA 215,000,000 618,123.99
13 MOTOR GRADER >100 HP E13 125.0 - - 1,300,000,000 683,034.04
14 TRACK LOADER 75-100 HP E14 75.0 1.5 M3 700,000,000 402,437.01
15 WHEEL LOADER 1.0-1.6 M3 E15 120.0 1.5 M3 860,000,000 573,624.55
16 THREE WHEEL ROLLER 6-8 T E16 55.0 8.0 Ton 410,000,000 269,496.25
17 TANDEM ROLLER 6-8 T. E17 60.0 8.0 Ton 910,000,000 335,318.71
18 TIRE ROLLER 8-10 T. E18 60.0 10.0 Ton 710,000,000 307,102.98
19 VIBRATORY ROLLER 5-8 T. E19 60.0 8.0 Ton 960,000,000 389,042.36
20 CONCRETE VIBRATOR E20 3.0 - - 900,000 36,011.45
21 STONE CRUSHER E21 220.0 50.0 T/Jam 1,410,000,000 1,004,239.09
22 WATER PUMP 70-100 mm E22 6.0 - - 10,000,000 46,142.11
23 WATER TANKER 3000-4500 L. E23 100.0 4,000.0 Liter 355,000,000 404,654.97
24 PEDESTRIAN ROLLER E24 8.8 1.00 Ton 90,000,000 75,939.49
25 TAMPER E25 5.0 0.20 Ton 26,000,000 56,012.18
26 JACK HAMMER E26 0.0 1,330.00 - 120,000,000 50,046.55
27 FULVI MIXER E27 345.0 2,005.00 - 50,000,000 1,337,893.76
28 CONCRETE PUMP E28 100.0 8.00 M3 130,000,000 354,496.36
29 TRAILER 20 TON E29 175.0 20.00 Ton 1,300,000,000 815,274.28
30 PILE DRIVER + HAMMER E30 25.0 2.50 Ton 1,100,000,000 335,918.36
31 CRANE ON TRACK 35 TON E31 125.0 35.0 Ton 1,350,000,000 673,062.44
32 WELDING SET E32 40.0 250.0 Amp 19,600,000 150,273.08
33 BORE PILE MACHINE E33 150.0 2,000.0 Meter 2,476,000,000 972,944.78
34 ASPHALT LIQUID MIXER E34 5.0 1,000.0 Liter 100 39,572.17
35 TRONTON E35 150.0 15.0 Ton 100 601,750.03
36 COLD MILLING E36 248.0 1,000.0 m 100 796,164.02
37 ROCK DRILL BREAKER E37 3.0 - - 100 52,705.03
38 COLD RECYCLER E38 900.0 2,200.0 M 100 2,780,200.02
39 HOT RECYCLER E39 400.0 3.0 M 100 1,258,700.02
40 AGGREGAT (CHIP) SPREADER E40 115.0 3.5 M 100 471,025.05
41 ASPHALT DISTRIBUTOR E41 115.0 4,000.0 Liter 441,000,000 485,853.57
42 SLIP FORM PAVER E42 105.0 2.5 M 100 361,015.02
43 CONCRETE PAN MIXER E43 134.0 600.0 Liter 100 541,990.03
44 CONCRETE BREAKER E44 290.0 20.0 m3/jam 100 923,970.02
45 ASPAHLT TANKER E45 190.0 4,000.0 liter 100 658,127.16
46 CEMENT TANKER E46 190.0 4,000.0 liter 100 602,527.16
47 CONDRETE MIXER (350) E47 20.0 350.0 liter 26,250,000 94,475.43
48 VIBRATING RAMMER E48 4.2 80.0 KG 100 40,044.19
49 TRUK MIXER (AGITATOR) E49 220.0 5.0 M3 456,750,000 791,597.44
50 BORE PILE MACHINE E50 125.0 60.0 CM 100 491,232.17
51 CRANE ON TRACK 75-100 TON E51 200.0 75.0 Ton 100 632,957.16
52 BLENDING EQUIPMENT E52 50.0 30.0 Ton 588,000,000 294,125.36
53 ASPHALT LIQUID MIXER E34a 40.0 20,000.0 Liter 100 146,077.17
54 BAR BENDER E53 3.0 0.0 0 100 26,990.75
55 BAR CUTTER E54 3.0 0.0 0 100 26,990.75
56 BREAKER E55 80.0 3.0 m3/jam 100 267,797.16
57 GROUTING PUMP E56 100.0 15.0 Ton 100 328,657.16
58 JACK HIDROLIC E57 3.0 150.0 Ton 100 33,486.16
59 MESIN LAS E58 3.0 0.2 Ton 100 35,562.21
60 PILE DRIVER LEADER, 75 kw E59 70.0 75.0 kw 100 237,367.15
61 PILE HAMMER E60 10.0 0.0 0 100 61,707.21
62 PILE HAMMER, 2,5 Ton E61 1.0 2.5 Ton 100 27,400.15
63 STRESSING JACK E62 89.0 15.0 Ton 100 295,184.17
64 WELDING MACHINE, 300 A E63 5.0 0.0 0 100 39,572.15
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT MIXING PLANT E01
2. Tenaga Pw 150.0 HP 5,756,815.74
3. Kapasitas Cp 40.0 T/Jam
4. Alat a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,005,000,000.0 Rupiah

5 Kapastas tangki aspal Ca 30,000.00 liter

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 100,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23740 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 107,362.52 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,005.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 108,367.52 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H1 250,200.00 Rupiah
Bahan Bakar Pemanasan Material = 12 ltr x Ms H2 4,670,400.00 Rupiah Khusus AMP
dan aspal (Oil Heater)
Bahan Bakar Pemanas Aspal =1/1000 *Ca*Ms H3 417,000.00

2. Pelumas = (2.5%-3%) x Pw x Mp I 206,250.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 43,969


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 62,812.50 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah
6 Pembantu Operator = ( 3 Orang / Jam ) x U2 M 25,714.29 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 5,692,131.25 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 5,800,498.77 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Rp./liter
5. Bahan Bakar Solar Ms 13,900.00 Rp./liter
6. Minyak Pelumas Mp 55,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan bakar Batubara 500.00 Rp/kg
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT FINISHER E02
2. Tenaga Pw 50.0 HP
3. Kapasitas Cp 5.0 Ton 392,399.28
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,800.0 Jam
c. Harga Alat B 1,140,000,000 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 114,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23740 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 135,315.95 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,266.67 Rupiah


W

Biaya Pasti per Jam = (E+F) G 136,582.61 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 83,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 68,750.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 55,417


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 79,166.67 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,571.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 311,090.48 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 447,673.09 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Liter
5. Bahan Bakar Solar Ms 13,900.00 Liter
6. Minyak Pelumas Mp 55,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan COMPRESSOR 4000-6500 L\M E05
2. Tenaga Pw 60.0 HP 216,570.67
3. Kapasitas Cp 5,000.0 CPM/(L/m)
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 45,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 4,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23740 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 4,807.28 Rupiah
W

b. Asuransi, dll = 0.002 x B F 45.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 4,852.28 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 100,080.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 82,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 1,969


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 2,812.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,571.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 211,718.39 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 216,570.67 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Liter
5. Bahan Bakar Solar Ms 13,900.00 Liter
6. Minyak Pelumas Mp 55,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3-4 M3 E08
2. Tenaga Pw 100.0 HP 457,104.17
3. Kapasitas Cp 6.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 600,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 60,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23740 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 64,097.03 Rupiah
W

b. Asuransi, dll = 0.002 x B F 600.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 64,697.03 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 166,800.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 137,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 26,250


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 37,500.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,571.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 392,407.14 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 457,104.17 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Liter
5. Bahan Bakar Solar Ms 13,900.00 Liter
6. Minyak Pelumas Mp 55,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 80-140 HP E10
2. Tenaga Pw 80.0 HP 572,858.83
3. Kapasitas Cp 0.50 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,425,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 142,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23740 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 152,230.44 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,425.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 153,655.44 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 133,440.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 110,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 62,344 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 89,062.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,571.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 419,203.39 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 572,858.83 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Liter
5. Bahan Bakar Solar Ms 13,900.00 Liter
6. Minyak Pelumas Mp 55,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan GENERATOR SET E12
2. Tenaga Pw 180.0 HP 618,123.99
3. Kapasitas Cp 180.0 KVA
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 215,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 21,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23740 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 22,968.10 Rupiah
W

b. Asuransi, dll = 0.002 x B F 215.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 23,183.10 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 300,240.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 247,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 9,406 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 13,437.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,571.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 594,940.89 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 618,123.99 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Liter
5. Bahan Bakar Solar Ms 13,900.00 Liter
6. Minyak Pelumas Mp 55,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan MOTOR GRADER >100 HP E13
2. Tenaga Pw 125.0 HP 683,034.04
3. Kapasitas Cp -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,300,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 130,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23740 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 138,876.89 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,300.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 140,176.89 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 208,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 171,875.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 56,875 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 81,250.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,571.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 542,857.14 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 683,034.04 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Liter
5. Bahan Bakar Solar Ms 13,900.00 Liter
6. Minyak Pelumas Mp 55,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WHEEL LOADER 1.0-1.6 M3 E15
2. Tenaga Pw 120.0 HP 573,624.55
3. Kapasitas Cp 1.5 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 860,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 86,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23740 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 91,872.41 Rupiah
W

b. Asuransi, dll = 0.002 x B F 860.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 92,732.41 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 200,160.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 165,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 37,625 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 53,750.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,571.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 480,892.14 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 573,624.55 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Liter
5. Bahan Bakar Solar Ms 13,900.00 Liter
6. Minyak Pelumas Mp 55,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TANDEM ROLLER 6-8 T. E17
2. Tenaga Pw 60.0 HP 335,318.71
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 2.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 5,000.0 Jam
c. Harga Alat B 910,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 91,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.54544 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 89,342.56 Rupiah
W

b. Asuransi, dll = 0.002 x B F 364.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 89,706.56 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 100,080.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 82,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 15,925 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 22,750.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,571.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 245,612.14 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 335,318.71 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Liter
5. Bahan Bakar Solar Ms 13,900.00 Liter
6. Minyak Pelumas Mp 55,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TIRE ROLLER 8-10 T. E18
2. Tenaga Pw 60.0 HP 307,102.98
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 2.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 5,000.0 Jam
c. Harga Alat B 710,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 71,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.54544 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 69,706.83 Rupiah
W

b. Asuransi, dll = 0.002 x B F 284.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 69,990.83 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 100,080.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 82,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 12,425 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 17,750.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,571.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 237,112.14 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 307,102.98 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Liter
5. Bahan Bakar Solar Ms 13,900.00 Liter
6. Minyak Pelumas Mp 55,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. E19
2. Tenaga Pw 60.0 HP 389,042.36
3. Kapasitas Cp 8.000 Ton
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,500.0 Jam
c. Harga Alat B 960,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 96,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.28859 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 99,737.22 Rupiah
W

b. Asuransi, dll = 0.002 x B F 768.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 100,505.22 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 100,080.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 82,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 33,600 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 48,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,571.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 288,537.14 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 389,042.36 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Liter
5. Bahan Bakar Solar Ms 13,900.00 Liter
6. Minyak Pelumas Mp 55,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. U R AI AN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L. E23
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4,000.0 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 355,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 35,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23740 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C) xD E 37,924.07 Rupiah
W

b. Asuransi, dll = 0.002 x B F 355.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 38,279.07 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 166,800.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 137,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 15,531 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 22,187.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 15,785.71 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8,571.43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 366,375.89 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 404,654.97 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6.00 % / Tahun
2. Upah Operator / Sopir U1 15,785.71 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 8,571.43 Rp./Jam
4. Bahan Bakar Bensin Mb 13,900.00 Liter
5. Bahan Bakar Solar Ms 13,900.00 Liter
6. Minyak Pelumas Mp 55,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

You might also like