Professional Documents
Culture Documents
File 000551
File 000551
:Temporary piping repairs may remain for an indefinite period of time if they are approved and documented by the -1
?Which of the following is not a required marking on a B-16.5 flange or flanged fitting -2
Welders who qualify with one filler metal are qualified to weld with any filler metal having the same -3
.F-number .1
.P-number .2
A-number and P-number .3
A-number .4
When the maximum allowable working pressure is recalculated for the continued use of a piping system, the wall -6
:thickness used is the
.Actual thickness .1
.Actual thickness minus the estimated corrosion loss before the next inspection .2
Actual thickness minus two times the estimated corrosion loss before the next inspection .3
Actual thickness minus four times the corrosion loss experienced since the previous inspection .4
7.Thickness measurement location (TML) readings on a piping system indicate that the corrosion rate has
increased. The inspector's most appropriate response is to:
.hot-formed metal .1
.Forging .2
.Casting .3
Heat-treated metal .4
9. When prioritizing piping systems for positive material identification (PM.1) testing, which of the following is
the most important item?
The likelihood of a material mix-up during construction 1
The cost of the PMl testing program .2
The accessibility of piping segments .3
The process unit downtime schedule .4
10. A piping system installed in January 1993 had an initial thickness of 0.32 Inch, In January 2004; a thickness
of 0.20 inch was recorded just prior to a change of service on the piping system. The January 2009 thickness
measurement was 0.18 inch. The retirement thickness of 0.15 inch will be in met in:
January 2012 .1
.June 2012 .2
January 2015 .3
January 2039 .4
11. According API standard 570 the owner / user shall maintain piping records that are:
12. To which of the following fluid services does API 570 specifically apply?
15 What type of inspection could be performed at ground level over the buried pipeline?
:Image quality indicators are always selected on the basis of the .18
?Which of the following need not be taken into account when specifying piping for original installation .19
Corrosion allowance .1
Threads .2
Stresses caused by other loading .3
API Standard 570 classification .4
A piping system carrying a flammable petroleum process fluid may be categorized as a Class 3 system if it .20
:contains
:A carbon-steel piping circuit in caustic service that was originally stress-relieved .22
.Should be examined at twice the inspection interval of systems that are not stress-relieved .1
.Should be checked for cracking with magnetic-particle testing .2
.Requires Brinell hardness testing at the first inspection interval .3
Should never be hammer tested .4
.
Welders Performance Qualification Record documents:23. The
.That the weldment provides the required properties.1
The suitability of a weld process for a given service .2
.The ability of the manufacturer to control the welder .3
The welder's ability to make sound welds .4
A Class1piping system has had its service changed to carry a non-corrosive, inert gas with an extremely low . 25
:potential to a safety emergency in the event of a leak. The unit inspector should
:An external visual inspection of aboveground piping should always include .26
Carbon steel .1
.Monel2
series stainless steel 300 .3
Cr-- 2 Mo .4
:An imperfection of a type or magnitude exceeding the acceptable criteria is known asa/an .28
.Indication .1
,defect ,2
.Discontinuity .3
Flaw .4
.During radiographic examination of a weld, the wire type 1Q1 shall be placed.29
.Adjacent to the weld so that the length of the wire perpendicular to the weld .1
Adjacent to the weld so that the length of the wire parallel to the weld .2
.On the weld so that that the length of the wire perpendicular to the weld .3
On the weld so that that the length of the wire parallel to the weld .4
Local post weld heat treatment (PWHT) may he considered for piping repairs under all of the following .30
:condition
.considered alterations .1 .
.Located downstream from any control valves .2
.Designed per the applicable code .3
radiographed 100% .4
?Which of the following techniques is most effective in finding process pluggage in pipes .33
Under which circumstance may a welder be qualified by a production weld instead of on a coupon .34
When 6 inches (150 mm) of the welder's first production weld pass the specified radiographic .1
Examination
When a coupon is removed from one of the welder's production welds and passes mechanical testing .2
.When the welder has welded on plate steel within the past 12 months .3
.Never; welders may not qualify by this method. 4
I. When the welder's foreman discovers that the welder is not making acceptable welds
When the welder has not welded with the same P number in the previous 3 months 2
When the welder has not worked as a welder for the previous 2 months 3
When the welder has not requalified within the past 12 months .4
All of the following are appropriate for measuring the skin temperature of hot spots except .36
high-tempera t re ultrasonic .1
.A handheld pyrometer .2
.temperature-indicating paints .3
.A portable thermocouple .4
A Procedure qualification record (PQR) test made for a shielded met arc welding process used plat with .37
:thickness ⅝". The maximum thickness production weld qualified is
.inch 5/8 .1
.inch1 2
inch 1/4 1 .3
inch 3/4 1 .4
.
The extent of verification of materials used for repairs or alterations of alloy systems is determined by the .38
.Material supplier .1
.Repair organization .2
.owner/user .3
piping engineer ,4
.
Measurements from an inspection of a Class 3 pipe reveal an actual metal thickness of 0.350" (8.89 mm). The .39
calculated minimum thickness is 0.250 inch (6.35 mm). If the corrosion rate is 0, 0025" (.064 mm) per year, the
:next thickness measurement inspection should be scheduled within
years 3 .1
years 5 .2
years 10 .3
years 20 .4
: Which tow position qualify welder of all position when weldin an 8" pipe .40
2G, 5G .1
1G, 3G .2
1G, 2G .3
2G, 3G .4
5% .1
10% .2
25% .3
50% .4
Gate .1
Globe .2
Slide .3
Ball .4
.Inspection reports shall document the: 45
Allowed for Class 1 and Class 2 piping systems if the welds receive magnetic-particle testing or penetrant .1
testing
.Not allowed for Class 1 piping systems .2
Allowed for Class 1 and Class 2 piping systems if the welds are 100% radiographed or suitably .3
.ultrasonically tested
Not allowed for Class 1 or Class 2 piping systems .4
.
:The positive material identification (PMI) testing program within a warehouse . 47
.A weld groove completely removes the defect and is then filled with weld metal deposit .1
The piping component is hydro tested to 150% of the maximum allowable pressure .2
A box-type enclosure is installed. p .3
.A full encirclement welded split sleeve is installed per API 570 .4
:ASME, Section IX assigns base metals to a P-number category in order to reduce the number of required .50
.WPQs .1
-PRQs .2
.PQRs .3
WPSs .4
.
After welding is completed, a pressure test should be performed if it is practical and deemed necessary by the .51
.Inspector .1 .
.owner/user and the piping engineer .2
.The piping engineer .3
owner/user's insurance carrier and the piping engineer .4
.
.ASNI Recommended Practice SNT-TC-1 A is a52
.Verify the certifications of penetrant and developer materials for chlorine or fluorine content .1
.Check the material container for identification and batch numbers .2
.Verify the certifications of penetrant and developer materials for lead content .3
.Check the material container for indication of VOC content .4
When inaccessibility prevents placing the penetrameter(s) manually on the source side of a weld being . 54
radiographed, what identification is placed on the radiograph to indicate that film-side penetrameters were
? used
"IQI " .1
"F" . 2
"B " .3
" F.S.P " .4
Vertical supports constructed of pipe components should be checked to determine if they are filled with .55
:water, because water inside a support may cause
A metal thickness reading of 0.220 inch is obtained during an inspection on June 1, 2006. The baseline .57
reading for the thickness measurement location (TML) was 0.250 inch on May 31, 7000, thecorrosion rate is
.Piping engineer .1
.Nondestructiveexaminer .2
Piping inspector .3
.Certified welding inspector 4
?What is the cause for rejection of the "B" image on a film due to excessive backscatter .60
.Any image e .1
No image .2
A light image .3
A dark image .4
Which inspection method is most appropriate for detecting external chloride stress corrosion cracking 61
?Inaustenitic stainless-steel piping systems
Dry magnetic-particle .1
Liquid-penetrant .2
Longitudinal ultrasonic .3
Radiography .4
If the corrosion rate for a piping system cannot be determined by similar service, initial thickness .63 .
:measurements should be taken within
months 3 .1
months 6 .2
months 9 .3
.year 1 .4
.Material toughness .1
.Number of thermal cycles .2
.Tensile strength .3
Long-term overstressing .4
In-service u ultrasonic testing measurements at the thickness measurement location (TML) points indicate .66
thinning in the heat-affected zone of an elbow-to-weld neck flange on an NPS 30 (UN 750) vapor line. What is
?the best method to determine the extent of deterioration during the next scheduled downtime
Internalinspection n .1
Ultrasonic A-scan of the elbow .2
Spot radiograph of the welds .3
Full radiography of the elbow .4