Professional Documents
Culture Documents
1. The activities and time estimates for a particular project are as follows:
Immediate time
in days
ACTIVITY Predecessor To Tm Tp Te
A - 7 8 15
B A 10 11 12
C A,B 5 7 9
D B, C 11 14 17
E D 5 7 9
F E 5 7 11
What is the critical path and expected project completion time? ANS.
b. Determine the expected projected completion time and critical path.
c. Using te, determine the earliest and latest activity times and slack times. Given ES=0 and
EF=LF.
Normal
Activity time crash time cost/day
A 6 12000
B 8 4000
C 4 7000
D 11 2000
E 5 7000
F 4 3000
Path ‘n=0 1 2 3 4 5
Activity
Crashed
Cost