You are on page 1of 9

Development of Lean Model for House Construction Using

Value Stream Mapping


Haitao Yu1; Tarry Tweed2; Mohamed Al-Hussein3; and Reza Nasseri4

Abstract: Lean construction has recently attracted considerable attention in the home building industry. Lengthy delivery time and
significant waste in the construction process have caused many home builders to seek a more effective production model that will increase
process reliability, reduce total lead time, and improve quality. However, although housing construction provides the closest analogy to
manufacturing, a high level of variability prevents the direct transplantation of lean paradigm and techniques. In collaboration with a local
home builder, a systematic approach based on value stream mapping technique is developed in this research to analyze the current process
and to formulate a lean production model. The model has four main features: synchronized first-in, first-out lane-based flow, production
leveling at pacemaker, work restructuring, and improved operation reliability. A simulation template is built to verify the model and to
assist in the development of interim implementation models. This paper presents data collection and value stream selection, current
practice analysis, and specific changes proposed for the lean production model.
DOI: 10.1061/共ASCE兲0733-9364共2009兲135:8共782兲
CE Database subject headings: Buildings, residential; Housing; Lean construction; Production management; Construction
management; Process control.

Introduction to Construction.” This notion quickly attracted the attention of


researchers in residential construction. Gann 共1996兲 and Barlow
In North America, the home building industry has changed little et al. 共2003兲 compared industrialized housing with automobile
since the 1920s, when the wood platform-frame structure manufacturing in Japan, highlighting the similarities existing in
emerged as the standard building technology. Although advances their production strategies, but the focus of the papers was on
in tools and materials have led to some incremental improve- product development, supply-chain coordination, marketing, and
ments, the fundamentals of the construction process remain al- sales, rather than on fundamental construction practice. Zhang
most identical and no significant improvements in productivity et al. 共2005兲 proposed a waste-based management approach that
have been observed 共Zhang et al. 2005兲. In contrast, other indus- considered all process inputs, including labor, equipment, materi-
tries have experienced remarkable productivity improvements als, data and information, work space, and time, as potential
through the application of innovative technologies and operation sources of waste. Two case studies in housing construction were
management tools. A recent example is the automobile industry, presented to demonstrate that minimizing resources waste would
where manufacturers have dramatically improved productivity significantly improve productivity and quality. Ballard 共2001兲
through the adoption of a new production philosophy which has suggested that variability was the major source of waste in con-
led to the “lean production system.” Popularized by Womack’s struction and that even flow production could increase the reli-
book, The Machine That Changed the World 共1990兲, “lean ability of work flow and thus reduce cycle time in home building.
theory” has been widely employed by a range of industrial sectors Bashford et al. 共2003兲 further discussed implications of even flow
in the past decade. production and concluded that the strategy had minor impact on
Research on the implementation of lean theory in construction construction duration but could significantly reduce work flow
began in the early 1990s, when Koskela 共1992兲 wrote a ground- variability.
breaking paper, “Application of the New Production Philosophy The research presented in this paper continues Ballad and
Bashford’s efforts on house production flow management, but
1
Ph.D. Candidate, Dept. of Civil and Environmental Engineering, proposes a new lean production model by utilizing value stream
Univ. of Alberta, Edmonton AB, Canada T6G 2W2. E-mail: hyu@ mapping 共VSM兲. VSM, referred to at Toyota as material and in-
ualberta.ca formation flow mapping, is the most commonly used tool in lean
2
General Manager, Landmark Homes, 9765-54 Ave., Edmonton AB, planning. It helps lean system practitioners to think about flow
Canada T6E 5J4. instead of isolated wastes and to implement a lean system instead
3
Associate Professor, Dept. of Civil and Environmental Engineering, of individual lean techniques. Some research has been done in the
Univ. of Alberta, Edmonton AB, Canada T6G 2W2. application of VSM to construction, but these efforts have either
4
President, Landmark Group, 9765-54 Ave., Edmonton AB, Canada focused on macroprocess level, such as supply chains 共Arbulu
T6E 5J4.
and Tommelein 2002; Fontanini and Pichi 2004兲 and project de-
Note. This manuscript was submitted on November 1, 2007; approved
on March 11, 2009; published online on July 15, 2009. Discussion period livery 共Mastroianni and Abdelhamid 2003兲, or on single opera-
open until January 1, 2010; separate discussions must be submitted for tion, such as masonry 共Pasqualini and Zawislak 2005兲 and
individual papers. This paper is part of the Journal of Construction components manufacturing 共Alves et al. 2005兲. No report has yet
Engineering and Management, Vol. 135, No. 8, August 1, 2009. been found on the use of VSM for fundamental construction pro-
©ASCE, ISSN 0733-9364/2009/8-782–790/$25.00. cess improvement.

782 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2009

Downloaded 22 Nov 2011 to 146.155.155.20. Redistribution subject to ASCE license or copyright. Visit http://www.ascelibrary.org
A number of factors impede the application of VSM to the research. The writers have redefined most of the concepts used in
main construction stream at the operational level. First, an under- traditional VSM to suit the context of construction, and have de-
lying prerequisite for VSM is the repetition of the production signed two new measurements 共BT and PSS兲 specifically for the
process. In manufacturing, hundreds of thousands of products in a application of VSM in construction.
product family pass through similar processing steps, so it is fa- In addition to data collection, two management decisions must
vorable to develop and implement a lean system to continually be made prior to the commencement of VSM: 共1兲 select a value
improve that process. A construction project, in contrast, presents stream; and 共2兲 decide on the level of mapping. A value stream is
a unique design, specifications, and context, and must be con- a series of activities required to bring a product or service from
structed accordingly—following a unique construction process raw state through to the customer. As a manufacturing plant usu-
共value steam兲. As VSM requires diligent management commit- ally fabricates multiple products—each by a unique transforming
ment coupled with massive efforts in systematic data capture and process, the product family with the highest production volume is
analysis, lean training, core implementation team assembly, and generally selected as the target on which to focus improvements
working process transformation, practitioners have been hesitant 共Tapping et al. 2002兲. The products of a home building company,
to invest such efforts to improve a process that may not recur. on the contrary, can be seen as a single product family, because
Second, VSM is a quantitative tool that uses a list of process data they are generally constructed following similar processing steps
to depict the current state of the process and to determine what and utilizing the same subtrade pool. However, the housing con-
the future state will be. Construction companies, however, gener- struction process is a complex system that involves tens of trade
ally do not fully track construction processes. Moreover, most of contractors and consists of hundreds of construction activities. A
the construction steps are lengthy and subject to numerous vari- single map encompassing the entire process would be too large
ables. Site investigation is useful to assist researchers in under- and cumbersome for a VSM team to handle. In fact, a rule of
standing the process, but it has proven nearly impossible to thumb for VSM is that the target value stream should include no
collect statistically meaningful data in a short time period. Third, more than 12 tasks 共or process stations兲. A feasible solution is to
key concepts/elements used in VSM, such as cycle time, change- divide the entire production flow into stages, with each stage con-
over time, up-time, and inventory, are defined in the context of sidered as an independent value stream in a supply chain. Another
manufacturing and seem nonapplicable to construction. reason to compartmentalize the construction process is that the
Although construction industry as a whole is defined very process is too long to be synchronized with one takt time. For
differently from manufacturing, home building, as a unique sector example, it is obvious that the capacity of excavation trade work-
in construction, provides the closest analogy to automobile pro- ing at the beginning of the process needs to match the current
duction 共Winch 2003兲. Its distinctive features, including high pace of sales, but for finishing trades at the tail end of the process,
production volume 共repetitiveness兲, controllable production flow, their production pace should be synchronized with the pace of
and large inventory of work in process, make the application of sales that had occurred 6 months ago. Based on the analysis of
VSM here favorable 共Yu et al. 2007兲. In the research, a seven- historical data, the writers recommend that the total production
step methodology is adopted: 共1兲 data collection and value stream duration of a stage be shorter than 2 months.
selection; 共2兲 current-state mapping; 共3兲 existing practice analysis Level of mapping is another important issue to be considered
and lean metrics development; 共4兲 formulation of lean production in defining the value stream. In manufacturing, mapping generally
model; 共5兲 laboratory testing of the model using simulation; 共6兲 begins at the level of the production process in a single plant, with
kaizen 共continuous improvement兲 plan development; and 共7兲 the activity box indicating a continuous product flow. In other
implementation of kaizen plans and results evaluation. This paper words, the tasks in the map are divided at the places where the
focuses exclusively on the first four steps, especially current- product flow stops and in-process inventory accumulates. In con-
state mapping and formulation of the lean production model; struction, the houses 共products兲 do not move along a production
simulation and the lean implementation are briefed to provide line but, rather, workers move from one house 共product兲 to an-
integrality. other. Thus, the operations of a trade crew can be regarded as a
continuous flow and would be shown with one activity box on the
map.
Data Collection and Value Stream Selection As shown in Table 2, the entire house production process was
divided into five stages after considering the size requirement of
An important rule in VSM is to bring the stopwatch when walk- the value stream map, total production duration, and the logical
ing along the actual pathways of material and information flow, relationship between the construction activities. The summary
and to rely only on information obtained firsthand 共Rother and data shown in Table 2 clearly demonstrate that Stage 1 is the most
Shook 2003兲. This rule, however, is not applicable in construc- problematic segment. The scheduled duration of Stage 1 is
tion. High variability in task durations as well as queuing times 20 days, but houses actually spend an average of 73 days 共365%
and complexity in the construction process make it impossible for of the scheduled duration兲 in this stage. In addition, a large stan-
a small team of researchers to collect sufficient data merely dard deviation 共35 days兲 indicates that the construction process in
through site observations. Instead, an intranet-based production Stage 1 was not effectively controlled and that a high potential
tracking system was developed, in which site managers recorded exists to reduce construction time by redesigning the process.
the booking date, confirmed start date, actual start date, and actual Based on the above-presented analysis, Stage 1 was selected by
finish date of every task in the construction process. This research the VSM team as the target value stream.
used production data collected in 2006—approximately 400
houses for each task. Based on the data, four basic measurements
were calculated: 共1兲 cycle time 共CT兲; 共2兲 booking time 共BT兲; 共3兲 Current-State Mapping
lead time between tasks 共LT兲; and 共4兲 percent started on schedule
共PSS兲. Table 1 shows the definitions and calculation formula of The goal of current-state mapping is to create a clear picture of
these measurements and other key VSM elements used in the the existing production process and to expose wastes. The con-

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2009 / 783

Downloaded 22 Nov 2011 to 146.155.155.20. Redistribution subject to ASCE license or copyright. Visit http://www.ascelibrary.org
Table 1. VSM Key Elements
Key concepts Definitions Formula
Cycle time 共CT兲 The duration that a subtrade needs to complete its work CT⫽actual finish date⫺actual start date
package.
Booking time 共BT兲 The time that a subtrade needs to deploy its crew to a BT⫽confirmed start date⫺booking date
given job.
Lead time 共LT兲 The time that elapses between one task being completed LT⫽actual start date of task i + 1⫺actual finish date
to the next task being started. In lean system, LT serves of task i
as a time buffer to shield downstream crews from
upstream variability.
Percent started on A measure of the proportion of start-date promises made PSS⫽number of tasks started on schedule/
schedule 共PSS兲 by subtrades that are delivered on time, in percentage. total number of tasks
Changeover time The time that a crew needs to switch from working at
one house to another, including demobilization and
mobilization.
Uptime A measure of the proportion of available production Uptime= 共APT− bad weather days− changeover time兲/APT
time 共APT兲 that is actually used on construction, in
percentage.
Work in process 共WIP兲 Number of uncompleted houses in the value stream,
including the houses in construction and those standing
idle waiting for the start of next activity.
In-process inventory/ The backlog of ready houses that stands idle waiting for Number of houses in inventory= LT/ operational
supermarket yield the start of a given task. In lean system, it serves as a takt time
buffer to protect the continuous work flow of
downstream crews.
Yield The percentage of houses that go through an operation
correctly, without any rework.
Takt time The rate at which a home builder must build the house
to satisfy customer demand.

ventional approach of residential construction management is where 11 trade crews 共represented by activity boxes兲 are in-
based upon a management model which views the construction volved. The process can be thought of as one house passing
process as a series of tasks to be completed in sequence 共Bashford through a line of process stations. Unlike with manufacturing,
et al. 2005兲, and each house is scheduled and managed individu- attributes of each task are not a constant, but are expressed in
ally as a small project using a Gantt chart or critical path method. the form of distribution in order to reflect the variability of the
Fig. 1 illustrates the conventional approach using predefined construction process. Site managers are the center of production
icons of VSM. It was drawn up in a 2 day VSM session attended control. Due to the unpredictability of both the market and the
by the lean team and an external lean expert. The information construction process, home building is essentially a “make-to-
recorded in the data box was estimated by site managers in the order” business. No overall production schedule exists in the
session and then verified by researchers using historical data home building company, and construction is triggered when the
which had been collected through the cooperating company’s pro- file of a new house is released by sales. Subsequently, the respon-
duction tracking system. A statistical software, Stat::Fit, was used sible site manager starts booking material and subtrades and tries
to process the data. The map shows the main flow of Stage 1, to push the process as quickly as possible. Meanwhile, no look-

Table 2. Construction Stages and Descriptive Statistics


Stage 1 Stage 2 Stage 3 Stage 4 Stage 5
Attributes foundation lock-up interior and siding prefinals finals
Start task Stake out Framing Verandahs, smart board, Plumbing prefinal Tile flooring
and rear deck and water test
End task Drill and place piles Roofing Drywall taping House clean and vacuum House possession
Number of tasks 11 11 11 12 14
Actual duration average 73 31 54 42 26
共calender day兲
Standard deviation 35 14 20 14 7
Coefficient of variation 共%兲 48 45 37 33 27
Scheduled duration 20 25 22 18 16
共calendar day兲
Difference 共actual⫺schedule兲 53 6 32 24 10

784 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2009

Downloaded 22 Nov 2011 to 146.155.155.20. Redistribution subject to ASCE license or copyright. Visit http://www.ascelibrary.org
Fig. 1. Current-state map of home building process 共Stage 1兲

ahead schedule is available for trade contractors. The booking a given house. As the excavation subtrade has already scheduled
information is generally issued by site managers via phone or fax other jobs on consecutive days for other home builders, the de-
on a task-by-task basis. layed job has to be rescheduled to the end of its working sched-
ule. Moreover, as the downstream task 共in this example, pouring
of footings兲 cannot begin until the excavation is complete, the site
Existing Practice Analysis and Lean Metrics manager has to cancel original bookings and attempt to get new
Development commitments based on the newly scheduled excavation date.
However, from the perspective of the footing contractor, a sudden
Upon drawing up the current-state map, several wastes can be schedule change means that it must find a new job fitting in that
identified immediately. In this case, the first observation was that time slot in a very short period of time. Then, overbooking 共i.e.,
lead times were very lengthy. The total duration of Stage 1 was subtrades accept jobs exceeding their capacity兲 has become com-
found to be 65.5 workdays, but the total lead time accounted mon practice. Consequently, a greater number of tasks fail to
for 50 workdays. This means that houses in construction stand begin on the scheduled start date and lead time becomes even
idle about 76% of the time, with no construction activity on site. more unpredictable.
One apparent cause of long lead time is the high level of variabil- Second, variations in cycle time are relatively high, especially
ity of the process. The booking times and cycle times in the map for tasks whose cycle times are described in distributions. Site
are very variable. Six of 11 booking times have a standard devia- managers have reported that the major cause of high variation is
tion in excess of 5 days and cycle times of five tasks must be not work-load differences between house models but the manner
described using statistical distributions. In the current practice, in which subtrades carry out their respective jobs. They tend to
site managers book the downstream subtrade immediately fol- deploy their crews continuously on new jobs where large quanti-
lowing confirmation of the start date of the upstream tasks. The ties of work are available, leaving uncompleted, minor details to
intention of this practice is to crash construction duration by rework crews. These rework crews follow separate working
overlapping booking time and task cycle time, but the actual re- schedules and usually arrive several days later to finish the job.
sult is that nearly half of the tasks cannot begin on the scheduled Quality problems are another cause of high variation in cycle
start date 共the average PSS on the current-state map is 54%兲. time. It has not been rare, for example, that the crews who install
Temporary contract relationship between home builder and trade the main floor spend 1 day cleaning the beam pockets and level-
contractors make any delay in schedule be magnified by ripple- ing the top of the foundation walls.
through effect. For example, bad weather 共e.g., heavy rain兲 pre- Based on the analysis of current practice, the aim of lean
vents the excavation from commencing on the confirmed date for initiatives for the cooperating company was set as increasing

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2009 / 785

Downloaded 22 Nov 2011 to 146.155.155.20. Redistribution subject to ASCE license or copyright. Visit http://www.ascelibrary.org
Table 3. Lean Metrics order to reduce the variability of the process, the following four
Metrics Baseline Goal a measures were taken in the future-state mapping 共Fig. 2兲: estab-
lishing a production flow and synchronizing it to takt time; lev-
Variation of production cycle time 共workdays兲 Up to 5 1 eling production at pacemaker task; restructuring work; and
Total lead time 共workdays兲 50 25 improving operation reliability with work standardization and
Value-added ratio 共%兲 17 25 total quality management.
Percent started on schedule 共PSS兲 45–77 90
Yield 共%兲 50–98 100
a
Decided after future-state mapping. First-in, First-out Lane-Based Flow and Its
Synchronization
productivity by stabilizing the process, reducing lead time, In manufacturing, continuous flow forms the centerpiece of the
and eliminating defects. Accordingly, the lean metrics shown in lean production system and is regarded as the most effective way
Table 3 were developed in order to clarify these goals and track of production. Nevertheless, the production system built on con-
progress. tinuous flow can only be used for a reliable process. As the sys-
tem is fully synchronized, any small delay or breakdown in one
operation will result in halting the entire system. Housing con-
Future-State Map struction is a site-based production 共as opposed to factory-based
manufacturing兲. Weather and site conditions have a significant
The focus of future-state mapping is to eliminate the root causes impact on the execution of construction activities, so variation in
of wastes and to link the value stream in a smooth flow. Unlike task duration is unavoidable. In addition, the housing construction
manufacturing, where the fundamental problem is overproduction process is a long process involving more than 60 work “pack-
caused by “batch and push” 共Womack and Jones 1996兲, the home ages” 共tasks兲. Connecting all the tasks into a continuous flow
building industry suffers most from variability. Unpredictability would make the system very fragile. Finally, construction work is
of the process causes all kinds of waste, not just of long lead performed by various trade contractors who have individual inter-
times and excess inventory. Uncompleted houses are vulnerable ests and are almost exclusively concerned with the efficient ex-
to weather, requiring temporary protection; to pilferage, requiring ecution of their individual tasks 共Bashford 2004兲. Therefore,
security and extra materials; and to vandalism, causing rework. keeping an excess capacity buffer to overcome minor flow fluc-
Variability also results in fluctuation of the production flow. This tuation is not practical for home builders.
means that home builders need to sustain a large workforce pool Another important lean tool, supermarket-based pull flow, is
and cannot provide stable work flows to trade contractors. In also nonapplicable in house construction. A pull-flow system is

Fig. 2. Future-state map of home building process 共Stage 1兲

786 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2009

Downloaded 22 Nov 2011 to 146.155.155.20. Redistribution subject to ASCE license or copyright. Visit http://www.ascelibrary.org
Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Note
Slot 1 Slot 2 Slot 3 Slot 4 Slot 5
Production Trade Partner 1
Slot 6
Slot
Slot 7 Slot 8 Slot 9 Slot 10 Trade Partner 2

2 jobs Job are released


Jobs Lead time: 3 days
booked by preceding task
1 job one day before
booked Lead time: 2 days booking.
2 jobs
Lead time: 2 days
booked
3 jobs
Lead time: 2/3 days
booked
2 jobs Lead time: 3 days
booked

Fig. 3. Typical scenario of lean booking

controlled by the pacemaker task, where customer orders enter March, the takt time is 0.49 workdays. In practice, the downtime
the production system. In manufacturing, the pacemaker is typi- was estimated as 5%, and the agreed capacity of each task was
cally the most downstream task in the value stream and the pro- designated as 10 per week. By reserving the same number of
duction pace of all upstream tasks is “pulled” by the pacemaker. kanban slots for each of the tasks in the value stream, the produc-
In construction, the pacemaker acts at the beginning of the pro- tion paces of working stations are synchronized.
cess. In order to develop a stable flow from the pacemaker task to The FIFO-lane-based approach is different from other sched-
the downstream end of the value stream, a FIFO-lane-based flow uling techniques for repetitive construction activities, such as line
system is proposed based on the theory of last planner described of balance, due to its ability to deal with the dynamic work
by Ballard 共2000兲. flow—i.e., new houses can enter into the production system
With the help of statistical analysis, the construction manager continuously—and high variation in productivity. In this system,
of the company can predict with great certainty the total number consecutive tasks are decoupled by the FIFO lane so that each
of houses that will enter the production system in the course of a task only deals with variations caused by the preceding task,
given month, but it is virtually impossible for site managers to which can be accommodated by adding a time buffer 共LT兲 be-
know with any certainty what the state of a given house will be tween tasks. For instance, task “Excavation and deep service” has
more than a week into the future; there are simply too many 1 day standard deviation in cycle time and a possible 2 day delay
variables that can affect the readiness of a particular job: weather, in booking time; thus a 3 day lead time for the next task can
work progress, material supply, trade availability for preceding effectively control the flow fluctuations caused by variations in
tasks, neighboring construction activities, etc. The fundamental the present task. In addition, the system is very flexible. Either
idea of the proposed system is to stabilize and reduce lead time by party can change the agreed capacity from time to time provided
guaranteeing trade contractors’ working load. In practice, this is that advanced notice is given 共in practice, the agreed upon notice
realized using agreed capacity, a commitment between a home time for capacity change is 2 weeks兲.
builder and its trade partner on the number of jobs 共kanban slots兲
that a subtrade will perform each week. For example, a home
Production Leveling
builder might predict that about 40 houses would enter the pro-
duction system next month and it might have two trade partners In the conventional production management approach, the vol-
working for a given task. Next, a trade booking agreement is ume of jobs performed typically occurs unevenly overtime. Fig.
signed between the company and each trade partner. Assuming 4共a兲 shows the monthly volume of files released to construction in
that one trade contractor has agreed to provide six kanban slots 2006, and Fig. 4共b兲 shows a typical record of the number of
weekly and the other four, a typical booking scenario would be released files over a 1 month period. The causes of this large
the one shown in Fig. 3. Site managers release specific job infor- fluctuation were unpredictability of sales and a pushed production
mation following the completion of the preceding task and load a management. Flow fluctuation causes several problems for a syn-
kanban slot. The capacity agreement in fact forms a first-in, first- chronized production system:
out 共FIFO兲 lane, and the jobs released are the inventory on the • There is no sense of takt time and it is difficult to decide the
lane. In this way, the FIFO lane links two separate tasks into a capacity requirement;
stable flow. In the future-state map, the cycle time 共CT兲 and • When peaks and valleys frequently appear, filling the agreed
changeover time 共CO兲 of each task remain the same as those in kanban slots consistently becomes a heavy burden; and
the current-state map, and the booking time 共BT兲 reflects the • A jangled flow makes the production difficult to monitor—“Is
length of the FIFO lane. the situation normal or not?”
The number of kanban slots is decided by takt time, which is a In order to avoid these problems, the production control must
function of customer demand. In the cooperating company, it usu- lower the peaks and raise the valleys in work load as much as
ally takes 30– 45 days from the customer signing the purchase possible so that the flow surface is smooth. This practice is re-
agreement to the release of the file package to construction, so the ferred to as production leveling or “even production flow.”
average volume of sales in the past 2 months is used to determine Bashford et al. 共2003兲 have described two common even
the takt time of the system. In the first 2 months of 2007, the sales production flow strategies 共activity based and start based兲 and
volumes of the company, including presales and spec houses, discussed their implications for the housing industry using simu-
were 47 and 42, respectively. As 22 workdays are available in lation. In this research, these two strategies were combined and

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2009 / 787

Downloaded 22 Nov 2011 to 146.155.155.20. Redistribution subject to ASCE license or copyright. Visit http://www.ascelibrary.org
Fig. 4. Typical record of files to construction

implemented in an innovative way. On the one hand, tasks due to the small amount of concrete pouring and underutilization
connected by the FIFO-based lanes form an activity-based even of wall forms is minor. The same strategy was also used for
flow system. Unlike fixed schedules, where a long duration electrical panel installation and shallow services, which were both
for each task must be chosen in order to ensure that it will not be electrical jobs. In fact, this work package was further integrated
exceeded, a booking system based on the agreed capacity had the with backfill tasks to be contracted to a cross-functional team.
capability to accommodate minor variation, so that time buffers The electrical, cable, and telephone 共shallow service兲 lines are
between construction tasks were significantly reduced. On the approximately 1 m 共3 ft兲 below finished grade. By installing them
other hand, a supermarket-based pull system was established at the same time with backfill, trenching operation is eliminated
between the pacemaker task 共excavation兲 and sales as a decou- and the quality of backfill is ensured. A similar consideration
pling buffer 共Ballard et al. 2003兲. The sales department typically led to the integration of task excavation and deep services 共water
releases the files of presale houses to the first supermarket, and sanitary兲, which are situated at approximately 2.7 m 共9 ft兲
and the downstream task withdraws the files. Once the number of underground.
files in the supermarket reaches the upper limit, the sales must
stop releasing, and when the number reaches the lower limit, the
Process Improvement Measures
sales releases the files of show homes and spec houses in small
and consistent quantities until the files of presale houses are The production process on the future-state map exhibits signifi-
available. The upper and lower limits are decided based on the cant overall improvements. Total construction duration of the
historical analysis of sales variability. In this research, they value stream decreases from 65.5 workdays to 38.5 workdays,
were set to 15 and 5 homes 共7.5 and 2.5 workdays inventory兲 amounting to a reduction of 27 workdays or over 5 weeks. The
respectively. percentage of waiting time drops from 76 to 65% and the value-
added ratio increases from 17 to 26%. However, achieving the
material flow envisioned in the future-state map requires that the
Work Restructuring
amount of inventory on FIFO lanes should ideally be stabilized
It is apparent that the total lead time can be effectively abated by around six houses 共i.e., 3 workdays lead time兲 and never less than
reducing the number of handovers. In an extreme case, if the four, so as to ensure that subtrades receive at least 2 workdays
entire value stream could be completed by a single crew, the notice. Based on the statistical analysis, PSS needs to be im-
house would pass directly from one task to the next in a continu- proved from current 45–77% to upward of 90% and with standard
ous flow, without any lead time in between. The factor that pre- deviation of cycle time for each task reduced to 1 workday, so
vents the same crew working continuously in a house throughout that the probability that the cycle times of any two homes in a
the value stream is that different tasks require different skills and series of six are longer than the average cycle time by more than
equipment. Although multiskilling and the use of cross-functional 1 workday is below 10%. Although the actual probability of a
teams were shown to be effective in reducing variability and thus shortage of jobs in the FIFO lane to fill the kanban slots might be
improving flow 共Ballard 2001兲, the reality is that the vast majority much lower due to possible completion of previous delayed jobs,
of trade contractors are specialized in one type of job. focused attention on improving the reliability of the operation of
A feasible solution is to examine adjacent tasks and consider subtrades will be required. In practice, the following kaizen foci
the possibility of integrating them into one work package to be were proposed by the core lean team:
performed by a single working team. The footing and cribbing • Work standardization—The work scope and quality standards
tasks, for instance, require a similar skill set 共framing and con- of each task are clarified in written documents and distributed
crete pouring兲 and can easily be completed by one crew. Histori- to related subtrades. The goal is “100% ready handover”;
cally, these two tasks have been performed separately, because • Total quality management—Trade contractors are required to
it is more productive to pour footings in batch 共where multiple control quality at the source, completing all repair work before
footings are poured within a subdivision at one time兲 and wall workers leave the site, when site managers are required to
forms are always moved around with the cribbing crew. On the check quality as the construction is in progress. The goal is
future-state map, these two tasks are combined into one work “100% first-time-through”; and
package with an expected cycle time of 4 workdays. Compared to • Long-term partnership with trade contractors—Lean imple-
a savings of 3 workdays lead time, the possible cost increase mentation involves significant behavioral changes in all parties

788 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2009

Downloaded 22 Nov 2011 to 146.155.155.20. Redistribution subject to ASCE license or copyright. Visit http://www.ascelibrary.org
linked to the system. It will take time to build up trust between requires considerable time, and subtrades have disparate attitudes
parties, train workers, and change the mindset of personnel. toward innovation. Therefore, it became necessary to develop an
These items are marked on the future-state map using a kaizen interim system, in which some tasks were connected by FIFO
lightening burst icon. An advantage of VSM is that the process lane and others by conventional pushed flow. What should the
improvement efforts become subordinate to the value stream de- minimum length of FIFO lane be to ensure that the kanban slots
sign, as opposed to stand-alone improvement activities, so that the are being filled? What are the implications of using this system?
lean team can focus on the improvements that have real impacts Is production leveling necessary? The answers to these questions
on overall process performance. were essential for management decision-making and could only
Information flow is another important issue in VSM. Without a be answered using simulation. Details of different simulation sce-
fundamental change in information management, it would be very narios and results will be reported in a subsequent paper.
difficult to operate a lean value stream. Unlike a manufacturing
production line, construction crews move from one house to an-
other that may be located miles away. Visual control cannot be Lean Implementation
applied in housing construction the same way that it is in manu-
facturing. Using the concept of the heijunka box, the writers pro- The implementation of the future state is ongoing in the cooper-
posed an internet-based “e-kanban” system, with a column of ating company, which completed approximately 460 single-
kanban slots for each workday and a row of kanban slots for each family dwellings in 2006 in metropolitan Edmonton. To ensure
trade contractor. Site managers place a kanban with the link of job that the leader of the lean initiative has sufficient authority to
information 共detailed address and technical drawings兲 into a de- allocate the organization’s resources and to instigate changes
sired kanban slot when a job is ready. The corresponding trade across various functions and departments, the general manager of
contractor then withdraws this kanban via the internet and allo- the company was designated as lean champion. A core lean team,
cates a crew to the job. If a slot is not loaded 2 days prior to its including researchers, the president of the subsidiary company,
start date, or if a kanban is not withdrawn until the start date, the construction managers, and site managers, was formed to lead
construction manager will be aware of a production problem. daily lean activities.
A yearly kaizen plan was formulated to break implementation
into steps and to provide a time frame for improvements. The
Simulation Experiment objectives of each step were outlined as follows:
• Standardize work packages and educate the subtrades to elimi-
In order to better understand the effects of the changes proposed nate handover problems;
on future-state map and to find the proper value for parameters of • Implement total quality control to raise the yield rate to 100%;
the system, a series of simulation experiments were undertaken, • Develop FIFO-lane-based flow from excavation through to
using discrete event simulation models constructed in a Simphony drilling and pile placement with 1 week lead time;
environment. Simphony was selected because it facilitates the de- • Develop an internet-based booking system;
velopment of a special purpose template for a focus area of ap- • Establish supermarket-based pull flow between excavation and
plication such that models with different configurations can be releasing of construction files;
easily built 共Hajjar and AbouRizk 1999兲. Although a complete • Restructure work packages 共depending on the availability of
discussion of the simulation method and results is beyond the cross-function teams兲; and
scope of this paper, a brief description is given to show the roles • Reduce lead time between tasks to the level shown on the
of simulation experiments in lean model verification and in the future-state map.
formation of a lean implementation plan. Naturally, these steps are not listed in sequence. Some of them are
Utilizing the hierarchical feature provided by Simphony, the in fact interdependent and must occur simultaneously. At the time
writers have developed two “composite” modeling elements for of writing, a detailed construction procedure was developed in
each task, one representing the current state and the other encap- collaboration with construction managers, site managers, and all
sulating the mechanism of FIFO lane. Simulation experiments related trade contractors. As a result, the construction sequence
were conducted using models with different combination of these has been completely standardized and the handover problems
two groups of elements. First, a model with all elements in group caused by coordination issues dramatically reduced. As for FIFO-
one and a model with all elements in group two were constructed lane-based flow, nearly half of the subtrade contractors have
to simulate the current state and future state, respectively. The agreed to use the lean booking system and have accepted 1 week
simulation results were consistent with the summary of statistics lead time. The analysis of production data from the 15 houses that
on the maps, which provided a cross check on the theoretical passed through the value stream via FIFO lanes showed that total
analysis. Moreover, as the computer simulation recorded richer construction duration had been only slightly attenuated, but that
data, such as work-in-process 共WIP兲 and utilization of resources, the standard deviations of total duration and lead times had de-
it helps practitioners to better understand the differences between creased dramatically. All of this means that the implementation of
conventional and lean models in a more comprehensive way. the proposed model can significantly reduce process variability.
Simulation also plays a critical role during lean implementa- Detailed discussion on results of the implementation, the strategy
tion. The future-state map describes the ideal state that the com- used by core lean team, lessons learned, and internet-based book-
pany is expected to achieve in a certain period of time, and in ing system will be reported on in future work.
most cases, it will not be possible to implement the entire lean
system at once. Interim lean models are needed throughout the
different phases of lean implementation. A good example is the Conclusion
establishment of FIFO-lane-based flow. As subtrades are indepen-
dent of home builders, any change to the existing production sys- The housing construction process is a complex system that in-
tem has to be built on consensus. However, achieving consensus volves numerous interrelated tasks performed by various trade

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2009 / 789

Downloaded 22 Nov 2011 to 146.155.155.20. Redistribution subject to ASCE license or copyright. Visit http://www.ascelibrary.org
contractors. In current practice, houses in construction are treated Ballard, G. 共2001兲. “Cycle time reduction in home building.” Proc., 9th
as a collection of small projects using a conventional project man- Annual Conf., Int. Group for Lean Construction, National Univ. of
agement method. The conflict between predetermined schedule Singapore, Singapore.
and unpredictable reality results in significant wastes in the sys- Ballard, G., Harper, N., and Zabelle, T. 共2003兲. “Learning to see work
tem. This research has focused on creating a stable production flow: An application of lean concepts to precast concrete fabrication.”
flow rather than eliminating individual waste. VSM, a powerful Eng., Constr., Archit. Manage., 10共1兲, 6–14.
lean planning tool, was used to analyze the construction process Barlow, J., Childerhouse, P., Gann, D., and Hong-Minh, S. 共2003兲.
and restructure the production system. However, compared to “Choice and delivery in housebuilding: Lessons from Japan for UK
housebuilders.” Build. Res. Inf., 31共2兲, 134–145.
manufacturing, the home building industry poses some significant
Bashford, H. H. 共2004兲. “The on-site housing factory: Quantifying its
particularities, making the direct application of VSM impossible.
characteristics.” NSF-PATH housing research agenda Vol. 2, 27–33,
This paper has explicated the major limitations of traditional
具http://www.pathnet.org/si.asp?id⫽1118典 共Sept. 15, 2007兲.
VSM and proposed a practical approach to utilizing VSM in a
Bashford, H. H., Sawhney, A., Walsh, K. D., and Kot, K. 共2003兲. “Im-
construction setting.
plications of even-flow production methodology for the U.S. housing
Detailed production data were collected through an intranet- industry.” J. Constr. Eng. Manage., 129共3兲, 330–337.
based production tracking system and analyzed to assess cycle Bashford, H. H., Walsh, K. D., and Sawhney, A. 共2005兲. “Production
time, lead time, booking time, and percent started on schedule. system loading-cycle time relationship in residential construction.”
Pushed scheduling and unpredictable process led to extremely J. Constr. Eng. Manage., 131共1兲, 15–23.
long lead time and low PSS. Thus, creating a stable production Fontanini, P. S., and Picchi, F. A. 共2004兲. ‘‘Value stream macro
flow became the top priority of future-state mapping. A FIFO- mapping—A case study of aluminum windows for construction sup-
lane-based system was used, in tandem with production leveling ply chain.’’ Proc., 12th Annual Conf., Int. Group for Lean Construc-
at pacemaker task, in order to control the sources of fluctuation tion, Lean Construction—DK, Lyngby, Denmark.
and to provide a predictable flow to trade contractors. Gann, D. M. 共1996兲. “Construction as a manufacturing process? Similari-
Compared to the current state, the future-state demonstrates a ties and differences between industrialized housing and car production
remarkable improvement in overall performance. With a stable in Japan.” Constr. Manage. Econom., 14共5兲, 437–450.
product flow, the capacity of each task is synchronized to takt Hajjar, D., and AbouRizk, S. M. 共1999兲. “Simphony: An environment for
time and fast response to sales change. By restructuring work building special purpose construction simulation tools.” Proc., Winter
packages, the number of handovers was reduced and total lead Simulation Conf., IEEE, Piscataway, N.J., 998–1006.
time was further reduced to 50% of that of the current process. Koskela, L. 共1992兲. “Application of the new production philosophy to
The impacts of the changes proposed on the future-state map construction.” Technical Rep. No. 72, Center for Integrated Facility
were investigated using simulation experiments. The implemen- Engineering, Dept. of Civil Engineering, Stanford Univ., Stanford,
tation of the proposed lean system is ongoing, and a significant Calif.
improvement in process reliability has been observed after the Mastroianni, R., and Abdelhamid, T. 共2003兲. “The challenge: The impe-
establishment of FIFO lanes. tus for change to lean project delivery.” Proc., 11th Annual Conf., Int.
Group for Lean Construction, Virginia Polytechnic Institute and State
Univ., Blacksburg, Va.
Pasqualini, F., and Zawislak, P. A. 共2005兲. “Value stream mapping in
Acknowledgments construction: A case study in a Brazilian construction company.”
Proc., 13th Annual Conf., Int. Group for Lean Construction, Univ. of
The work presented in this paper was supported by the Canadian
New South Wales, Sydney, Australia.
Mortgage and Housing Corporation 共CMHC兲 under the External Rother, M., and Shook, J. 共2003兲. Learning to see: Value stream mapping
Research Program 共Grant No. 6585-A075-1兲. The writers are to create value and eliminate muda, Version 1.3, Lean Enterprise
grateful to the industrial research partner, Landmark Homes Institute, Brookline, Mass.
共Edmonton兲, for providing access to production tracking data and Tapping, D., Luyster, T., and Shuker, T. 共2002兲. Value stream manage-
for assistance in lean system development. ment, Productivity Press, New York.
Winch, G. M. 共2003兲. “Models of manufacturing and the construction
process: The genesis of reengineering construction.” Build. Res. Inf.,
References 31共2兲, 107–118.
Womack, J. P., and Jones, D. T. 共1996兲. Lean thinking: Banish waste and
Alves, T. C. L., Tommelein, I. D., and Ballard, G. 共2005兲. “Value stream create wealth in your corporation, Simon and Schuster, New York.
mapping for make-to-order products in a job shop environment.” Womack, J. P., Jones, D. T., and Roos, D. 共1990兲. The machine that
Proc., Research Congress 2005, ASCE, Reston, Va. changed the world: The story of lean production, MacMillan, New
Arbulu, R. J., and Tommelein, I. D. 共2002兲. “Value stream analysis of York.
construction supply chains: Case study on pipe supports used in Yu, H., Tweed, T., Al-Hussein, M., and Nasseri, R. 共2007兲. “Management
power plants.” Proc., 10th Annual Conf., Int. Group for Lean Con- variability in house production.” Proc., 15th Annual Conf., Int. Group
struction, Federal Univ. of Rio Grande do Sul, Gramado, Brazil, 183– for Lean Construction, Michigan State Univ., Lansing, Mich.
195. Zhang, J., Eastham, D. L., and Bernold, E. B. 共2005兲. “Waste-based man-
Ballard, G. 共2000兲. “The last planner system of production control.” agement in residential construction.” J. Constr. Eng. Manage.,
Ph.D. thesis, Univ. of Birmingham at Birmingham, U.K. 131共4兲, 423–430.

790 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / AUGUST 2009

Downloaded 22 Nov 2011 to 146.155.155.20. Redistribution subject to ASCE license or copyright. Visit http://www.ascelibrary.org

You might also like