Professional Documents
Culture Documents
Product A is composed of 3 subassemblies: 3Bs, 2Cs, and D. C is assembled using 2Es, F, 2Gs.
On hand inventories are 50Es, and 100Fs. Scheduled receipts are 150Es at the start of week 1.
300 As will be shipped at the start of week 5 and another 400 at the start of week 8. Lead times
are as follows: 1 week for 0-1499 order quantity, 2 weeks for order quantity of 1500 above.
Each order of F comes in lot size of 50 units. Develop the MRP for items A, C, E, F.
3B 2C D
2E F
GIVEN:
Weeks 1 2 3 4 5 6 7 8
Item: A
Week 1 2 3 4 5 6 7 8
S/R
POH (50)
Week 1 2 3 4 5 6 7 8
S/R
POH
Item: E (2)
Week 1 2 3 4 5 6 7 8
S/R 150
Week 1 2 3 4 5 6 7 8
S/R
Legend: G/R= gross requirements, S/R = scheduled receipts, POH = planned on hand, N/R = net
requirements, POR = planned order receipts, PRL = planned order releases