rerra URd edt sdfdeoca fafties
Wile Bharat Heavy Electricals Limited
‘URUU QIOR UAB, /TBG
ff ear construction Management
400/220kV substation extension, Mysore
Ref: TBSS/MYSORE/NOTICE/SLOW PROGRESS Date 29.10.2020
To,
M/s Sri Sai Sadguru Engineering and Erectors
#9-636-6, Rounaq Complex, Mydukur Road
Proddatur-516360
Dist: Kadapa (Andhra Pradesh)
Kind Attn: Sh. P. Nageswara Rao
‘Sub: Balance civil works of 400KV switchyard inclucing reactor and SPR for 400/220kV substation
extension at Mysore in Karnataka: Notice regarding slow progress of work.
Reference
1. Work Order: TBSM/ MYSORE/BAL_CIVIL/WC/01/20-21, Date 30.04.2020
Dear Sir,
This is in reference to subject work awarded to you vide work order, dated 30.04.2020. BHEL has already
requested you over phones and various emails to purchase the materials and deploy sufficient manpower to
complete the balance work. It has been observed that despite various commitments, no action has been
taken by M/s Sri Sai Sadguru Engineering and Erectors. As per your request, the detail specification and
sources of materials have also been communicated to you. The time extension granted to you has
already been expired on 30.09.2020. As on date following works are still balance:
é
SN | item Status Issue
1_| Road PCC Kerb stone = [Labour not available |
2 [Chain link] Only poles ere works completed. | Wire mesh not
fencing Plastering work for 230 mtrs length and fixing of wire | purchased. Labour not
| mesh and flat for 145 mts. lergth is balance. | available.
3 | Earth pit cover | 27 nos. earth pit cover balance | Material not purchased
a = | Labour not available.
It is once again requested to procure the required material and deploy sufficient manpower to complete the
balance work at the earliest.
In case no positive steps are taken by M/s Sri Sai Sadguru Engineering & Erectors to expedite the work,
BHEL will be left with no other option but to execute the balance work at ‘Risk and Cost’ of M/s Sri Sai
Sadiguru Engineering & Erectors as per terms and conditions of the contract for civil works
ywtraye*
(Nandial Vermnay
Sr. Manager/ TBS
Copy to:
AGM/TBSM, Noida: For necessary action
GM/ TSS, TBWS & TBTS