Mr.

Iqbal,

Col. and Col. cap beam detail.

1) Longitudinal Elevation of Girders, - Grid-PE1, Det.-1, Grid- PE2, PE4 - Det.-2, write properly.

2) Plan at Top of col. cap beam lvl.1890 Dim. beam to beam show plt. c/c. 670-550-670=1890.and
below plt. girder 500x550x25 thk. batten plt. and batten plt.250x550x25 thk.
and 1910 = 670-550-690 show c/c. dims. Delete dim.250 and 675.

3) Longitudinal Elevation of Col. cap beam. - cols. PE2,PE3 and PE4.  1) Gap 20 show between col. cap
beam and bracing gst. plt. and stiff. plt. above col. two shown one stiff. plt. delete.

4) Plan at bottom of col. cap beam lvl.  1) change dim. of batten plt. and on col. cap plt.750x750x25
thk. and beam batten 700x700x25 thk. plt. and plt. girder location 500x550x25 thk. - batten
plt.250x550x25 thk.

5) Plan at Top of Col. cap beam lvl. - Longitudinal Elevation of col. cap beam - cols.- GPE1, PE5. and
Plan at bottom of col. cap beam and make same as per above col. cap beam.

6) Single col.- from center of col.450 on both side.

7) Detail - 1, ( PE1, PE3, PE5 ),  Stiff. plt. dim. in plt. girder 175 from center on both side. Cap beam
plt. 500x550x25 thk. on top and bottom 700x700x25 thk. batten plt. Sec. 1a-1a, batten plt
500x550x25 thk. Detail - 2, ( PE2, PE4 ) - stiff.plt.dim.in plt.girder175 from center on both side. Cap
beam plt.500x550x25 thk, on top and bottom 700x700x25 thk. Sec. 2a-2a, batten plt.500x550x25
thk.

8) Sec. 1 - 1, Top batten plt.500x550x25 thk. and bottom700x700x25 thk. and col. cap
plt.750x750x25thk. Sec. 2-2, open in col. cap plt 250x250, and vertical plt. show on four sides, 

9) Total length of col. cap beam 16600 but can make 16000 length and then end dim. of from center
of col. or beam show 430 dim. on both sides.