You are on page 1of 1

Saura Import &Export Co., Inc v. DBP, G.R. No.

L-24968 April 27, 1972


Facts:
In July 1952, Saura, Inc., applied to Rehabilitation Finance Corp., now DBP, for an industrial
loan of P500,000 to be used for the construction of a factory building, to pay the balance of the jute mill
machinery and equipment and as additional working capital.  In Resolution No.145, the loan application
was approved to be secured first by mortgage on the factory buildings, the land site, and machinery and
equipment to be installed.
The mortgage was registered and documents for the promissory note were executed. But then,
later on, was cancelled to make way for the registration of a mortgage contract over the same property in
favor of Prudential Bank and Trust Co., the latter having issued Saura letter of credit for the release of the
jute machinery. As security, Saura execute a trust receipt in favor of the Prudential. For failure of Saura to
pay said obligation, Prudential sued Saura.
After almost 9 years, Saura Inc, commenced an action against RFC, alleging failure on the latter
to comply with its obligations to release the loan applied for and approved, thereby preventing the
plaintiff from completing or paying contractual commitments it had entered into, in connection with its
jute mill project.
The trial court ruled in favor of Saura, ruling that there was a perfected contract between the
parties and that the RFC was guilty of breach thereof.

Issue:
WON there is a perfected consensual contract?

Held:
YES. There was a perfected consensual contract, as recognized in Article 1934 of the Civil Code.
Article 1934.: An accepted promise to deliver something by way of commodatum or
simple loan is binding upon the parties, but the commodatum or simple loan itself shall not be
perfected until delivery of the object of the contract.
There was undoubtedly offer and acceptance in the case. The application of Saura, Inc. for a loan
of P500,000.00 was approved by resolution of the defendant, and the corresponding mortgage was
executed and registered. The defendant failed to fulfill its obligation and the plaintiff is therefore entitled
to recover damages. When an application for a loan of money was approved by resolution of the
respondent corporation and the responding mortgage was executed and registered, there arises a perfected
consensual contract.
However, it should be noted that RFC imposed two conditions (availability of raw materials and
increased production) when it restored the loan to the original amount of P500,000.00. Saura, Inc.
obviously was in no position to comply with RFC’s conditions. So instead of doing so and insisting that
the loan be released as agreed upon, Saura, Inc. asked that the mortgage be cancelled.The action thus
taken by both parties was in the nature of mutual desistance which is a mode of extinguishing obligations.
It is a concept that derives from the principle that since mutual agreement can create a contract, mutual
disagreement by the parties can cause its extinguishment.

You might also like