NS-1™ Number: NS 10.35.24.2111
Revision Date: June 2007
Equipment Name: TELESCOPIC TUBING JOINT ASSEMBLIES
Manufacturer: GENERAL
Model/Type: VARIOUS
Material Group: MEDIUM ALLOY STEEL
Service: SOUR
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 1
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
SCOPE
This COMBINED NS-1™ specification specifies the minimum quality and inspection requirements applied to
wrought Medium Alloy Steel Telescopic Tubing Joint Assemblies.
It applies to:
• SOUR service conditions, employing medium alloy steel (e.g. 9Cr to 13Cr).
• All sizes and Rated Working Pressure of 20.7 MPa (3,000 psi) through 103.4 MPa (15,000 psi) inclusive.
• All operating temperatures.
The matrix of this COMBINED NS-1™ specification provides a quality template that can be applied to any make
and type of Telescopic Tubing Joint Assembly. This COMBINED NS-1™ specification in combination with the
manufacturer’s parts list(s) and drawing(s) completes the product quality specification.
When ordering spare parts or sub-assemblies, the applicable quality requirements shall be those specified for
the components supplemented by the relevant requirements called out for the complete assembly.
Design verification, approval and other design related parameters are specifically excluded from this COMBINED
NS-1™ specification.
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 2
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
SUPPLEMENTARY REQUIREMENTS
The following requirements are supplementary to, and shall be applied in conjunction with, the Quality Sub-
specifications of this NS-1™ specification:
1. WELDING
(Ref. Sub-Spec. 30.1 & Sub-Spec. 60.3)
1.1 No fabrication or repair welding shall be performed in or on pressure containing and major load
bearing parts.
1.2 Fabrication welding and repair welding shall be restricted to non-critical attachment welds only.
Welds which are uninspectable are not permitted.
2. MATERIAL TESTING
(Ref. Sub-Spec. 10.1 & Sub-Spec. 10.4)
3. HARDNESS TESTING
(Ref. Sub-Spec. 70.1)
i. Where the diameter to wall thickness ratio is such that it can adversely affect the accuracy of the
hardness measurements.
Each assembly shall be hydrostatically tested to the manufacturer’s procedures and specifications with the following
minimum requirements:
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 3
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
The timing of the holding periods shall not start until the test pressure has stabilized, the equipment
and measuring devices have been isolated from the pressure source and the external surfaces of the
equipment thoroughly dried.
The above test durations shall be applied to the assembly first in the fully extended position and then
in the fully contracted position.
Where the test pressure is limited by the threaded end connections, it shall be calculated using the
following formula:
P = (2 . f . Yp . t) / D
Where:
P = hydrostatic test pressure, in (MPa)
f = a factor of 0.8 of specified minimum yield strength
Yp = specified yield strength for the pipe body (MPa)
t = nominal design wall thickness adjacent to thread connection (mm)
D = nominal outside diameter of the connecting thread (mm)
As a minimum, the hydrostatic test pressure shall not be less than the equipment rated working
pressure.
5. FUNCTIONAL TESTING
(Ref. Sub-Spec. 130.1)
Functional testing shall be carried out to the manufacturer’s specification but shall include the following as a
minimum:
• Each complete assembly shall be fully stroked through one complete cycle after hydrostatic testing. There
shall be no evidence of scoring on the O.D’s. of the inner tubular parts.
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 4
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
MATRIX
Equipment Name: Telescopic Tubing Joint Assemblies
Specification: 10.35.24.2111
Manufacturer: General
Model/Type: Various
Material Group: Medium Alloy
Service: Sour
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 5
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 6
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 7
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 8
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
Photocopying or reproducing this page in any way constitutes as infringement of the license agreement
for the continued supply of the NS-1™ Service
NS 1 Page 9
Quality and Inspection Requirements for New and Refurbished Drilling and Well Completion Equipment
Once printed this specification becomes an uncontrolled copy of the online version.
Complete Assembly
Number Title
10.1 Material Certificates – General
10.2.2 Material Certificates – Assembly Certificate
20.3 Traceability – Serialization Traceability
90.1 Dimensional Inspection – General
100.2 Hydrostatic Testing – General
130.1 Functional Testing – General
160.1 Non-Conformity Procedure – General
170.1 Boxing/Packing/Marking – General
170.2 Boxing/Packing/Marking – Critical Service (H2S, CO2, Low Temperature)
180.1.3 Quality Documentation for Non-Welded Products
Notes
1. When applicable; Threaded parts shall be examined in accordance with Sub-Specs 40.6.1.3, 40.6.2.3 &
40.6.3.2 as indicated.
2. Parts designed to take combined loads (e.g. tension & compression): The most stringent quality requirements
based on the "Worst Case" loading condition shall apply. In such cases class code B1, D shall be default.
3. Complete assemblies which by design include fabrication welds: Documentation quality Sub-Spec 180.1.3