Open Access Charges:

Hon'ble Commission has approved Wheeling charge, Cross subsidy surcharge, additional
surcharge for the open access consumers. In case of an Open Access consumer procuring
power from RE source, the full Cross Subsidy Surcharge (CSS) as determined shall be
applicable. The charges for FY 2018-19 & FY 2019-20 are as follows:

Wheeling Charges / losses:


Wheeling Loss Wheeling Charges
Particulars
(%) (Rs./kWh)
FY September 2018-19
33 kV 6.00% 0.15
22 kV 7.50% 0.38
11 kV 9.00% 0.78
LT Level 12.00% 1.30
FY 2019-20
33 kV 6.00% 0.15
22 kV 7.50% 0.37
11 kV 9.00% 0.76
LT Level 12.00% 1.28

Cross Subsidy Surcharge:

Category FY Sept. 18-19 FY 2019-20


CSS Rs./ kWh CSS Rs./ kWh
HT Category – EHV (66 kV and above)
HT I (A): Industry 1.57 1.58
HT II : Commercial 2.52 2.59
HT IV: PWW 1.31 1.33
HT (IX)B: Public Service 2.02 2.07
HT Category –33 kV
HT I (A): Industry 1.55 1.59
HT II : Commercial 2.53 2.61
HT IV: PWW 1.37 1.41
HT (IX)B: Public Service 2.15 2.20
HT Category –22 kV
HT I (A): Industry 1.62 1.66
HT II : Commercial 2.55 2.59
HT IV: PWW 1.46 1.51
HT (IX)B: Public Service 2.15 2.20
HT Category – 11 kV
HT I (A): Industry 1.90 2.02
HT II : Commercial 3.08 3.19
HT IV: PWW 1.55 1.59
HT (IX)B: Public Service 2.53 2.67

Page 1 of 2
Additional Surcharge on wheeling:

The Commission has approved the Additional Surcharge of Rs.1.25 per unit to be
applicable with effect from 1st September 2018. The Additional Surcharge shall be
applicable to third party open access consumer and Captive users of Group captive power
plant in addition to open access consumer with prospective effect.

Operating Charges:
For Open Access Capacity <= 5 MW : Rs. 14,500 / Month.
For Open Access Capacity > 5 MW : Rs. 28,000 / Month.

Energy Banking Charges:

Banking Charges shall be in kind @ 2% of the energy banked.

Application Processing Fee:

Processing Fee per


Open Access Capacity G.S.T. (18%) TOTAL
Application
For Load up to 1 MW Rs. 14,500/- Rs. 2,610/- Rs. 17,110/-
For load more than 1 Rs. 22,000/-
Rs. 3,960/- Rs. 25,960/-
MW and up to 5 MW
For load more than 5 Rs. 44,000/-
Rs. 7,920/- Rs. 51,920/-
MW and up to 20 MW
For load more than 20 Rs. 75,000/-
Rs. 13,500/- Rs. 88,500/-
MW

Transmission Charges:
(The MERC in case no. 265 of 2018 dated 12.09.2018 has determined revision of intra-
state Transmission Charges /losses, as follows)

Voltage FY Trans. Power Transaction Types


level of Loss Medium Term/long Short Term/ Short term
drawl (%) term collective & Renewable
point (Rs/KW/Month) energy (Rs/KWh)
EHV, 33 Sept.18-19 199.75 0.27
KV and 3.30
19-20 213.46 0.29
below

Page 2 of 2