Professional Documents
Culture Documents
Page
Appendix:
2
The Road to Lean
3
What is Value?
Value-Adding Activities
7
Steps in Value Stream Mapping
Implementation N
Stop VSM
Justified?
Y
Develop Work Plan for Implementation
Analysis.
Implementation N
Stop VSM
Justified?
Volume/
Revenue Runners Repeaters Strangers Select a Product Family
Medium here N
Implementation
Earners
Stop VSM
Justified?
Low Y
Earners
10
Selecting a Product Family (contd.)
Weekly 1
Manual Electronic
Supermarket Schedules Operator
Information Flows
Kaizen
Daily
Priorities
Daily ship Daily
Schedule
2X per
month Shop SHIPPING
Orders
staging
To weld-area I
supervisor
2 days
I CUT I WELD#1 I WELD#2 I DEFLASH I PAINT I ASSEMBLY I
Rods 1 1 1 Subcontract 6
20 days 5 days 3 days 3 days 5 days 6 days 4 days
C/T = 15 secs C/T = 10/30 secs C/T = 10/30 secs C/T = 10/30 secs C/T = 195 secs
C/O = 15-60 mins C/O = 15-60 mins C/O = 15-60 mins C/O = 15-60 mins C/O = 10 mins
Uptime=100% Uptime=90% Uptime=80% Uptime=100% Uptime=100%
I M/CING I
Forgings
20 days 4 days
C/T = 30 secs
C/O = 120 mins
Uptime=100%
20 days 5 days 3 days 3 days 5 days 2 days 6 days 4 days
16
Costing the Wastes in the Value Stream Map
17
Costing the Wastes in the Value Stream Map (contd.)
• Number of workcenters.
• Purchase cost per machine.
• Installation cost.
• Depreciation over the life of the machine.
• Maintenance cost.
19
Parameters for Estimation of Quality Costs
20
Parameters for Estimation of Space Costs
21
Parameters for Estimation of Labor Costs
22
Parameters for Estimation of Transportation Costs
• Capital cost.
• Overhead cost rate per piece of equipment.
• Frequency of flow between all pairs of locations.
• Number of parts flowing between all pairs of locations.
• Distance traveled between all pairs of locations.
• Load/Unload time for each order at each machine.
• Number of pieces of equipment ex. forklifts, pallet
jacks, cranes, etc.
• Life of any piece of equipment.
• Average velocity of a move between any pair of
locations.
23
Parameters for Estimation of Queuing Costs
24
Parameters for Estimation of Inventory Costs
25
Reading the Current State Map
27
Reading the Current State Map (contd.)
• Why is batching necessary? Can we reduce the
setup times to facilitate smaller batches?
• Why is the average machine uptime low? Should
we initiate TPM programs to increase it?
• What are the reasons for scrap? Which processes
cause scrap? What are the root causes for why the
processes cause scrap? Were SPC, DOE, etc.
studies conducted to identify the root causes for
out-of-control processes?28
Reading the Current State Map (contd.)
32
Best Practices for Eliminating Wastes
Best Practices
• Make-to-Order.
Wastes • Optimize Layout.
• Over-production • Setup Reduction.
• Waiting • Total Productive Maintenance.
• Multi-function Workers.
• Transport
• Pull Scheduling/Production
• Inappropriate Processing
Smoothing/FCS.
• Unnecessary Inventory • Line Balancing to Takt Times.
• Unnecessary Motion • One-Piece Flow.
• Defects • Supplier Control for JIT.
• Time Study/Motion Study.
• Quality Control/DOE.
33
• Design for Manufacture.
Drawing the Future State Map
• The Future State Map is the improved flow
diagram for material flow and a „How it
should be‟ map for the (desired
configuration of the) production system . Select a Product Family
• This map should be the basis for the Draw the Current State Map
implementation road map to identify and Draw the Future State Map
Daily
Weekly OXOX
CUT
WELD + DEFLASH Max. 1200 pieces PAINT Empty Daily ASSEMBLY SHIPPING
C/T = 30 secs
C/O = 30 mins
7 days Same day
1 day 1 days 1 days 1 days
30 secs 90 secs 195 secs
35
Comparison of the Current and Future State Maps
36
Decision-making with the Current State Map
37
How much to improve a Current State Map?
• Plot the potential benefits
versus the cost to implement
each of the changes identified
to realize the Future State Potential Benefits
Map. Stop VSM
39
Planning for Implementation (contd.)
• Regular reviews should
be conducted by the
Value Stream Manager
to ensure smooth
progress of the project.
• Complete a project to
the fullest expectations
set initially before
moving to the next
project. 40
Starting the Implementation
• Focus on the pacemaker process i.e. the most
downstream process (the “Drum” in TOC speak).
• Create a detailed implementation plan outlining the
following details:
– Tangible goals to be achieved, ex. 1 day of WIP at the
bottleneck machine.
– Process improvement activities to achieve this goal.
– Owner (Person/Team responsible).
– Completion Date.
– Performance measures to evaluate the impact of each
suggested improvement to achieve the Future State
Map.
41
Starting the Implementation (contd.)
• OR, using the Current State Map,
brainstorm to identify a pilot project that
seeks to demonstrate the impact of each of
the critical “tools of Lean Manufacturing”
ex. Cells, Quality, Setup Reduction, 5S,
Process Standardization, Andon, Poka-
Yoke. Execute these projects in parallel and
develop a report that describes the how-to’s
for each tools and also shows how each of
them adds value by improving Delivery,
Cost and Quality.
42
Sustaining the Continuous Improvement Program
45
Preliminary Comments
• “Learning to See” suggests adding extra
elements to the data box as and when
applicable
• Add links to VSM of another product in
case of sharing resources
• Capacity constraints, Yield and other
calculations can be easily done with the
information provided on the VSM.
46
IE Techniques to enhance VSM
Point of Comparison: Single Part vs. Part Family
VSM IE Techniques
Representative part from a MultiProduct Process Chart
family is chosen based on could represent the entire
routings of similar parts family
47
IE Techniques to enhance VSM
Product Family
Current State Drawing
Future State Drawing
Plan and Implementation
Nonidentical
routings, but
one can be
merged into the Identical routings, but non
other identical operation times
48
IE Techniques to enhance VSM
Point of Comparison: Material Flow
VSM IE Techniques
Flow shown on a straight Material Flow Diagram
line •Existing Facility on a 2D Plane
•Flow Quantities
•Travel Distances
FromTo Chart
•Flow Quantities
•Total Picture of Family
49
IE Techniques to enhance VSM
Point of Comparison: Relationships between Departments
VSM IE Techniques
Process boxes representative of •Relationship Charts
department/workstation •FromTo charts
No spatial/activity relationships •Multiproduct Flow Diagrams
represented
50
IE Techniques to enhance VSM
Point of Comparison: Product as an Assembly of Components
VSM IE Techniques
Follows path of main Assembly Precedence Diagram
product and assumes 1. Considers all subassemblies
availability of Operations Process Chart
components at all 1. Shows operation sequences performed on
assembly points – no each part during fabrication of final product,
information on VSM for including their precedence relationships
each component 2. Includes all operations, movements,
inspections, delays, decisions and storage
activities in material flows.
51
IE Techniques to enhance VSM
Point of Comparison: Takt Time vs. Line Balancing
VSM IE Techniques
Tries to match cycle time to takt time Assembly Line Balancing algorithms
that map demand onto station cycle
times
Finite Capacity Scheduling
52
IE Techniques to enhance VSM
Point of Comparison: Scheduling
VSM IE Techniques
•GoSee scheduling •Job sequencing rules
•FIFO sequencing rule SPT (Shortest Processing Time), EDD (Earliest
Due Date), MWKR (Most Work Remaining), CR
•Single timeline (Critical Ratio), SLK (Minimum Slack), LIFO (Last In
First Out)
•Gantt Chart to integrate multiple timelines
53
IE Techniques to enhance VSM
Point of Comparison: Material Control
VSM IE Techniques
PUSH Icons, PULL loops, FIFO and MRPII for demand forecasting
Flow Icons
Signals – Kanban Post and Card Finite Capacity Scheduling for shop
loading
EOQ models for transfer batch
selection
Master Production Scheduling models
Kanban Lot sizing and Supermarket
Capacity analyses
54
IE Techniques to enhance VSM
Point of Comparison: Material Handling System
VSM IE Techniques
No Consideration – just PUSH / PULL Dynamic Routing Algorithms
icons w/ inventory levels recorded in
Triangles
Transfer Batch Size = ? Lineofsight visual layout
No scheduling of material handlers Shopfloor control methods
55
IE Techniques to enhance VSM
Point of Comparison: Computerized vs. Manual methods
VSM IE Techniques
Tedious manual method Use of computers with softwares like
Excel, Visio and Microgafx Flowcharter
Paper size restricts quantity of No restrictions on the detail of information
information captured – show/hide the necessary information
depending on analysis
No provision for zooming (or added Spreadsheets promote arithmetic
information) on a particular process calculations
box
Data recorded on VSM does not Simulation allows study of dynamic Value
encourage arithmetic calculations Streams
56
IE Techniques to enhance VSM
Point of Comparison: Resource Sharing
VSM IE Techniques
Does not consider “Process Boxes” as Value Network Mapping (VNM)
resources shared by other streams
Computer models for capacity
constrained shop loading and
scheduling
57
IE Techniques to enhance VSM
Point of Comparison: Macro vs. Micro Level
VSM IE Techniques
Modeling tool at Production Control Modeling Tools at Manufacturing
level Engineering level
•Overall picture of the entire •Machine level analyses
organization •Individual departments analyzed in
•Manager’s view of overall detail
performance •Standards and procedures from an
operators point of view
58
IE Techniques to enhance VSM
Point of Comparison: Graphic Communication Tool
VSM IE Techniques
Managers eyes glaze over at pretty Process Flow Chart uses as few as 6
pictures of VSM symbols with clear meanings
Charts reviewed for compliance with More technical information than VSM
drawing standards instead of technical that can be computer modeled using
content and shopfloor status Visio, Simul8 or Arena
59
IE Techniques to enhance VSM
Point of Comparison: Stochastic Behavior of Processes
VSM IE Techniques
Deterministic cycle times Considers stochasticity of process
times
Variaions in operation times require Simulation – easy changes in values
that the value streams must be gives quick results for “whatif”
mapped repeatedly scenarios
60
VSM + IE Techniques
Conclusion:
VSM is a good starting point to map any process at
a Macro level. But, you need additional Industrial
Engineering techniques for complete analysis at the
Macro and Micro levels.
61
Foundation for Value Network
Mapping (VNM)
• Developers of VSM state that “many value streams have
multiple flows that merge. Draw such flows over one
another. But do not try to draw every branch if there are
too many. Choose the key components first, and get the
others later if you need to” (Rother & Shook, 1999, p. 19).
• High variety facilities have multiple product flow routings
which are usually dissimilar and use capacity at shared
resource locations.
62
Foundation for Value Network
Mapping (VNM) (contd.)
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11
COMPONENTS
VNM APPLIES VERY WELL AT
THIS LEVEL
ASSEMBLY 1
ASSEMBLY 2
ASSEMBLIES
VSM APPLIES VERY WELL AT
THIS LEVEL 63
Goals of Value Network
Mapping (VNM)
• To map the complete network of flows in a complex
Value Stream.
• To computerize basic Industrial Engineering (IE) tools for
material flow mapping, using a software package for
material flow analysis PFAST (Production Flow Analysis
and Simplification Toolkit).
• To integrate the material flow mapping power of PFAST
with the Finite Capacity Scheduling (FCS) power of
PREACTOR.
64
Assembly utilized for VNM study:
ED1M00932
65
VNM: Methodology for
Enhancement of VSM
VSM VNM
Form a Product Family: Tool used Form a Product Family: Tools used
1. ProductProcess Matrix Clustering 1. ProductProcess Matrix Clustering
(Downstream processes close to the 2. ProductComponent Matrix Clustering
customer end of the value sream are used 3. PQRS Analysis
to identify a product family)
Visualize the Flow: Tools used
1. B.O.M for the product
2. Operations Process Chart
3. MultiProduct Process Chart (MPPC)
4. Flow Diagram
Collect Data: Tool used
1. Enhanced Flow Process Chart
Merge Similar Routings: Tool used
1. Modified MultiProduct Process Chart
(MMPPC)
Draw the Current State Map:Tool used Draw the Current State Map: Tools used
1. Collect data and draw the map using a 1. MMPPC
pencil 2. Enhanced FPC
Develop a Future State Map
Develop an Action Plan
66
Implement the Action Plan
VNM: Operations Process Chart
for ED1M00932
GANG TUM
NOTCH SHEAR
DRILL GRIND
ROUGH
GRIND
MIG MIG
WELD WELD
ROUGH ROUGH
GRIND GRIND
ASSMY
INSPEC
67
VNM: MultiProduct Process
Chart (MPPC) for ED1M00932
68
VNM: Flow Diagram
for ED1M00932
69
VNM: Enhanced Flow Process
Chart (FPC) for ED1M00932
70
VNM: Modified MultiProduct Process
Chart (MMPPC) for ED1M00932
71
VNM using PFAST and Preactor/FCS
for ED1M00932
HAEGAR ASSLY
1 X/Y
BURTON X/Y
3
X/Y
TU GRIND 1 3 X/Y X/Y
Value Network Map TS GRIND
GSW S CNC BR
2 X/Y
X/Y 2 3
X/Y
1 1 2 6
5 X/Y
X/Y
X/Y
1 X/Y
PAINT
VNM
X/Y
SHEAR 1 1 1 L MECH BR
X/Y
X/Y
NOTCHER 1
1
Gantt
Chart
72
VNM Symbols for
Enhancement of VSM
• VSM is a mapping tool that maps not only material flows
but also information flows that signal and control the
material flows.
• This visual representation helps to identify the value
adding steps in a value stream and eliminate the non
value adding steps, or waste (muda) in product flow
paths.
73
VSM + Layout = Flow Diagram
Process Box
I ?
300 pcs/day
C/T = 45 secs
Inventory
C/O = 30 mins
3 shifts
2% scrap
Data Box
Process Box
C/T = 45 secs
C/O = 30 mins
3 shifts
2% scrap
Data Box
Process Box I
300 pcs/day
Inventory
?
C/T = 45 secs
C/O = 30 mins
3 shifts
2% scrap
Data Box
74
VNM Symbols for
Enhancement of VSM (contd.)
This icon indicates the absence of a clear lineof
sight between consecutive process locations.
Hence, placing this icon between two consecutive
process boxes will communicate the impact of
LineofSight layout on the material and information flows.
_____ ft This icon indicates the distance (in feet) between
consecutive processes and will be placed between
Material Handling each pair of process boxes.
Distance
75
VNM Symbols for
Enhancement of VSM (contd.)
These icons are traditional IE icons used to
indicate the Quantity and Quality Inspection, if
used, done at each process box. Also, the
resources i.e. time and # of operators required will
Quantity and Quality be indicated on them.
Inspection
This symbol indicates the choice of material
handling equipment – forklift, conveyor, push cart,
hand cart, manual, etc. and will be placed
Material Handling between every pair of process boxes.
Equipment
76
VNM Symbols for
Enhancement of VSM (contd.)
This symbol indicates the types of communication
systems in use on the shopfloor:
M – for material handling between interacting
processes/work centers.
S – for support functions that support the
Communication operators at each workcenter ex. Production
System Control and Maintenance.
Q t , N This symbol indicates the transfer batch size (Q t )
and the transfer frequency (N) i.e. total number of
transfer batches of a particular part type being
Transfer Batch moved between two consecutive process
Size and its
locations.
Frequency
77
VNM Symbols for
Enhancement of VSM (contd.)
This icon indicates the sequencing rule used to run
SEQ orders at each process box, such as:
FIFO (First In First Out); SPT (Shortest Processing
Sequencing Rule Time); EDD (Earliest Due Date); MWKR (Most
Work Remaining); CR (Critical Ratio); SLK
(Minimum Slack); LIFO (Last In First Out)
This icon indicates the percentage of available
capacity at each process that will be allocated to a
particular product family.
78
VNM Symbols for
Enhancement of VSM (contd.)
Material Handling
_____ ft
Distance
Material Handling
Distance
Transfer Batch Size
Q t , N and its Frequency
Example of a material handling data box between
any two process boxes.
79
Pros of VNM
• VNM analyses all the value streams of a product family
with dissimilar routings.
• VNM analyses all flows for a product family that merge
at assembly points or at shared locations.
• VNM enables analysis of processspecific parameters (like
available time at a process) with respect to part specific
parameters like cycle times for all parts that share that
process.
• VNM integrates various visual tools of IE with a VSM
to enable a comprehensive analysis to eliminate wastes.
80
Pros of VNM (contd.)
• VNM utilizes Finite Capacity Scheduling to estimate and
reduce the production lead time for a product family.
• VNM has an additional set of icons suited for highvariety
facilities.
• VSM has no mention of process loops. VNM addresses
this issue with the inclusion of a symbol to map the loop.
81
Cons of VNM
• VSM recommends drawing the map by hand on a 11’’ x
17’’ ledger size paper. VNM may require many more
pages.
• VSM does not mention for duplication of process boxes as
required by the routing of the parts. VNM fails when a
process is visited by the chosen product family multiple
times and at intervals of considerable sequence of
operations.
• VNM does not give a future state layout perspective.
82
Cons of VNM (contd.)
• VNM analyses the flow of the product family through
shared locations. Hence, in part, it is a merged
operations process chart for the product family.
• VNM requires detailed collection of data with domain
knowledge to prove beneficial. For example, a
subsequence of operations in the route of the product
family could be represented by a single process box. This
would reduce the number of process boxes on the map
making it easy to read and analyze.
• VNM is timeconsuming and requires time no less then
would be required for a fullfledged project undertaking.
83
Value Stream Mapping from an Industrial Engineering Viewpoint
Sadono C. Djumin, Yuri Wibowo and Shahrukh A. Irani1
Department of Industrial, Welding and Systems Engineering
The Ohio State University
Columbus Ohio 43210
Objectives
Introduction
Constraints placed on the Japanese car manufacturing industry after the World War II led
Taiichi Ohno of Toyota Motor Corporation to pioneer a new type of production system –
Toyota Production System (TPS) – that was ―so different, and so much better than mass
production‖ as to guarantee a new type of manufacturing system
(http://www.lean.org/Lean/Community/Resources/thinkers2.cfm). Jim Womack and Dan
Jones enhanced the original concepts of TPS into the framework of Lean Thinking that
was first introduced in the US in the Fall of 1996. It extends continuous improvement
efforts to reduce the costs of serving the customer/s beyond the physical boundaries of a
manufacturing facility, by including the suppliers, distributors and production system that
support the manufacturing function.
Lean enterprises organize their activities with less effort, space, inventory, defects, and
product development time in comparison with traditional mass production systems. These
improvements and cost reductions are achieved by eliminating the muda (wastes)
associated with all the activities. Wastes are defined as ―all activities that consume
resources (add costs to the product) but contribute zero value to the customer‖.
1
Contact Information: irani.4@osu.edu (email), (614) 688-4685 (phone), (614) 292-7852 (fax)
84
Five Steps for Implementation of Lean Thinking2
3. Flow
This step identifies and eliminates any muda-causing structures or activities in the
product flow that increase the manufacturing lead-time. It encourages companies
to look at the physical distance that separates all pairs of functional departments
that are utilized during the order realization process to fulfill customer demand.
The most dramatic reductions in total lead time will be achieved by a product-
focused organization (focused factory).
4. Pull
After the wastes in the system are reduced, a lean enterprise would use a strategy
of pulling inventory through the system based on actual customer product
demand, in contrast to the traditional approach of pushing inventory through the
system. In a pull environment, the tendency of overproduction, which leads to
increased inventory levels, can be controlled. In addition, letting the customers
pull products as needed will eliminate the need for (unreliable) sales forecasts.
5. Perfection
This concept reminds the lean enterprise to continuously improve the production
system, and move its performance towards perfection. The entire process of lean
implementation must be a never-ending process since, in practice, the process of
reducing effort, time, space, mistakes, and costs can never be perfect. For
example, for further lean transformations in a company that wishes to offer a
better product as per customer desires, it is necessary to go back to Step 1 in this
5-step process.
2
http://www.lean.org/Lean/Community/Registered/Steps.cfm?
85
Value Stream Mapping (VSM)
Unlike traditional process mapping tools, VSM is a mapping tool that maps not only
material flows but also information flows that signal and control the material flows. This
visual representation facilitates the process of lean implementation by helping to identify
the value-adding steps in a value stream and eliminating the non-value adding steps, or
wastes (muda).
Production
Control
Note:
Information Flow
Material Flow
Using a VSM process requires development of maps: a Current State Map and a Future
State Map. In the Current State Map, one would normally start by mapping a large-
quantity and high-revenue product family. The material flow will then be mapped using
appropriate icons in the rich VSM icon template. The product will be tracked from the
final operation in its routing to the raw material storage. Relevant data for each operation,
such as the current schedule (push, pull, order dispatching rules in effect at any process
ex. FIFO) and the amount of inventory in queue, will be recorded. The information flow
is also incorporated to provide demand information, which is an essential parameter for
determining the ―pacemaker‖ process in the production system. After both material and
information flows have been mapped, a time-line is displayed at the bottom of the map
showing the processing time for each operation and the transfer delays between
operations.
The time-line is used to identify the value-adding steps, as well as wastes, in the current
system. The comparison between the processing times and the takt time (calculated as
Available Capacity/Customer Demand) is a preliminary measure of the value and waste.
This takt time is mostly used as an ideal time for each operation to achieve (ideally, the
cycle time for each operation should be the takt time).
Based on the analysis of the Current State Map, one then develops a Future State Map by
improving the value-adding steps and eliminating the non-value adding steps (waste).
86
According to Rother & Shook, there are seven guidelines, adapted and modified based on
the concepts of Lean Thinking, that can be followed when generating the Future State
Map, or lean value stream (Rother & Shook, p.44-54):
Helps to unify several IE techniques for flow analysis, such as Production Flow
Analysis (PFA), Business Process Reengineering (BPR), and Process Analysis
and Improvement (PA&I) that, to date, have been taught and implemented in
isolation.
Provides important descriptive information for the Operation and Storage process
elements that, to date has not been captured in standard Flow Process Charts used
by IE’s.
87
Fails to relate Transportation and Queuing delays, and changes in transfer batch
sizes due to poor plant layout and/or material handling, to operating parameters
(ex. machine cycle times) and measures of performance of the manufacturing
system (ex. takt time)3.
Lacks any worthwhile economic measure for ―value‖ (ex. profit, throughput,
operating costs, inventory expenses) which makes it similar to the Flow Process
Charting technique used by IE’s.
Lacks the spatial structure of the facility layout layout, and how that impacts
inter-operation material handling delays, the sequence in which batches enter
machine queues, container sizes, trip frequencies between operations, etc.
Tends to bias a factory designer to consider only continuous flow, assembly line
layouts, kanban-based Pull scheduling, etc. that are suitable mainly for HIGH
volume and LOW variety manufacturing systems4.
Fails to show the impact on WIP, order throughput and operating expenses of in-
efficient material flows in the facility ex. backtracking, criss-cross flows, non-
sequential flow, large inter-operation travel distances, etc.
Fails to handle complex BOM’s that translate into branched and multi-level
Operation Process Charts and Flow Diagrams for the products.
Lacks the capability, due to the manual process of creation, for rapid development
and evaluation of multiple ―what if‖ analyses required to prioritize different
alternatives for improving a Current State Map when time and/or budget
constraints exist.
3
Reasons for this could be (a) because the impact of a poor facility layout on order throughput, product
quality and operating costs is assumed to be trivial or (b) superimposing all the information contained in a
map onto a CAD drawing of the facility layout would reduce the readability of the map.
4
These are design and operational strategies that are suited mainly for low-variety high-volume (LVHV)
facilities, such as automotive OEM’s and their Tier 1 or Tier 2 suppliers, and not high-variety low-volume
(HVLV) facilities such as jobshops and Make-To-Order companies.
5
This could be easily and effectively done if computer simulation were used to develop and model the
performance of the system represented by any map.
88
VSM: The Traditional Approach VSM: An Enhanced IE Approach
Develop a Current State Map 1. Obtain the CAD drawing of the current facility
layout.
2. Map the material flow for the product family
onto the layout to generate a Flow Diagram using
the enhanced set of VSM icons.
3. Enhance the Flow Diagram into a Flow Process
Chart by recording different types of
wastes/delays in the process flow.
4. Expand the Flow Process Chart by incorporating
all elements of standard VSM analysis.
Develop a Future State Map 1. Use VSM and PA&I thought processes for analysis
of the Current State Map to identify wastes.
2. Develop a Future State Map by eliminating
different types of wastes in the Current State Map.
3. Develop a layout for the product family based on
the Future State Map
In order to support universal process mapping, a set of icons that is rich in functionality
and flexible in application must be developed. The icons contained in each of several IE
tools – FPC, BOPC, PA&I – that are similar to VSM are tabulated in Appendices A, B,
C, respectively. This study is based on the observation that, while the icons available in
the IE tools are similar to those used for VSM, still the VSM icons capture a lot of
process flow aspects that the IE tools ignored! Appendix D presents a table that compares
the icons in various IE tools with those used for VSM.
The following table presents a potential integrated set of icons for universal process
mapping by combining the capabilities of the different tools:
QUALITY INSPECTION
90
TRANSPORTATION This icon is used when the product produced is ―pulled‖ in
a certain amount or quantity from the supplying process to
the supplied process.
PULL arrow
This icon is referred to as CONWIP. It is used in the
situation where the supplying process only produces when
the buffer in front of a bottleneck process (or pacemaker),
CONWIP arrow that holds work-in-progress (WIP) inventory, allows a
space for new inventory to be added. If the WIP buffer is
full, the supplying process must stop producing until the
next (supplied to) process has used up some of the existing
inventory. This will prevent the supplying process from
overproducing.
This icon represents the planned accumulation of
I inventory at the starting and ending points of the entire
product flow that represent the storage of raw material and
finished goods inventories, respectively.
STORAGE Raw Material and
Finished Goods
This icon represents ―safety stock‖ that protects the system
S against sudden fluctuations in customer demands. It is
intended as a temporary, not a permanent storage of stock;
hence, there should be a management policy on when to
Safety Stock use it.
This icon represents the unscheduled accumulation of
partially finished parts or products. The accumulation is
called ―unscheduled‖ when the parts do not have a definite
schedule when to be produced next. While mapping, one
WIP accumulation needs to give a rough estimate on the amount of
DELAY accumulation of this type of WIP.
When mapping the flow of people, this will represent the
delays experienced by the operator while processing the
product ex. the time wasted while waiting for material to
arrive.
Operator Delay
INFORMATION This is the icon generally used to represent flow of
FLOW information.
91
APPENDIX A: FLOW PROCESS CHARTING (FPC) ICONS6
Subassembly,
storage. Assembly, or
Occurs when information is given or received or when planning or Disassembly.
calculations take place.
Represents the period of time when a person is doing work.
RED
Transportation (or
TRANSPORTATION material handling )
activities
Occurs when an object is moved from one place to another, except when such
movements are a part of the operation or are performed by the operator at the ORANGE
Transportation
6
Source: Niebel & Freivalds, p. 32
7
The recommended colors are adapted from the International Materials Management Society’s Standard
Color Codes for use in layout planning and materials handling analyses. These colors are used to classify
various areas in the plant. The colors of the different activity areas are particularly useful when attempting
to consolidate similar functional activities within a plant, e.g. centralized support functions or centralized
storage areas and to identify the extent of floorspace dedicated to non-value adding activities.
92
Storage activities
STORAGE ORANGE
Occurs when an object is kept and protected against unauthorized
YELLOW
removal.
Occurs when materials, parts, or products are accumulated as per a
prior plan.
Retention
VOLUME INSPECTION
BLUE
Occurs when a product is examined for identification purposes or for
validation of quantity or amount against a pre-specified level to assess whether
a discrepancy exists.
93
QUALITY INSPECTION
94
APPENDIX B: BUSINESS AND OFFICE PROCESS
CHARTING (BOPC) ICONS8
APPROVAL
Used to show flow of information.
PAPERWORK FLOW
Used to show flow of information by telephone or
computer.
TELEPHONE
Used to show computer processing.
PROCESSING
Indicates delay in a process, such as waiting for approval.
DELAY
8
Source: Meyers & Stephens, p. 332.
95
APPENDIX C: VALUE STREAM MAPPING (VSM) ICONS9
This icon is generally placed under other icons that have significant
information/data that will be required for analyzing and observing the system
being mapped.
C/T (Cycle Time) — time (in seconds) that elapses between one part
coming off the process to the next part coming off,
C/O (Changeover Time) — time to switch from producing one product on
the process to another
Uptime— percentage time that the machine is available for processing
EPE (a measure of production rate/s) — Acronym stands for ―Every Part
Every___‖.
Number of operators — use OPERATOR icon inside process boxes
Number of product variations
Available Capacity
Scrap rate
Transfer batch size (based on process batch size and material transfer
9
Source: Rother & Shook, Appendix A
96
rate)
This icon represents the accumulation of inventory between two processes. While
mapping the current state, the amount of inventory can be approximated by a
quick count, and that amount is noted beneath the triangle. If there is more than
one inventory accumulation between processes, draw this icon to represent the
inventory in each location.
INVENTORY
This icon is also used to represent storage locations for raw materials and
finished goods, since they represent the start and finish of the material flow for
producing any product in a facility.
This icon represents the movement of raw materials from suppliers to the
Receiving dock/s of the factory. Or, the movement of finished goods from the
Shipping dock/s of the factory to the customer/s.
FINISHED GOODS TO
CUSTOMER
This icon represents the type of transportation mode being used inside or outside
the facility. The frequency of shipping is recorded inside the icon.
TRUCK
This icon represents the ―pushing‖ of material from one process to the next
process in a manufacturing routing. Push means that a process produces
something regardless of the actual needs of the downstream process that will
consume its outputs.
PUSH
This icon represents an inventory ―supermarket‖ (or buffer). Depending on the
predictability of the customer demand, the material flow through the system
might be continuous (one-piece flow). If the demand is fairly predictable, then
the flow of the product could be continuous, thereby eliminating the need for a
supermarket. However, when continuous flow (one-piece flow) fails in a system
and the upstream process must operate in batch mode, then this icon should be
SUPERMARKET located between two processes in order to (a) halt overproduction and (b) provide
visual feedback on customer requirements. The storage capacity of the
supermarket for various items in inventory will control the amount of product
withdrawals from the supermarket, either to supplying or receiving processes.
This icon indicates that a ―pull‖ system of material flow control being used to
connect a SUPERMARKET icon with the manufacturing process that supplies
product into the supermarket.
PULL WITHDRAWAL
97
This icon is synonymous to CONWIP (constant work in process). It is used
where the supplying process only produces when the FIFO storage lane has an
empty space for new product additions. If the FIFO lane is full, then the
supplying process must stop producing until the next process has used up some
FIRST IN FIRST OUT of the inventory stored in the lane. This will prevent the supplying process from
(FIFO) overproducing. The maximum quantity in the FIFO lane should be recorded.
This icon represents a ―shopping list‖. It is a note card or device that instructs the
material handler to get and transfer parts from a supermarket to the receiving
process. The material handler (or operator) will go to the supermarket and
WITHDRAWAL withdraw the desired number of parts needed at the receiving process.
KANBAN
This icon is used whenever the on-hand inventory levels in the supermarket
between two processes drops to a trigger or minimum point. When a Triangle
Kanban arrives at a supplying process, it signals a changeover and production of a
predetermined batch size of the part noted on the Kanban.
This icon represents a pull system that gives instruction to subassembly processes
to produce a predetermined type and quantity of product, typically one unit,
without using a supermarket.
SEQUENCED –PULL
BALL
98
This icon is a tool to batch kanbans in order to level the production volume and
mix over a period of time.
LOAD LEVELING
KAIZEN LIGHTENING
BURST
This icon is used to represent an inventory ―hedge‖ (or safety stock) against
problems such as downtime, to protect the system against sudden fluctuations in
customer orders or system failures. Notice that the icon is closed on all sides. It is
intended as a temporary, not a permanent storage of stock; thus; there should be a
clearly-stated management policy on when such inventory should be utilized by
operators.
SAFETY STOCK
This icon represents an operator. It is usually placed in a MANUFACTURING
PROCESS box to indicate the number of operators working at a particular
workstation.
OPERATOR
99
APPENDIX D: COMPARISON OF INDUSTRIAL
ENGINEEERING TOOLS AND VSM ICONS
Operation
This icon is more specific about any operations In VSM, both icons represent operations, processes, or
performed in a department or between two process departments.
departments.
Transportation
Does not describe the type of material flow
occurring between operations/processes.
100
Storage
This icon represents a scheduled accumulation of
materials, parts, and products. The type of This icon is used only to represent safety stock to
inventory could be: safeguard against any fluctuations that might occur in
Raw materials the system. In VSM, this is distinguished from Work-In-
WIP Progress (WIP) that is viewed as ―bad‖ inventory (and
Finished goods should be reduced), whereas safety stock is viewed as
Safety stock ―good‖ inventory and should be kept under lock and key.
Typically, this means getting permission from a high-
level manager, who might want to study the need for
using safety stock using a Root Cause Analysis and
identify solutions before giving any permission to access
this safety stock
Delay
This represents any unscheduled accumulation of This icon also represents WIP accumulation in VSM;
materials, parts, and products in any process flow. however, it also records the amount of inventory
Examples of such accumulation are: accumulated. It is also used to represent storage
Work-In-Progress (WIP) locations for raw material/s and finished good/s.
Parts queued up before a machine
Delay/ idle time of the operator
101
REFERENCES
Niebel, B. N. & Freivalds, A. (1999). Methods, Standards, and Work Design. New York,
NY: McGraw-Hill.
Rother, M. & Shook, J. (1999). Learning to See: Value Stream Mapping to Add Value
and Eliminate Muda. Brookline, MA: Lean Enterprise Institute (www.lean.org).
Womack, J. P. & Jones, D. T. (1996). Lean Thinking: Banish Waste and Create Wealth in
your Corporation. New York, NY: Simon & Schuster.
―What is the Theory of Constraints, and How does it compare to Lean Thinking?‖
http://www.lean.org/Lean/Community/Resources/thinkers2.cfm.
102
Evaluation of the Value Stream
Mapping Icons for Use in Jobshop-
type Facilities
Sadono Djumin, ZahirAbbas N. Khaswala, and Shahrukh A. Irani 1
Department of Industrial, Welding and Systems Engineering
The Ohio State University
Columbus Ohio 43210
Abstract
Value Stream Mapping (VSM) is an effective tool for visual representation of the
material and information flows in a facility with similar or identical product routings,
typically an assembly line type of facility that makes a low variety of products in high
volumes. However, the developers of VSM do not acknowledge the limitations of their
tool when deployed in facilities where multiple value streams merge/diverge because
they share one or more common capacity-constrained workcenters. This is typically the
case in jobshops (machining, fabrication, tool and die, injection molding, etc.) and any
Make-To-Order manufacturing facility with a NAICS code in the range 311-315, 321-
327, and 333-337. Based on the US Census Bureau’s 1997 Economic Census, a
conservative estimate of the number of such small- and medium-sized manufacturing
facilities (SME’s) with 50-249 employees is greater than 50,000!
Value Network Mapping (VNM) is the proposed tool that could map a multi-level Bill Of
Routings for a complete assembled product (furniture, excavation equipment, stamping
die, airframe structure, etc.), or reduce a diverse product mix with 1000+ active
components into several families of parts with similar manufacturing routings. This new
mapping tool needs meaningful icons that can be used to draw Current and Future State
Maps for the manufacturing system under study. Hence, a preliminary step taken was to
study the template of icons for VSM, which is mainly applicable to low variety high
volume (LVHV) environments, and modify or extend them, as appropriate, to suite high-
variety low-volume (HVLV) facilities.
1
Corresponding Author: irani.4@osu.edu, Ph: (614) 688-4685, Fax: (614) 292-7852
103
CURRENT STATE MAP
104
MATERIAL FLOW ICONS
Applicable
XYZ Corporation XYZ Corporation
Not Applicable
105
VSM Applicability to VNM Proposed Icon for VNM
106
VSM Applicability to VNM Proposed Icon for VNM
C/T = 45 secs
Applicable
C/O = 30 mins
3 shifts
2% scrap Not Applicable
107
VSM Applicability to VNM Proposed Icon for VNM
Applicable
Qt, N
I
Not Applicable
Transfer batch size and
300 pcs/day Needs modification frequency of tansfer
Inventory
This icon represents the
As VNM maps a group of This symbol indicates the transfer
accumulation of inventory batch size (Qt) and the transfer
selected parts, there is a
between two processes. frequency (N) i.e. total number of
need to capture the
While mapping the current transfer batches of a particular part
inventory accumulation
state, the amount of being moved between two process
due to different parts.
inventory can be locations.
Hence, VNM
approximated by a quick
recommends that the icon
count during the facility
representing the amount
walkthrough, and that
of inventory be drawn for
amount is noted beneath the
every part found in the
triangle.
inventory.
A plot of generic
inventory level (measured
in hours of workcenter
capacity) of the parts
found in the inventory
location can also be
computed.
Mon+
Applicable Delivery Schedule
Wed
108
VSM Applicability to VNM Proposed Icon for VNM
109
VSM Applicability to VNM Proposed Icon for VNM
1 1
Drum or Pacemaker
110
VSM Applicability to VNM Proposed Icon for VNM
Applicable
Not Applicable
Applicable
Not Applicable
Needs modification
Rope to upstream processes Rope from downstream processes
111
VSM Applicability to VNM Proposed Icon for VNM
Applicable
Not Applicable
Needs modification
Safety Stock
This icon is used to
represent the “buffer stock”
which is used to protect
against all sudden
fluctuations in customer
orders. Safety stock should
be temporary and used only
till the root cause of a
problem is found and
eliminated.
Applicable
Not Applicable
Finished Goods Needs modification
to Customer
112
INFORMATION FLOW ICONS
Applicable Delivery
Parts from
Not Applicable supplier
schedule
Needs modification
1 Daily
2 Weekly
This icon represents any Due to the variations in the 3 Random
periodic schedules within frequency of customer orders,
any processes in the plant, there is need for a more compact
such as schedules of representation for multi-part data.
customer orders (fax/request
frequency), production
control schedules to
customer and supplier, etc
113
M Applicability to VNM Proposed Icon for VNM
114
VSM Applicability to VNM Proposed Icon for VNM
Manual Electronic
Applicable
M/H or S
Information Flows Not Applicable
Communication System
Needs modification
These icons capture the
This symbol will be used to indicate
information flows in any
the types of communication systems
map. The icon representing
in use on the shop floor:
the manual flow of
M/H – for material handling
information is simply a
between interacting processes/work
straight arrow. The wiggle
centers.
arrow represents the
S – for support functions that
electronic flow of
support the operators at each
information.
workcenter ex. Production Control
and Maintenance.
115
VSM Applicability to VNM Proposed Icon for VNM
Applicable M1 3 4 1 2
M2 11 3 2 4
Not Applicable
Withdrawal Kanban M3 2 3 1 4
Needs modification 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
This icon represents a
“shopping list”. It is a card The Job-Order Kanban is suited for
or device that instructs the There are other types of Kanbans
used in specific situations: HVLV environments with non-
material handler to transfer recurrently produced parts.
from a supermarket to the Express and Emergency
Kanban: This Kanban is Shown above is a customized
receiving process. version of a Gantt Chart issued for
issued only when there is a
shortage of a part and the Job #1. Notice that, only the
Kanban is collected just after processes (M1, M2, and M3) which
its use. The shortage of the the job uses in its route are shown.
Production Kanban part could be due to defective The time blocks indicate the work
units, machine troubles, etc. content for jobs at the shared
This icon triggers one resources after the shop has been
production of a pre-defined Job-Order Kanban: For
non-recurrently produced loaded to the jobs as determined by
number of parts. It is used as
products, a job-order Kanban the schedule developed for the VNM
a signal for a supplying
is prepared for the dedicated timeline. Hence, after being
process to feed and provide
production line and is issued processed at M2, Job #1 would need
parts to the next
for each job order. real time status of Job #3 & Job #4
(consuming) process. at M1.
Through and Common
Kanban: This type is used
The Express and the Cart Kanban
where two or more processes
types would also be applicable in
are so closely connected with
HVLV environments.
each other that they can be
Kanban Arriving in Batches seen as a single process. In
this case, a common sheet of
This icon triggers Kanban is used by both the
simultaneous production of preceding and subsequent
several parts. This icon has processes.
to be used in conjunction Cart or Truck Kanban: In
with Load Leveling to this case, the cart used to
control the release of transfer parts between
kanbans for each part. This processes is itself a Kanban.
icon is appropriate when it Although a Kanban must be
is not possible to produce a attached to the parts as a rule,
pre-defined quantity of a the number of carts equals the
single part. number of Kanbans.
116
VSM Applicability to VNM Proposed Icon for VNM
Signal Kanban
This icon is used whenever
the on-hand inventory levels
in the supermarket between
two processes drops to a
trigger or minimum point.
When a Triangle Kanban
arrives at a supplying
process, it signals a
changeover and production
of a predetermined batch
size of the part noted on the
Kanban.
117
VSM Applicability to VNM Proposed Icon for VNM
C2
Timeline Applicable M1 3 4 1 2
M2 1 3 2 4
Not Applicable
This icon drawn under the Needs modification
M3 2 3 1 4
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
process boxes and inventory C3 C1 C4
triangles is used to indicate
the production lead time, As VNM maps a group of parts, the
which is the time it takes one equivalent of the timeline icon is
part to make its way through the Gantt chart. This shows the
the shop floor, beginning utilization of capacity constrained
with its arrival as raw shared resources by the selected
material through to shipment parts. (Ci = Completion Time of
to the customer. Jobi in the production schedule; M
= Machine)
2 hrs
In VNM, a weighted VAR must be
40 secs
Applicable computed from the Gantt chart. The
Not Applicable weights can be based on criteria
Value adding
time Needs modification
such as profit margin , selling price,
The metric used for VSM to importance by customer, etc.
measure the efficiency of a
Current State Map is the
Value Added Ratio (VAR).
As shown above, the value
added time is indicated at
each process. The VAR is
computed by calculating the
total processing time and
dividing it by the total
production lead time.
118
VSM Applicability to VNM Proposed Icon for VNM
119
Value Network Mapping (VNM):
Visualization and Analysis of
Multiple Interacting Value
Streams in Jobshops
Shahrukh Irani
120
Introduction to Lean Thinking
121
Flow: Foundation of Lean Thinking
122
Designing a Factory for Flow
• Eliminate operations
• Eliminate handling
• Combine operations
• Minimize handling costs
• Minimize multiple paths
Adapted from: Tompkins, J.A., et al. (1996). Facilities planning. New York, NY: John Wiley.
123
What is Value Stream Mapping (VSM)?
124
Reasons for using Value Stream Mapping (VSM)
125
Standard Symbols for VSM
C/T = 45 secs
ASSEMBLY
XYZ Corporation
C/O = 30 mins
3 shifts
I
2% scrap
300 pcs/day
Process Box Outside Sources Data Box Inventory
Weekly 1
Manual Electronic
Supermarket Schedules Operator
Information Flows
Source: Rother & Shook, 1999, ISBN 0-9667843-0-8
126
Standard Symbols for VSM (contd.)
Kaizen
127
An Example of a Current State Map
128
An Example of a Future State Map
129
Advantages of Value Stream Mapping
130
Disadvantages of Value Stream Mapping
131
Foundation for Value Network Mapping (VNM)
132
Foundation for Value Network Mapping (contd.)
Raw
COMPONENTS
C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 Materials
Manufacturing Systems
Production Flows in the
SUB ASSEMBLIES SA 1 SA 2 SA 3 SA 4 SA 5
133
Our Goal
134
Comparison of Value Stream Mapping (VSM)
and Value Network Mapping (VNM)
VSM VNM
Form a Product Family: Tool used Form a Product Family: Tools used
1. Product-Process Matrix Clustering 1. Product-Process Matrix Clustering
(Downstream processes close to the 2. Product-Component Matrix Clustering
customer end of the value sream are used 3. PQRS Analysis
to identify a product family)
Draw the Current State Map:Tool used Draw the Current State Map: Tools used
1. Collect data and draw the map using a 1. MMPPC
pencil 2. Enhanced FPC
135
Fundamental Problems in VNM
136
VNM for a Machining Jobshop
137
Sample of Machined Parts in the Jobshop
138
Machines in the Jobshop
139
Product Mix Segmentation – I: P-Q Analysis
120
100
80
Quantity
60
40
20
0
5 12 3 13 9 2 1 7 8 6 4 10 11
Part Number
140
Revenue Product Mix Segmentation – II: P-Q-$ Analysis
141
Product Mix Segmentation –III: P-R Analysis
3 9 10 4 6 12 11 7 2 5 8 1
5 1 1 1 1
11 1 1 1 1
1 1 1 1 1 1
2 1 1 1 1 1 1
12 1 1 1 1 1
13 1 1 1 1
6 1 1 1 1
7 1 1 1 1
3 1 1 1 1
4 1 1 1 1
8 1 1 1
9 1 1 1
10 1 1
Part Number
2 4 6 9 10 11 12
1 6 9 10 11 12
11 3 9 10 12
12 3 6 4 10 12
13 4 6 4 10 12
5 3 7 10 12
6 1 7 9 10
4 4 7 9 10
8 4 7 9
9 2 7 9
10 2 9
3 5 8 9 10
7 1 8 9 10
142
Product Mix Segmentation – IV: P-Q-R-$ Analysis
143
Product Mix Segmentation – IV: P-Q-R-$ Analysis
(contd.)
144
How NOT to Draw a Value Network Map (VNM)
3 9 10 4 6 12 11 7 2 5 8 1
3 10 90 100
9 240
10 275 85
4 165 120 45
6 85 165
12
11 85
7 135 100
2 15 70
5 80
8 110
1 20 30
145
How to Draw a Value Network Map (VNM)
Part #
1 6 9 10 11 12 4*
2 4
6 9* 10* 11 12
13
12 3 3
5 7
7*
Exception Operation
11
10
9 2 2
4 4 4*
6 7 7*
7 1 1
3 8 9 10 8 9* 10*
5
5
* Should multiple process boxes be drawn in the map for these duplicate machines?
146
Design of Flexible Factory Layouts using VNM
Modular Layout
5
Cellular Layout Module 1 Hybrid Flowshop Layout
1 8
7 9 10
2
4
3 6 9 10 11 12
Module 2
147
VNM for a Fabrication Jobshop
148
Product utilized for VNM study: ED1M009-32
149
Components in ED1M009-32
150
Workcenters used to make ED1M009-32
Machine # Machine Description
1 Shear
2 Laser
3 Vipros (NCP)
4 King (NCP)
5 Time Saver
6 Manual Grind
7 Large Mechanical Brake (L. Mech.)
8 Small Mechanical Brake (S. Mech.)
9 Large CNC Brake (L. CNC)
10 Small CNC Brake (S. CNC)
11 Gang Drill
12 MIG Weld
13 Rough Grinder
14 Notcher
15 Burton Plating (Outsource)
16 Paint Line
17 Assembly
18 Tumbler
151
Multi-Product Process Chart (MPPC) for
ED1M009-32
152
Flow Diagram for ED1M009-32
153
Enhanced Flow Process Chart (FPC) for
ED1M009-32
154
Enhanced Flow Process Chart (FPC) for
ED1M009-32 (contd.)
155
Modified Multi-Product Process Chart (MM-PPC)
for ED1M009-32
156
VNM: Overall Flow Diagram
LASER SHEAR
X = Travel distance
X/Y X/Y
X/Y
Y = MHE used
M. GRIND VIPROS / KING
L CNC BR
X/Y
X/Y
X/Y
X/Y
X/Y X/Y
TS GRIND M. GRIND
X/Y X/Y X/Y
X/Y X/Y
X/Y
X/Y X/Y
L CNC BR GSW
X/Y X/Y X/Y
X/Y
S CNC BR X/Y
WELD
X/Y
X/Y
X/Y
X/Y
R GRIND BURTON
X/Y X/Y
PAINT
X/Y
X/Y
ASSLY
157
VNM: Assembly Operations Process Chart
MAN TS TS TS
VNCP VNCP VNCP VNCP VNCP VNCP VNCP VNCP VNCP VNCP VNCP HAEG
GRIND GRIND GRIND GRIND
SM SM LM LC LC MAN
KNCP KNCP KNCP KNCP KNCP KNCP KNCP KNCP KNCP
BRAKE BRAKE BRAKE BRAKE BRAKE GRIND
GANG TUM
NOTCH SHEAR
DRILL GRIND
TS TS TS TS TS TS TS TS
GRIND GRIND GRIND GRIND GRIND GRIND GRIND GRIND
LM LC LC LC LC GANG GANG
BRAKE BRAKE BRAKE BRAKE BRAKE DRILL DRILL
ROUGH
GRIND
MIG MIG
WELD WELD
ROUGH ROUGH
GRIND GRIND
ASSMY
INSPEC
158
VNM using PFAST and PREACTOR/FCS
159
VNM using PFAST and PREACTOR/FCS (contd.)
NO OPRN 1065-2 1065-3 1064-3 1062 1063 0126 0127 1066 1067 1068 0229 0228 0211 0210
1 SHEAR 1 1 1 1 1 1 3 1 1 1 1 1 1 1 1
160
VNM using PFAST and PREACTOR/FCS (contd.)
HAEGAR ASSLY
1 X/Y
BURTON X/Y
3
X/Y
TU GRIND
1 3 X/Y X/Y
X/Y
X/Y
SHEAR 1 1 1 L MECH BR
X/Y
X/Y
2
X/Y
X/Y
1 1 S MECH BR 1
X/Y
X/Y
NOTCHER 1
1
161
VNM: Reduction of Multiple Value Streams to
arrive at the Future State Network
• Group components that use same machines into “kits” that are “group released”
on one cart.
P99SS1069 P99SS1146 P99SS1145 P99SS1064-2 P99SS1064-3 P99SS1065-3 P99SS1065-2 P99SS1063 P99SS1062 P99SS0126 P99SS0127 P99SS1066 P99SS1067 P99SS1068 P97SS0229 P97SS0228 P97SS0211 P97SS0210
LASER LASER LASER LASER Shear SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR
P :29 :26 P :27 4:22 P :21 P :23 P :31 :23 :41 P :37 P 1:07 P :2 :2 :1 P :12
P P P :13 :28 P :15 P P P P
S :7 S :7 :15 :15 S :15 P S :15 S :15 S :15 S :15
S :7 S :7 S :15 S S S :15 S :15 S :15 S :15 S :15
T :4 :4 T :4 S :15 T :4 :4 T :4 T :4
T :4 T T :4 T :4 T :4 T :4 T :4 T :4 T :4 T T :4 T :4
Q :12 :22 Q 0 T :4 Q :17 :12 Q 0 Q 0
Q 0 Q Q 0 Q 2:17 Q :30 Q Q 0 Q 0 Q :54 Q Q 0 Q 0
Q 0
SM SM LM LM MAN TUM
BRAKE BRAKE SHEAR GRIND
P 1:02
BRAKE :59 1:06
P 3:48 BRAKE GRIND P 3:29 :20
P P 1:13 P
S :46 S P 2:44 S :53
S :46 S :46 S :42
:12 T :12 S :42 T :12 :12
T T :12 T :12 T
Q :55 Q 4:47 T :12 Q 0 0
Q 0 Q :32 Q
Q 0
GANG TS TS TS TS TS TS TS TS
NOTCH GRIND GRIND GRIND GRIND GRIND GRIND GRIND GRIND
P 1:14 P 5:04 DRILL P 2:28 P 3:57 P 4:02 P 2:04 P 2:08 P 2:32 P :32 P :30
S :51 S 1:20 :42 :42
S S :42 S :57 S :42 S :42 S :42 S S :42
T :16 T :16 :12 :12
T T :12 T :16 T :12 T :12 T :12 T T :12
Q :55 Q 5:44 1:53 0
Q Q 0 Q 0 Q 2:36 Q 1:32 Q :12 Q Q 0
1:10 12:24
GANG GANG
DRILL DRILL
P :43 P :40
S :49 S :49
T :16 T :16
Q 0 Q 0
LC LC LC LC LC LC
BRAKE BRAKE BRAKE BRAKE BRAKE BRAKE
P 9:39 P :55 P 3:46 P 5:46 P 5:55
S :46 S :50 P 3:30
T :12 T :8
S
T
1:17
:16
S 1:17 S
T
1:17
:16
S
T
1:32
:20
SC SC
Q 4:02 Q :50 T :16
17:50 2:43
Q 0
Q 5:08
Q 0 Q 0
BRAKE BRAKE
P 1:24 P 1:13
S 1:24 S 1:24
:20 :20
GANG MIG GANG GANG T
Q 1:13
T
Q 0
DRILL P 7:09 WELD DRILL DRILL
P 10:21 P 6:30 P 6:27
:53 S 1:35 1:24 1:24
S S S
:16 T :20 :20 :20
T T T
Q 6:19 Q 9:26 Q 0 Q 8:03 BURTN BURTN BURTN BURTN BURTN BURTN
P 42:04 P 42:08 P 42:32 P 41:24 P 41:13 P 40:20
MIG ROUGH S :42 S :42 S :42 S 1:24 S 1:24 S :42
T :16 T :16 T :16 T :24 T :24 T :16
P
S
13:57
1:08 WELD P
S
7:10
1:39
GRIND Q 2:36 Q 1:32 Q :12 Q 1:13 Q 0 Q 0
T :20 T :24
3:17 1:58 2:37 Q 6:19 21:45 Q 9:26 18:39 8:14 16:14
MIG
MIG P 6:27 WELD
S 1:32
P
S
27:50
1:23
WELD T
Q
:20
19:33
T :24
Q 6:19
ROUGH
ROUGH GRIND
P 34:00 P 6:53
S 1:27 GRIND S 1:36
T :28 T :24
Q 6:19 42:14 Q 25:46
162
VNM: Reduction of Multiple Value Streams to arrive
at the Future State Network (contd.)
LASER LASER LASER LASER Shear SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR
P :29 :26 P :27 4:22 P :21 P :23 P :31 :23 :41 P :37 P 1:07 P :2 :2 :1 P :12
P P P :13 :28 P :15 P P P P
S :7 S :7 :15 :15 S :15 P S :15 S :15 S :15 S :15
S :7 S :7 S :15 S S S :15 S :15 S :15 S :15 S :15
T :4 :4 T :4 S :15 T :4 :4 T :4 T :4
T :4 T T :4 T :4 T :4 T :4 T :4 T :4 T :4 T T :4 T :4
Q :12 :22 Q 0 T :4 Q :17 :12 Q 0 Q 0
Q 0 Q Q 0 Q 2:17 Q :30 Q Q 0 Q 0 Q :54 Q Q 0 Q 0
Q 0
SM SM LM LM MAN TUM
BRAKE BRAKE SHEAR GRIND
P 1:02
BRAKE :59 1:06
P 3:48 BRAKE GRIND P 3:29 :20
P P 1:13 P
S :46 S P 2:44 S :53
S :46 S :46 S :42
:12 T :12 S :42 T :12 :12
T T :12 T :12 T
Q :55 Q 4:47 T :12 Q 0 0
Q 0 Q :32 Q
Q 0
GANG TS TS TS TS TS TS TS TS
NOTCH GRIND GRIND GRIND GRIND GRIND GRIND GRIND GRIND
P 1:14 P 5:04 DRILL P 2:28 P 3:57 P 4:02 P 2:04 P 2:08 P 2:32 P :32 P :30
S :51 S 1:20 :42 :42
S S :42 S :57 S :42 S :42 S :42 S S :42
T :16 T :16 :12 :12
T T :12 T :16 T :12 T :12 T :12 T T :12
Q :55 Q 5:44 1:53 0
Q Q 0 Q 0 Q 2:36 Q 1:32 Q :12 Q Q 0
1:10 12:24
GANG GANG
DRILL DRILL
P :43 P :40
S :49 S :49
T :16 T :16
Q 0 Q 0
LC LC LC LC LC LC
BRAKE BRAKE BRAKE BRAKE BRAKE BRAKE
P 9:39 P :55 P 3:46 P 5:46 P 5:55
S :46 S :50 P 3:30
T :12 T :8
S
T
1:17
:16
S 1:17 S
T
1:17
:16
S
T
1:32
:20
SC SC
Q 4:02 Q :50 T :16
17:50 2:43
Q 0
Q 5:08
Q 0 Q 0
BRAKE BRAKE
P 1:24 P 1:13
S 1:24 S 1:24
:20 :20
GANG MIG GANG GANG T
Q 1:13
T
Q 0
DRILL P 7:09 WELD DRILL DRILL
P 10:21 P 6:30 P 6:27
:53 S 1:35 1:24 1:24
S S S
:16 T :20 :20 :20
T T T
Q 6:19 Q 9:26 Q 0 Q 8:03 BURTN BURTN BURTN BURTN BURTN BURTN
P 42:04 P 42:08 P 42:32 P 41:24 P 41:13 P 40:20
MIG ROUGH S :42 S :42 S :42 S 1:24 S 1:24 S :42
T :16 T :16 T :16 T :24 T :24 T :16
P
S
13:57
1:08 WELD P
S
7:10
1:39
GRIND Q 2:36 Q 1:32 Q :12 Q 1:13 Q 0 Q 0
T :20 T :24
3:17 1:58 2:37 Q 6:19 21:45 Q 9:26 18:39 8:14 16:14
MIG
MIG P 6:27 WELD
S 1:32
P
S
27:50
1:23
WELD T
Q
:20
19:33
T :24
Q 6:19
ROUGH
ROUGH GRIND
P 34:00 P 6:53
S 1:27 GRIND S 1:36
T :28 T :24
Q 6:19 42:14 Q 25:46
163
VNM: Reduction of Multiple Value Streams to arrive
at the Future State Network (contd.)
• Identify families of parts with identical routings that can be
“compacted” into a single value stream.
P99SS1069 P99SS1146 P99SS1145 P99SS1064-2 P99SS1064-3 P99SS1065-3 P99SS1065-2 P99SS1063 P99SS1062 P99SS0126 P99SS0127 P99SS1066 P99SS1067 P99SS1068 P97SS0229 P97SS0228 P97SS0211 P97SS0210
LASER LASER LASER LASER Shear SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR SHEAR
P :29 :26 P :27 4:22 P :21 P :23 P :31 :23 :41 P :37 P 1:07 P :2 :2 :1 P :12
P P P :13 :28 P :15 P P P P
S :7 S :7 :15 :15 S :15 P S :15 S :15 S :15 S :15
S :7 S :7 S :15 S S S :15 S :15 S :15 S :15 S :15
T :4 :4 T :4 S :15 T :4 :4 T :4 T :4
T :4 T T :4 T :4 T :4 T :4 T :4 T :4 T :4 T T :4 T :4
Q :12 :22 Q 0 T :4 Q :17 :12 Q 0 Q 0
Q 0 Q Q 0 Q 2:17 Q :30 Q Q 0 Q 0 Q :54 Q Q 0 Q 0
Q 0
SM SM LM LM MAN TUM
BRAKE BRAKE SHEAR GRIND
P 1:02
BRAKE :59 1:06
P 3:48 BRAKE GRIND P 3:29 :20
P P 1:13 P
S :46 S P 2:44 S :53
S :46 S :46 S :42
:12 T :12 S :42 T :12 :12
T T :12 T :12 T
Q :55 Q 4:47 T :12 Q 0 0
Q 0 Q :32 Q
Q 0
GANG TS TS TS TS TS TS TS TS
NOTCH GRIND GRIND GRIND GRIND GRIND GRIND GRIND GRIND
P 1:14 P 5:04 DRILL P 2:28 P 3:57 P 4:02 P 2:04 P 2:08 P 2:32 P :32 P :30
S :51 S 1:20 :42 :42
S S :42 S :57 S :42 S :42 S :42 S S :42
T :16 T :16 :12 :12
T T :12 T :16 T :12 T :12 T :12 T T :12
Q :55 Q 5:44 1:53 0
Q Q 0 Q 0 Q 2:36 Q 1:32 Q :12 Q Q 0
1:10 12:24
GANG GANG
DRILL DRILL
P :43 P :40
S :49 S :49
T :16 T :16
Q 0 Q 0
LC LC LC LC LC
LC
BRAKE BRAKE BRAKE BRAKE BRAKE
P 9:39 P :55 P 3:46
BRAKE P 5:46 P 5:55
S :46 S :50 P 3:30
T :12 T :8
S
T
1:17
:16
S 1:17 S
T
1:17
:16
S
T
1:32
:20
SC SC
Q 4:02 Q :50 T :16
17:50 2:43
Q 0
Q 5:08
Q 0 Q 0
BRAKE BRAKE
P 1:24 P 1:13
S 1:24 S 1:24
:20 :20
GANG MIG GANG GANG T
Q 1:13
T
Q 0
DRILL P 7:09 WELD DRILL DRILL
P 10:21 P 6:30 P 6:27
:53 S 1:35 1:24 1:24
S S S
:16 T :20 :20 :20
T T T
Q 6:19 Q 9:26 Q 0 Q 8:03 BURTN BURTN BURTN BURTN BURTN BURTN
P 42:04 P 42:08 P 42:32 P 41:24 P 41:13 P 40:20
MIG ROUGH S :42 S :42 S :42 S 1:24 S 1:24 S :42
T :16 T :16 T :16 T :24 T :24 T :16
P
S
13:57
1:08 WELD P
S
7:10
1:39
GRIND Q 2:36 Q 1:32 Q :12 Q 1:13 Q 0 Q 0
T :20 T :24
3:17 1:58 2:37 Q 6:19 21:45 Q 9:26 18:39 8:14 16:14
MIG
MIG P 6:27 WELD 7:47
S 1:32
P
S
27:50
1:23
WELD T
Q
:20
19:33
T :24
Q 6:19
ROUGH
ROUGH 45:38 44:38 43:42
P 34:00 P 6:53
GRIND
S 1:27 GRIND S 1:36
T :28
Q 6:19 42:14
T
Q
:24
25:46
34:39
164
Acknowledgements
165
Value Stream Mapping of a Complete Product
Shahrukh A. Irani and Jin Zhou
Department of Industrial, Welding and Systems Engineering
The Ohio State University
Columbus, OH 43210
Introduction
Lean Thinking, a concept that is based on the Toyota Production System, extends
continuous improvement efforts to reduce the costs of serving customer/s beyond the
physical boundaries of a manufacturing facility, by including the suppliers, distributors
and production system that support the manufacturing function [Womack and Jones,
1996]. These improvements and cost reductions are achieved by eliminating the muda
(wastes) associated with all activities performed to deliver an order to a customer. Wastes
are defined as “all activities that consume resources (add costs to the product) but
contribute zero value to the customer.” According to Womack and Jones, there are five
steps for implementing Lean Thinking in an enterprise: 1) Define Value from the
perspective of the Customer, 2) Identify the Value Streams, 3) Achieve Flow, 4)
Schedule production using Pull, and 5) Seek Perfection through Continuous
Improvement. Womack and Jones define a Value Stream as “the set of all the specific
actions required to bring a specific product through the three critical management tasks of
any business: …problem solving, …information management, …physical
transformation”. Alternatively, Rother and Shook define a Value Stream as “all the
actions (both value-added and non-value-added) currently required to bring a product
through the main flows essential to every product” [Rother and Shook, 1999, p. 3].
Value Stream Mapping (VSM) is the process of mapping the material and information
flows required to coordinate the activities performed by manufacturers, suppliers and
distributors to deliver products to customers. Unlike the traditional process mapping
tools used by IE’s, VSM is a mapping tool that maps not only material flows but also
information flows that signal and control the material flows. This enhanced visual
representation facilitates the identification of the value-adding steps in a Value Stream
and elimination of the non-value adding steps, or wastes (muda). Using VSM, many
OEM’s and their top-tier suppliers have changed their existing facility layouts, as well as
existing systems for material handling, inventory control, purchasing and scheduling, to
reduce the total throughput times of orders and current levels of work-in-process (WIP)
inventories.
A typical VSM project involves the development of maps: (1) a Current State Map and
(2) one or more Future State Maps that represent progressive improvements in the
Current State Map. In the Current State Map, one would normally start by mapping a
product family that accounts for a significant proportion of the total annual production
volume and sales earnings (or even profit margin) of the company. Usually, the material
Based on the Current State Map, a Future State Map is generated for improving the
value-adding steps and eliminating the non-value adding steps (waste) in the current
system. Based on the concepts of Lean Thinking, Rother & Shook provide seven
guidelines to follow when generating the Future State Map for an improved
manufacturing system (Rother and Shook, 1999, p. 44-54):
Provides important descriptive information for the Operation and Storage icons in the
standard Flow Process Charts used by IE’s.
Provides a company with a “blueprint” for strategic planning to deploy the principles
of Lean Thinking to facilitate their transformation into a Lean Enterprise.
Fails to map multiple products that do not have identical manufacturing routings or
assembly process flows.
Fails to relate Transportation and Queuing delays, and changes in transfer batch sizes
due to poor plant layout and/or material handling, to operating parameters (ex.
machine cycle times) and measures of performance (ex. takt time)1 of the
manufacturing system.
Lacks an economic measure for “value”, such as profit, throughput, operating costs,
inventory expenses, etc. unlike the Flow Process Charting technique used by IE’s.
Lacks the spatial structure of the facility layout, and how that impacts inter-operation
material handling delays, the sequence in which batches enter the queue formed at
each processing step in the manufacturing routing/s, container sizes, trip frequencies
between operations, etc.
Tends to bias a factory designer to consider only those strategies2, such as continuous
flow, assembly line layouts, kanban-based Pull scheduling, etc., that are suitable
mainly for high-volume low-variety (HVLV) manufacturing facilities.
1
Reasons for this could be (a) the impact of a poor facility layout on order throughput, product quality and
operating costs is assumed to be trivial by the developers of VSM or (b) superimposing all the information
contained in a VSM onto a CAD drawing of the facility layout reduces the readability of the map.
2
These are design and operational strategies that are suited mainly for low-variety high-volume (LVHV)
facilities, such as automotive OEM’s and their Tier 1 or Tier 2 suppliers, and not the sub-tier suppliers and
other Make-To-Order manufacturers who operate high-variety low-volume (HVLV) facilities.
Fails to handle the complete BOM (Bill Of Materials) of a product since that usually
results in a branched and multi-level Value Stream.
Fails to factor queuing delays, sequencing rules for multiple orders, capacity
constraints, etc. in any map3.
Lacks the capability, due to the manual mapping method, for rapid development and
evaluation of multiple “what if” analyses required to prioritize different alternatives
for improving a Current State Map when time and/or budget constraints exist.
3
This could be easily and effectively done if queuing network analysis, simulation or a Finite Capacity
Scheduling (FCS) software were used to develop and model the performance of the manufacturing system
represented in a Current State Map.
4
For further details, please refer to [Muther 1955, Chapter 15, Pages 193-209].
The locations for the different process boxes in Figure 2 become the basis for drawing the
Value Network Map for the gate valve assembly on a sheet of paper. It minimizes criss-
cross flows among process boxes that could have been incorrectly located in a hand-
drawn Current State Map for the same product. Thereby, the computer-aided method of
Value Network Mapping (VNM) helps to reduce the chaos (and frustration) of
implementing Value Stream Mapping in complex manufacturing facilities.
Based on the initial VNM shown in Figure 2, it may be required to determine if certain
workcenters must be duplicated at several locations to eliminate criss-cross flows in the
5
For further details, please refer to [Muther, 1955, Page 176, Figure 14-1].
6
Detailed analysis was not done to determine if this workcenter could serve as the Drum in a Drum-Buffer-
Rope scheduling system [Goldratt and Fox, 1986] for the focused factory.
Since a typical Value Network Map will involve large numbers of value streams and
process boxes, a clutter-free drawing of the complete material flow network is a must.
Figures 5(a)-(c) present a preliminary idea of a Bubble Diagram-like grid [Muther, 1955,
p. 196, Figure 15-4] on which the process boxes could be entered in order to make
adjacent strongly-connected pairs of workcenters in the material flow network. Further,
the size of paper on which the map is drawn could constrain the number of process boxes,
and therefore number of value streams, that could be included in a single map. In which
case, for complex products and large samples of components, connections among
multiple maps will need to be established and maintained.
The icons used for Value Stream Mapping are relevant mainly for assembly line-like
repetitive flow systems for low-variety high-volume (LVHV) manufacturing facilities.
Jobshops and Make-To-Order manufacturing systems have considerably more complex
material flow networks, and produce orders to customer-specified due dates using finite
capacity scheduling methods. Therefore, a new set of icons is being developed for VNM
that can be obtained for evaluation from the authors on request.
How does one show all the data for a large number of components at each workcenter?
And, if one were to incorporate details relating to production control, operations
scheduling and shopfloor control on the same map that contains the material flow
network, then the resulting map would easily become unreadable. Hence, it is desired to
develop a separate map showing the information flows involved in the manufacturing
system being studied.
Lastly, a typical Make-To-Order assembly facility produces a wide range of products that
use different combinations of parts and subassemblies, whose routings will therefore
feature different sets of workcenters located in the same facility. Hence, the proposed
method must be enhanced to represent, possibly aggregate, multiple OPC’s for different
products being produced in the same facility.
Conclusion
References
Apple, J. M. (1977). Plant Layout and Material Handling. New York, NY: John Wiley.
Costanza, J. (1996). The Quantum Leap .... in Speed-To-Market. Denver, CO: John
Costanza Institute of Technology, Inc.
Goldratt, E.M. & Fox, R.F. (1986). The Race. Croton-on-Hudson, NY: North River Press.
Irani, S.A., Zhang, H., Zhou, J., Huang, H., Udai, T.K. & Subramanian, S. (2000).
Production Flow Analysis and Simplification Toolkit (PFAST). International Journal of
Production Research, 38(8), 1855-1874.
Muther, R.M. (1955). Practical Plant Layout. New York, NY: McGraw-Hill.
Rother, M. & Shook, J. (1999, June). Learning to See. Version 1.2. Brookline, MA: Lean
Enterprise Institute.
Zhou, J. & Irani, S.A. (2000, June 27-30). Design of modular layouts for fabrication-
based assembly facilities. Proceedings of the Third World Congress on Intelligent
Manufacturing Processes & Systems, Massachusetts Institute of Technology, Cambridge,
MA, and the International Institution for Production Engineering Research (CIRP), 62-
69.
Womack, J. P. & Jones, D. T. (1996). Lean Thinking: Banish Waste and Create Wealth in
your Corporation. New York, NY: Simon & Schuster.
O-30 Clean O-26 Bore O-24 Cut O-17 Clean O-12 Clean O-6 Clean O-2 Thread
Parts Manufacturing
Portion of Facility
O-31 Ream O-27 Tap O-18 Mill O-13 Drill O-7 Drill O-3 Mill
O-22
Gasket SA-1
Countersink
1001
A-1
A-2
Grease
1201
A-3
A-5
of Facility
A-6
Washer A-7
0204
Staples
I -1
1503 SA-3
Label
1603
A-9
Parts
Handle Cap Ferrule Body Gate Bushing Stem
Cast Drill Bore Cast Cast Cast Turn
Clean Bore Cut Clean Clean Clean Thread
Ream Tap A-4 Mill Drill Drill Mill
Paint Cut A-5 Drill Tap Bore Cut
A-6 SA-2 A-6 Bore Mill Turn A-1
A-5 Tap A-2 Thread A-2
A-6 Countersink A-3 SA-1 A-3
A-3 A-4 A-1 A-4
A-4 A-5 A-2 A-5
A-5 A-6 A-3 A-6
A-6 A-4
A-5
A-6
Parts
Handle Body Gate Bushing Stem Ferrule Cap
Cast Cast Cast Cast
Clean Clean Clean Clean
Ream Mill
Paint Drill Drill Drill
Bore Bore
Tap Tap Turn Turn Drill
Countersink Mill Thread Thread Bore Bore
SA-1 Mill Tap
Cut Cut Cut
A-1 A-1 SA-2
A-2 A-2 A-2
A-3 A-3 A-3 A-3
A-4 A-4 A-4 A-4 A-4
A-5 A-5 A-5 A-5 A-5 A-5
A-6 A-6 A-6 A-6 A-6 A-6 A-6
Parts
Handle Body Gate Bushing Stem Ferrule Cap
Cast
Clean
Ream Mill
Paint Drill
Bore Bore
Tap Turn Drill
Countersink Mill Thread Bore
SA-1 Mill Tap
Cut
A-1 SA-2
A-2
A-3
A-4
A-5
A-6
13 10 1. Cast
2. Drill
3. Bore
4. Cut
18 19 7
5. Clean
6. Thread
7. Ream
11 16 17 5 1 8. Tap
9. Mill
10. Paint
11. Countersink
14 15 8 2 12. SA-1
13. SA-2
14. A-1
15. A-2
12 9 3 16. A-3
17. A-4
18. A-5
6 4 19. A-6
Countersink
O-27 Tap
Gasket
SA-1 O-4 Cut O-24 Cut O-28 Cut
1001
A-1
A-2
Grease
1201 Packing SA-2
0601
A-3
A-4
Assembly Portion
of Facility
A-5
A-6
Washer A-7
0204
Nut A-8
Box
0105
1402
Staples I -1
1503 SA-3
Label
1603
A-9
Figure 2 Rearranged Operations Process Chart for the Gate Valve Assembly
Clean
Ream Mill
Part Manufacturing
Portion of Facility
Paint
Paint Drill
0403
Bore
Drill
T ap T urn Bore
T hread T ap
Packing
SA- 2
SA- 1
0601 Gasket
Greas e
1001
1201
W as her A- 7
0204
Nut
A- 8
0105
Box
O-3 3 Clean
1402
O-3 4
I -1
Staples
A- 9 SA- 3 1503
Label
1603
Figure 3 Value Network Map for the Gate Valve Assembly: Alternative #1
Clean
Part Manufacturing
Ream Mill
Portion of Facility
Paint Drill
Bore Turn
Packing Gasket
SA-2 SA- 1
0601 1001
Grease
1201
Assembly Portion
A- 6 A- 5 A- 4 A- 3 A- 2 A- 1
of Facility
Washer A- 7
0204
Nut
A- 8
0105
Box
O- 3 3 Clean 1402
O- 3 4
I -1
Staples
A- 9 SA- 3 1503
Label
1603
Figure 4 Value Network Map for the Gate Valve Assembly: Alternative #2
1. Cast
2. Drill
3. Bore
4. Turn
19 20 11 8 5. Cut
6. Clean
7. Thread
18 1 8. Ream
14 17 12 6 9. Tap
10. Mill
11. Paint
5 9 2 10-1 12. Countersink
15
13. SA-1
14. SA-2
15. A-1
13 16 10-2 3 16. A-2
17. A-3
18. A-4
19. A-5
7-1 4-1 7-2 4-2 20. A-6
811ASMLY
Y Y
T201972-4300 T201972-6700 TA201974 TB201971
13640300A MZ0901010166 TN100429 TN100432 TB100423 MZ060200142
763PRBRK 763PRBRK 764WELDM TB100408-5 TB100426
MZ0901010091 TA800218 TN100430
763SHR16 761SPWLD 761POLSH
763SHR16
Y
TB201970 TB201973 761HSTUD 761TWELD
MZ1304010054 MZ1304010054
763PRBRK
TA000009 TB100413-5 TB100416 TN200671 761FORM2
761PUNCH 761POLSH 761DBURR
761DBURR
763SHR16 TC201989-1
761TWELD 761PUNCH
771HCFIN 761PUNCH
761DBURR
763WELDM
761PUNCH
MZ1304020031
Z Z Z Z Z X X X Y X
T201962-6544 T201963-6431 T201964-6544 T201965-4738 T201966-4738 TA201967 TA201968 TA201969 TC201501-105 TN202444
MZ0901020056
763PRBRK 763PRBRK 763PRBRK 771VIKIN 771VIKIN 763ACRO 763DRLPR 763DRLPR
763PRBRK 763PRBRK
763IRONW 761PUNCH 763ACRO 764PSMAO
763SHR16 763SHR16 763SHR16 763BDSAW 763BDSAW 763IRONW
763SHR16 763SHR16 763BDSAW 764PSMAP
X Y Z STORAGE LOCATIONS
Y Y
TA201974 TB201971 T201972-4300 T201972-6700
13640300A MZ0901010166 TN100429 TN100432 TB100423 MZ060200142
764WELDM 763PRBRK 763PRBRK MZ0901010091 TN100430 TB100408-5 TB100426
TA800218
761SPWLD 761POLSH
763SHR16 763SHR16
Y
TB201970 TB201973 761HSTUD 761TWELD
MZ1304010054 MZ1304010054
763PRBRK
TA000009 TB100413-5 TB100416 TN200671 761FORM2
761PUNCH 761POLSH 761DBURR
761DBURR
763SHR16 TC201989-1
761TWELD 761PUNCH
771HCFIN 761PUNCH
761DBURR
763WELDM
761PUNCH
MZ1304020031
X X X Y X Z Z Z Z Z
TA201968 TA201969 TA201967 TC201501-105 TN202444 T201964-6544 T201966-4738 T201962-6544 T201963-6431 T201965-4738
MZ0901020056
771VIKIN 763ACRO 771VIKIN 763DRLPR 763DRLPR 763PRBRK 763PRBRK 763PRBRK 763PRBRK 763PRBRK
763ACRO 764PSMAO 763IRONW 761PUNCH
763BDSAW 763BDSAW 763IRONW 763SHR16 763SHR16 763SHR16
763BDSAW 764PSMAP 763SHR16 763SHR16
Figure 7 Operations Process Chart for Product # 2158002065 – A with Part Families
761
761
HSTUD/
FORM
LASER 761PEM 764BURNM 770PANG
761PUNCH
761AMADA
761 761
DBURR TWELD
761 761
761ASY
POLSH SPWLD
764BRAKE
764SHR20
764UNPUN 764SUBMR
764BEVLR
812ASM
763DRLPR
Y 763IRONW
763
771
MONRC 763
VIKIN 771HCFIN/
MON45 811ASM Shipping
763BDSAW
771 771TEXTR
763ACRO 771 FSWHL
SNDBL
X Y Z STORAGE LOCATIONS
761 761
761ASY
POLSH SPWLD
764BRAKE
764SHR20
764UNPUN 764SUBMR
764BEVLR
812ASM
763DRLPR
Y 763IRONW
763
771
MONRC 763
VIKIN 771HCFIN/
MON45 811ASM Shipping
763BDSAW
771 771TEXTR
763ACRO 771 FSWHL
SNDBL
X Y Z STORAGE LOCATIONS
TC201989-1
771HCFIN 761DBURR
770WHLBR 761PUNCH
763WELDM MZ1304020031
MZ0901020056 TA201968 TA201969 TA201967 TC201501-105 TN202444 T201964-6544 T201966-4738 T201962-6544 T201963-6431 T201965-4738
771VIKIN 763ACRO 771VIKIN 763DRLPR 763DRLPR 763PRBRK 763PRBRK 763PRBRK 763PRBRK 763PRBRK
763WELDM 761POLSH
763SHR16
761TWELD
761FORM2
MZ0901020056 TA201968 TA201969 TA201967 TC201501-105 TN202444 T201964-6544 T201966-4738 T201962-6544 T201963-6431 T201965-4738 761DBURR
763DRLPR 761PUNCH
764PSMAO
764PSMAP
763PRBRK
763IRONW
761PUNCH Sub-network 1
763SHR16
Sub-network 2
771VIKIN
Sub-network 3
763ACRO
763BDSAW
761PUNC 761DBUR
761FORM2 761TWELD 761POLISH 761HSTUD 761SPWLD
H R
761ASMLY
771HCFI
763SHR16 763PRBRK 763/764WELDM 770WHLBR 811ASMLY
N
Sub-network 2
Sub-network 3
811ASM
761 761 761 761ASY
FORM TWELD POLSH
763IRONW
771 / TEXT
771HCFIN
770WHLBR
763DRLPR 771
R
VIKIN
764PSMA
763BDSAW
763ACRO
Sub-network 2
Presenters:
Lily Susanto
Christine Djunaedi
• Application of Theory of
Constraints to supplement
lean thinking in custom
forge shops
through
Continuous
Improvement
*Source: Womack, J.P. and Jones, D.T. (1996), Lean Thinking: Banish Waste and Create Wealth in Your Corporation. New
York, NY: Simon and Shuster. ISBN 0-684-81035-2.
• Founded in 1923
• Located near Chicago, IL
• More than 300 forgings Testing
(mostly brass and
aluminum)
• Serves variety of
industrial customers
Forgings
Enhance the VNM with Flow Process Charts and Spaghetti Diagrams
to identify the Seven Types of Waste
TQM Six
Tools Identify the Bottleneck Process in the VNM Sigma
Method
s
Exploit/Elevate the Bottleneck Lean Toolkit
Analysi
s
Performance Evaluation of the VNM (using MPX, ARENA, CPLEX) to
compute their Impact on Throughput, WIP, and Operating Expenses
NO
Has the entire VNM for this part family been optimized?
YES
Subordinate the Value Network to the Beat of Have all part families been NO
the Bottleneck using DBR/FCS Scheduling investigated?
YES
STOP
• Routings of Parts
• P-Q Analysis and P-Q-$ Analysis
• From-To Chart
• Flow Diagrams for Current Layout
• Machine-Part Matrix Analysis
• Dendograms for Part Family Formation
• Modified Multi-Product Process Chart
160,000.00
140,000.00
120,000.00
Confidential
100,000.00
Quantity
80,000.00
60,000.00
40,000.00
20,000.00
0.00
$0.00 $100,000.00 $200,000.00 $300,000.00 $400,000.00 $500,000.00 $600,000.00 $700,000.00 $800,000.00
Revenue
3,500.00
CONFIDENTIAL
Criterion:
SELECT a part to include in Quantity
3,000.00
Six part families were formed (only Family 5 and Family 6 shown here)
Complete PFAST report available in Appendix
Transpor
tation
3.7 days
on
average
Bottleneck
ortation
Transp
SAWING VIBRATORY FORGING TRIMMING INSPECTION SHIPPPING
I I I I
I I
1025 pcs 1025 pcs
1025 pcs 1025 pcs 1 Days
2 Days
4 Days 1 Days
C/T = 11 sec C/T = 12 sec C/T = 22 sec C/T = 14 sec C/T = 7.3 sec
C/O = 20 min C/O = C/O = 36 min C/O = 36 min C/O =
Downtime = Downtime = Downtime = Downtime= 1h/ Downtime =
VSM: A visual1 Operator tool that helps
Operator
to understand
1 Operator the information and 2wk
Operator
Operator material flows for a part
family, from 2raw
Shift
Mat‟l Handling:
material Iuntil
Shift shipment 3 Shift
to the customers.
Mat‟l Handling:
Shift
Mat‟l Handling:
The method allows us to
Shift
Mat‟l Handling:
Mat‟l Handling:
identify the bottleneck/pacemaker
Forklift Forklift in a facility andForklift
Forklift
eliminate it Forklift
by using a process of
continuous improvement, such as Theory of Constraints (TOC). In the case of a
jobshop, due to the large number of interacting value streams, a Value Network Map
for each product family must be analyzed.
FORGING-1050 FORGING-1060
wee
ks
1 Days
Forklift
I
I I I I
4 Days C/T = 1800 sec 4 Days C/T = 22 sec 1 Days C/T = 22 sec 5 Days C/T = 14400 sec
C/T = 31 sec
Tugger Forklift Forklift Forklift C/O = min
C/O = 20 min C/O = C/O = 36 min C/O = 36 min
Downtime = Downtime = 2h/wk Downtime=2h/wk Downtime =
Downtime =
Operator 1 Operator 1 Operator Operator
1 Operator
Shift 3 Shift 3 Shift Shift
2 Shift
0 Days I I I
I
Forklift
0 Days 3.4 Days
9 Days C/T = 22 sec
1 Days C/T = 1800 sec C/T = 7.3 sec
C/T = 14 sec Forklift
Forklift Forklift
C/O = 36 min C/O = 36 min C/O = C/O =
Downtime= 1h/ Downtime=2h/wk Downtime = Downtime =
2wk
Operator 1 Operator Operator Operator
I
Shift 3 Shift Shift Shift
1 Days
Forklift
C/T = 14 sec
C/O = 36 min
I I I I
Ship Via
4 Days 9 Days 1 Days 5 Days UPS
C/T = 31 sec Tugger C/T = 1800 sec Forklift C/T = 22 sec
Forklift Forklift
C/T = 22 sec C/T = 14400 sec
C/O = 20 min C/O = C/O = 36 min C/O = 36 min C/O = min
Downtime = Downtime = Downtime = 2h/wk Downtime=2h/wk Downtime =
1 Operator Operator 1 Operator 1 Operator Operator
2 Shift Shift 3 Shift 3 Shift Shift
INSPECTION SHIPPPING
TRIMMING- ACID DIPPING AGING-8030 VIBRATORY
2010
I I I I I I
31 secs 1800 secs 22 secs 22 secs 14400 secs 14 secs 900 secs
4 days 9 days 1 days 5 days 1 days 4 days 0 days
Sawing Vibratory Blocking Forging Solution Trimming Acid Dip
36000 secs 1800 secs 7.3 secs
1 days 0 days Lead Time = 25.63 days VAR = 0.025
Processing Time = 54996.3 secs
Aging Vibratory Inspection
10.00
5.00
Acid Dip
14%
0.00
Trimming
ng
ip
be
g
e
n
n
rg
tio
in
io
D
Vi
gi
16%
t
Fo
lu
ec
d
A
im
ci
So
sp
A
Tr
In
Solution
Operation
20%
4020 2050
EXIT EXIT
4010 4020 FORGE OFFICE 5040
K.O. AREA VIBE
WATER
8030 ROD STORAGE
VIBE WOMEN
8010 TREAT
MEN
8030
8010 8010 STORAGE
LUNCH
VIBE HEAT ACID
ROOM
8010
SHIP.
ACID TREAT OFFICE
8010
DIP SHIPPING &
RECEIVING
TOOL INS. HOLD INSPECT
OFFICE DOCK
& DIE
INSPECTION
EXIT DEPT. EXIT
CAD
OFFICE
WOMEN
NURSE
MAINT. MAINT.
MEN
FINISHED
STORAGE
GOODS DEPT. OFFICE
CONF.
ROOM
Flow of Part Family #5
EXIT
Flow of Part Family #6
Location of Bottleneck
Jobshop Lean: Lean Manufacturing in Custom Forge Shops 206
Exploit/Elevate the Bottleneck
handling distances
Punch Presses Saws
• Poor lines of sight
Vibra
tory– Rod
Brass Heat
Material Flows in Slug
Treatment
Storage
PROCESS LAYOUT
• Flexibility (accommodates
new products and demand
fluctuation)
• Lacks „flow‟
• Batching → High queue times
→ High production lead times
CELLULAR LAYOUT
• Ideal for one piece flow and
short production lead times
• Needs duplication of same
machine type/s in multiple
cells
MODULAR LAYOUT
• Suited for complex flow networks
• Several machines are clustered
together to form „modules‟ (or
partial cells)
• Creates „flow‟ by linear
arrangement of „modules‟
Heat Treat
5050 (Vibratory
EXIT 1010
FORGE
4020 2050
EXIT EXIT
4010 4020 FORGE OFFICE 5040
Bowl)
K.O. AREA VIBE
• Split 8030
2030 2040 2010 SAWS
PUNCH PRESS
WATER
8030 ROD STORAGE
VIBE WOMEN
(Heat Treat)
8010 TREAT
MEN
8030
8010 8010 STORAGE
LUNCH
VIBE HEAT ACID
ROOM
8010
SHIP.
ACID TREAT OFFICE
EXIT
& DIE
DEPT.
INSPECTION
EXIT
in Appendix
CAD
OFFICE
WOMEN
NURSE
MAINT. MAINT.
MEN
FINISHED
STORAGE
GOODS DEPT. OFFICE
CONF.
ROOM
Flow of Part Family #5
EXIT
Flow of Part Family #6
Location of Bottleneck
Jobshop Lean: Lean Manufacturing in Custom Forge Shops 213
Exploit/Elevate the Bottleneck (contd.)
Performance Measures
STORAGE
1010 EXIT
EXIT FORGE
1020
Virtual Cell for Family #6
Virtual Cell for Family # 6
EXIT EXIT
Monuments/Shared
VIBE
VIBE
Monuments/Shared Resources
2060
K.O. AREA ACID DIP
8010 8010
2030 2010 2040
Workcenters
HEAT
STORAGE
ROD STORAGE
ACID
VIBE
TOOL
& DIE
SHIP.
OFFICE each part family even if
DEPT. SHIPPING &
relayout is not possible
LUNCH
ROOM
• Assign dedicated
OFFICE
EXIT EXIT
material handlers to
WOMEN
NURSE
FINISHED MAINT.
expedite the
MEN
Non-Value Added
Activity by Operator
during (Long) Die
Heating Process
Operator movement
1 trip back 1 trip back while waiting for the die
STORAGE
2 trips and forth and forth to heat up
Die movement
EXIT
FORGE OFFICE
K.O. AREA
EXIT
DIE STORAGE
25.00
20.00
15.00
Durations
10.00
5.00
0.00
Delay associated with Die Delay associated with Material Value Added Operations Operator Movement to Get/Put
Heating Handling Away Tools
Activities
Operator movement
1 trip back 1 trip back while waiting for the die
STORAGE
2 trips and forth and forth to heat up
Die movement
EXIT
FORGE OFFICE
K.O. AREA
EXIT
DIE STORAGE
Obvious Improvement: Move the switch board and tool rack closer to
the forge press and assign dedicated material handler for this forge
press (i.e. operate a Virtual Cell that has this forge press as the Drum)
Jobshop Lean: Lean Manufacturing in Custom Forge Shops 228
Exploit the Bottleneck (contd.)
Summary of Proposed Setup Activity on the Forge Presses 1030 and 1060
(Based on Video Tape)
25
Future Activity to
Exploit/Elevate
20 the Bottleneck
15
Durations
10
0
Delay associated with Value Added Delay associated with Operator Movement to
Die Heating Operations Material Handling Get/Put Away Tools
Activities
Operation
Op er at io n Transport
T r ansp o r t Delay
D elay Savings
9%
4 45%
21
24 51%
17 26
36% 55%
2
4%
0%
Total number of activities: 47 Total number of activities: 26
Operation Operation
Transport
Transport Delay
Delay Savings
Delay
29%
Savings
41% 14.97 min
10.78 min
20.64 min
Operation
24.14 min 56%
1.67 min
Transport Operation
66% 0.98 min
5%
Delay
Transport
3%
0%
Total setup time: 36.59 min Total setup time: 21.62 min
$100,000 $75,000
Costs $
$80,000
$60,000
$40,000 Paybac
Paybac Paybac
k k
k
$20,000 12
9 8
months months
months
$0
Minimum Expected Maximum
Scenario
$104,581
Purchase a multi-function
Use automated (or semi-
automated) systems for
Redesign other parts to eliminate features requiring Purchase new machines that cycle
“Exploit the constraint”
several machines
value-added tasks
one or more operations on the machine
material handling
(MAKE BETTER USE OF AVAILABLE CAPACITY) faster for some parts
Optimize process parameters using Six Sigma
Outsource
methods
Add a shift?
Group schedule part families to exploit Depending on the sophistication of the machine(s), Use overtime?
common setups, tooling and process they could be run in lights-out mode overnight
settings
Redesign the parts to eliminate the
feature(s) requiring the external operation
“Elevate the constraint”
(ADD CAPACITY)
Reduce (if any) absenteeism and “bs-ing time”
Reduce transfer batches (“one- Modify their current process plans to use
piece flow”) to minimize machine or alternative machine already in the host
idle time due to inter-machine Eliminate exception operations that are cell
Overlap shift changes to eliminate tear-down transfer delays forcing parts to leave their host cell to
and start-up delays visit machines external to that cell
Virtual Cells with
material handlers to
“group/connect” the
Reduce downtime using TPM Strategies to reduce, Hybrid Cellular Layout
machines in the cell for
each part family
strategies better yet eliminate, Cascading
Shared machine types can be Flowlines
intercell flows of parts retained in process groups, Hybrid
but individual machines could Flowshop
Reduce tool-changing times ex. machining and turning
centers have pre-set tooling, ATC‟s, combination tools,
that utilize available be dedicated to part families Remainder
Cell
large tool magazines, toolwear sensing with replaceable capacity on common Modular Layout
inserts, etc.
machine types (Partial Cells)
238
(Suri) Use smaller-scale
- Change material
across multiple cells; seek smaller
and cheaper machines suited to
certain families of parts (each
family is specific to any one cell)
(Suri)
Ex: Dishwasher vs. (Large) Wash
Tank, Table-mounted Saw vs.
(Large) Band Saw, Electrical
induction-hardening furnace vs.
(Large) Gas-fired furnace (for Heat
Treatment), (small & off-line) Paint (H&W) Operate the
(H&W) Launch an
Conveyorized) Paint Line
program (SMED)
Reduction
each part family into two
Group schedule
common setups
LMP2 LMS2
to exploit
(Suri) If most of the machines
needed cannot be dedicated (H&W, Irani) Create dynamic (H&W, Irani) Execute the P-Q-R-$ Analysis module in
and co-located in a cell, create a and reconfigurable cells, or PFAST; say we are able to segment the product mix
time-sliced virtual cell partial cells (LAYOUT being run through the Monument into Runners/
MODULES) by placing the other Repeaters/Strangers and know which part families they
In-process Vision
(H&W, Irani) Outsource the machines required in a mobile belong to; dedicate some machines in the department to
gauging & Sensors
process (ex. purchase pre- cell on wheels and moving them run the High Volume (and/or) High Revenue parts but,
control
painted parts to eliminate the so as to co-locate them at/near for the REMAINDER CELL of machines in the
department which must run the rest of the parts, deploy Die
centralized painting department) the Monument. When the orders Six Sigma
SMED , group tooling, etc. quick response strategies Design
and establish a “milkrun” for the part family “dry up”, this
schedule for parts delivery “phantom cell” is dismantled,
and the equipment is re- (Irani) Execute PFAST on a daily, maybe weekly, basis to identify, possibly
Electronic Heijunka allocated into new mobile cells, revise, part families and recognize outliers; assign each part family to a
Kanban (Level Loading) suited for new part families virtual cell in the (existing?) Process Layout, and let each material handler
identified (by PFAST) in the act as a roving “Cell Foreman” and Expeditor for that part family
Schedule visibility via internet current product mix
239
Acknowledgements
• Ryan Engelbrecht
• Doug Brown, George Layne, Peter Campbell
• Venkatesh Kenthapadi, Nitin Jain
• Forging Defense Manufacturing Consortium
• Advanced Technology Institute
• Forging Industry Association
• National Science Foundation
FORGING-1050 FORGING-1060
Bottleneck
wee
ks
1 Days
Forklift
I
I I I I
4 Days C/T = 1800 sec 4 Days C/T = 22 sec 1 Days C/T = 22 sec 5 Days C/T = 14400 sec
C/T = 31 sec
Tugger Forklift Forklift Forklift C/O = min
C/O = 20 min C/O = C/O = 36 min C/O = 36 min
Downtime = Downtime = 2h/wk Downtime=2h/wk Downtime =
Downtime =
Operator 1 Operator 1 Operator Operator
1 Operator
Shift 3 Shift 3 Shift Shift
2 Shift
I I
I
Bottleneck I
2050
I I
0 Days I I I
I
Forklift
0 Days 3.4 Days
9 Days C/T = 22 sec
1 Days C/T = 1800 sec C/T = 7.3 sec
C/T = 14 sec Forklift
Forklift Forklift
C/O = 36 min C/O = 36 min C/O = C/O =
Downtime= 1h/ Downtime=2h/wk Downtime = Downtime =
2wk
Operator 1 Operator Operator Operator
I
Shift 3 Shift Shift Shift
1 Days
Forklift
TRIMMING-2030
1021 Blocking
1060 & 1050 1012 ELECT.
Movement Distances Equipment
1040
Forging
COMP. Receiving 1 51 Manual
Opr 3 1020 1030
STORAGE EXIT
1 2 26 Tugger
EXIT
FORGE
1010 2 3 276 Forklift
4020 2050
Vibratory
3 4 257 Forklift
EXIT Opr 2 EXIT
4010 4020 FORGE OFFICE 5040 4 5 47 Forklift
K.O. AREA VIBE
5 6 153 Forklift
2060 2045 2035 2040
6 7 85 Forklift
2030 2040 2030 EXIT 7 8 82 Forklift
DIE STORAGE
2030 2040
Trimming
2010 SAWS
8 9 211 Forklift
PUNCH PRESSOpr 5
Sawing 9 Shipping 291 Forklift
Opr 1
Solution WATER
8030
Aging ROD STORAGE
VIBE WOMEN
8010 TREAT Raw Mat‟l Supplier
Opr 7 Opr 4 MEN
Vibe 8030
Opr 8 8010 8010 STORAGE s
LUNCH ek
VIBE HEAT ACID we
ROOM 6
4-
8010
NURSE
FINISHED MAINT.MAINT.
MEN
STORAGE
GOODS DEPT. OFFICE
Careful Analysis of
MMPPC for All Parts
U-Shape Flow
Alignment
Preliminary Block
Layout Diagram
Start Implementation
of Layout
Forge Press
FORGE OFFICE
1021
COMP.
STORAGE
1010 EXIT
EXIT 1020
FORGE
EXIT EXIT
VIBE
VIBE
2060
K.O. AREA ACID DIP
8010 8010
2030 2010 2040
HEAT
TREAT EXIT
DIE STORAGE 8010 8030
8010 2040 2030 2040
8010 SAWS
8030
PUNCH PRESS
WATER
2045 2035 2040
TREAT
Future Layout
MEN
STORAGE
ROD STORAGE
ACID
VIBE
TOOL SHIP.
OFFICE
& DIE
DEPT. SHIPPING &
RECEIVING
LUNCH
ROOM
WOMEN
NURSE
FINISHED MAINT.
MEN
When applied to a single factory, the classic framework for manual implementation of Production
Flow Analysis (PFA) consists of four stages, each stage achieving material flow reduction for a
progressively reducing portion of the factory: Factory Flow Analysis (FFA), Group Analysis (GA), Line
Analysis (LA) and Tooling Analysis (TA).
In FFA (Figure A.1), dominant material flows between shops (or buildings) are identified. In addition,
if parts are observed to backtrack between any of the shops, these flows are eliminated by a minor
redeployment of equipment. FFA may often be redundant for a factory that essentially consists of a single
machine or fabrication shop.
MATERIAL
28
16 2
15
1
27 3
53 1 3
1
1
1 24
3 1
126
84 151 3
4
8
1
1 12 26
3 DEPARTMENTS
9 27 1 = BLANKS
5 45 1 2 = SHEET METAL WORK
3 3 = FORGE
1 4 = WELDING DEPT
2 5 = MACHINE SHOP
6 = ASSEMBLY
9 = OUTSIDE FIRMS
FINISHED
6
PRODUCT
MATERIALS 1 MATERIALS 1
5 4 3 2 5 3&4 2
6 6
FINISHED FINISHED
PRODUCT PRODUCT
248
In GA (Figure A.2), the flows in each of the shops identified by FFA is analyzed. GA analyzes
operation sequences of the parts being produced in a particular shop to identify manufacturing cells. Loads
are calculated for each part family to obtain the equipment requirements for each cell. Each cell usually
contains all the equipment necessary to satisfy the complete manufacturing requirements of its part family.
Due to sharing and non-availability of equipment, some intercell material flows and flows to/from vendors
may arise.
In Line Analysis (LA) (Figure A.3), a linear or U-layout is designed for the machines assigned to each
cell. The routings of each part assigned to the cell and the frequency of use of each routing are used to
develop a cell for efficient transport as well as minimum material handling and travel by operators.
MATERIAL
65 7
1
1 2 3 2
HS4 MO HS
1
2 6
11
3 3 2 4
5 7 6 4
MV DH MH DS
1 1
1
8
SA
41 2 5 4 4 16 2
MATERIALS
72
1
HS4
17 6 4 3
4 2 6 1 7 1 5
42
DH MH DS MV
1 2
8
15
5
8
SA
72
249
PART/PRODUCT
K L L M M L M M E E E E E K E E K E M K M M M K E E E K K M E
4 4 4 4 4 4 4 4 4 4 3 1 1 4 4 4 3 3 4 4 4 4 4 3 7 4 3 4 4 6 1
8 8 8 4 7 8 8 4 1 8 4 2 2 7 7 8 4 3 8 4 5 5 8 4 3 6 3 5 3 1 8
2 3 2 2 6 3 1 2 7 5 2 2 2 6 7 5 5 4 2 2 6 6 3 0 9 3 2 1 5 5 6
5 8 6 7 9 8 9 7 9 9 6 0 8 9 8 8 9 9 6 7 9 9 8 9 2 6 9 9 9 9 9
1 8 7 6 3 8 5 6 5 6 7 4 8 7 2 6 6 4 5 6 1 1 6 8 4 5 9 0 2 4
A B E F M C D D C D B H A
M DMT(3) X X X X X X X X X X
A DM(3) X X X X X X X X X X X X X
C
H PG X X X X X X
I DXY(3) X X X X X X X X
N
P&GR X
E
/ PGR X X
W PGH
O
R
K PGG X X X
S P&G X X X X X X X X X X X X X
T
A RP X
T PGB X X X X X X
I
O W&P X X X X X
N WG3 X
COMPONENT – MACHINE CHART. INITIAL RECORD. FORGE.
PART/PRODUCT
L K M E K L E K K K M M M E E E E E M K L M M M K E E E E E M
4 3 4 3 4 4 7 3 4 4 6 4 4 3 1 1 4 4 4 4 4 4 4 4 4 4 4 1 3 4 4
8 4 8 3 4 8 3 4 5 3 1 8 4 4 2 8 1 8 8 8 8 5 5 4 7 7 6 2 3 8 7
2 5 2 4 2 3 9 0 1 5 5 1 2 2 2 6 7 5 3 2 3 6 6 2 6 7 3 2 2 5 6
6 9 6 9 7 8 2 9 9 9 9 9 7 6 0 9 9 9 8 5 8 9 9 7 9 8 6 8 9 8 9
7 6 5 4 6 8 8 9 0 2 5 6 7 4 4 5 6 6 1 8 1 1 6 7 2 4 8 5 6 3
B D C M A C D H A D B E F
PG X X X X X X
GROUP-1
DM 3/1 X X X X
M DXY 3/1 X X
A RP X
C FAMILY - 1
H
I P&G X X X X X X X X X X X X ONE “EXCEPTION” X
N DMT 3/2 X X X X X X
E DM 3/2 X X X X X X
GROUP-2
/
W DXY 3/2 X X X X X X
O W&P X X X X X
R WG3 X
K
S FAMILY - 2
T PGG X X X
GROUP-3
A PGB X X X X X X
T
I PGR X X
O DMT 3/3 X X X X
N DM 3/3 X X X
P&GR X
FAMILY –3
COMPONENT – MACHINE CHART. AFTER FINDING FAMILIES AND GROUPS
250
In Tooling Analysis (TA) (Table A.1), the principles of GA and LA are integrated with data on the
shape, size, material, tooling, fixturing, etc. attributes of the parts. TA helps to schedule the cell by
identifying families of parts with similar operation sequences, tooling and setups. It seeks to sequence
parts on each machine and to schedule all the machines in the cell to reduce setup times and batch sizes.
This increases available machine capacity on bottleneck work centers in the cell.
φ
(( ∃% ; 56, %
/ ((( −
;%∋ ;%∋
∃ ∃ <> 0
=(((
> ++,4
−
:, ∃= 2
4 ∃2,4
2
∃ 56,4
%∋
6
1 .∋ >
? 7 , ?
%∋
%9
251
Design of High-Variety Low-Volume (HVLV)
Manufacturing Facilities using PFAST
Shahrukh A. Irani
Department of Industrial, Welding and Systems Engineering
The Ohio State University
Columbus, OH 43210
Phone: (614) 688-4685
Email: irani.4@osu.edu
Introduction
Finally, the re-design of an existing facility layout to simplify material flows and map interacting
value streams prior to the implementation of Lean Manufacturing for high-variety low-volume
(HVLV) manufacturers has been simplified! PFAST (Production Flow Analysis and
Simplification Toolkit) is a software package for material flow analysis developed at the Ohio
State University that extends the classical manual methods of Production Flow Analysis
developed by Prof. John L. Burbidge in the early 1970’s. PFAST can be used to analyze material
flows at any level in a facility: Between buildings, between departments or shops in the same
building, between cells in a shop, between machines in a manufacturing cell, in the workspace
around a single machining center, etc.
252
Table 1(b) Causes of Inefficient Material Flows in a Facility
Building architecture
Locations of manufacturing departments
Locations of support services and utilities
Design of the network of material handling aisles
Locations of input/output points of access between departments
Shortage of space for facility expansion
Process plans for making parts and products
Variety of routings in the part mix
Current manufacturing technology
Current material handling equipment
Current parts and WIP storage systems
Current material handling scheduling policies
Choice of subcontracted operations and/or parts
In addition to the design of greenfield or brownfield facility layouts, PFAST could help to
evaluate the strategic benefits of numerous other strategies for material flow simplification to
support Lean Manufacturing, as shown in Table 2.
Since PFAST uses three types of input data – operation sequences, machine-part matrices and
From-To charts, it could be used for a variety of projects dealing with material flow analysis and
simplification. Brief descriptions of these projects appear in Tables 3(a)-(e).
Descriptive statistics for routing data based on P-Q Analysis, P-Q-$ Analysis and P-Q-R-$ Analysis
Descriptive statistics for material flow network in facility
Grouping of similar routings
Detection of redundant variety in routings
Identification of “misfit” (or outlier) routings
Analysis of in-house vs. subcontracted material flows
Elimination or reduction of poorly utilized material flow paths
Detection of flow backtracking in routings
Detection of flow backtracking in material flow network
Detection of cross flows among aisles in the facility
Detection of recurrent combinations (or sequences) of operations in routings
Evaluation of current vs. desired flexibility of existing manufacturing equipment
Creation of alternative routings for key products
253
Table 3(b) Using PFAST for Cellular Manufacturing
Feasibility assessment for implementation of manufacturing cells using SICGE
classification of the machines
Shared machines that will be required in several cells
Parts whose routings contain only unshared machines
Parts whose routings contain only shared machines
Parts whose routings contain both unshared and shared machines
Specific number of cells that could be implemented
Parts that could not be produced in cells due to complexity of their routings
Composition (machine group and part family) of each cell
Complexity (number of different machines and parts) of each cell
Homogeneity analysis of the part mix based on routing similarities
Parts that do not belong to any cell
Parts whose routings span more than one cell
Parts with “exception” (or outlier) operations external to their host cell
Parts that could be produced in more than one cell
Duplication of equipment required in two or more cells
Alternatives for the number and composition of the cells due to shared machines
For a fixed number of cells
For a variable number of cells
Analysis of the stability of cell compositions due to changes in part mix
Prioritization of Integrated Product and Process Design (IPPD) in order to
eliminate intercell flows, exception operations and capacity sharing between cells
Support of kaizen events for detailed planning of each cell
Capacity Requirements Planning
Machine allocation and load balancing, especially if intercell flows involved
Capital investment for purchase of new machines and technology upgrades
Layout, material handling and scheduling of intra-cell part flows
Layout, material handling and scheduling of inter-cell part flows
TOC analyses of capacity-constrained machines in each cell
Support of what-if analyses to evaluate strategies to eliminate intercell flows
Redesign the parts to eliminate exception operations
Combine cells that require common machines
Subcontract, even eliminate, parts with exception operations
Buy extra machines to distribute among competing cells
Purchase multi-function centers to replace 2-3 machine sets in one or more cells
Put shared machines in a centrally located Common Facilities cell
Reroute operations on bottleneck machines to alternative machines in the cells
Design the overall facility layout to minimize inter-cell transfer delays
Speed up the material handling between the cells using visual signals
Adopt priority scheduling rules for parts that require inter-cell flows
254
Table 3(c) Detailed Computer-aided Design and Operations Analysis for a Pilot Cell
Selection of the family of parts to produce in the cell
P-Q Analysis and P-Q-$ Analysis of the “business” assigned to the cell
Capacity requirements for the cell
Machine requirements vs. actual allocations made to the cell
Exception operations that cannot be done inside the cell
Machines that could not be assigned to the cell due to insufficient workload
Monuments that are external to the cell
Support services that are external to the cell
Intercell flows
Due to exception operations
Due to machine overloads caused by fluctuations in customer demand
Access to identical machines in other cells when internal breakdowns occur
Access to identical machines in other cells where operators with similar skills work
Line, U or S layout for the cell using STORM and PFAST software tools
Flow Diagram for the cell
Current and Future State Value Network Maps (VNM) for the cell using Visio and
FactoryFlow software tools
Performance evaluation of the cell using MPX and Arena simulation software tools
Operations scheduling for the cell using PREACTOR or ASPROVA software tools
255
References
Arvindh, B. and Irani, S. A. (1994). Cell formation: The need for an integrated solution of the
subproblems. International Journal of Production Research, 32(5), 1197-1218.
Chen, C.Y. and Irani, S.A. (1993). Cluster first-sequence last heuristics for generating block
diagonal forms for a machine-part matrix. International Journal of Production Research, 31(11),
2623-2647.
Daita, S.T., Irani, S.A. and Kotamraju, S. (1999). Algorithms for production flow analysis.
International Journal of Production Research, 37 (11), 2609-2638.
Irani, S.A., Zhang, H., Zhou, J., Huang, H., Tennati, K.U. and Subramanian, S. (2000).
Production flow analysis and simplification toolkit (PFAST). International Journal of Production
Research, 38(8), 1855-1874.
Irani, S.A. & Huang, H. (2000, May 24-26). A pattern recognition approach for facility
compaction and selection of flexible automation. Proceedings of the North American
Manufacturing Research Conference (NAMRC ), Vol. XXVIII: University of Kentucky,
Lexington, KY, and NAMRI/SME, Dearborn, MI, 365-370. Available as SME Technical Paper#
MS00-225.
Irani, S.A. and Zhou, J. (1999). Algorithms for Production Flow Analysis. In Industrial
Engineering Applications and Practice: A Users’ Encyclopedia (CD-ROM, ISBN 0-9654599-0-
X), A.K. Mital & J.G. Chen (Eds.), International Journal of Industrial Engineering: Cincinnati,
OH.
Irani, S.A. and Huang, H. (1998). Layout Modules: A novel extension of hybrid cellular layouts.
Proceedings of the 1998 International Mechanical Engineering Congress and Exposition, Winter
Annual Meeting of the ASME, November 15-20, Anaheim, CA.
Irani, S.A. and Ramakrishnan, R. (1995). Production Flow Analysis using STORM. In Planning,
Design and Analysis of Cellular Manufacturing Systems. Editors: A.K. Kamrani, H.R. Parsaei
and D.H. Liles, Elsevier Science BV: New York, NY.
Irani, S.A., Cavalier, T.M. and Cohen P. H. (1993). Virtual manufacturing cells: Exploiting
layout design and intercell flows for the machine sharing problem, International Journal of
Production Research, 31(4), 791-810.
Irani, S.A., Cohen P. H. and Cavalier, T.M. (1992). Design of cellular manufacturing systems.
Journal of Engineering for Industry, 114(3), 352-361.
Minitab (Rel. 11) Reference Manual (1996, June). State College, PA: Minitab Inc.
256
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
Abstract
This paper contrasts the “Toyota Lean” model with the “Jobshop Lean” (JSLEAN) model and
lists key reasons why custom forge shops need to adopt the JSLEAN model instead of the
“Toyota Lean” model. The foundation for the JSLEAN model is a focus on “Lean Flow” to
design a flexible layout for a forge shop i.e. a layout that (1) minimizes overall production flows,
(2) maximizes unidirectional paths for the production flows and (3) minimizes the cost of
production flows to fulfill to each and every order. A detailed case study is presented to
illustrate the approach to design of flexible forge shop layouts using the PFAST (Production
Flow Analysis and Simplification Toolkit) software. PFAST helps to implement a new
computer-aided layout design method developed specifically for jobshops that facilitates the
deployment of the JSLEAN approach.
Introduction
Forgings are often dismissed for short run opportunities due to either the misperception that
forgings are not suited for short run production or the lack of enabling technology to produce
short run forgings. In addition, forging education continues to limit the use of forgings in both
industry and the Department of Defense. In many cases, forging designers and buyers are
hamstrung with a lack of acquisition data, source data, or capability data to source forgings.
Lastly, the process-oriented facility layout of most forge shops engaged in short production runs,
combined with their batch-oriented processes and equipment monuments, further limits their
ability to be cost-effective suppliers to the military.
In the report developed by the Forging Industry Association titled Forging Industry Vision of the
Future1, it is stated that, “to position itself for world leadership in the year 2020, the forging
industry has determined that its primary efforts should fall into five program groups: (1)
production efficiency, (2) energy efficiency, (3) recycling, (4) environmental protection, (5)
enterprise issues ……. Through the process of analyzing the key competitive challenges that will
shape its future, the forging industry has identified specific goals that will have the most
profound impact on the competitiveness of the industry as a whole and on the value of its
contribution to the global manufacturing market by the year 2020. Attaining these strategic
targets will assure that the U.S. forging industry becomes the world leader in customer-focused,
efficient and cost effective supply of superior quality components. These goals include:
Tooling--Increase die life by at least 10 times that of current levels. Reduce per-part die system
costs by at least 50%. Produce tooling within 24 hours from time of order.
1
Available at www.forgingmagazine.com/misc/vision/.
257
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
Energy--Reduce the total forging process energy input by 20% while cutting the per-piece energy
cost by 75%.
Material utilization--Achieve a minimum overall reduction in raw material consumption of 15%.
Reduce the scrap rate (increase material utilization) by 90%.
Productivity--Improve per-employee productivity by 50%. Reduce per-piece labor costs by 60%.
Achieve average forging facility up-times of 90%.
Quality--Reduce rejected or returned work to less than 25 parts per million. Achieve ±6 sigma
process control.
Environment--Generate no harmful gas combustion products; completely eliminate aerosol
emissions within forging plants; and recycle all fluids necessary to forging operations …..”
Also, a recent survey of 200 North American mid-sized manufacturers (Manufacturing
Engineering, October 2000, page 22) states that “… some 60% of the companies surveyed
reported that improving plant-floor productivity is the most important issue they face. Within
this group, half are seeking ways to shorten the time needed to implement workflow process
changes …… many who responded to the survey want to improve workflow processes on the
fly, and also want operations people on the shopfloor, not IT personnel, to implement these real-
time solutions that are easy to implement and use”.
This paper presents an approach for custom forge shops supplying the Defense Logistics Agency
(DLA) and Department of Defense (DOD) to understand the complex multi-product flows in
their facilities. It will help them to recognize how their current facilities help/inhibit the design
and operation of waste-free flow of orders. In turn, this will help them to identify and prioritize
the implementation of Jobshop Lean initiatives for cost and lead time reduction that are designed
specifically for jobshops, and not high-volume assembly line-type facilities. Forge shops could
streamline their existing layouts, improve the performance of their existing material handling
systems and change shopfloor communication systems to be more responsive to the needs of
their customers. With an effective layout and complementary shopfloor systems in place, any
forge shop could realize savings due to reduced work-in-process inventory, reduced scrap and
rework, reduced production lead times and effective order tracking and progressing.
So, should forge shops adopt standard Lean Manufacturing strategies such as Manufacturing
Cells, Setup Reduction, Process Standardization, Visual Workplace Design and Pull Scheduling
2
Customer Wait Time = Administrative Lead Time [ALT] + Production Lead Time [PLT]
258
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
that have been adopted in other sectors of industry, especially automotive and aerospace OEM’s
and their Tier 1/Tier 2 suppliers? Unquestionably, the OEM’s and their top-tier suppliers have
realized major productivity improvements by implementing the well-known “Toyota Lean”
model. However, custom forge shops that supply the DLA and DOD operate more like
jobshops. Hence, their business model (high product variety and low volumes, or HVLV) is
unlike the business model (low product variety and high volumes, LVHV) of the OEM’s and
their top-tier suppliers.
259
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
1(a) shows the flow path of a single forging that is being produced in at least three different
locations. This dispersion of the manufacturing assets, and the functional (or process village)
layout of the facility at each location, results in a Value Added Ratio (Actual Man Hours/Total
Lead Time) of about 1%. Figure 1(b) presents a comparison of the Administrative Lead Time
(ALT) and Production Lead Time (PLT) of several forgings supplied to the DLA by a single
forge shop. Forgings that have a high unit price are seen to have the highest lead times in both
dimensions, which is the primary reason for high WIP costs. Figure 1(c) illustrates the existing
chaos in the material flow network at a DOD supplier of forgings. Figure 1(d) illustrates the
existing chaos in the material flow network at a DLA supplier of forgings.
Clearly, there is a need for new concepts and analysis tools suited specifically for forge shops to
“undertake the journey" to Lean Manufacturing in a manner that suits their business model and
manufacturing environments, instead of verbatim adopting the Toyota Lean model. It is not our
intention to take anything away from what the architects of the Toyota Production System have
achieved. However, it must be recognized that the typical HVLV manufacturer operates in a
Make-To-Order business environment. Hence, these jobshop-type manufacturers do not have an
extensive suite of well-documented and easy methods and tools to support their implementation
of Lean Manufacturing!
Some Key Challenges for Jobshops that wish to Implement Lean Manufacturing
The how-to books on design and operation of “Lean” jobshops are significantly fewer in number
than those written for Lean Manufacturing for assembly line-type facilities. Here is a sample of
challenging issues in the JSLEAN arena that lack effective solutions:
How does a jobshop segment its product mix into categories such as “Runners”,
“Repeaters” and “Strangers”? Are computer-oriented methods, such as Product-
Quantity-Routing-Revenue (P-Q-R-$) Analysis, Group Technology and Product-Process
Matrix Clustering, capable of analyzing a large database of anywhere between 500 to
5000+ routings?
How does a jobshop identify and implement not just a single “pilot” cell, but all
potential cells for different families of parts that may exist in its large product mix?
What does it do about the “cats and dogs” in its product portfolio? Could it implement
virtual (dynamic and reconfigurable) cells for a portion of its product mix?
How does a jobshop develop a self-motivated workforce knowledgeable in Industrial
Engineering skills who seek to eliminate muda in a wide variety of administrative and
production processes on a daily basis?
How does a jobshop adopt, or adapt, the concepts and models of Lean Thinking when:
o demand forecasts are unreliable or non-existent?
o suppliers may not be prepared to deliver JIT?
o equipment must be multi-function, and not right-sized, to compensate for a small
multi-skilled workforce?
o customers could be here today but gone tomorrow?
o drawings, route sheets, inspection plans, gauges, tools, etc. for past (or new)
orders need to be retrieved (or developed from scratch) on a routine basis?
260
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
Location 1 Facility
~
~ Processor
Shipping
38 39
35 36 37 41 42
~
1500'
~
Location 3 Facility
4 Straighten
Inspect 18 27
15
8 Age
Saw Trim 31 28
5 11 16
2760 100' 10 Etch Heat Treat
3000 6
Grind
12 17 14 29
26
500 260.4
0 100' 200' 100'
Frequency of
8
Occurance
6
4
2
0
Age
Machine
Penetrant
Heat Treat
Etch
Grind
Cleanup
Shipping
Straighten
Inspect
Saw Trim
Stockroom
Press
Processor
Shop
Outside
Operation
700
600
500
400 Low Unit Price Parts
100 Average LT
0
0 50 100 150 200
261
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
262
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
How does a jobshop define and distill its “core manufacturing competencies” into a
guidebook that its sales staff could use to accept, evaluate or reject new orders based on
past cost/benefit performance measures?
How does a jobshop implement Finite Capacity Scheduling without purchasing
expensive software, since Theory Of Constraints and Drum-Buffer-Rope scheduling
have been known to succeed in such facilities?
How does a jobshop layout its facility to achieve flow and be flexible to changes in
product mix, demand and manufacturing technology?
How does a jobshop train its material handlers to perform shopfloor scheduling and
order progressing functions, similar to the “whirligig beetles” (“mizusumashi”s) who are
employed in the Toyota Production System?
How does a jobshop adopt real-time inventory tracking technology utilized in
warehouses and distribution centers to achieve pseudo-JIT operations?
How does a jobshop develop a partnership with its suppliers in order to better estimate
and control supplier delivery schedules?
Typically, the forging equipment in a forge shop is in some type of work cell composed of
heating, forging and trimming capabilities. Unfortunately, these machines have significant
foundations that make it economically infeasible to relocate them. However, the support
equipment for forging, such as induction heating, flash trimming and machining, are mobile, as
are other support operations such as material storage, tool and die storage/repair, material cutting
(shear and saw), shot blasting, magnetic particle inspection. Therefore, the foundation for
implementation of Jobshop Lean in forge shops is:
(1) grouping of the equipment for these support operations into layout modules, and locating
these modules in close proximity to the forging machines,
(2) scheduling the monuments such as heat treatment and plating to coordinate with the
production schedules of the layout modules.
263
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
Machine shops that are attached to forging facilities are highly suited for implementation of both
manufacturing cells layout modules. Conversion of machine shop layouts into Cellular or
Modular configurations will automatically help forge shops to improve delivery performance,
reduce work in process inventory levels and eliminate scrap.
264
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
Case Study
The Jobshop Lean strategy was used to design a flexible layout for a custom forge shop, with the
help of the PFAST (Production Flow Analysis and Simplification Toolkit). PFAST is a software
package that consists of an integrated library of computer programs for material flow analysis.
This package integrates Systematic Layout Planning (SLP) and Production Flow Analysis (PFA)
to implement a new computer-aided layout design method developed specifically for jobshops. A
primary capability of this package is the ability to analyze the manufacturing routings of up to
1000 different forgings and identify part families i.e. parts that use the same sets of resources and
have similar, often identical, routings.
1. Data Collection
The sample data provided by the company consisted of 530 products and 57 pieces of equipment.
For detailed Production Flow Analysis of the facility, we collected the P-Q-R-$ information for
each product, which includes: (1) Product Number and Name, (2) Annual Production Quantity,
(3) Manufacturing Routing, and (4) Annual $ales/Revenue. To explore the potential for
manufacturing cells, layout modules and/or product-focused factories, we requested additional
attributes for each piece of equipment besides equipment number and description of equipment:
movability and duplicability. These two additional attributes of each machine, respectively,
address the following two questions: (1) Would it prove exorbitantly expensive to relocate that
piece of equipment? and (2) Could additional copies of the equipment be purchased at reasonable
expense if it is required by several families of products, and each family were to be produced in a
dedicated manufacturing cell?
265
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
80-671391
80-4012179 80-35-B357
80-4010346
80-4012174
Product Quantity
80-4030011870964
80-27708-302UP
Product Revenue
In the P-Q-$ Analysis plot (Figure 2), all of the products in the complete list of forgings
manufactured by the forge shop have been plotted in two dimensions: The X axis of the scatter
plot represents Revenue and the Y Axis of the scatter plot represents Quantity. If we split each
axis into two zones – Low and High – then the product mix could be split into four segments –
(High Volume, High Revenue), (Low Volume, High Revenue), (High Volume, Low Revenue)
and (Low Volume, Low Revenue). Hence, P-Q-$ Analysis provides important guidelines for
correctly selecting a representative sample of products from the original population of products,
preferably those products that represent a large proportion of the Total Quantity produced and
Total Revenue earned by the company. Based on this analysis (and indicated by the dotted line
circling the products selected), only those products produced in quantities greater than 1800 and
earning revenues higher than $30,000 were selected as the “Working Sample” of products on
which to base the facility layout design. The number of products included in this sample is 44,
which is only about 8% of the total number of products in the complete population. However,
this sample of products accounts for 68% of the Total Production Volume and 46% of the Total
Revenue for the company. After the absorption of 35 additional products that have routings
identical to the 44 products, the final Working Sample of products (Table 1) included about 15%
of the total number of products in the original population of 530 forgings, yet accounted for 74%
of the Total Production Volume and 54% of the Total Revenue earned by the company.
266
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
“1”s) cannot be isolated into independent sets, it was concluded that the ideal of Lean
Manufacturing as observed at OEM and Tier 1 or Tier 2 facilities – independent product-focused
(or product family-based) manufacturing cells – may not be the best option for the custom forge
shop. Therefore, it was decided to explore Hybrid Layout options that would achieve streamlined
flow for the diverse sample of products.
To design a Hybrid Layout for the forge shop, we used PFAST to generate the Modified Multi-
Product Process Chart (MM-PPC) (Table 3) for the Working Sample of products. Unlike the
Machine-Product Matrix representation of the product routings, where the “0/1” coding of the
operations loses the actual material flow path of any product, here each routing is modeled as a
linear production line dedicated to the production of that product. The products are shuffled and
re-arranged such that products with similar routings are grouped together and machines that they
use are placed in a Flowline configuration, similar to an assembly line. Using the MM-PPC,
flexible layout configurations (Cascading Flow Lines, Virtual Cells, Hybrid Flowshop and
Modular Layouts) that are well suited for the high-variety low-volume manufacturing conditions
of any jobshop can be generated. This is because the MM-PPC visually guides the Industrial
Engineer to group products with similar/identical routings into families, and the machines that
each family uses into layout modules, manufacturing cells or functional departments.
267
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
268
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
269
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
80-9627713-301UP 17 6 56 16 11 10 6 7 12 8 54 57 54 53 8 55
80-9627715-301UP 17 6 56 16 11 10 6 7 12 8 54 57 54 53 8 55
80-3260-041 17 6 2 11 10 29 28 54 57 55
80-C27416-2 17 6 2 11 10 29 54 55
80-121009-00 17 39 40 21 22 55
80-121188-002 17 39 40 21 22 55
80-121018-00 17 39 40 21 22 M3 55
80-4030011870964 17 39 40 21 22 53 29 28 4 55
80-921790 17 3 7 12 8 54 29 28 4 55
80-4030007296091 17 M4 3 7 12 8 4 54 29 4 55
80-4030007296094 17 3 7 12 8 4 54 29 4 55
80-671635-00 17 M2 3 7 12 26 4 55
80-671391 17 16 11 10 26 4 54 55
80-051-1 17 1 26 4 M5 55
80-121148 1 50 26 27 55
80-4035149 1 28 50 27 48 55
80-4030339 1 27 9 57 48
80-4030341 1 27 9 57 48
80-4009121 1 57 25 52 48 55
80-4009263 1 M1 57 25 52 48 55
80-4009270 1 57 M7 25 52 48 55
80-4010346 1 57 25 52 48 55
80-4010348 1 57 25 52 48 55
80-4010350 1 57 25 52 48 55
80-4041707 1 57 25 52 48 55
80-4011714 1 26 57 52 48 55
80-4012169 1 26 57 52 48 55
80-4012174 1 26 57 52 48 55
80-4012179 1 26 57 52 48 55
80-9033023-303 57 54 57 55
80-4067179 17 39 40 26 57 54 57 55
80-27750-01 17 39 40 42 41 3 7 12 M6 57 54 55
80-150T084LT 17 6 2 7 12 8 42 41 57 55
80-NL150T060LT 17 6 2 7 12 8 42 41 57 55
80-NL150T072LT 17 6 2 7 12 8 42 41 57 55
80-37355-1072 17 6 2 7 12 8 42 41 57 55
80-37355-1084 17 6 2 7 12 8 42 41 57 55
80-W101-2006 17 6 2 42 33 41 54 57 4 55
80-35-B357 17 1 57 4 54 55
80-B113-1001 17 56 57 54
80-3249869 17 56 1 17 29 26 54 57 48
80-191820 17 16 11 10 26 29 28 27 48
80-S113-1001 17 16 11 10 57 53 55
80-27708-302UP 17 39 40 16 9 11 10 39 40 57 54
270
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
Based on the flow diagram for the Modular Layout, the Modular From-To Chart (Table 4) was
generated. This chart is a reduced version of the original From-To Chart where the aggregate
flows between pairs of individual (ungrouped) machines were shown. Now, many of those
machine-to-machine flows have been completely absorbed into a single module, which results in
fewer long-distance flows between pairs of machines placed in different layout modules. With
reference to the Modular From-To Chart, “M1-M7” are the layout modules, “56” is an individual
machine, “IN” is the Receiving area, “OUT” is the Shipping area (or office location), and
“External” is a group of machines - #53, #54, #55 and #57 – located off-site, including the
Machine Shop located far away from the forge shop.
1
11 10
M1 17 M3 21 22
M2 16
39 40
9
50
6 3 27 41
M4 M5 26 4 28 M6 42
2 7 12 8 33
29
M7 25 52 48
271
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
External
M3 M6
IN M1 M4 M5 M7 OUT
56
M2
272
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
The flow diagram for the proposed Modular Layout (Figure 6) shows the recommended
relocation and grouping of various sets of machines into several layout modules, each of which
could be operated by a single, or small group of associates, and the flows in the Modular From-
To Chart superimposed on the proposed layout. Also, the different modules have been assigned
to a new “desired or recommended” location on the forge shop premises in order to minimize the
total distance (and time) of travel between different pairs of modules. Machines represented as
white rectangles are the “monuments” that cannot be re-located in any new layout that the
company decides to implement.
A comparison of the two flow diagrams shows that, without moving the monuments, if the other
machines on the premises were to be grouped into modules and relocated, then there would be a
drastic improvement in (1) the speed of material flows between the modules, (2) visual
connectivity and communication among interdependent machines and (3) multi-machine
operation by individual operators. If it were possible to relocate some of the monuments and
place them at locations that matched their “optional locations” in the improved material flow
network, then even more significant reductions in scrap, order completion time, material
handling costs and wasted labor hours would be achieved.
273
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
M4
2
12 3
6
8
M7 Machine Shop < 1000
25 57 1000-2000
55 54 53
7 48 2000-3000
52 3000-4000
11
External >4000
10
16 9 56 28 27 26
29 50 4
M2
M5
M3
1 40 21 22
17 39
M1
33 M6
12
41
Conclusion
Custom forge shops that are suppliers to defense organizations, such as the Defense Logistics
Agency, are typically high-variety low-volume (HVLV) jobshops. When the traditional Toyota
274
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
Lean methods are applied in a jobshop, a majority of the tools either need significant
modification to be applicable, or they must be replaced by alternative methods that address the
core complexities of a jobshop (diverse product mix, variable demand and wide customer base).
The JSLEAN (Jobshop Lean) approach, powered by the PFAST (Production Flow Analysis and
Simplification Toolkit) software for material flow analysis, part family formation and facility
layout, that has been developed at The Ohio State University, has proved to be a strong
foundation for deployment of Lean Thinking in jobshops. In a pilot project done at a custom
forge shop, PFAST helped to develop a “road map” for the FDMC project partner to acquire new
equipment, systematically reorganize their layout, review outsourced operations and initiate
training programs to educate their workforce on Lean Thinking.
Acknowledgements
This paper is based on work that has been supported by numerous individuals, in particular:
Jon Tirpak, Advanced Technology Institute
Dr. Rajiv Shivpuri, Ohio State University
Doug Brown, Inductoheat/Inductotherm Group
George Layne and Charlie Hageman, Forging Industry Association
Sadono Djumin, Christine Djunaedi, Heng Huang, Smart Khaewsukkho and Lily Susanto,
Ohio State University
Clearly, this initiative to develop and deploy JSLEAN and PFAST is a team effort that involved
valuable contributions from numerous individuals and organizations!
This work would not have been possible without the support of several custom forge shops –
Aluminum Precision Products, Anchor Harvey, Commercial Forged Products, Consolidated
Industries, General Dynamics–Ordnance and Tactical Systems (formerly Intercontinental
Manufacturing Co.), Scot Forge, Turbine Engine Component Technologies (TECT), Ulven
Forging Inc. – who agreed to open the doors of their facilities to our inquisitive eyes, hired
several ISE graduate students as full-time interns and partnered on our FDMC project to deploy
Lean Thinking in their facilities. In particular, we wish to thank Andy Ulven (President, Ulven
Forging Inc.) for providing valuable data and information for our case study, and committing to
implementation of many of our recommendations derived from that study.
We wish to sincerely thank the other core members of the PFAST development team – Smart
Khaewsukkho and Dr. Jin Zhou – for developing this exciting new software tool that has made it
possible to rapidly execute a JSLEAN deployment project in just about any jobshop, regardless
of industry sector or SIC code.
The following federal organizations provided funding that has sustained this R&D project for
several years:
(1) National Science Foundation (NSF): This material is based upon work supported by the
National Science Foundation under Grant Nos. DMI-9521278, DMI-8523809 (later DMI-
9796034), DMI-9734815, DMI-9821033 and DMI-9908437. Any opinions, findings, and
conclusions or recommendations expressed in this material are those of the author(s) and do
not necessarily reflect the views of the National Science Foundation.
(2) PRO-FAST Program supported by the Defense Logistics Agency (DLA): The PRO-FAST
Program is enabled by the dedicated team of professionals representing the Department of
275
Proceedings of the 25th Forging Industry Technical Conference, April 19-21, 2004, Detroit, MI
Defense (DOD) and industry. These teammates are determined to ensure the Nation's
forging industry is positioned for the challenges of the 21st Century. Key team members
include: R&D Enterprise Team (DLA J339), Logistics Research and Development Branch
(DLA - DSCP).
Finally, we wish to thank all the members of the JSLEAN (Jobshop Lean) discussion forum at
http://groups.yahoo.com/group/JSLEAN/ whose comments and suggestions have guided the
development of the Jobshop Lean strategy and functional capabilities of PFAST.
276