G Gammon OTHER SUBMISSION ‘SUBMISSION ReF.: | SUB/3110/ mis /041 ‘J3038/ 304.7.1 1109624 ‘Major Trade Contracter {Gammon Building Construction (Macau) Limited | Page ‘We submit herewith the following submission to HCEM for (¥ ) Comment / Approval (_) Information (Others EXPECTED COMMENT/APPROVAL DATE: 14 APR. 2006 ILATEST APPROVAL DATE: 14 Apr. 2006 jubject. __ WP3710 — HOTEL CURTAIN WALL and GLAZING & ALUMINIUM CLADDING 2° SUBMISSION OF METHOD STATEMENT (SUB/3110/MIS/041, DETAILS: REFER TO PREVIOUS SUBMISSION REF: SUB/3110/MIS/002 DATED 18/7/2005 AND COMMENT REF.: CAM-000437 DATED 4/8/2005. Co WEL wheels rene) wi ()AEDAS w__sels ene () w___sets of en (OAR w__setsofenct. () wi sesotene. | Charlz Yan ) w. ) ) seis ofenel | Authorized Representative _ [4 (PBA wl sets of enc |_setsofencl. | project Manager (Lae w_ses of net ‘wi sets of enc, (“yobom, ws ses of nat sess of ene ray wi sets fend) wy sets of ene ete ‘Submission Date (OMY) 34 March 2006 CYIPCIENipiat ‘bee. Architectural / Structural / QS /QA / Planning [Setting Ou PC/EI/ BT/ Netfortune (3110) CL Poon [We had received the above submission from Major Trade Contractor, Gammon Building Construction (Macau) Lid. The |cubmission is considered necessary for your corresponding response. Kenneth Yiu (Project Manager) [Signature Date of lesue (¥iM/D) je forward herewith the above consultant's response and endorse the same for your follow up action. Endorsed by: Date: Kenneth Yiu (Project Manager) Hsin Chong Engineering (Macau) Lt. JVGL w/__salsafencl ( )PBA wi__setsof endl Official Use )AEDAS w!__seisofencl ( }18B — wi_selsofenc, JOA wi__saisofenct | )GBCML wi__sets of enc, )PGA wi _selsofenct wl sats of enc, pe OTHER SUBMISSION ‘SUBMISSION REF.; | SUB/3110/MIS/041 GBCML REF: (J3039/ 304.7.1 / 009524 ‘Major Trade Contractor [Gammon Building Construction (Macau) Limited | Page: | ( 2 ) of ( 2 ) Gueor iO = HOTEL CURTAN WALL GLAZING E ALUMINIUM GLADBING) r 2 SUBMISSION OF METHOD STATEMENT (SUB/3/70MISI041 Consultant Remark Status tom Numbere Descripion Aken Method Statement for Hotel Curtain Wall / Glazing & ‘Aluminium Cladding and GRC Cladding installation 2 proceed to coneructon thou ttherenange 6 proceed to consuctan subject changes mecatod C“esabint pata protouang fron constuction We de seen > Aya 42 (3848) RNA RADA Netfortune Engineering (FEA) Macau Limited LETTER OF TRANSMITTAL pate 29-Mar-06 To Gammon Building Construction (Macau ) Limited, Ref “VHCM/T165 Attn = Mr, Photo Cheng Job No. : VHCM. Project: Wenetian Macau ‘in Cotai, Macau ‘Package 3110- Hotel Curtain Wall/ Glazing & Aluminium Cladding Re ‘Method statement for hotel curtain ‘wall / glazing & aluminium cladding & GRC cladding installation Wo are sending you the following = {for your comment 1 for your approvel 1D osrequested D for your information OD for your endorsement — _—_—— _ Deesirtion ‘uentity Method statement for hotel curtain wal/ glazing & aluminium cladaing & - GRC cladding installation (Rev. 9) Distributions : Remarks : 1D Pleas sign and return For and on behalf of Netfortune Engineering (FEA) Macau Limited XK P___-Vj-3 >G AL/TCH| G Gammon OTHER SUBMISSION ‘SUB /2420/ MIS! GBCMIL REF. Gs0%e 1308747 [ Beortesoeccer Gammon Building Construction (Macau) Limited | Page: | (1 )of( 1) Tle submit herewith the following submission to HGEM for (7 ) Comment / Approval (Information (_ ) Others: EXPECTED COMMENTIAPPROVAL DATE: 6 APRIL 06 [LATEST APPROVAL DATE: GUBIECT: METHOD STATEMENT FOR HOTEL CURTAIN WALL / GLAZING & ALUMINIUM CLADDING & GRC CLADDING INSTALLATION (REV. 0) Get WEL weer sat ofendl | Authorized Representative { )AEDAS wea tert | et ort ()ORP wise of eres, wousebotect | Charlz Yan ()Pok sat oferet |__sebotenct_ | Project Manager ()URE wi nsets fone ert (/j8CML Wate font ses of ec. sul__ete of ene ‘ ‘abinision Date (YAW) 29 March 06 bce, Architestral Stuclural -MBEHOS-+-Planaing Trad TeEned Tne Shove submission om Najor Trade Conractor, Gammon Bulding Consisucton (Macau) Ltd. The submission is considered necessary for your corresponding response. ndorsed by: Kenneth Vi (Project Manager) Hsin Chong Engineering (Macau) Lid Isignature Date ofiscue (VIM) ic forward horevah the above consultants response and endorse the same for your follow up Endorsed by. Date: Kenneth Viu (Project Manager) Hsin Chong Engineering (Macau) Lid. GET VEL wL__setsofecch (PBA w__selsof endl { )AEDAS wiueateotencl — (}188wl__sets af nat ()OAP)— wheelsofenc —( )GBCML wets of ench. (C)PBA Wo_setwotend §—¢) ws ofench Updated : 11-Mar-05 Nesfortune Engineering (FEA) Macau Limited ‘Method Statement for Hotel Curtain WallGlazing & ‘Aluminium Cladding And GRC Cladding, Installation METHOD STATEMENT FOR HOTEL CURTAIN WALL/GLAZING & ALUMINIUM CLADDING AND GRC CLADDING INSTALLATION FOR PACKAGE 2120/3110— HOTEL CURTAIN WALL/GLAZING & ALUMINIUM CLADDING AND GRC CLADDING INSTALLATION FOR VENETIAN MACAU IN COTAI, MACAU Nesfortune Engineering (FEA) Macau Limlted ‘Method Statement for Hotel Curtain Wall/Glazing & ‘Aluminium Cladding And GRC Cladding Installation CONTENTS: 1. SCOPE OF WORK 1.1 Specification Reference . .5 12 Third Party Interfaces 5 2. WORK METHODOLOGY 21 Time a . 6 2.2 Duration 6 23 Sequence - 6 1 Curtain Wall Installation 6 Monorail Installation 9 ‘Aluminium Cladding Installation u GRC Cladding Installation 12 ‘Non-Typical Area Installation 16 Extended Living Room Installation 18 Installation for Left Out Openings 19 Material Delivery, Distribution and Storage 21 Field Water Test Procedure . 23 Protection . 23 24 26 3. RESOURCE REQUIRED 3.1 Personnel 27 32 Plant 29 3.3 Material 29 34 — Specialist Services 29 3.5 Supervision ... 30 4. ASSESSMENT OF SIGNIFICANT RISKS 41 Access/Egress 31 42 Place of Work... 31 43° Others at Risk... 31 44 Competence for ‘Key’ Activities 32 45 Dangerous Goods, Noise, Manual Handling, ete, 2 4.6 Environmental Impacts... 7 32 5. CONTROL MEASURES TO BE USED 5.1 Emergency Arrangements 52 Security ... i [Netfortune Engineering (FEA) Mact Lirnted Page :3 0f49) ‘Method Stacement for Hotel Curtain Wall/Glazing & Doc. No. : VECMMSIO02 ‘Aluminium Cladding And GRC Cledding, Issue : 001 Installation ‘Date : 23-Mar-2006 53. Third Party Liaison ..... 33 $4 Work Instructions and Field Controls 34 35 Permits 34 5.6 Personal Protective Equipments 34 5.7 Specialist Training 36 PROVISION OF INFORMATION 6.1 Changes to Information .... see 62 Confirmation of Emergency Asrangements/Drills 63 Employee and Third Party Briefings. VERIFICATION RECORDS 7.1 _ Initial Records Requirements _.. 38 72 Records to be Taken During Construction 38 73 Completion Certificate Package... 38 7A Filing Arrangements 38 APPENDICES 8.1 Hazard Mentification Sheet 39 82 Risk Assessment Sheet 40 83. Field Control Sheet .... 8.4 Field Control Briefing 8.5. Labour Histogram A. For Curtain Wall & B. For GRC Cladding C.For Overall : Curtain Wall, Aluminium Cladding & GRC Cladding juminium Cladding 8.6 Installation Programme 8.7 Installation Sequence... A. For Curtain Wall B. For Aluminium Cladding For GRC Cladding 8.8 Production Schedule ....... A. For Curtain Wall B. For Aluminjum Cladding 89 Sketches ... A. Zoning Plan B. Sketch No. 1 —Loading Platform CC. Loading Platform Layout Rev.0 Netfortune Engineering (FEA) Macau Limited Page: 4 of 49 Method Statement for Hotel Curtain Wall/Glazing & Doe.No. VECMMS/002, ‘Aluminium Cladding And GRC Cladding Tissue : 001 Installation, 8.10. ‘Evererete’ Method Statement for Waterproofing Application 8.11 Inspection & Test Plan and Checklist 4 HESENY RO ROREP AMM EOMED ‘Date : 23-Mar-2006 ‘Sketch No. 2.— Hoisting of Curtain Wall Unit Sketch No. 3 — Installation of Curtain Wall ‘Sketch No, 4 — Installation of Aluminium Cladding Sketch No, 6 — Loading & Unloading Arrangement (Late Ces tip lcompless) Sketch No. 7 — Installation of GRC Cladding ‘Sketch No. 8 —Loading & Unloading Arrangement (Lste Cas Suip Comes) ‘Sketch No. 9 Welding at L7 Sketch No. 12~ Internal Lining Installatio Sketch No. 14~ Installation of Extended Living Room Sketch No. 15-1 — Left Out Installation Monorail Arrangement Monorail Detail at L21 (for Typical) ‘Monorail Detail at 121 (for End Wall) Monorail Detail at L32 & L39 (for Typical) Monorail Detail at L32.& 39 (for End Wall) Hoisting System Layout at RAF Hoisting System Detail at RUF Scaffolding Arrangement Scaffold Layout at End Wall Sketch No. 17 & 17-1 ~ Installation at End Wall Scaffold Layout for L36~ RE Sketch No. 18 & 8-1 — Installation from L36 ~R/F 48 49 Rev.0 Netfortune Enginesring (FEA) Macau Limited ‘Method Statement for Hotel Curtain Wall/Glazing & ‘Aluminium Cladding And GRC Cledding Installation 1. SCOPE OF WORK. 14 Specification Reference LL1 Design - Technical Specification Clause 6.2 1.12 Fabrication _ - Technical Specification Clause 6.3 11.3 Material - Technical Specification Clause 7 114 Workmanship - Technical Specification Clause 9.2.3 11.5 Galvanizing _ - Technical Specification Clause 7.24.1 111.6 Cast-in Embed - Technical Specification Clause 9.5 117 Safety = Hong Kong Factories and Industrial Undertakings Regulation, Code of Practice for Scaffolding Safety (HK) and The Charters of Construction Safety and Hygiene (Macau) 12 Third Party Interfaces ‘The curtain wall, aluminium cladding and GRC cladding installation for this project is independently installed extemally as a external fagade system and will have no direct interface with other trade except for internal finishing. Field water test of curtain wall requires witness by Consultant, Rev.0 Netfortune Engineering (FEA) Macau Limited Page : 6 0f49 ‘Method Statement for Hotel Curtain Wall/Glazing & Doo. No. : VHCM/MSI002, ‘Aluminium Cladding And GRC Cladding, Installation, 2. WORK METHODOLOGY 2A 22 23 Time ‘The extemal facade system will be installed under normal working hours. Night shift for installation will be required subject to the available of Tower Crane and actual site progress. Duration ‘The external facade system will be installed according to approved installation programme and summarized as pet below: a, Curtain Wall +: 6-Apr-06 to 24-Oct-06 b. Aluminium Cladding — : 19-Apr-06 to 21-Oct-06 ¢, GRC Cladding 2 27-Apr-06 to 8-Dec-06 Sequence 23.1 Curtain Wall Installation 23.1.1 Cast-in Embed a Curtain wall insert placing to be carried out in accordance with approved embed layout plan. b. Check and inspect the installed inserts are in the correct location before concrete pouring, Any inserts that are beyond the allowable tolerance ‘hall be rectified prior to concreting. FEA. will issue inspection record to Major Trade Contractor before each casting, c. Survey and inspect the inserts after removal of formwork. Any inserts that are out of tolerances will be highlighted and submitted to Major Trade Contractor for record. 4. Any curtain wall insert which is out of nominal position by a ‘dimension greater than +/- 15mm in any direction due to concrete out “ftolerance shall be recorded, and submitted for consultant's review, e. Any remedial works must be approved by consultant prior to execution. 23.12 Setting Out a. A set of reference grid lines and level datum to be provided by the Major Trade Contractor, Accuracy verified by joint surveying between FEA surveyor and Major Trade Contractor's building surveyor. b. The setting out of the curtain wall floor by floor, will be carried out in accordance with the agreed set of reference gridlines and level datum throughout the whole building. Netfortune Engineering (FEA) Macau Limited Page: 7 0f49) Method Statement for Hotel Curtain Wall/Glezing & Doo. No. : VHCMIMSi002 ‘Aluminium Cladding And GRC Cladding Issue = O01 Installation Date : 23-Mar-2006 ‘Assign a set up floot for every five floors where optical laser surveying jnstrament will be engaged to layout the reference lines of the curtain wall. ‘Curtain wall reference and anchor locations at intermediate floors will be set out with the aid of wires tensioned between set up floors. (Level reference on all floors will be transferred by optical level). 2.3.13 Bracket Installation Clean the top face of pre-cast imbed by wire brush to remove dust and cement slag. Major Trade Contractor to make-good any uneven concrete surface at insert location to achieve a smooth bearing surface prior to bracket installation. Install the bracket onto the embed by fixing. Set the bracket in accurate in and out position and tighten the anchor bolts. Set the aluminium serrated plate on accurate level and tighten the anchor bolts. Double check the set curtain wall anchors for accuracy. Set up of proper working platform by approved competent worker prior to welding of ems bracket at L7. ‘The surface of cast-in plate and the edge of support bracket will be removed the galvanized coating for welding contact area by using of brush or grinding machine prior to welding, ‘The certified welder will weld the intermediate support gms bracket to the cast-in plate according to the approved shop drawing. ‘After welding the weld slag will then be removed by slightly harnmering or by brush. 23.14 Curtain Wall Installation (Typical Areas) a Curtain wall units are unloaded onto the Loading Platform on 8/F, 26/F, 34/F at different stages for temporary storage until they are required for installation. During storage on site, the units will be covered with plastic sheet. ‘A triple track monorail system will be used and set up at 21/F and double tack at 32/F respectively for installation of curtain wall from L6-L18, L19-L30 & L31-L37 at different stages. For installation works at End Wall and L38 & L39 will be referred to below Special trrangoment. A protective catch fan shall be erected by Major Trade Contractor above the monorail to prevent falling objects during our installation. ‘An electric chain block of SWL 1.0 & 2.0 MT will be mounted onto the ‘steel monorail track. The complete system shall undergo safety load Rev.0 Netfortune Engineering (FEA) Macau Linited Page: 8 of49) Method Statement for Hotel Curtain Wall/Glazing & oo. No, : VHCMMSI002, ‘Aluminium Claiding And GRC Cladding Issue : 001 Installation Date : 23-Mar-2006 test by an independent qualified party and test reports/statutory forms are then submitted to Main Contractor for record, ‘To install fire insulation according to approved shop drawing at fop part of concrete beam surface prior to curtain wall installation. Curtain wall units are then hoisted up from the Loading Platform by means of this monorail and electric chain block and place in position at floor edge for fixing to the pre-installed anchor brackets. Upon final adjustment of the units by means of dummy level, theodolite, ete. tighten the fixing bolts to its correct torque by torque check test on site with RE / MTC inspection. Proceed with next curtain wall unit installation and sea! all gutters as per approved shop drawings details. A 100% flood test to the gutters shall be carried out by Factory for a period of no less than 24 hours without water seepage. Take record and fend to site together with unit delivery for site reference. Install EPDM flashing and seal up the curtain wall system 2s a ‘waterproof barrier. Teotall thermal, acoustic insulation to the curtain wall. Inspection to be ‘camied out by RE / MTC for the satisfactory of the pre-installed fire insulation prior to the g.m.s. smoke seal installation. Workers will install the curtain wall unit mainly inside the building except for the two End Wall, blind wall and 38-39/F which will be carried out by using scaffold and gondolas. Rev.0 Netfortune Enginearing (FEA) Macau Limited Page: 9 0f49 ‘Method Statement for Hotel Curtain Wall/Glazing & Doo. No. : VHCM/MSI002 ‘Aluminium Cladding And GRC Cladding Installation ‘Date : 23-Mar-2006 232 Monorail Installation 2.3.2.1 Monorail at L21, L32 &L39 b. ce 8. “The monorail will be pre-fabricated and assembled in segment with all track installed. ‘The pre-assembled monorail segment will be hoisted up by Tower Crane and be delivered up to designated level. ‘A manual chain block will be set up intemally to assist for the ‘adjustment the monorail in correct position, To fix the connection between monorail and the bracket and ensure the bolts are tightened. Release hook of cower crane and then the chain block, Repeat Step b~ ¢ fo complete installation of remaining of monorail system. Place a working platform onto the installed monorail with support of manual chain block internally. Workers will working on the platform to fix and tightened the connection plate between each track conjunction. For End Wall/Blind Wall installation, a catch fan will be located at one floor below our monorail system by Major Trade Contractor. Scaffolding will be erected onto the catch fan for bracket and monorail installation. ‘The monorail system for End Wall/Blind Wall will be specially designed as a hooking system with guardrail on top with mesh walkway and toeboard to form a self access. “The special monorail will be pre-fabricated and assembled in segment with all track installed ‘The pre-assembled monorail segment will be hoisted up by Tower Crane and be delivered up to designated level ‘A banksman stand on the scaffolding will co-ordinate with Tower Crane operator to ensure the monorail is hook on correct position with assistant of 2 installers. Workers will work on the self walkway on top of the monorail to adjust the monorail by tighten the bolt at both top and bottom bracket in correct position. Tighten the fixing bolt after the monorail is in correct position. Release hook of tower crane. Finally workers will work on scaffolding to fix and tightened the connection plate between each track conjunction. ‘The monorail will be inspected by RPE with valid certificate before use. 2.3.2.2 Hoisting System at RF ‘The hoisting system is specially designed for the purposes of both lifting materials and carry temporary gondola for the installation of Rev.0 [Nerfortune Engineering (FEA) Macau Limited Page: 10 of 49 ‘Method Statement for Hotel Curtain Wall/Glazing & Doc, No, : VHCMIMSI002 ‘Aluminium Cladding And GRC Cladding Issue : 001 Date : 23-Mar-2006 curtain wall and GRC cladding fiom L36 ~ R/F especially for the 9.5 M. high GRC column, The maximum weight for GRC cladding must be limited to 5,000 kg as agreed. The hoisting system will be located at R/F where the areas that Tower Crane cannot reach, Scaffolding will be erected to form a working platform at the location where the hoisting system will be located. Derrick crane will be set up at R/F in order to install /dismantle the hoisting system. The derrick crane to be inspected by RPE with valid certificate before use. The pre-febricated hoisting system will be delivered to site and be hoisted up by Tower Crane to PVF. To install the pre-fabricated hoisting system by derrick crane with assistance of workers working on scaffold platform. To weld/tighten the bolt at all connection affer the hoisting system is in correction position “To inspect the hoisting system by RPE with valid certificate before use. Dismantle the scaffold platform after all works/inspection is completed. Rev.0 [Netfortune Engineering (FEA) Macau Limited “Method Statement for Hote! Curtain Well/Glazing & Aluminium Clalding And GRC Cladding Installation 233 Aluminium Claddi 233.1 a b. b. 2333 23.34 Installation Cast-in Embed Curtain wall insert placing to be carried out in accordance with approved embed layout plan. Check and inspect the installed inserts are in the correct location before concrete pouring. Any inserts that are beyond the allowable tolerance ‘hall be rectified prior to concreting, FEA will issue inspection record to Major Trade Contractor before each casting. Survey and inspect the inserts after removal of formwork. Any inserts that are out of tolerances will be highlighted and submitted to Major Trade Contractor for record. Any curtain wall insert which is out of nominal position by dimension greater than +/- 15mm in any direction due to concrete out oftolerance shall be recorded, and submitted for consultants review. ‘Any remedial works must be approved by consultant prior to execution. approved embed layout plan Setting Out Conduct a checking on cast-in channels (before and after concreting ) based on the reference and setting out lines provided by the Major “Trade Contractor and as per approved shop drawings. Provide remedial proposal for cast in channel with excessive tolerance for Main Contractor and Aschitect’s comment/approval if necessary. Apply Water Proofing please refer to Appendix - Everorete's Method Statement. ‘Alaminjum Cladding Installation Carry out remedial works to cast-in embed where necessary. ‘Apply waterproofing onio conorete surface before any fixing of tprackets, No installation should proceed without inspection by MTC. Fix S/S brackets to pre-cast channel by bolts and nuts or welding. Set the brackets in accurate in and out position and tightening the anchor bolts. ‘Adjust the vertical plumbing, alignment and leveling for the hook on brackets in accordance with selting out line and approved shop drawings. Hoist and install aluminium cladding panels. ‘Apply caulking sealant to joints where applicable as shown in approved shop drawings. Final cleaning to be carried out upon instruction received. Rev.0 Netfortune Engineering (FEA) Macau Linited Page : 12 of 49 ‘Method Statement for Hotel Curtain Wall(Glazing & Doe. No. : VECMMS/002 ‘Aluminium Cladding And GRC Cladding Tssue : 001 Installation Date: 23-Mar-2006 234 GRC Cladding Installation 2.3.4.1. Design and Supply of Materials a ee ‘These items are to be provided by other Specialist GRC Supplier: Design and supply of GRC panels complying with Statutory and ‘Technical requirements. Design of the GRC panels must be modified to allow for those projected pieces to be installed at later stage. ‘Maximum weight of individual GRC panel must not exceed 5,000 Kg. ‘All necessary technical submission and approval to attain statutory consent to commence work. Permanent cast-in-embeds for supporting structural sub-fame and GRC panels. Fully pre-assembled/ pre-welded structural sub-frame for supporting GRC panels. Delivery of GRC materials (tagged) to job site Ground Level to suit the required installation programme and sequence. Fabrication and production drawings including but not limited to GRC; structural sub-frame; cast-in-embeds. ‘All permanent materials including but not limited to GRC panels; cast- jn-embeds; fixing bolts and nuts; sealant and interfacing closure pieces etc. Off-site storage yard where required, and any associated cost. Co-ordination with MTC and Installation Sub-Contractor. “These items are to be provided by GRC Installation Sub-Contractor: Installation of permanent cast-in-embeds. Installation of temporary cast-in-embeds for supporting temporary hoisting systems. ‘Any cost associated with temporary storage at both off-site yard and at site. ‘Any cost associated with utilization of tower crane for: = transportation of temporary hoisting materials and assistance in installation. _ transportation of GRC panels from Ground level to podiumn/roof if appropriate. - Distribution of GRC panels within podium; roof ete for installation, Structural checking of R.C. structure to cater for imposed loads due to the hoisting of GRC panels as provided herein, as well as the associated strengthening of the structure where required ‘These items are excluded in GRC installation sub-contractor’s scope of works: Rev.0 Netfortune Engineering (FEA) Macau Limited Page: 13 of 49 Method Statement for Hotel Curiain WallGlazing & Doe. No. : VHCMIMS/002 ‘Aluminium Cladding And GRC Cladding, Issue : 001 Installation ate : 23-Mar-2006 © installation of permanent cast-in-embeds. © Installation of temporary cast-in-embeds for supporting temporary hoisting systems. © Any cost associated with temporary storage at both off-site yard and at site. © Any cost associated with utilization of tower crane for: transportation of temporary hoisting materials and assistance in installation. = transportation of GRC panels from Ground level to podium/roof if appropriate = Distribution of GRC panels within podium; roof etc for installation. ‘© Structural checking of RC. structure to cater for imposed loads due to the hoisting of GRC panels as provided herein, as well as the associated strengthening of the structure where required. Installation Method (Typical Area from L6~L8): Cast-in-embeds for permanent GRC installation: © ‘These permanent GRC castin-embeds are to be supplied by the specialist GRC supplier to the MTC for installation in accordance with the approved layout shop drawings and required delivery schedule. © ‘These installed cast-n-embeds will be inspected against the correct Tocation jointly by GRC supplier and MTC prior to concreting, in accordance with the GRC supplier's approved shop drawings. © Survey and re-ingpect cast-in-embeds after removal of form work by the GRC supplier. © Should any embeds be found cast with excessive tolerances, the GRC supplier should submit remedial method statement and must be approved by MTC/ Consultant Team prior to commencement of remedial works by MTC. @ The curtain wall and aluminium cladding sub-contractor to commence water proofing works to concrete surface. Cast-in-embeds for temporary hoisting equipments: © These cast-in-embeds are to be supplied by the GRC installation sub- contractor to the MTC for installation in accordance with the approved temporary hoisting equipment design drawings. © These installed cast-in-embeds will be inspected against the correct location jointly by the GRC installation sub-contractor and MTC prior to concreting. © Survey and re-inspect these temporary cast-in-embeds after removal of form work, by GRC installation sub-contractor utilizing temporary gondola mounted on monorail system. Rev.0 Netfortune Engineering (FEA) Macau Limited Page : 14 of49 ‘Method Statement for Hotel Curtain Wall/Glazing & Doe. No. : VHCMIMS/002 ‘Aluminium Cladding And GRC Cladding Installation ‘Should any embeds be found cast with excessive tolerances, the GRC installation sub-contractor to submit remedial method statement and must be approved by MTC/ Consultant Team prior to commencement of remedial works by MTC. Location of temporary hoisting systems: Once the RC structure is completed up to Level 23, MTC to install @ catch fan above Level 21. A triple track monorail system at Level 21 is installed in accordance with illustration at Appendix A, and all around the building. Please note the monorail system is modified and strengthened to cater for hoisting a maximum loading of 5,000 kg for GRC panels. (Original monorail system for curtain wall installation ‘was designed to hoist a maximum load of 1,000 kg). The workers will fix the GRC panels while in the temporary gondola for L6 ~ L8 typical area ‘The second temporary hoisting system will be installed at roof level for the area that tower crane could not reachicover, inside of the roof parapet wall as illustrated in Appendix B, This system is designed to hoist up GRC panels from roof level passing above the parapet wall, and drop down to the fagade for installation. ‘All temporary hoisting systems will be submitted for approval prior to installation, and tested according to statutory requirements prior to use. Gondolas and Monorail : Installation of GRC at Level 6 to 8 (Typical Arca): = Hoisting of GRC materials to final position by monorail with electric chain block of SWL 5.0 situated at level 21. “Temporary gondola to assist for the installation. Installation of GRC at Level 36 to Roof: Please refer to special arrangement described below. ‘Transportation of GRC Panels: 16 to L8: = GRC panels will be hoisted up from Ground Level through the Podium left-out openings up to Podium Level by means of tower crane. = Distribution of GRC panels on loading platform by tower crane, = Hoisting up of GRC by Level 21 Monorail and shifted side way until final location. L346 to Roof: GRC panels will be hoisted up from Ground Level to podium roof by means of the 70m jib crane situated at South-East comer of the building, Rev.0 Netfortune Engineering (FEA) Macau Limited Page: 15 of 49 ‘Method Statement for Hotel Curtain Wall(Glazing & Dos. No. : VHCM/MS/002, ‘Aluminium Cladding And GRC Cladding Issue : 601 Installation Date : 23-Mar-2006 = Once landed on podium, the GRC panel will then be hoisted by Roof tower rane to the rooflevel. = Once landed on tower Roof, the Roof tower crane will help to distribute the panel to the appropriate location. = The temporary hoisting system / Tower Crane will lift up the GRC panel from interior of the parapet wall to the exterior of parapet wall, and drop down for installation. = Refer to Sketch No. 8. Installation procedure: inspect water proofing on concrete surface. clear up foam left in cast-in-embeds. Survey and setting out for bracket installation Install fully pre-assembled steel sub frame and bracket in accordance with theoretical position. Install fixing angles to receive GRC panels. It is understood that no welding works are required for bracket installation other than tack weld for positioning. Install GRC panels by means of monorail or hoisting system, with ‘workers working on gondola (above L8) Remove proteotion (by others) if any, and final inspection. Rev.0 Netfortune Engineering (FEA) Macau Limited Page : 16 of 49 ‘Matod Statemeat for Hotel Curtain Wall/Glaring & Doe. No. : VHCMIMS/002 ‘Aluminium Cladding And GRC Cladding Issue: C01 Installation Date : 23-Mar-2006, 238 Non-Typical Area Installation: 2351 ‘The installation works for both End Walls and L36 ~ R/F including curtain wall, aluminium cladding and GRC cladding will be specially arranged as per following. End Wall Installation (L6 ~ L35): (please refer to Appendix ~ Scaffold Layout Plan and Sketch 17 & 17-1) Double row scaffolding will be etected at different zones to satisfy actual site condition and progress as at both End Walls: - L6~L9 = L10~L15 = L16~L19 = £20~123 = 124-127 = 128-131 = L32~135 Leave a vision glass opening (about every 4 floor) to our curtain wall at the nearest point to end wall to allow access for workers to work. Scaffold support frame will be fixed directly to external wall at the post-fix GRC panel at 6 and upper level of aluminium cladding area to hold the scaffolding with scaffold tie on external wall. Interval of scaffold support frame will be placing at about every 4 floor which should be less than 15 M. ‘After scaffolding erected from L6 ~ L9 with our monorail installed at 121 without the part of GRC *Venetian’ logo area, setting out lines laying, embed remedial (if required), waterproofing application will be carried out in 1* priority. Bracket of curtain wall and GRC will be installed according to approved shop drawing in correct position. Curtain wall will be installed first by using our monorail system and then install GRC panel by using Tower Crane. Scaffolder will be full time on site to modify the scaffold tie once the GRC panel is installed. Ali scaffold tie will be relocated to the vertical ‘gap between curtain wall unit and GRC panel. ‘After completion of all installation works from L6 ~ L8, the scaffolding ‘will continue to be erected from L9 upward as per ‘Item a’ zoning. Repeat step e ~ g for completion of curtain wall, aluminium cladding and GRC cladding up to 133. Netfortune Engineering (FEA) Macam Limtted Page : 17 of 49 ‘Method Statement for Hotel Curtain Wall(Glazing & Doe. Ne. : VECMIMS/002 ‘Aluminium Cladding And GRC Cladding, Issue : 001 Installation Date : 23-Mar-2006 23.5.2 L36~RF Installation (please refer to Appendix — Scaffold Layout Plan and Sketch 18 & 18-1) 4-Row scaffolding will be erected all around the building perimeter from 136 ~ RIF. Leave 16 vision glass openings at L38 to our curtain wall to allow access for workers to work, Scaffold support frame will be fixed directly to external wall at the post-fix aluminium cladding at L35 (top panel) to hold the scaffolding with scaffold tie on external wall, ‘After scaffolding is erected and set up of hoisting system at roof certain area that Tower Crane that cannot reach), setting out lines laying, embed remedial (if required), waterproofing application will be carried in 1" priority. Bracket of curtain wall and GRC will be installed according to approved shop drawing in correct position. Cirtain wall will be installed first by using Tower Crane and our hoisting system at roof for those areas that Tower Crane cannot reached and then install GRC panel by using of Tower Crane. Special arrangement for scaffolding modification will be cary out during GRC panel installation: = Install L36 GRC panel using existing 4-row scaffolding | Modify the 4-row scaffolding to double row in order to install the L37 projected moulding. ~ After completion of installing 137 projected moulding, re-modify the Gouble row scaffolding to triple row in order to install the remaining GRC panel including the column and top pieces. Scaffolder will be full time on site to modify the scaffold tie once the GRC pane! is installed. All scaffold tic will be relocated to the vertical gap between curtain wall unit and GRC panel. Rev.0 Netfortune Engineering (FEA) Macaw Limited Page: 18 of 49 ‘Method Statement for Hotel Curtain Wall/Glazing & Doo. No. : VHCMMSI002 ‘Aluminium Cladding And GRC Clodding Tsue : 001 Installation, Date : 73-Mar-2006, 23.6 Extended Living Room Installation: (please refer to Appendix ~ Sketch 14) Double row scaffolding will be erected all around the perimeter of Extended Living Room. Scaffold support frame will be fixed directly to external wall at the post-fix GRC panel at 16 to hold the scaffolding with scaffold tie on external wall ‘After scaffolding erected, setting out lines laying, embed remedial (f required), waterproofing application will be carried in 1* priority Bracket of curtain wall and GRC will be installed according to approved shop drawing in correct position. Cartain wall wil be installed first then install GRC panel by using Tower Crane. ‘Scoffolder will be full time on site to modify the scaffold tie once the GRC panel is installed. All scaffold tie will be relocated to the vertical gap between curtain wall unit and GRC panel. Rev.0 Netfortune Engineering (FEA) Macau Limited Page: 19 of 49 ‘Method Statement for Hotel Curtain Wall/Glazing & oe. No. : VHCM/MSI002, ‘Aluminium Cladding And GRC Cladding Tssue : 001 Snstallation Date : 23-Mar-2006 23.7 Installation for Left Out Openings (please refer to Appendix — Sketch 15-1) Left out openings are required either for access or scaffold support fame ‘at curtain wall vision glass, aluminium cladding areas and post-fix GRC panel. ‘A custom made steel rigger support frame will be mounted at roof parapet wall in order to carry temporary gondola and support of lifting fraterials. A winch system will be set on roof floor for the purpose of ‘material lifting for the case of installation works at end wall and blind wail areas. For Glass Installation (Typical Area with opening): = All the concemed glass will be packed with wooden crate and delivered {fo the designated floor by means of Tower Crane with assistance of Joading platform at early stage: = Remove all debris from the opening to be glazed; ~ Prior to setting glass, solvent clean all glass edges, on the interior and exterior surfaces of the full perimeter, = Setting blocks are to be installed prior to setting the glass to position; = Lift the glass with suction cup internally and place the glass in correct position with assistance of extra worker externally working on gondols; = Apply weatherseal sealant (DC 791) extemally ip order to fill the entire ‘eal cavities afier setting of glass and ensure the glass is installed correctly = Too! all sealant within 10 minutes of sealant installation and clean all excess sealant from the glass; = Install the extemal aluminium capping back to original position with gasket, asa fixture to hold the glass. For Glass Installation (End Wall or Blind Wall areas): _ ‘All the concerned glass will be packed with wooden crate and delivered to the podium floor by means of Tower Crane and distribute the glass to the exact location of the installation area. = Remove all debris from the opening to be glazed; = Prior to setting glass, solvent clean all glass edges, on the interior and exterior surfaces of the full perimeter, = Setting blocks are to be installed priot to setting the glass to position; = Lift the glass with electric suction cup which to be hoisted by winch system at roof floor; ~ Workers on gondola will stabilize the glass upward simultaneously during hoisting of the glass to avoid any impact to the installed external fagade. the glass with electric suction cup and place the glass in correct position; Rev.0 [Nerfortune Engineering (FEA) Macau Limited Page : 20 of 49 Method Statement for Hotel Curtain Wall/Glazing & Doc, No. : VHCMMSI002 ‘Aluminium Cladding And GRC Cladding Issue : 001 Installation Date : 23-Mar-2006 = Apply weatherseal sealant (DC 791) externally in order to fill the entire seal cavities afier setting of glass and ensure the glass is installed correctly; = Tool ali sealant within 10 minutes of sealant installation and clean all excess sealant from the glass; - Install the extemal aluminium capping back to original position with gasket, asa fixture to hold the glass. c. For Aluminium Cladding Installation: = The post-fix aluminium cladding will be specially designed for later on installation; = All the concemed cladding will be packed with wooden crate and delivered to the podium floor by means of Tower Crane and distribute to the exact location of the installation area; = Lift the cladding winch system at roof floor; * Workers on gondola will stabilize the cladding upward simultaneously during hoisting of the cladding to avoid any impact to the installed external facade. = Lift the cladding and place in coect position. 4. For GRC Ciadding Installation: = The post-fix GRC cladding will be specially designed for later on installation with anchorage and lifting point at externally by the Supplier; = All the concerned GRC cladding will be packed in steel rack and delivered to the podium floor by means of Tower Crane and distribute to the exact location of the installation area; = Lift the GRC cladding with custom made support frame anchored to the panel externally and be lifted up by fork lift. - Place the GRC panel in correct position and adjust alignment prior to tighten the fixing boltextemally; = Touch up to the anchorage and lifting point by the Supplier. Rev.0 Netfortune Engineering (FEA) Macau Limited Page: 21 of49 Method Statement for Hotel Curtain Wall/Glazing & Doe. No, : VHCM/MS!002, jam Clodding And GRC Cladding Tssue : 001 Date : 23-Mar-2006 2.38 Material Delivery, Distribution and Storage 23.8.1 Off-site Storage a Since it is not practical to store curtain units inside hotel building due ‘0 the enormous external wall hindering the hoisting, it is proposed to employ an offsite yard to temporarily store curtain wall units and other materials after delivered from factory. b. The yard shall be approximately 700 sq. m for curtain wall and 600 sq. m for GRC cladding materials which could reserve for the next of seven (7) days installation on site. c. The yard shall be fully secured and insured, and provided by Client. 23.82 Delivery from off-site yard to site ‘a This will be carried out by truck which the overall height is less than the minimum headroom of Podium Ground Floor. (4.4 m). b. Only those material requiring installation immediately are delivered. 23.83. Vertical delivery from Podium Ground Level to Podium Roof 2. There should be horizontal left-out openings at podium structure adjacent to Hotel Tower provided by MTC. b. —Thesteel rack of curtain wall units/GRC panel will be hoisted up through these openings from Ground Floor to Loading Platform by means of tower crane provided by MTC c. These units/panels will be temporarily stored at Loading Platform prior to installation. 2.3.84 Provisions of catch fan by Main Contractor a. Any fagade installation works sball be protected by catch fan above. “The catch fan shall be situated above our monorail system. b. Any catch fin below fagade installation works will obstruct vertical ‘material hoisting of fagade materials and shall be dismantled prior to actual installation. c. Catch fan installation and dismantle shall be co-ordinated and agreed ‘upon with Major Trade Contractor. 23.85 Material delivery plan © curtain wall units arriving site by truck (Sketch 6) © curtain wall unloaded ffom truck under the left-out opening (Sketch 6) ‘© hoisted up through Ieft-out opening by tower crane provided by MTC (Sketch 6) Rev.0 Nesfortune Engineering (FEA) Macau Limited Page: 22.0f49 Method Statement for Hotel Curtain Wall/Glazing & Doc. No.: VCMMSI002 ‘Aluminium Cladding And GRC Cladding Issue : 001 Installation, Date : 23-Mar-2006 © curtain wall units shifted to designated Loading Platform for installation. (Sketch 6) © curtain wall units hoisted up by electric chain block on monorail for installation. (Sketch 2) Rev.0 Netfortune Engineering (FEA) Macau Limited Page : 23 of 49 ‘Method Statement for Hotel Curiain Wall/Glazing & Doe. No. : VHCM/MSI002, ‘Aluminium Cladding And GRC Cladding Tesue : 001 Installation, Date : 23-Mar-2006 239 Field Water Test Procedure 23.9.1 Preparation and Set up of Equipment : ‘© This field check is intended to determine the resistance to water leakage of only those joints, gasket and sealant details in the glazing which are designed to remain permanently closed and watertight. The overall testing shall be ‘complied with AAMA 5012-94. © Gondola / scaffolding shall be set up / erected for the application of water spraying to the designated curtain wall. ‘© The test shall be conducted using a Type B-25,#6.030 brass nozzle with & 12" FPT with a 3/4” diameter hose end shall be provided with a control valve and a pressure gauge between the valve and the nozzle. The water pressure to the nozzle shall be adjusted to produce 30 to 35 psi at the nozzle inlet. 2.3.9.2 Procedure ‘e ‘The water shall be directed at the test section and perpendicular to the face of the wall. The nozzle shall be moved slowly back and forth above approximately 5 linear feet of the framing and joints, ata distance of 1 foot from the most exterior surface of the wall for a period of S minutes. © Working from the exterior, the wall test section shall be selectively wetted progressing from the lowest horizontal framing member, then the adjacent faming intersections, then the adjacent vertical framing member, ete. During the test, an observer at interior side of the wall shall check for any water Jeakage and shall note where it occurs. © Ifo leakage occurs during the 5 minutes test, the next 5 feet of framing shall be wetted for 5 minutes, and testing continued in this manner until the entire test area is tested, @ If leakage occurs and the source of the leakage cannot be identified, the {following sequence shall be followed. "After allowing the wall to dry completely and working downward from the top of the area to be checked, all joints, gaskets and framing within this arca sball be completely and tightly covered, ‘on the outdoor side, with water proof adhesive masking tape. © Starting at the bottom of the prepared area, the masking tape shall be removed from the lowest horizontal framing for a distance of not more than 5 feet from one end of the frame, including the joint intersection or comer at that end, This exposed length shall be ‘subjected to the nozzle spray as directed in Section 2 © Ifno leakage oocurs during the 5 minutes test period, this length of framing shall be considered satisfactory and shall remain ‘uncovered, If leakage has occurred at any point, the framing shall bbe re-taped at such points to prevent further Icakage of these points during subsequent checking of joints and framing adjacent to or above them. © This process shall then repeated on all framing, gasket and joint intersections within the designated area, using increments of exposed framing length not exceeding, 5 feet and always working Rev.0 Nesfornme Engineering (FEA) Macau Limited Page: 24 of 49 ‘Method Statement for Hote) Curtain Wall/Glazing & Doe. No, : VHCM/MSI002 ‘Aluminium Cladding And GRC Cladding Issue : O01 Installation Date: 23-Mar-2006 upward on the wall. 2.3.93 Remedial Work and Re-checking : © Whenever leakage has occurred, the framing shall be made watertight ia a manner acceptable to the Architect/Consuliant. Remedial work involving the tuse of euring-type compounds shall be allowed to set before itis re-checked for leakage. © After all necessary remedial work has been completed, the required curing time, if any, has elapsed, all repaired framing sections shall again be checked, following the same procedure as before on Section 2.0. Should teakage still be found, further remedial measures shall be taken and checking shall be repeated until all framing in the designated arca is found to be satisfactory. NOTE : According to Specification AAMA 501.2-94, water leakage is defined as any uncontrolled water that appears on any normally exposed interior surfaces, that fs not contained or drained back to the exterior, or that can cause damage to the adjacent matetials or finishes. Water contained within drained flashings, gutters dand sills is not considered water leakage. The collection of up to one half ounce of Vater (15 mi) in a 5 minute test period on top of an interior stop ot stool integral ‘with the system shell not be considered water leakage. Rev.0 [Netfortune Engineering (FEA) Macau Limited Page : 25 of 49 Method Statement for Hotel Curtain Wall/Glazing & Doe. No. : VHCMIMS/002 ‘Aluminium Cledding And GRC Cladding Issue : 001 Installation Date : 23-Mar-2006 23.10 Protection 2.3.10.1 Proper Protection The glass supplier does not recommend any Kind of plastic protection film to be applied directly to either face of glass as after long exposure to sunlight (UV) and heat, plastic films will stay very film on glass surfaces and become extremely difficult to be removed without causing and adverse effect to the glass surface. Adhesive transfer from the protection film onto glass surface will also be occurred. Moreover, applying protection films (usually coloured) will further decrease the light transmission and affect other trade's work which, by experience, ‘will result in more aggravated breakage. Should any welding on site is necessary, welding workers will employ ‘custom made catch buckets bedded by wet cloth to screen off the ‘welding spatter drepping down or damaged any installation. Itis highly rnot recommended to have any major welding works carried out after the curtain wall units are installed. ‘All exterior and interior finished aluminium surfaces will be wrapped ‘with approved plastic protection film to avoid surface damage during handling and after installation. Following the installation of the curtain wall units, a transparent polythene sheet screen will be properly fixed along all sides at the back of the curtain wall to screen off other trade from physical approach and fact as a protection screen for the glazing. However, this screen can in no way be watertight as to totally screen off aqueous contamination such as grout spills which may result from floor screening works and incontrolled drainage of water/dust slurry from the floors above, etc. Extra protection fo curtain wall units and GRC panels at L6 Podium ‘will be implemented with thin plywood at about 1.5M height for both intemal and external face in order to prevent any external impact directly onto the installed units and panels. It will be the Major Trade Contractor's responsibility to instruct and ensure that these protection not to be removed or vandalized by other trades. 2.3.10.2 Protection - By Other Trade e The area arcund any water supply point is recommended to be dammed out and drained in order to avoid water from spilling down at the slab edges. all-out such as spilling of wet cement grout to the installed curtain ‘wall, care must be exercised during materials hoisting to prevent. Not to allow any use of shop-saw, oxy-acetylene gas cutter, or wherever equipment which will give rise to sparks, to cut metal or Rev.0 Netfortune Engineering (FEA) Macau Limited Page: 26 0f 49 Method Statement for Hotel Curtain WallGlazing & Doe.No. : VECM/MS/002 ‘Aluminium Cladding And GRC Cladding Issue : 001 Installation Date : 23-Mar-2006, 24 metal pipes at a distance so close to the installed curtain wall as to ‘cause damage to the curtain wall components by the sparks emitted. Whenever welding work must be carried out by other sub-contractor that welding sparks are totally screened off from the curtain wall. It is expected other trades (including their material) shall stay clear of the curtain wall, installation and temporarily stored units on site. Under no circumstances must other trades remove or damage the protective transparent plastic screen as described above. No cement grout spilling will occur at the edge of the slab during floor screeding works. No wet trade workers shall site mix cement mortar om the floor so close to the edge of the slab as to let cement water spill down onto the installed curtain wall. ‘The curtain wall, aluminium cladding and GRC cladding installation will be carry throughout the whole external fagade of the Hotel building from L6 to R/F. Rev.0 Netfortune Engineering (FEA) Macau Limited Page : 27 of 69 ‘Method Statement for Hotel Curtain WalliGlazing & Doc. No. : VHCM/MSI002 ‘Aluminium Cladding And GRC Cledding Tssue : 001 Installation, Date : 23-Mar-2006 3. RESOURCE REQUIRED 341 Personnel £ k. Deputy Project Director (one no.) He will overall monitor and responsible for the project. Project Manager (one no.) He will overall monitor the project for the progress as well as site safety. Assistant Project Manager (one 10.) He will assist project manger to monitor site progress as well as site safety. ‘Designer Engineer (one no.) Hie will be responsible for the design of the monorail to comply with al] requirement. Site Manger (one no.) ‘He will overall monitor the site team members for the execution of site work. Safety Supervisor (three nos.) He will be responsible for site safety to ensure all working procedures are in a safe working environment. Surveyor (five teams-~ three nos/team) ‘They will layout all required reference lines for the installation of ‘monorail system priot work commencement. Supervisor (three nos.) ‘They will be responsible for site work execution and ensure all works are properly done according to approved shop drawing. Logistic Supervisor (one no.) He will be fully responsible for all materials transportation either from factory/supplier to off-site storage of from off-site storage to site. Storekeeper (one no.) Fe will be fully responsible for all materials and equipments/tools stored at site store house. Banksman (eight nos.) Rev.0 Netfortune Engineering (FFA) Macau Limited Page : 28 of49 ‘Method Statement for Hotel Curtain Wall/Glazing & ‘Doe. No. : VHCMIMS/002 Aluminium Claiding And GRC Cladding Tssue : 001 Installation Date : 23-Mar-2006 1 5. They will be fully responsible for the co-ordinations with Tower Crane operator and other lifting appliances operator for material hoisting, loading and unloading. Rigger (six teams — 6 nos./team) ‘They will be fully responsible and co-ordinate with banksman for the hoisting, loading and unloading ofall materials. ‘Welder (four teams—2 nos/team) They will be fully responsible for all welding works on site. Ganger (four tears ~2 nos /team) He will be the team leader of installer's team to lead their team ‘members fo install the works according to approved shop drawing. Installer ‘They will install the following works according to approved shop drawing, Curtain Wall : four teams~ 6 nos /team Curtain Wall Bracket six teams~2.nos/team Aluminium Cladding, six teams ~ 2 nos team ‘Aluminium Cladding Bracket + six teams - 2:nosJ/team GRC Cladding four teams— 8 nos.team GRC Cladding Bracket eight teams—2 nos./team Internal Lining : four teams ~ 4 nos,/team Waterproofing Applicator (four teams~ 2 nosJteam) ‘They will carry out the waterproofing works to extemal wall. Electrician (two nos.) They will carry out all the installation, fiequent checking, and maintenance of electrical equipments. Canlker (six teams ~ 2. nos/team) They will carry out all the sealant application works. General Labour (six teams ~ 4 nos /team) They will carry out all the miscellaneous works on site. such as housekeeping, distribution of parts, protection to installed fagade, safety facilities set up and eto. Rev.0 [Netfortune Engineering (FEA) Macau Limited Page : 29 of 49 Method Statement for Hotel Curtain Wall(lazing & ‘Doe. No. : VHCMIMSI002 ‘Aluminiam Cladding And GRC Cladding Tasue : 001 instalation Date : 23-Mar-2006 _ 32 Plant ‘Tower Crane (provided by Major Trade Contractor) b. Triple Track Monorail System at L21 c. Double Track Monorail System at L32 & L39 Triple Track Hoisting System at R/F © Derrick Crane at R/F (for erection/dismantle of Hoisting System at R/F) £ Electric Chain Hoist SWL LOMT 10 sets, SWL 2.0 MT 2 sets SWL5.0MT 5 sets Welding Machine 8 sets ‘Temporary Gondola 24 sets Fork Lift 3 nos. Lorry Crane 2 nos. 33 Materials ‘All materials to be used will be clearly stated in our approved shop drawing. 3.4 Specialist Services Specialist scaffolding contractor will be hired for this project to erect scaffolding a both End Walls from L6 to L35, Extended Living Room and perimeter around the building from L36 to R/F |All concerned method statement and calculation will be submitted for approval prior fo the commencement of scaffold erection |AIl scaffolds will be erected, modified and dismantled according to related regulations and must satisfy all safety requirement during work execution, [All scaffolds will be erected, modified and dismantled by competent workers and inspected by competent person with valid certificate. Rev.0 Netfortune Engineering (FEA) Macau Limited ‘Method Statement for Hotel Curtain Well/Glazing & ‘Aluminium Cladding And GRC Cladding Tssue : 001 Installation, Date : 23-Mar-2006. 35 Supervision 2 Ovr site manger will carry out a briefing to all team members to explain all ‘working procedures as well as site safety prior to work commencement, b. Our supervisor will full time supervise the work to ensure all works are done according to approved shop drawing. c. Our Safety Supervisor will check the work at the following stages: i) Stage 1 — before work commencement © To ensure all workers are equipped with proper personal protective ‘equipments. © To ensure the workplace is in a safe working environment with proper access. © To ensure all scaffolding and loading platform to be obtained with valid certificate. © To ensure all lifting appliances and gears are in a safe order with valid certificate. ii) Stage 2 ~ during working ‘@ To check all workers are wearing proper personal protective equipments. © Tocheck all workers are working in a safe manner. iii) Stage 3 ~ after work completion © To ensure all debris are clear off. © No oil / grease remained in the workplace. © No fire source left on the workplace. Rev.0 [Nesfortune Engineering (FEA) Macau Limited Page: 31 of 49 ‘Method Statement for Hotel Curtain Wall/Glazing & Doo. No. : VHCMIMS/002 ‘Aluminiam Cladding And GRC Cladding Tsgue : 001 Installation Date : 73-Mar-2006, 4, ASSESSMENT OF SIGNIFICANT RISKS Our Assistant Project Manager and Site Manager together with our Safety Supervisor will arty out risk assessment to identify the effective procedures and practices and the possible Situations where the plant or associated systems of work may pose hazards. Funk sesesoment will be recorded with detailed precautions. It should be used to formulate clear instructions for all persons involved. Toreseeable hazardous operations associated with this project are summarized as follows: 41 Access/Egress © —_Alllaccess/egress to be kept clear without any obstructions. @ Report to Major Trade Contractor for any obstructions/unsafe condition in rain road access. © Ta ensure a proper access fo allow workers to get in/out from working platform and scaffolding. @ To fiequent check all accesslegress to be maintained in a clear access free from obstruction. 42 Place of Work © All work arcas must be kept clean and orderly, Rubbish, debris, waste and tiselese material constitute # fire hazard, as well as a potential tripping hhavard on the job, and must be removed from work areas as fast as they accumulate. Areas for temporary accumulation to be provided by Major Trade Contractor for dumping of debris. © All work areas must be kept clean and free from Joose material and trash. Storage and stacking areas must be kept in an orderly condition to allow safe access to the materials. Access road to site office and site store must be kept clear and clean. © Stacking of materials shall be properly arranged and not placed at access and egress. © All management and supervisory personnel are required to carry out Continual health and safety surveillance and take immediate steps to remedy defects or unsafe practices they observed. 43 Others at Risk © Toestablish a scheme for precaution for working or work suspension during “Tropical Cyclones and Heavy Rainstorm. © To notify and monitor all visitors including driver & labour of material transportation to wear proper personal protective equipments. © To notify and monitor all drivers of all vehicles will be in possession of @ valid license for the class of vehicle they drive. Rev.0 Netfortune Engineering (FEA) Macau Limited Page: 32.0f49 Method Statement for Hotel Curtain Wall/Glazing & Doo, No. : VHCMIMS/O02 ‘Alaminium Cladding And GRC Cladding Issue : 001 Installation ate : 23-Mar-2006 44 Competence for ‘Key’ Activities ‘All competent person and workers tobe recorded in a List of Competence of Work {s per Major Trade Contractor's standard form and be submitted to Major Trade ‘Contractor for Record. The List shall include the following works; © Safety Supervisor © Scaffolding erection and dismantle @ ~~ Welding Works © Gondola regular inspection © Fork Lift Driver License e Abrasive wheel Cartridge operation © Test Laboratory for Weld Test/Embed Test © __ RPE for checking of Lifting Appliances and Gears 45 Dangerous Goods, Noise, Manual Handling, ete. Netfortune will establish and maintain procedures designed to control risks arising from handling, storage, use and disposal of substances hazardous to health ‘The procedures will be based on a requirement contained in the respective procurement process for every supplier of a hazardous substance to provide the relevant substance hazard information ‘Netfortune will supervise and monitor the implementation of the procedures which will include, but may not be limited to: © establishing an inventory of all hazardous substance. @ maintaining a file of relevant supplier hazard data information. © carrying out an assessment ofthe proposed handling, storage and use ofthe hazardous substance and completion of an assessment report detailing the hazards and any necessary precautions. © ensuring that personne! exposed to hazardous substances are provided with ‘witten. safety and health instructions, training where appropriate, and observe the precautions therein. 46 Environmental Impacts © All work areas must be keptclean and orderly. © Tokeep the work place free from oil/grease. © To-ensure workers to wear ear protector for drilling, hacking and ete that ‘works would cause noise exposure, © Apply permit to work for any works caried out at night. Rev.0 Neyfortune ‘Method Statement for Hotel Curtain Wall/Glazing & ‘Aluminium Cladding And GRC Cladding Installation 5. Engineering (FEA) Macau Limited Page: 33 of 49 oc. No. : VHCMMS/002 CONTROL MEASURES TO BE USED 5a 53 Emergency Arrangements © The Company will follow the Major Trade Contractor's emergency procedures and participate in drills for emergency situations, including fescue operations. The foreseeable emergencies would include, but may not be limited to fire, persons falling from height, falling object onto persons, persons injured and/or stranded aloft © The Company’s Site Safety Supervisor shall be also act as emergency coordinator and shall keep close contact to Major Trade Contractor's appointed Emergency Coordinator. © Irease of emergency on site such as fire, flooding or collapse of equipment plant, all employees at the workplace shall stop the work immediately and Inform our Site Safety Supervisor or directly report to the Major Trade Contractor’s Emergency Coordinator and follow their arrangements and jostructions. In the meantime our Site Safety Supervisor will also report (0 ur Project Manager for details of the emergency incident. © Incident Report will be prepared by our Project Manager with assist of Site Safety Supervisor ‘and be submitted to Major Trade Contractor within 24 hours. © Gur Project Manager should debrief the site personnel and instruct how fo prevent the similar recurrence. Security © All security services/ixilities to be provided by Construction Manager / Major Trade Contractor to maintain a clean and ordered site condition. © To fallow all in-house rules established by Construction Manager / Major Trade Contractor. Third Party Liaison [All sorts of communication including work instruction and documents will be sent / pore 0 287 argo soy ug sein on ‘on anda sere ayo osu p00 rr aayes a pea wig o ead Aare, pass and caf omere por agg ome soy, eqopue vw pono sq mo 23 reo optus op ow ‘ana ka panes vo Sugion a epi pu was sno 9 2 va | rgenresumion | ‘samovaye jonuog Sane ‘purzes JoasmeD S00E INTE ON MEATY 1130 Z98eq ‘woneTeIsU pury Suippeid wnmununry "eA UTEIND + AtARoW 200~ IH/NOHA # JON yooyg uoHLOyyWep] prvzey ponuayy moony (Vag) SupsaouStagy oumIOfON SET — yo weauouydas sy vosiod warsuco mod - suryoeu Sido ate a qd etnias sma) + donut oop oweurgy | Suypaut fq Amt, THR STEOSUE oT POR HATS OH ‘x yan Kings amas pr SOUT ARGO 30H) = uosiad mireduoo J suoped Suppor yo wopradsin soy ‘auuado ey ufnong wnored opom jo | imal oes Anmoss ene puoi OL + nea pra uss dosed a}aon “poo oq pu 040m notation rion e SuHO ‘estan pogitnb 2 Bp poi | sexo soyen; pue sag ms | pronase oon} 30 aga owudoxde soy - Bus 7 ‘ung pas 2m fpniea Fompom ap 63H npoea | symds upon Baieg | Aaposnea én PW, a sang BUGON oy DO] 7 | 4a yo paynes 29 pr : topos Sng ad oat a, : Argereg | __ sSeyeoy Areata, vornsonsetg | : onto: | pom Sunpuey | Sunpuey enous 1] pengpuespeg | __fenmaytsedasdin | Ko pasmo nti | open peuiag | rpese swipes | 9 paReoht — = al L eyoxg eum soy | _PRTHJO STO Ure pomaary a00q Lr TL go ¢oBeg voweyresay Burppe|> SUD 9007 SEW TZ ag 00 ‘ON MALATE, pay Supper murray ‘pea WeUND | KEATON 200 TH/INDHA ? PU yeayg woRNByHUep] PALZeHL panwuiry nvonpy (AA) SussaouySug aunyofion, "Tod Sasa oy pau Samosa ony Aaajes asta oe ssoaEY ARFES IEE = ‘woused swoyedaioo sxgneyd Beno | voxenaisy vonemsur bo BUDHON eFTH “proofs 9 usnooy’ PUR sq paar sj won Bupi0n ae Aue amnogey 105i rorswsony PUY |S ‘Boymp uoddns 0 2808 Supp08 31006 pats ar doo} ines 2 soremg | _ wey se Suro | soofao Sues ujod aBwsayou 0} pas famoos 09 con req ages cms pie Sst qHustay dossiasdng yes 09 joo Tuyugen auTedg ‘stom, op aap orezado ura sseyms poues AIO, yon, ni | _ wien eS, rapes Ba oo s22N09e7 np soteo Sunes | _“2888ry vejesul | vopenest 8A WEL Pa ee Pp Buyr od semenapyfonen Suet pu Joost DOE FA Te area 00 “ON MAIADY, 1130 paded u puy Sumppeyg wrruranyy 200~ THANOHA + PU yoays BoHVIBHUSp] Pxezey panuny moonyy (Vax) SupsoouyBusy 21MHOfON ome pr Suey ARS JA, ‘uosred wtaditoo A Baoeso vos 8 ‘avayp320 1.409 pane 9 Fo som sondtoo Aqparross st urpauess on omsug _- yoy |__Bo ve Soo | nity wos yea | Tyee” Symp vodns wn pu ‘yop pan pu doay Anja axu foray | wuftea we Semon | tow sofgo Sane quem 23 wooaig 2uiproures 5 Toor HU rey 9p omeus pu gad owed ue poyion ag uno exoypem woxednD twnaduos dq jp yo ur Bat 6a mas | opus 190, eye oi aetedo uo sino, ‘ae usp oteyp Bury 9450 ‘agi fq pages 010 919 VT {Jo Bujpuauneo aseyaq ayop susie jo 931 voadsu poem ued Buggy sade 130s Beg puy Suyppeig warareny 200~ IH/NOHA } PU PRE ang wu 180 pera jo 25789, ah Heng : AUAROY yooyg WoHRIyHUAp] psezEH D007 FEN TZ aed 00 ON MaLAOY pannury mvonpy (Pa) Supoausug oumsopion TeapaaaTAOR aL —- wonesado ump nodes wurypany 523308 01 _ yey | wBjou re forvon | __ swafao Sure -paond amnbope ss rogpd sodond 9pi401g as poomena sua yoo 2) SI ammng | _ ney amyON, saypeg | __wftoqe spon ano Sumas 29) tune fone] pure Sou ‘souaye) 800) 0 39 Ayes msi pu sson70y Kage 19, ‘age 9 pauwors nti ze UHM ofeamg | Buppeyp pogo tise | TTL Jo Sujauauoo a10}0q 12y9p wae Jo 991 So Suys pre wey Fury ap Jo woes, ‘ant 4 pouaoxs oe 919 VTE OSES at pout aa ames SUL oY a poucusxa a swrope(d Supeo, 238 doyewa | __ Berurt sndosday | anp saotgo fumes po uontay worATS enpinga totems j poviou Bayi ruarsedosd yas FuoM = | font, | pomepa Sepa | Supuny eeu swysze jo Tncaw depen ag doy =| —_pomarpow yong | feniesodontay | qpemeeauy | stnage wee |_ pom Supra So a sansa Js BUNS rake to premajoang | pH powagy aidbed Lor 11 Jo 928q woreressuy BupPEID YD. 9000 TN IZ aed 00 ‘ON MOLAR 700- IHNOHA + puy Suippeig waren yooyg BoNwONHUEp] pawzey yy WEIN : AIAROY pamuuyy nooupy (VaeD Supsooup Bust oumssofion ny Seip pant jo wBTTSDETST sy wasted mojaduoo uyoddy = sisi ‘uyeur ao Se qgaovniorddn sina, ~ onto 363, Joouyy oupsmay | Sumpuys Aa Xanfoy Tod aaoepue Aurea sutag 8 Buz Ba Powe 01 ‘ayn uogosyud aplaoud og, = umqpuv 253 64 aon Afi, supe | op suds Bupa = stor famwoors wopransoorg ‘Po gag ompaaua s pen rewarded yun Sup = powyy pony | Sorpum ence smog] amiamuon andeox «| Anfupenrpweeeg| Mut | __Saposea cnt | sop pune | Suprawmieeg | it = sue osaD Sem arn i 209 IRE. 30 200 Ree papayy atioag 38 gE wa 11 JO Le8eg ‘uoRey} 9007 TZ aed 00 ON MOHAeY puy Suippeyg urmrumyy ‘ea, UUM | AyaRoy 200 ~ TH/INHA | PY yooys vonVIHUSpy Prezey paynuagy moonyy (VI) SmusoouSug aunpsofien cea condo ‘Buump noddns wy paw so9301 01 pap pe doo] aps anny oy soon pany y+ Aree ou 1 BuO, spafgo Sure ox paxgy Atomoas 24 ‘mst pe soured osiod wusadnos £9 Bopp O49 Se uonondeu soy = usps Angerea toy ye Bun40y4 yes x09 yon Fupuen oyroads 08 30 Baus sxojoq =p compres Sang] samogey ee ore vireensug - neg | pom ovonp sooijesonmey | ‘8h myeset sea -samseayy jonus,) Be P jo aan sprwey 29 jonuaD Sur Sei eo seep JO 2800 prea pamagy tdoag Tyo g 98ed ‘wonerersty BuIpPEID DAO. poor Ic pury Suppo] wonquaniy ‘eA WELT : ANARDY 200 ~TH/IWOHA | 324 yooyS UOHOYHUepy pavzeyy ponuyT moony (VHD) BupoouSusy aunpsofian. Sees oe wousyeg pu sorezado poy poquacs | eames Bury or Syewa | __ Suyrysedoxdmr | snp spafge Sumre, Jo Burauauruen anjou 2j9p wo} Josey cp BURT OM, i sot] pomena tepn | pomerpun peat |_fommpe sone | ranoger 38h 7 (rae) wopejersuy wiaIsss BaNSIOH ZT pseu a Jo asnt aE 9} 1 Ws a6 Tog |_pemanemo | penn panauy aden EL a 11 30 6 sind iDPEID DUD 9007 FEW IZ ed 00 "ON MO}AD Tea wen + AIANDV 200 THANOHA : 34 HIGHUEP] PILZ pomuyy mvovyy (VoL) Bupsoousug ounsofieN ET efeoeidBuppon epomsus oy - ‘wenuro[3 ing yo 9A Joong sey Bus wonouuoo 2 age pamnouse 40 geo yp a joond sone 257, ‘Susoau Buppon pt 20:27 2poqt ov meg popmoNDeIE, (Himba wompuREag sooys Somes Ba gga owudosdde sito, Z ‘sree sBeeoy Arun, “fo pompeyy Sexpu, =| din pm pur yore [poopy sodosdu sys) x09 yon ‘Bure Jo Suu any 9p uayed Jo 204 o1e Buy aso Boot py Bug ‘gana 9 pout voperTsysu ciepemetuies| mon yvtiwaniy saeeg | pou Sr tot remap wontg ue | zz ear [ cone Sade og |_PaHIO H Pa powagy aos reraer | wo T1J0 01 98eq ‘uoneypersay SUpppeD UD 9002 “TEN TZ aed 00 "ON MALAY 200 - IHNOHA ? PH puy Surppeio un nT TBA WEEN : MEAL yooys UOHKOyHMp] prezey ponuyy moaoyy (VED BusoouSuy sunuofien - J : Aye, pou Suppo soefgo Bure Rip PUR jo wawenedss ejuntied nigadtuoa teddy = soso sugpeur et ao fo gag awndordde svoj ~ santa aka eau ansesay | Supun® ka Xan, oe aRIpUE con pont dtamoae aq 169 AIOE ‘ams pus ssouney A051, : Apes w@ioue2onsoy | __PISU UO TE ‘nyphen top ‘ond Bupion 3 pappowd vs SEPA ib 94 : som ovata san0j8souwot pt pais sseut ony Bo-gad aeudodde sry = sumq poe ‘ivan Buoy sin Soo > Sypueg | 9p sys Supra 8 ny 6a poss nf (eau) | eet peur] samneeay Jono Suns eee PR papas aqdoaa SEL = —=_=7 11g0 11 98a wor east SUIPPETD QUO 900 THN TE ore 00 ON MONO ary Buippeio wt ‘aeag wenn) : Auapoy 200- TEH/WOHA | 8 yooyg woRKIyHUeP] paczey porary moovpy (Wate) StsoounSuzy aunniofien, Neforsune Engineering (FEA) Maca Limited ‘Method Statement for Hotel Curtain WallGlazing & ‘Aluminium Cladding And GRC Cledding Installation 8. APPENDICES 8.2 Risk Assessment Page: 40 0f 49 Doe. No.: VHCM/MS1002 Tissue : 001 Date : 73-Mar-2006, Rev.0 cam) AAT NE “€ (syua ten upg covanbasuoy G)urereg omy Supey poowreyrT 2 Gingoaese “1 ON opus — wog spalyo Bugis | yoads pnarg | (WOU) 9 £ z aus opus uo Bury0m 8 € z se wropucd poe mois yosouons op amy |r wou WOH RTs PO Kase apo | 39 0 99 ayes : 2g x00 oorapiseud |_(oH24) 9 £ z e-pand ombop Sumaen ayrsods spor | em pre weeny pu sd pogo >on. zo Sutouou jo 904 ome Buys pov urea yscins as079 du 49 pou axe Bang rods SpIAOH £ £ aang Aa poutuss ae emapeld Buyproy ams = |_ovanp sreefgo Sart Tiuionbag Gorsnueag sso age $0 34g soe ie Sup posse anppoieu mmiey |_ (01 6 £ £ sumenoyoeds apinorg | _(woner) 9 £ z syromuags uo Bayo conan nto won neg | 1 et x09 100; apron | (noiPA) 9 £ z “Reouenbssmy_ | Aiigeaona | ntoy, von popuottuo3oy gee ERL aOR sominspy 102009 on wa A Ayon re wa BumoR + Ka ISSO ones BapppeID DUO PAY StuppeID UAMIUTINY 7 SUIZEIO/|IA VIAN PH OITE|OTIE + HARA HPAL BOW HOD UE HORTA MENU GEOET sroafona 1130 1 8804 wonerr mI IZ 00 “ON MOTAD pay Suppeio wmmerany 2y 700 — NINS/PA/NOHA ? PU yooyg jueUIssessy YS pamuyy nvovpy (VID) Brysooindugy a1umns0fON (aw) € (1) mo1koa WNT 7 G)ajqssodiy— @) sem9y T8108 TT “Treg oor SumEN oy SeMS fia USL ay sep 0K pu vopuads Bunn Bik seo p tod ato os qa aes sto peozo spo Kep am es HSNO ute ange oe ps ESSN + aun - uns Supeiado =| s8ppye on sao Waiiado duatip Bod Saquen ayods apraoid cxpan pure doo} aes ax of 100) pg for BUNA, posr A sour qe ayy omsis pur jad awutosdde sure, ‘oped wo paypoxs.aq tts ssouom ved ‘ene wostod grado Aq wjopuod jo woods ‘Be Ag pauses owen appods apiaoig uy oopuo8 pow wanes poouow ey oO onay papuamnooay gemoERE 1130 7 #Bed 9002 HN TZ ore “ON MOLADY puy Supppeio wr 200 ~ NINSVU/NOHA #38 yooyg JuauIssassy YSN pomnary mvonyy (VEL) SumpsoounBugy oumsofian (gama) (MOTTE) @DNW¥O) (om oT As “€ (DaeTeon ACT (Epa a (1 io, Buyey suanbastey ()aqpreduy —Gowouey (19H sigeng G)uRvED omy eopRY PoOMLOATT-OAmIGEAeGT“N P ‘pn o ruanaoeydar 1 vossed mojadtoo jody — = uypot ages x0g joo spina | (u2219) » z z sof8208 of0 Bo qd swucdonddn sreayy + | __Sunpanl Aa Amn Tifa SUH OF POR KaiTOOE 2 neg gs sto ps KE oA we moradtuos fg angpejé Bupys0% Jo voHDadsty 2p ‘Sumiedo a yma wope(d Burz0% Jo Bums avoid oy es Aymoas ean aptacid OL, = ‘qgs99 res wroperd ys uossed uaaduoo 21013 Deyop w3;ed sey ze Buje pre vgs Suryy 2x9 Jo woRDadeiy = ‘gan Aq pours sxe Ow VII ORI = ‘dele pootaroes aye toy ures ange Bu é ‘ ue waists perowour "wnop|d sinpeo] an amsuy = | onampereefgo anes |g aay | OI 997 992 HeEL JON samivoyy T0s1U60, isn we wopoadsuy snow | (WoHeA) 6 vonsy papenaonay, 1130 aed woe Tsay FLIPPED DY 9008 TR TE ow 00 ON MOIR pay Suippeio umrumuny “yey UES : AyaeY 200 AINS/VWINOHA : PU JooYg Juourssassy SNA pos y mvovyy (vad) SuproounStgy aunssofion’ (1) 807.220 (1) atessodi (010K) 6 t T 0M, roTsar Oi POND KOS 3 ov es amsue pssa AE 54 odnana fg Rupes Jo vonadsty se syeagnsss ssn td an pd se eyuom atau Ky popes (woIPA) 9 1 yy ort Buy pod ‘orpan put doo, Ages ax oy spotyo Suyted Sumon aypods apiaaig (wo1lRA) 9 59 oor "Fa pam dtodeud 9q 0 _oureqey oxy ames paw ig ado sjop wo payuoxs. aq ued sion ueIadIOD. 18 wo Supuos. Brey wos ye IL en (016 eH nay papuowniesay TL yo s ava 200 ~ DINS/VU/WOHA ! 3X OD ERE poe wotate yesouots tugged Seupvo| 21 Sm. samsnays Jon1i09) omg oxanp se0fan wot ‘300 TN TE ord poy’ suppeig TenTURUNyY TBA ORAM + ATAROY yoayg yuourssassy AST 00 “ON MeIAOY, pamuyy mooopy (aa) Suysoomsuzz aumefon (amin) Gao’) Wacthea @soy una GDaessoday — )oyomy (EMG Nv) ax) sek ENE“ (Bury, Supey sovenbesuoy “7 rgeqarg (6) umIRD MowTY Fur poomoxFT 0 AaeGaG “1 :SION = __arreg eorspivors | wounds | z £ : nolo Sune sons hajramsin po soy Ames oy = oqadunoo 4 Bupjoysns Jo uensedouy epg eeriey ums yas uosred waiadinos €q paradsar 0g pue | Suipjayeds vo Bupa yp x09 yo eprorg | (noua) 9 £ z : wou 2409 00s Buren autrodg 2p jo Bajuaumsos asojag ayep wowed Jo say ar Sus pus ureyp Buys 2m) jo uonzedsy = amy San yes 309 joo prong | (62240) » Bay Aq paummo ar OTS yiwanse] _- | _crenp ssfao Runes yu, ony papuowsmeney quoryent samsroqy fone) yen 110 gaeg meIsuy SUIPPEID SUD ‘900E TN Tz aed 00 “ON Mata, rea ureLN : AUAROW 200~ NWSVWINDHA | PU JoYg JWaUssassy YsRy parry nvsnpy (Yq) SupsoousSusy aunniofion (jommaa) (@onvwo) amo pan Gu GG) HBT Aion yssog—(P)ygeaog 6). fap wsowmyy uy power 1 GIAREGOKE “L ATA Supe sousnboscoy 7 PN es £09 10, =pHO4g 9011199 Ayes ama pu Sst, yepien ajbape yas mop sa corso Buynp odds wayypaey s ‘oypaty pu doo Ares oan $1001 A — =| sooigo san ye x0q oon apnosa (won) 9 é z oi ey wou ne onwiado Suunp vols uuypuy 810% [| seria wo apnais | votes) 9 z £ or pan pre doo Ages ax 0 00 eI stgo Sune ‘Elod SFIOHSU O PHY Noo oryeg Aaps amsue pe essary Aiseoy —- | uo1E/ eke | spOM In; uO ur -povnog oo opuns | or 4) 9 £ z ry Blog wos (o0t12A) 6 £ £ yo oa ge Sus pow ep Burpy om Jo VOR ‘ae a pauruexa ome O7 39 VTE ams sa ig poutine azo suame(d Buxpwo] ams ‘amy 0g coxonp s29%g0 Sums jnusnbag voisreang soos dyes 9 gaa audoutde sions, poxjour Bugy onsen odozd qin Sua gpg ores wonsodau soy | (oma) 6 £ £ pn are Sunn0n an doy, qpasmea Gut | CTL oes USISKS WEAVOH TT gray, PAT somieay 101009 an wan ee 11309 a8ea wonetfersuy SUPPL JUD 9008 FN TE aed 00 “ON MEATY 200 NISHA : 3a pay Suppers wnrununpy TEA weHAD + GyAnow yooyg JUoUIssassy ASA ponuayy moony (Ya) Supsoouy Suzy oum0fiON ———$—<—_$ $< (Qo ke (Dargis (smi APA, 3 pun jo wotreneidat 25 wostad mistadutoo awoddy see *t uyoy souonbestoy —"Z soury Suey poouayrT wm ATgeqorE “YPN suypeut L sya x0q yoorsptiota | _(u2250) » z ‘suf8908 ao 3a ada eUdowe sway Bupurs 6 infor auipogos wo BPH. aye x0g yoorapyiosd | _(woHtea) 9 £ amp peu OH 1x09 J00) pot ur plonrisou snes a agg serous 5300), fp wom Bupgiom au d323 ang put 2 4 poses dai re x09 yoo 9pIA0rd wore |e 6 3 patares 2g pinou 123082 Bn yo 93 J0014 290), jaye patnautse 10 ajge> yo oda Joond. peu Supp pi Gaoow woumrssy woun2er2 cmp watt0 rodoag poy 1 una woneomarg | posed 28019) (wonea) 6 gry uonoy papususoney, 1190 L 38d 200 DSWINDHA | 3H £ SEIS | MOT IENE uc pay Surpprio yeoqS Juoussassy YSN Tusibay uoisiuadng goons Ags 2 Gd srendosdde 519 poxsau Sy nue zedoud qua Sapo. ‘Kop ware Sunow ay) aos, samseayy fone ——— 9002 THN TZ awa ugpuny genoa fey pasnea Aanfuy SG CON IAC pasuary moony (V1) SupsoousSug aunofion [TT (QeoTséEA MOL (C)aiqissodiy (2) a019y (ue) TOASTED Hy AAT ‘en pur uouisyuag pu soyereds pogenb uSiesy yon Jo Suusuaoo a1ojaq wayep weyed 08, isadsuy ysis oop onsig pur Sururen ayroads apsaoug | (mot]A) § £ £ 31d Buipeo} amsueg_ oj anp sipelgo 8d — BH WOIs|ATBEAS done 9, poi Br onc don pm BoP GO spun vwomedsu santo | (wot) 6 ‘ £ pram Sujet oy Aaron STATS | RT lo woroy pepuaumomy | garT SR TR semeop 02809 1130 6 a8bg ‘wonaTeisur Surppe|> SAO 9000 TRIN IZ red 00 “ON MATAR puy Surppeio umranunry ‘yey, wey : (Any 200 NINSAWIAOHA + PX Jays JWMUSsassW ¥STY posnuyT moo (Wate) SusoouySuy oumpofion x) GOxVyO) sassr eye i GNARL A ‘Supoy asuanbosiog 7 ag oury Bu OMTOHT 0.AANEeROY “TNL are x0q oo} apisosd | _(noulea) 9 £ z osssadns 8019 | (OPA) 6 6, £09 00) oprAoH suas ‘voray papustmoasy, =| TOOL ated ‘woneyfersuy SUIDPEID YD 9007 “FEW IZ aed 00 “ON MOqARY puy Suippeio waurunyy ‘Tea WEN : Akapoy 00 - INS/VW/NOHA | PY yooYg Wourssassy Ysny pauayy moony (yA) FupsoausBug sunyofan (momma) GoxVEO) (an) por *e mG somnbasto) nd GoM GRD BMY FapRY poOWSHT LOANED —T=ONL ~ GS SET TD SY {__ | _afs 709 wor spend | (HoU9A) 9 z £ : seo Bu | : sunou __apsxea oo epnoig | (2219) » z z 2] soupuys ani Seproneag areixoaioorepnorg | (voreA) 9 £ z : pur ppaspysem sony So aga swede sq, ug poe ‘pp vam Bupyon 2m day, ay ha pasos nti, (one) 9 ssemsrayy yonu0) peusy, wonpy popuamutosey, 1130 11 3804 su} SIPPELD IUD SERN TE CON ML puy Semppey wmrununyy "pea, wren + GIARoy 200 NWS/VW/NOHA + 3H yoayg JWOUISsSSY YSN panuary nooupy (Patel) BtxysoounSugy aunssofon Netfortune Engineering (FEA) Maca Limited Page: 41 0f 49 ‘Method Statement for Hotel Curtain Wall/Glazing & Dos. No. : VHCM/MS/002 Aluminium Cladding And GRC Cladding Installation Date : 23-Mar-2006 8. APPENDICES 8.3 Field Control Sheet Rev.0 ‘Netfortune Engineering (FEA) Macau Limited FIELD CONTROL SHEET Project : “Venetian Macau in Cotal, Macau FCS No. : _2120/3110/VHCM/FCS/002 Loe: Date: 22-Mar-2006 Prepared by : Leung Wai Man/ Ricky Ip (ost : Site Manager / APM ) Hazard Control Sheet Attached : ¥es_| No Period of FCS Validity : One Month Subject : ESS IS - ILE ORC HL Hotel Curtain Wall,Aluminium Cladding & GRC Cladding Installation Documents/Permit Required : Certificated Skills and Training Required : Hot Work Permit 1. Safaay induction Training LPH Se WE 2. RPE Signed Certficte for all Lifting Appliances & | 2. Field Control Briefing Gears 3, “LIBRE ASTRA DL DERE BR 4, Welder's Certificate 3. RPE Signed Certificate forall Monorail & Hoisting SPCR System at UF 5. Training Course for Qualified Banksman HORM POA ROR SRA 4, Valid Certificate for Scaffolding 6. Licensed Fork Lift Operator a : BARTER 5. Valid Certificate for Working Platform 7. Competent Worker & Person for Scaffolding Erection Gee eee Se Inspection 6, Valid Certificate for gondola SWI EA ce AAR, 8. Competent Person for Gondola Inspection emis Rie Plants, Materials, Dangerous & Carcinogenic Substances ‘1. Tower Crane (provided by Major Trade Contractor) ‘S. Gondola 2578 (LARRY fat 2, Electric Chain Hoist 6 Darrick Crane rd ares 3. Welding Set 1. Pork Lit aot Ba 4, Working Platform ‘8 Lorry Crane. |__sc fear 7 Fae Key Environmental Controls : Key Quality Controls 1. All work areas must be Kept clean and orderly 1. Enoure te works have been cared ou per Bee DONS approved shop deaving 2. Tocensure workers to wear ear protector for drilling, RCRA LAO Jacking and ete that works would cause noise 2 exposure RTA REE RE REM RRS Z TAUAUTTL, TELS Apply permit to work for any works carried out at night FARTS Cea TRE Ensure all Site QC Procedures are properly pesformed according to inspection & Test Plan PRT A CELLAR RTT P1of2 Netfortune Engineering (FEA) Macau Limited FIELD CONTROL SHEET Significant Health & Safety Hazard and Controls : “High visibility vest along with safety helmet and shoes are compulsory once entered site area FALABA TURAL AAE, KBE BIDE ‘Trained operative for manus! lifting operations Assia tit “Training to banksman and operatives RRS Ensure all handy tools have safety loop and tied to ‘worker's hand/firm support during operation AFLAC AWE TRL REET L Ensure all iting appliances & gears are examined by RPE with valid certificate TCA NED RB IR og Ensure all workers working at height to wear safety hhamess and ensure safety belt to be securely fixed to "7. Ensure workers wear proper PPE when using welding ‘equipment and apply Hot Work Permit prior to work ‘commencement HEL APRA Se ES AT. | SPRL RE | 8 Ensure workers to wear eye goggles when using abrasive wheel and apply Hot Work Permit prior to work commencement TER, FAL) DARE RL AD PRRCLIPR TEE 9. Ensure cartridge operator to wear eye goggles and ear plug during operation IPT RION, FL) RAR BT = 10, FCS and Tool Box Talk shall be provided prior to every working procedure to be commenced to acknowledge all workers to realize every step of the independent safety line ‘work and concemed safety BEL (BS, SLAMS RL SHUN LNG, HIME ROR LR eRe RAL RALTAL FRAMES Signature : Date : ‘Name : B2 of 2 Netfortune Engineering (FEA) Macav Limited Page : 42 of 49 Mathed Statement for Hotel Curtain Wal/Glazing & Dos, No. : VHCM/MS#002 ‘Aluminium Cladding And GRC Cladding Issue : 001 Installation Date : 23-Mar-2006 8. APPENDICES 8.4 Field Control Briefing Rev.0 ‘Netfortune Engineering (FEA) Macau Limited Page : i SHEEP SR FIELD CONTROL BRIEFING I Date: EH Time 8B Ref. : 2120031 ]OVHCM/FCB/002 NGI Trainer/Organisation Ercole 433039 - Package : 2120/3110 #28 Lectin: AM Sujet: ya Cul € Cg lin SBC) ECE) Shee (rt BZ Chinese Name English Name LD. Card No. Nature ‘Signature i 2 3 4 Ss 6 7 8 9 10 VW 13 a 15 16 7 18 19 20 21 2 23 24 | 25 ize Remark : SIAL, Trainer's Signature Netfortune Engineering (FEA) Macau Limited Page : 43 of 49 Method Statement for Hotel Curtain Wall/Giazing & Doe, No. : VHCM/MS#002 ‘Aluminium Cladding And GRC Cladding Issue : OOF Installation Date : 23-Mar-2006 8. APPENDICES 8.5 Labour Histogram A. For Curtain Wail & Aluminium Cladding B. For GRC Cladding C. For Overall : Curtain Wall, Aluminium Cladding & GRC Cladding Rev.0 Netfortune Enginnering (FEA ) Macau Limited Site : Hotel Tower for Venetian Macau in Cotai, Macau Project : Curtain Wall and Aluminium Cladding Subject : Labour Histogram - Curtain Wall & Aluminium Cladding Installation 160 140 120 (Govan Oa (Cw 8 8 8 rf amoduew Ave 40 sommese ‘eoast nose ocr seek somoee eaves eon se0s10 smear faeovre fetmrt0 sche ere jotta sovee foovs soovon sers0 aot roo: feos sree: roses Date rnweronmttenete Speed tmpme CE Pato untas narR ENS REAR AMED erec iy ha short i . woxeus i eee vourret uone}e}suy BUIPpeID OY - wesGO3SIH snogeT :39e/gng WORBTENSUT SuIPPELD DUD SUPPEID UMRURINTY "TEA TEIN : wafOorg eoeY HOD Tr MORIA WERAMDA 105 TOMO], ROH : IS PTL ; & g i oz ov 09 08 oat Jemoduew Alea parry neseyy (Vas) SuoUMsug oum20;0N, votre coowio wore rower moterst arhoeso comes eres neo eee gggseasaes? uonere}su) Buppeld ONS 2 BuIppe|D wnrujUINy “HEM ULeUND - WeIBOISIH snogey : yoafans VOHRTTEISUT SaIPPELD OUD PUY FuIpperD UMMUTUANTY “TEAL WENO : oforg MEDEA THIOD UF eDUY UERSTOA 105 TOMO], TIOH : US. os. 0b ost 002 osz oo samodueyy Ateq paymyy neoeyy (VAT ) Suprouujsug ouny0}eN Nesfortune Engineering (FEA) Macex Limited Page: 44 0f49 Method Statement for Hotel Curtain WallGlazing & Dee. No. : VHCM/MS/002 ‘Aluminium Cladding And GRC Cladding Issue : 001 Installation Date : 23-Mar-2006, 8. APPENDICES 8.6 Installation Programme Rev.0 ‘aap reap way wen, sug’ pa Steg Bong Fess steeshtg cee TET nt enn ang Uae aren ees inns Pend Nog Bg oct ee, Ra i pn tp any yon yas ee beg bag DOL coum ‘oxy pa bappauny yen wey sunt Spend ing ng yoo t nays ciesdig nian sop asa eve ia use tar rave aay pane ng lg as LL peur eon ya sisson aoe eer = ing Steg oto | T a 7 a somaya ———, ee sl sear a a = zs Nesfortune Engineering (FEA) Macau Limited Page: 45 0f 49 Method Statement for Hotel Curtain WallGlazing & Dos. No. : VHCMIMS/002 ‘Aluminium Cladding And GRC Cladding Issue = 01 Jnstallation Date : 23-Mar-2006, 8. APPENDICES 8.7 Installation Sequence A. For Curtain Wall B. For Aluminium Cladding C. For GRC Cladding Rev.0 SON TOT | auppep ows supper ammemny EE] vas meng EE} TRY pvr msn (vas Fuse sna, CousLeewE ree au soxore |{ sowres || sonasst || =x -won vast | ton | neon ou CO] z ampprigrinmsemy EE] A wvessamnng EE TPIT (rava] a ave [ee |e Av [ Aydonad PA ‘Aayrorad 381 (ClO MOISIONNO) paren (yad) Sponge Bou eU Mere ee supp ous C] appa wimenemy FZ] areas anny TPIT ‘son szst || ‘Son ZL avin || 9090 as ava [vs ava] TVA ONG teeta Wir LSet Os OOOO OO GO Nesfortune Engineering (FEA) Macau Limited Page : 46 0f49 Method Statement for Hotel Curtain WallGlazing & Doe. No. : VHCM/MS/002 ‘Aluminium Cladding And GRC Cladding ‘Issue: 001 Installation, Date : 23-Mar-2006 8. APPENDICES 8.8 Production Schedule A. For Curtain Wall B. For Aluminium Cladding Rev.0 one 208 apne tr ue aL pinay : 5 z i sls el= z A a g & = t a z £| i } eee a soz erg soa fe wen vee Suppo 24D Dey BUR UNI y Baewone i wN O ona STIVACRIVLEND OY STGIATS NOM IGORE ESET THRO URIS USAUEA TP poyury nesey (Yad) BusooUlbu euniOpON ou on we 64 sco 055 wah ore seme dunn onus ° ort sens ous 04 ees coe sonata a | Tw awa] St] ss] eas] on] va] vec | va] vv aa] ven ea] vou] 0] var] ve] vat] oa aaa seer | ool ooe Toe | 8 [8] [or emmy ao [Tot ote] oo | a we] uel ove | ot | ote 0 | vr | ot | oor oor | va | 0 om [ortosfomtae] of e [| moras at wo | T 7 Lt mie] g ie - Ct tele pete ete} ro : ar tt { i Te ct Z|, i eatery i i eit wt «(ele e paps t ct 1 fs ze 1 ape { = oe = Le i —| B\= = | wafer Pes | fle ee i wen [er ae Ble) ae =e . [eT] | t Lo 3 7 a % git oe ate i 3 mT waren fe t Eis} ‘er Te tt wee £/2) ‘et ata i => we é [ss atm & eee eee iz pe res a ee ‘pion Neffortune Engineering (FEA) Maca Limited Page : 47 of 49 ‘Method Statement for Hotel Curtain Wall/Glazing & oe, No. : VHCMIMS/002 ‘Aluminium Cladding And GRC Cladding Issue : 001 Installation Date : 23-Mar-2006, 8. APPENDICES 8.9 xmas ne RpOroOZEer AS Sketches Zoning Plan Sketch No, 1 — Loading Platform Loading Platform Layout ‘Sketch No, 2 Hoisting of Curtain Wall Unit Sketch No. 3 ~ Installation of Curtain Wall Sketch No. 4~ Installation of Aluminium Cladding Sketch No. 6~ Loading & Unloading Arrangement (Late Cast Strip Incompleted) ‘Sketch No. 7~ Installation of GRC Cladding Sketch No. 8~Loading & Unloading Arrangement (Late Cast Strip Completed) Skeich No. 9— Welding at L7 Sketch No, 12 ~ Intemal Lining Installation Sketch No. 14— Installation of Extended Living Room Sketch No. 15 ~ Left Out Installation Monorail Arrangement Monorail Detail at £21 (for Typical) Monorail Detail at L21 (for End Wall) ‘Monorail Detail at 1.32 & L39 (for Typical) Monorail Detail at L32 & 139 (for End Wall) Hoisting System Layout at R/F Hoisting System Detail at R/F Scaffolding Arrangement Scaffold Layout at End Wall Sketch No. 17 & 17-1 ~ Installation at End Wall Scaffold Layout for L36 ~ RF Sketch No. 18 & 18-1 ~ Installation from L36~ R/F Rev.0 Netfortune Engineering (FEA) Macau Limited J3039 Venetian Macau in Cotai, Macau Work Package 3110 - Curtain Wall/Glazing & Aluminium ‘Cladding Zoning Plan Netfortune Engineering (FEA) Macau Limited 432039 Venefan Macauin Coil, Macau ‘Work Package 3110 - Curtain Wall/Glazing & Aluminium Cladding SED LOADIN FO) SKETCH1 SECTION FT) ms 1020 ———— 4500 Netfortune Engineering (FEA) Macau Limited 33039 Venetian Macau in Cotai, Macau ‘Work Package 3110 - Curtain Wall/Glazing (& Aluminium Cladding, Loading Platform Layout (6m x 4.5m wide a loading platform — 10 nos.) 4 at L8, L26 & L34 respectively ai Netfortune Engineering (FEA) Macau Limited 43039 Veneiian Macau in Cotai, Macau ‘Work Package 3110 - Curtain Wall/Glazing & Aluminium Cladding || HOISTING OF CURTAIN WALL UNITS Monorail System, a i (Criple Track for L21 : i Level 21/32/39 Double Trick for L32 & 39) TS v Monorail Track for ‘Temporary Gondola — Electric Chain Hoist Curtain Wall Units in Steel Rack Safety Belt connected to anchorage point Workers assist to| stabilize the unit [during hoisting [ _ a ra Loading Platfornr Netfortune Engineering (FEA) Macau Limited 113039 Venetian Macau in Cotai, Macau : SKETCHS Work Package 3110 - Curtain Wall/Glazing & Aluminium Cladding | INTALLATION OF CURTAIN WALL UNITS ‘Monorail Syst (Triple Track for L21 Double Trick for L32 & 39) Level 21 (32/39 v Monorail Track for Temporary Gondola — Electric Chain Hoist Safety Belt connected to anchorage point Bracket (pre-installed and adjusted) ‘Curtain wall unit (under installation) Safety Belt connected ‘to anchorage point Installed Curtain Wall Unit Netfortune Engineering (FEA) Macau Limited 438039 Venetian Macau in Cotai, Macau. ‘Work Package 3110 - Curtain Wall/Glazing & Aluminium Cladding, INTALLATION OF ALUMINIUM CLADDIN Monorail System (Triple Track for L2E Double Trick for L32 & 39) Level 21/32/39 an Monorail Trackfor ‘Temporary Gondola —~ Electric Chain Hoist Aluminium Cladding Sub-frame (pre-installed and adjusted Safety Belt connected to anchorage point. ———> Aluminium Cladding (under installation) Installed Aluminium Cladding | Netfortune Engineering (FEA) Macau Limited 418089 Venetian Macau in Cota, Macau “SKETCH 6 ‘Work Package 3110 - Curtain Wall Glazing & Aluminium Cladding LOADING & UNLOADING for CURTAIN WALL & ALUMINIUM CLADDING. and GRC Cladding (6~9/F) West Podiam Hotel Tower | East Podium Curtain Wall Unit / GRC Cladding in steel rack { ‘and Aluminium Cladding wood erate ' | Lory Crane OR Trailer Loy Mas Heiht= 44M ¥ @ “Transportation of Curtain Wall units GRC Pane! in steel rack & Aluminium Cladding in wood erates fom Offsite Storage to the appointed loading & unloading area a ste. @ B) Curtain Wall units / Aluminium Claddings will be hoisted up throurh the Left-out Openings up to Loading, Platform situated at Level 8 OR high fevel at Inter Stage. Netfortune Engineering (FEA) Macau Limited J3039 Venetian Macau in Cotai, Macau Work Package 3110 - Curtain Wall/Glazing & Aluminium Cladding, INTALLATION OF GRC CLADDING : Monorail System at Level 21 Monorail Track for ‘Temporary Gondola Electric Chain Hoist GRC Cladding Sub-frame Safety Belt connected to anchorage point ‘Temporary Gondola GRC Cladding, (under installation) Installed GRC Cladding | Netfortune Engineering (FEA) Macau Limited 418038 Venetian Macau in Cota, Macau Work Package 3110 - Curtain Wall/Glazing & Aluminium Cladding LOADING & UNLOADING for GRC CLADDING (37-Roof) Tower Crane “Transportation of GRC Claddings in steel rack from Offsite Storage to the appointed loading & unloading area at ste, Roof ¥. @ GRC Claddings will be hoisted up to the Podium Level 6 by means of 70M, Jib Crane. e) “Transfer GRC Claddings from Podium Level to Roofby means of Tower Crane. Lorry Crane OR Trailer GRC Cladding in steo! A 70M. Jib Crane Netfortune Engineering (FEA) Macau Limited 1J3039 Venetian Macau in Cotai, Macau ‘Work Package 3110 - Curtain Wall/Glazing & Aluminium Cladding sit DING OF INTERMEDIATE GMS BRACKET AT. L7 | | Level 8 ee Welding Shield Intermediate GMs. Peres Safety Belt connected oo to anchorage point Working Platform Security Rail to prevent falling of ‘working platform through the opening Welding Machine Fire Extinguisher Level 7 Netfortune Engineering (FEA) Macau Limited 43039 Venetian Macau in Cota, Macau 7 ; ete 1 Work Package 3110 - Curtain WallGlazing & Aluminium Cladding WORKING PLATFORM FOR INTERIOR WORKS Floor Level v Installed Curtain Wall_| | TPE ah) Safety Belt connected oo ‘to working platform _— Top Rail | Intermediate Rail — Teeboard «Metal Scaffold Working Platform (Gvhen platform exeeed 3M or above) Inspection Form Floor Level v. Netfortune Engineering (FEA) Macau Limited 43038 Venetian Macau in Cotal, Macau Felon Work Package 3110 - Curtain Wall/Glazing & Aluminium Cladding INTALLATION WORKS FOR EXTENDED LIVING ROOM ‘Tower Crane q : Safety Belt connected to anchorage point 18 t v eee | | GRC Cladding to be installed with assist of Tower Crane_ oo 2 16 | Scaffold Working Platform Netfortune Engineering (FEA) Macau Limited 413039 Venotian Macau in Cotai, Macay Work Package 3110 - Curtain Wall/Glazing & Aluminium Cladding SKETCH 15-1 LEFT OUT INSTALLATION (Blind Wall Area) Pulleys Se Custom Made Rigger Frame (for carry Gondola and Lifting support) |Gondola| ‘Winch Operator _Blectric Suction Cup (for Glass Glazing Only) Netfortune Engineering (FEA) Macau Limited 1J3039 Venetian Macau in Cotal, Macau Work Package 3110 - Curtain Wall/Glazing & Aluminium Cladding Monorail Arrangement © oe _End Wall) Monorail at | 1393 stage) Monorail at £32 (2° stage) Monorail at L2t (4% stage) ‘Typical Areas) Monorail System at L21 (Typical Details) 2 Monorail System at L21 (For End Wall) ty Monorail System at L32 & L9 (Typical Details; Monorail System at L32 & L39 (For End Wall) Perera HOISTING SYSTEM LAYOUT AT RIE ‘And Derrick Crane Layout HOISTING 8275, 3000 reyporay Somme 1 q soe 0F cancer Bey | ct oF oi i ol | é 1 race oF axc——t tt 1 { | \ Netfortune Engineering (FEA) Macau Limited J3039 Venetian Macau in Cotal, Macau ‘Work Package 3110 - Curtain Wall/Glazing & Aluminium Cladding Metal Scaffolding Arrangement s) Oo © L36+R/F 132~L35 L26~L31 L24~L27 L17-L23 LI6~Li9 L10~-L15 L6-L9 DOUBLE ROW SCAFFOLD Negotne Exner (FEA) Maco Lint aaron se Wot Psat 10- Con Wang Anan Cae rewom [aaron UALIATION OF GRC CLADDING-Ead ob | Toes i Go 15-49 1. Tone tia Wat Ui Stage 1 | 2-Aoplywaeprafing Stage 2 | ernment) ‘esta GRC eee Tot ORC Pre rq (yma oe) » » {bom ne arnchaee y ok x nnn | Ley | seating Sead Ties ~ hain ; i i, GRE Panel if [td sg i ¥ 2! | a |, i wl eo A HL] | cxcrnestst AY | satis SE euatanmincitnnies | ES [| [Ue is ne Samiti 1st fl From L10-LIS 2 Ayly wsooes 2 I GRC kt {Regent el oman G) . ES Lo eu 00 |] 650 Scala Support {isselterty €¥on 2 tat Amon Cog A) 0 Lr _f Lo ‘sxEra 5.Totnall ele Wat Us se nan Cg 235) Gmina) 2 Fetal GRC Panes (yoann Co) un a ‘GRC Fal (Jobe installed) uo i a [acim HI GRC Pane sled) ' 7 | _t. | | tt oe Li 2 | | 2 i / / AROW SCAFFOLD _/ FOLD LAYOUT eR ert Engng (FEA aceite ‘itm cee “i ag 10-Gune Wing Aen hg teem aaron 4 1 dl (Jom Stage 2 | | remanent 1 oem Ci et HSL) | 2apsnaeotns omnes | Sint cine 2 Foto one re 30 | I | (hymemesTone em) { “E 1 LI | ® Seafold Suppor [amass ng es) ng Coan Wall Units | _fratiminiom cide NeertneEnginesing (FEA) Mace Ut ‘save na em Wk Pie 310 -Cai Waving Ami Cg a ai 4 Basksnen ff | Stage 3 Banksman{}] || Stage 4 q ks U ena ail fen to Tomi eto mario hae vor caren 2 al nig RCT | rematrert iy al f T | lsat Ly EE [aos Li e —— Ipsallel GRC Panel Seated Support Nefortune Engineering (FEA) Macau Limited ‘Method Statement for Hotel Curtain Wall/Glazing & ‘Aluminium Cladding And GRC Cladding Installation, 8. APPENDICES 8.10 ‘Evercrete’ Method Statement Application Page: 48 of 49 Doe. No. VHHeMns02 Dat 25-Mar-2006 for Waterproofing Evercrettf PERFORMANCE SPECIFICATION FOR EVERCRETE’S DEEP PENETRATING SEALER (DPS) FOR ‘WATERPROOFING WORKS TO CONCRETE STRUCTURES BEHIND CLADDING 1, PREAMBLE The following specification is designed for Evefcrete Deep Penetrating Sealer (DPS) material performance on normal, sound construction grade concrete be it new or old structore, wet or dry. However for concrete found to bave abnormal conditions such as excessive carbonation, alkali aggregate reaction, very high permeability or other significant factors affecting the concrete, this specificstion may ot apply and a new specification may nced to be tslored to suit on a specific case by case basis, The supplier of the material will be able to advise further. 2, GENERAL Treatment shall be carried out to the surfaces described in the contract im cordance with the menafoctarer’s instructions. All wosks to be in accordance oth the relevant Occupational Health and Safety requirements. No works shall be Saried out on the site without the Engineer or his representative in attendance, unless agreed. 3, MATERIAL STORAGE 311 Materials stall be stored in an enclosed cool dry area, protected from direct sunlight. 4.2 The material shall remain in its original sealed containers until time of use. 33 The contractor shall provide the Engincer, upon delivery, proof that the material is 3 eouine Evererete Deep Pencrating Scaler. No material shall be used om site unit this information has been provided and accepted by the Engineer. 4.4 The material shall be used as supplied and not dibuted. 3S-The contractor shall deliver to site sufficient material to cary out the work i sealed containers bearing a label, which shall list the mamufocturer’s name, trade ame, application rate snd precautionary methods required. ! 4, SPRAY EQUIPMENT 421 By brush, roller or spray in accordance with the manufacturers structions. 4.2. No water shall be permitted to enter any part of the system 43 Low pressure spray (anax 20-30 psi). vier Center . 201 South Biscayne Blvd. Floor 28 . Mioml FL S313}4925 “fot 21 205 538-0921 Fax: #1 308 538-6729 . Email nfo@evererete-com . wrweveretee-comn 5, SURFACE PREPARATION 5.1 All surfaces to be treated shall be cleaned of mortar, concrete, dirt'and oil; nail holes and voids pointed and concrete rubbed. No surface shall be treated that is not clean. Cleaning works to be carried out by others. 5.2 Cracks larger then 0.3mm and voids, holes etc shall be filled in with a compatible cementitious repair material. 5.3 Drilling of holes’ by other trades’ shall be carried out prior to the application of Evercrete Deep Penetrating Sealer (DPS). 5.4 If such drilling of holes is carried out after the application of DPS, Evercrete will sell DPS material to the Main Contractor, in order to re-spray those areas. 55 All se-spraying of boles shall be treated in accordance with the manufacturer's instruction see item 9 below. 6. PROTECTION ‘All surfaces that are not to be treated shall be protected from spillage, dripping, or splatering of the waterproofing material. Immediately wipe off the materia ifit is a sprayed onto glass or aluminum. 7. MATERIAL 711 Waterproofing. material shall be clear, colorless, odorless, nonflammeble end nontoxic, tasteless. When sprayed onto the hardened concrete it should penetrate the surface to become an integral past of the concrete by chemically reacting with the calcitun hydroxide (lime and alkali) from the cement to form a non-soluble seal within the pores and copillaries of the concrete, permanently sealing it against ingress of moisture yet allowing the concrete to breathe. It chould have a permeability of not more than 0.093 mi/m"/s in accordance with BS1881. P15: 1970 Jnitial Surface Absorption Test (ISAT) There should be no change to the surface characteristics after the application of the Deep Penetrating Sealer. 7.2 The material shall not be diluted by solvent or any other fluid. 73 The material shell possess the following properties: ‘Water based: yes: Specific gravity: 1.094 PH: 11.50 Flash point: non-flammable Non-toxic: yes Chemical identity: proprietary mixture, containing silicates, bonding catalysts and inerts 8. TRAINING AND SITE SUPERVISION Tn all cases where DPS shall be applied by a contractor, who is not an epproved applicator, Evercrete shall offer to train the contractor's site staff and Jabourers if reaquired to apply the material in accordance with the requirements. Training will include cleaning of the area, equipment usage and spray methods, Cemier 201 South Biscayne Blvd . Floor 28. Mirai FL S9131~4225 +1 305 530.8730 . Emil: info@everesote.com , wors.evercrate.comn 9. APPLICATION 9.1 Records The contracior shell maintain a record ‘of the quantity of material used and the gress treated for each application to verify that the minimum required coverage fate hes been achieved. The format of such record’shall be agreed with the Engineer and~Kept up t0~dateand-available—for~the ~-Engineer’s_inspection throughout the course of the work. 9.2 Evercrete Deep Penetrating Sealer Applicstion 1. Work sequence to be agreed by the Engineer. 2. Shake or stir Evercrete DPS prior to use. 3, Ensure concrete surface is clean and free from oil and grease. 4. Pre wet the concrete. 5. Apply using a low-pressure garden-type sprayer, bush, voller or mop. a. Apply liberally and saturate all areas. . Vertical walls should be applied from. the bottom up to ensure uniformity of application. . On horizontal surfaces the material should be applied so that the surface has a mirror wet look for at least 5 seconds afer ‘pplication, It should not be excessively applied so as to cause 4. Om soffit areas the material shall be applied by continuous spray! soller/ brush technique. The treated surfaces shall have 2 “misror ‘wet look” for at least 5 seconds. 6. Normal coverage is about 15m” per US gallon for two coats. ‘The coverage: rate depends on the porosity of the concrete and varies from project 10 ‘project. Under narmal conditions, for general concrete waterproofing, 2 boats are required. Depending on the concrete porosity, additional coats may, sometimes be required. 7, Under normal ambient conditions, its secommended that the second coat ‘end any subsequent coats be applied at least 24 hours after the first pplication. £. Holes drilled after the application of the second coat of Evercrete DPS, should be re-treated with another two coats of Evercrete DPS in accordance 7 _with jtems S above. 9. Where itis desired fo paint the surface, the paint should be epplied zt least 7 days after completion of Deep Penetrating Sealer application, after first ensuring the surface is dry. Adiami Genter .201 South Biccayne Blud Floor 28 . Mimi FLSSTS-4325 sen #1 308 590-8921. Fox: #1 306 636:6729 . Emails nfo@-evererete.com . wormevercree.comn | (Tet sao AM) SHIT] (sda 209 ,,2) uoneauddy) (Te'sao A) —AT] (saq 1809 ,.4) uonestiddy, ae nea [= — —_—_|—— uoyoedsuy eeying| ae Be a ae ae fee fq pax22u9. faperdessy | vary | “oN Summesg woRz207 area aa )Su) Bulppeld O¥O Puy Suppe|D uinluLUny y BUIZEIDNEM VELND [SICH OF LE/OSZ «ON eBEHOE neoeN ‘1800 U! Ja}OH UeNEUA : SlOld BERETA / YR Suyooudseyeyy\ 10} p1osey uoeoyddly pue UoRo|dsu| JRewwsg Netfortune Engineering (FEA) Macau Limited Page: 49 0f49 ‘Method Statement for Hotel Curtain WallGlazing & Doe. No. : VHCMMMS/002 ‘Aluminium Cladding And GRC Cladding Issue : 001 Installation Date : 23-Mar-2006 8. APPENDICES 8.11 Inspection & Test Plan and Checklist Rev.0 seayoq Supjpeg pue 199394 an0q09 3 TeNSIA ON ‘uorsuaund| quawiamnseayy| ‘uorsuaumg ‘sedty 100 $5849) apg sun0g WIN sxopo3 ‘fapoyy “AID 194209} aidung ay yensi,} aosiwsadng ong %I ramrutumnpy Jo Sunyo94D| | sey pg sut04 VIN Sourep sagps ON Tensta} sostazadng ous | %001 ated OUD Jo Beppe) waqyeq Bupjpeq pv 399704 | mojo) TensiA ON ‘uorsuauNG]| quauramsvay(] [op uorsuauncy ‘adA], Smppeip| apg swioy VIN sgoj09 Japayy “MH 1981103} aidung % jensta| sostarodng ang %1 ummtumpy Jo BurysayD| t reajed Supe pue ioaeg| i 210 9 Teas, ON “cossuotT juauiarnseay,| tuoqsuanarg ‘od, sjaueg 1284] avg sunog VIN ssoJ09) YPM “AY 399410] ajdung 2 fensi,| sostazodng aug iexang pazrmin jo Rary97}5} = yoqed suppeg pue 29390 { mojo =| Tension. ‘worstom) yuouaanseayy crorsuauitg ‘odK, worsnanx| arg sunog VIN aojag apoy, “AA 1993109} ajdung 2p rensia} sosiasodng ants | tunnmumyy Jo Surysayp| ~ joao Suyoed (a daa “THR S| pute 20372 ens! ON quowiemnseoy ‘syjoq Bupxg) sazoss000u apa suog VIN so]OD apap! “Ad 1993105) adung 2p pens! jadng, 2g sureg yo SupypaqD| 5 7 a ae em soa spr039y viranag aiquidssoy | nef fowanbaag | vordyrosag Auansy aed PIOH RMES we] eae | GERaer aw [CON Sid oR ase Tdi STORET] SUG SBVIG OL HF UOTTSdSTT el: fat] zo: WBE ao H : WOHA + ON 190[04d ib YB ES EE COLE PON aBeyoug ) neseyy TeIOQ WO] weNeUEA ; 199forg HH BL] (weld 3881 B UORedSUl) [ME 4y BH IS yw Poy] Nesey] (WeLD) Supeoursary emmaiopaN, | ogg | ody 19 aH £661: 1LUVd 0805 $A) ‘2arionseq{ won) sostarodng aug | “eq sed sy | asa paqusg| qusuamsvayy| | ‘sere Suyes ToT tog an Suymesp doug 01 Baipr020y ajdung 29 Jensia} rosiasodng og %S ejnsu Jo Suyyoouy) vodoy 183, a seissa aaHONNSeq|UON| — geT ISA], wT | isa, SUIpIAAY woday 189.1, dH ‘StISSel uonsadsyy fensia} — qr 382 001 | wa, Banpiaay| poday if 89. JOVEN ay aBeyeo] ON] £8°7"10S WINWY) Jostaiadns ang | %001 sa] 27A\ PIA t quowiamnsvopy| ‘syaueg jfeA\| OL/OL H0g du Suweap doyg 0} Surpso99y/ a{dung 2 yensi,) sosturadng aug %S henna pez Jo SurypeyD! —— _ | i: Gayy/or9;9g)| [oo tog aH weg nosy] paguiy spry Keaing] 29242] eqoot | anoseey paqura jo Supppoug) - =a z 5 es ae =e wD) [ CAM) 1rd , 1 7 os SSOUIIA wosied sprossy | j(aqitiog | BteTID squada00y sqarsuodsey | S2uanbaaI | worndrioseg A1AH9V sa PIOH wae | Sexy | Fae | Game e we on oaea ‘GrdllNOHA ON dir. Del eISU] SING TaHLIG Woy wy woHoeTsuy, o/c 2 Si EI) ‘Sy ye OL 7 BaaeW ee 1 ON 300fotd Si MG El Ee Corig Pon aBeyoeg ) meoeyy 0g M JaIOH UNDE ; s99fo1g HF WL (ueiq 1891 B UONOedsu|) [Ee Bi VE ly Bi BY paqruary neoeyy (WALL) Supeoursasy aunyTOpaN) > (@3PC) Hie El oBwampy weforg “y : (WoI1S0g) Ti) + (QUEND SF) : (ampeusig) Bas] + (4q paredaia) i quatuainseay(| | ] ‘Suipprr, LO/DI WHO dH Swavexp doyg 0) Suypr099y} aydang 7 yenstA} sostasodng aus %S ‘DUO /SuIppeya Jo Buryoar a qusuramnseayy| | syromaunery| SO/DI WHOY du Suymesp doyg 01 Surprossy) aydurg 29 yensia| sosraiodng aug ~S | Suippriosoun Jo Supe] a i se ct fl ae TPP HD, DUD a Tapp TTT juowamnseayy [ | pO/DI WOg du Buymesp doyg 01 Bumpros9y! aidamg 2 pensia| sostasodng eits ~S | SuizePD Jo SuryoauD| 90/01 tog dH Sapaexp doug 01 Supr0s0y| sospzadng ays es spomanrerg Jo Sup}pa4| t ee ag i Lie SPoMnOT P 100g vosied | ci oah Q 7 sproosy | j(qy)aurog | B1aNTD alquidascy, pou siqistodsey | SUsMbeLE | donsdivosaq GuAHOY Be PIOH Huse BY | age | sae I iG St A VE Be BE “ON SBE q) “oN WosTAayy ql A TN dit TSU] OHS TG Wal P TOTIaATTy | oe: mn co: Ma LE vo i Bee ew eB NOH: ON 199fota RB EL i ‘oN aloygng ) nnDeyy “eI05) w foIoy weAeON ; 199fo4g MES HET] (uejd S21 B UONOOdSUl) fF +2 Me ek HH BI payrlary neoeyy (WALD) Saueeursay ounyOpEN TELE CRA TARA A RIGA: IOOL Nefortune Engineering (FEA) Macau Limited sS77A8E:01 ERS (RL ( Checklist for Cast-in Embed (after Concrete Pouring) ) 13039 Venetian in Cotai, Macau ‘BEA GOPRAEIR Max. Tolerance: CARA AB Project: | Work Package : 2120/3110 - Hotel Curtain Wall/Glazing & Aluminium Cladding FAS Date : Sf897 Ref. No. : EMA - (tt oon EE [: Gridhines : 5H: Dre. Refer x iat | BE 7 tte [RT {i | OR ; LOC | Type | ei LOC | Type at 7 7 LOC | Type x ee $F Checked by Nevlortune ‘GFE Reviewed by: ‘GaCML. FARA Date : EMS Date : THe LAGE WPA T Zuma: iis | BHR: 00 \Netfortune Engineering (FEA) Macau Limited BL H $18 HHH (Checklist for Glazing) [L824 Project : iit 2 {ik ft Check location : kness : ft Aah RM HE RAPA BE Thickness Accepted Unaccepted N/A Remarks ing: a Rete OF ae ese Fixing Accepted Unaccepted Remarks hy eae cm fe 2) Installation (gasket & beads) | l2) RHEE Sealant apply 7 & Wet sit Beis Surface : ‘Accepted Unaccepted Remarks 1) SB Coating condition Co [J oO (o: BER MRTR) {ie.: Any scratch or defects) 12) H Protection C ] lee #9 #814 Overall conclusion: 24% Accepted Rete RBS HR Unaccepted No report serial no. li 2 EL Checked by : Hi Date : (13 CAS GSE RP TERA \Netfortune Engineering (FEA) Macau Limited Ree 1 87 HH: 00 1/05, BEAMS (Checklist for Metal Frameworks) (FS AF 8D TK HBS BE) (Glass screen/Metal Cladding/Architectural Feature/Skylight/Canopy) #2447 Project : [Rae {iL Check location : Fixing : att Ae FMA wie FEB BE Fixing Accepted Unaccepted N/A Remarks 1) SIE Material L]| L La) TH i Comply to drawing J LJ (a TAL BE Be KS BE i AGH AL ‘fee Vertical and horizontal : Accepted Unaccepted N/A Remarks 1H) eae ae Rk PE Se RAE 7 ct Vertical and horizontal tolerance [_] L] CI face : at Ket FA iE Heil Surface Accepted Unaccepted N/A Remarks 1) WAT HU Free of damage a] J | j2) at: fe REAR HE Protection LJ _ UJ Ise H.R Overall conclusion: at Accepted eth RAPA MEST Unaccepted Nc report serial no. li #8 | Checked by : FM Date : 2 SAP PARA BALA ME: 1/06 45 ET MRE: 00 leffortune Engineering (FEA) Macau Limited SH | ERRARE Checklist for Frameworks (Window & Door) [2498 Project : (2 2 fc! Check location : LL BE Be ok > at Re RBA MRE \Vertical and horizontal : ‘Accepted Unaccepted N/A Remarks h) SERRATE RS Vertical and horizontal tolerance == [_ | ixing = & Raw MIB ARE fat Fal HE Fixing Accepted Unaccepted NIA Remarks it fa (a [Bw as ime Fixing lug comply to drawing | we ing : a6 Fe RMD MORE [Bak BLE Grouting Accepted Unaccepted NIA Remarks 11) Bi kc ae ve BE ee a Pg Waterproof cement grouting $i 7k No water leakage i ae Ret 7a ee j#tiH Surface petites undclitoa “hi Remarks 1) ME Bee HORE HH Free of damage | 2) Wi ARES EH2 Sealant quality Cl [ is) me + Z Sealant comply to drawing Mi REZ Overall conclusion: a Accepted |_| RAR AE TR SE Unaccepted|__| NC report serial no. lie#i A Checked by: FL Date : (re CGR TELA TI Samm: (Gor letfortune Engineering (FEA) Macau Limited 26 /GRORMARE (Checklist for Metal & GRC Cladding System) [TB 4% Project : ii # LE Check location : jals : ai Het ORM RE [Ft Materials Accepted Unaccepted NIA Remarks 1) JERE Thickness { | 2) Rf Dimensions ‘| C] ixing : BH Kee tae [BeBe Fixing : Accepted Unaccepted Remarks: 1) 88 Installation [ 2) eff Sealant apply [ C4 “] | 8 : # x aie peel Surface Accepted Una Remarks 1) SiH aR gE Surface condition 7 - (ia: 8 TE HMR) (i.e.: Any scratch or defects) IS HB REE Overall conclusion: gk = Accepted |_| Rete FAG BAS ER Unaccepted NC report serial no. let A Checked by : Fi Date : eGR APTA Rig BBE: IC/10 4557 MH: 00 vetfortune Engineering (FEA) Macau Limited BRERERE (Checklist for Unitized Curtain Wall Panels) TL 2 4 Project : lie #2 Et Check location : 1) 8h AALIR In and out direction l2) te 4 ir Left and right direction [3) 2 9989 Ge ae BE HE Protection EIA SEBE Glazing : | 1) Bee seme (EH RAR) Installation (Gasket & spacer tape) \2) {#8# Protection ER MAR Be BAG 2k Hib insulation & Firesafing : 1) 2 Ha a ER ee Installation comply to drawing la #8 432 Overall conclusion : ligt BL Checked by : TTT an Rat RRA ME [ARS IH Anchor fixing : Accepted Unaccepted N/A. Remarks 1) Hee Comply to drawing — |_| O a : ak Fat ABR Met JetE22 Aluminium Frame pchited unscented “NRT Remarks ate mB fait ce ti ‘ate Accepted Unaccopted NIA Remarks Rae aA TE Accepted Unaccepted NIA Remarks ae a Accepted He _—, SRS Unaccepted| | NC report serial no. Hifi Date : HEL REP PRA] BM: ICI 4 iT MR: 00 Nevfortune Engineering (FEA) Macan Limited RABRGKABARE (Checklist for Insulation & Firesafing) {C2 Ge Project : li 2 (i: Check location : if #} Materials : ah Rete Fa RE Accepted Unaccepted N/A Remarks 1) EE IEW Thickness a] ; CJ 2) sueIE HE Type LJ C i ae RAR cet MRE Bese Fixing : Accepted Unaccepted N/A Remarks h) eee mk see 7 i Installation comply to drawing C] [ AE WERE Overall conclusion: 2 Accepted |_| Ree REAM EER Unaccepted NC report serial no. itt A Checked by = HH Date :

You might also like