- Project Management= =
P Measures of project failure:
Failure to establish upper-management
commitment to the project
Lack of organization’s commitment to the
methodology
Taking shortcuts through or around the
methodology
Poor Project management:Project Life Cycle
Purpose
4 Stretesic Fit
* Objectives
Senpe (erat)
nemense
Drat Seneca
Budget Estimate
Scope Final
Select
Team Menbers
Plan Deliverakios-
uaiyP ian
Baseline Buicert
Risk Reuister
Business Case
Approvals
‘Communication F tary
Production of
_ Key Deliverables
Monvior Corte
‘Quality
Management
Cost Management
Frisk Managem et
lecus Reealution
charge Cantal
Reperting
Communications
Colekrate!
“Contract Chasecit *
Teamn Feedback 5
oe crn ieee
turner action
Prost irsplomenttion
Review
Saulé Comsmiting,aa
a
- What is Project Life Cycle? |
+ The attention that a project receives isn’t uniformly
distributed throughout its life span but varies from
phase to phase.
+ Most projects pass through the following five phases,
which tend to overlap at times:
Clean up
Conesptio |) petintion Implementatio_ Significance of Project Life
Cycle:
Olt defines:
» The phases of the project (time)
» The work performed in each phase (work)' Project Life Cycle
Phase 1
Concept
c
(Conceive)
Level of Total Effort
Phase 2
Planning i
2B
(Develop)
Phase 3
Execution
E
(Execute)
imeline:
Phase 4
Transfer
F
(Finish)
Identity need
+ Extabiich feasibility:
~ program. process
-sehematies
+ prelim budget,
+ project team
“financing
~ sks
+ Identify altematives:
+ Present proposal
+ Approval 10
proce
uw ever
+ Re-astess risks, alternatives
+ Present Project Briet
+ Obtain appraval to process ||
1
| Dewolop: I
1 cock aprons "
| —sketchos. outline drawings |
| coendards "
+ Conduct studies
I+ Select equipment M1
|“ Beooatim seanomics i
~ budget cash how
1 tnarcing i
[= schedule
1
1
+ Set uparganization
+ Working dae & specs
+ Design review
+ Procure equipmant
+ Procure consim services
+ Produce physical asset
+ Quality assurance/control
+ Verity performance:
+ Modify as required
+ Progress mentoring
| + Forecasts & reports
+ Deliver facility
Training operators
= Reviews & Accaptoncas
+ Rum up to capacity
+ Transtar materia
= Settle all accounts
+ Re-assign remaining team
‘Archive lessons learned
= Close all records
+ Deliver Final Report &
transfer responsiblity~ Conception/initiatior 7PRAcS,
+ Conception is the phase during which the project
idea finds genesis and germinates, out of:
Y the need to solve a problem,
Y the observance of one’s environment,
Y the drive to innovate something new.
* This phase is essential and if flawed, it may lead to
defective and dysfunctional projects.Definition Phase:
+ The definition phase of the project involves
developing the idea generated during Conception
phase.
+ It produces a document describing the project in
sufficient detail, covering all necessary aspects
like the manpower, materials, machinery, layout,
utilities and feasibility.Planning Phase:
* This phase starts almost immediately after the
conception phase and overlaps with both
definition and implementation phases.
* This phase involves the preparation for the
project to take — off smoothly and effects many
decisions related to the “project basics’.y Core Planning:
q Scope Definition en
im Activity Definition /---—
o Schedule Development en
Resource Planningry Facilitating Planning:
> Quality Planning
> Organizational Planning
> Staff Acquisition/ What is a Project?
» It is a group of unique, inter-related activities that
are planned and executed in a certain sequence to
create a unique product and services within a
specific time frame, scope and budget.
» The Project Management Institute (U.S.A.) hasImplementation Phase:
+ This phase is a period of “hectic activity”. During this
period, the idea starts materializing physically and
tangibly and for the first time, the project can be seen off
the paper.
+ Usually, 80-85 percent of the project work is done in this
phase using all techniques of project management.
Engineering moe | cm Comatiasoa :- Implementation Phase: (Contd)
= Project Plan Execution
* Complete Work Packages
* Information Distribution
= Scope Verification
= Quality Assurance Team Development
= Progress Meetings- Controlling:
* Controls are performed to regularly measure
project performance, to adjust project plans and
take preventive actions in anticipation of
possible problems.
De eed
(measurement)
Pe eet)
Planned to be?
See oT
Pee ed
Pree
Ct
(roe ety)_ Clean - up/Termination
Phase:
+ This is the transition phase in which the project is
handed over to the operators and/or agencies
responsible for maintaining it.
* This phase is a clean - up task in which all project
accounts are closed, Outstanding payments are
settled and dues are collected.(Contd)
+ Administrative Closure — generating necessary.
information to formally recognize phase or project
completion.
- Clean —up Phase
Contract Close-out — completion and delivery of
pro; ect deliverables and resolving open issues. It
includes:
¥ Purchase Audits
¥ Product Verification
v Acceptancea Synopsis:
| Projet Life Cycle LC)~ What is Project Management?
+ Project management is a system of procedures, practices,
technologies and know-how that enables the planning,
organizing, staffing, directing and controlling necessary
to successfully manage a project.
+ The primary challenge of project management is to
achieve all of the project goals and objectives while
honoring the preconceived constraints.e Project Manager: ~~
+ A project manager is the person responsible for
supervising a systems project from initiation to
conclusion.
ik
= Se de
rea wl iB
= ‘a 1 &_ Project characteristics
> Objective
» Unique activities
» Attainment of specific goal
» Specified time
> Interrelated activities
> Life-cycle- Project Parameters:
= Scope 2
= Quality__ Functions of Project.
Management:
+ Scoping - setting the boundaries of the project
+ Planning - identifying the tasks required to complete
the project
+ Estimating - identifying resources required to complete
the project
cheduling — developing a plan to complete the project__ Functions of Project
Management:
* Directing — coordinating the project
* Controlling - monitoring progress
* Closing — assessing success and failure—
, Measures of project success:
The resulting information system is acceptable
to the customers (e.g. users, managers).
= The system was delivered “on time.”
= The system was delivered “within budget.”