Routine maintenance and inspection

intervals
Interval Number Time Maintenance task
of
persons
Daily  Check the leakage at the
6 mechanical seal or the leakage
1 min. rate at the gland packing.
Weekly Check the pump operation:
 Inlet pressure
 Head
 Bearing temperature
15  Noises
1 min.  Vibrations
Monthly  Verify the torsional clearance of
the coupling (see operating
instructions of the coupling)
 Switch to a stand-by pump, if
15 any, or carry out a functional
1 min. check run (5 minutes).

Every 20.000 Replace the rolling element


operating hours 2 3h bearing.
Every 4 years or if  Generally inspect and overhaul
discharge head the pump in accordance with
drops the operating instructions.
 Check and replace, if necessary:
Bearings, casing wear
ring, impeller wear ring,
shaft protecting sleeve.
 Impeller and shaft.
2 6h  Fit new seal elements.