Table of Contents
SECTION 1: BIM PROJECT EXECUTION PLAN OVERVIEW.....................................................................................................7
1.1 Introduction........................................................................................................................................................ 7
1.2 Instructions for Use............................................................................................................................................ 7
1.3 Project Development Requirements.................................................................................................................. 7
1.4 Data Utilization and Ownership..........................................................................Error! Bookmark not defined.
1.5 Applicability........................................................................................................Error! Bookmark not defined.
1.6 Team Leads.......................................................................................................Error! Bookmark not defined.
SECTION 2: PROJECT INFORMATION................................................................................................................................... 8
2.1 Project and Title Information.............................................................................................................................. 8
2.2 Project Phases/Milestones................................................................................................................................. 8
SECTION 3: PROJECT CONTACTS....................................................................................................................................... 9
3.1 Core Collaboration Team................................................................................................................................... 9
SECTION 4: PROJECT GOALS /BIM USES......................................................................................................................... 10
4.1 Major BIM Goals/Objectives.............................................................................................................................10
4.2 BIM Uses............................................................................................................Error! Bookmark not defined.
SECTION 5: ORGANIZATIONAL ROLES /STAFFING..............................................................................................................12
5.1 Design Team BIM Manager............................................................................................................................. 12
5.2 Lead BIM Coordinators.................................................................................................................................... 13
5.3 Construction Team BIM Manager......................................................................Error! Bookmark not defined.
SECTION 6: BIM RESPONSIBILITIES..................................................................................ERROR! BOOKMARK NOT DEFINED.
6.1 Design Team Responsibilities............................................................................Error! Bookmark not defined.
6.2 Construction Team Responsibilities...................................................................Error! Bookmark not defined.
6.3 Record Models...................................................................................................Error! Bookmark not defined.
6.4 Project Team Responsibilities............................................................................Error! Bookmark not defined.
SECTION 7: MODEL OBJECTIVES AND APPLICATION...........................................................ERROR! BOOKMARK NOT DEFINED.
7.1 Programming/Pre-Design Phase.......................................................................Error! Bookmark not defined.
7.2 Schematic Design Phase...................................................................................Error! Bookmark not defined.
7.3 Design Development Phase...............................................................................Error! Bookmark not defined.
7.4 Construction Documents Phase.........................................................................Error! Bookmark not defined.
7.5 University Review...............................................................................................Error! Bookmark not defined.
7.6 Construction Phase............................................................................................Error! Bookmark not defined.
7.7 Project Closeout – Record Deliverables Phase.................................................Error! Bookmark not defined.
SECTION 8: LEVEL OF DEVELOPMENT (LOD).................................................................................................................... 14
8.1 Level of Development Procedures...................................................................................................................14
8.2 Model Detail & Level of Development (LOD) Chart...........................................Error! Bookmark not defined.
8.3 Construction & Record BIM................................................................................Error! Bookmark not defined.
8.4 Understanding Level of Development..............................................................................................................14
SECTION 9: BIM INFORMATION EXCHANGES AND MODEL SHARING....................................................................................16
9.1 Integrated Project Delivery (IPD) Methodology................................................................................................16
9.2 Geo-Referenced Model.................................................................................................................................... 16
9.3 Collaboration & Model Sharing........................................................................................................................ 16
9.4 Version Control................................................................................................................................................ 17
9.5 Efficient Project Work Flow.............................................................................................................................. 17
SECTION 10: QUALITY CONTROL...................................................................................................................................... 19
10.1 Overall Strategy for Quality Control.............................................................................................................19
10.2 Quality Control Checks................................................................................................................................ 19
10.3 Model Accuracy and Tolerances................................................................................................................. 20
10.4 Clash Detection/Coordination...................................................................................................................... 21
10.5 Meeting Procedures..................................................................................................................................... 22
10.6 Model Delivery Schedule of Information Exchange for Submission and Approval......................................23
SECTION 11: TECHNOLOGY PLATFORM AND SOFTWARE....................................................................................................23
11.1 Approved BIM Software for USF Projects...................................................................................................23
D. Brief Project Description: CONSTRUCTION OF THE ARCHITECTURAL BIM MODEL AND MANAGEMENT OF
THE OVERALL BIM MODELS PREPARED BY EACH RESPECTIVE CONSULTANT DURING TENDER STAGE. THE
OBJECTIVE FOR THE PREPARATION OF THE BIM MODEL IS TO RESOLVE CLASHES BETWEEN ARCHITECTURAL,
BUILDING SERVICES, STRUCTURAL, FAÇADE AND WATERPARK DISCIPLINES PRIOR TO THE COMMENCEMENT OF
CONSTRUCTION STAGE.
F. PROJECT NUMBERS:
Leigh & Orange Executive Architect BIM Manager Samantha Hu Samantha.hu@leighorange.com 28999600
Meinhardt MEP Consultant BIM coordinator Pinko K.T. Chung pinkoktchung@meinhardt.com.hk 28595477
The files format and version of the deliverables shall be defined and agreed by all teams prior to commencement
Page 21ofofproject
32 work. The deliverables shall
contain all final model and data of the project BIM for completion of BIM projects or particular project use.
FINAL DELIVERABLES
Overall building massing representative of area, height, volume, location, and orientation
may be modeled in three dimensions or represented by other data
Analysis may occur based on the volume, area and orientation of the general representation
of the Model Element
LOD 200 Approximate:
Model Elements are modeled as detailed assemblies that accurately represent quantity,
size, shape, location, and orientation. Any additional information may also be attached to
Model Elements
Analysis may occur based on the performance of selected systems of the specific
representation of the Model Element
LOD 350 Assemblies for Coordination:
Model Elements are modeled as detailed assemblies that accurately represent specific
systems, objects, or assemblies in terms of quantity, size, shape, orientation, and interfaces
with other building systems with the detail necessary for cross-trade coordination and
construction layout. Non-graphic information may also be attached to the Model Element
Model Elements are modeled as detailed assemblies that accurately represent size, shape,
location, quantity, and orientation with complete fabrication, assembly, and detailing
information. Any additional information may also be attached to Model Elements
Analysis may occur based on the performance of selected systems of the specific Model
Elements
LOD 500 Record Documents (Record BIM):
Model Elements are modeled as constructed assemblies actual and precisely representing
size, shape, location, quantity, and orientation, including “Recorded Field Data”. The model
should be configured to be the central data storage for integration into building
maintenance and operational systems. Any additional information may also be attached to
modeled elements
INTERFERENCE
Detect problems in the BIM where two building components are
CHECK/ CLASH All BIM Managers Navisworks Weekly
clashing including soft and hard of clashes
ANALYSIS
STANDARDS To ensure all the BIM and CAD standard if applicable have been
All BIM Managers/ Coordinators Revit After each work stage
CHECK followed
LOD CHECK To ensure LOD of BIM meets the requirement for each milestone All BIM Managers/ Coordinators Revit After each work stage
BIM DESIGN To ensure design intent and data incorporated are accurate and
All Project Designer Revit Continuously
CHECK correct by design architect
Ensure the project data set has no undefined, incorrectly defined or
MODEL Continuously
INTEGRITY CHECK
duplicated elements and the reporting process on non-compliant All Coordinators Revit
elements and corrective action plans
MODEL
Ensure the BIM model performs efficiently on local workstation for BIM
PERFORMANCE All BIM Managers Revit Monthly
CHECK operation
Standard Setting
Coordinate System Project Internal
Reference Datum 0,0,0 (-2400 to Q01, PAD)
Model Origin Point 0,0,0 (-2400 to Q01, PAD)
Model Unit Millimeter
Model Precision Millimeter
Model Levels (Structural) Level Schedule
Name Elevation (mm)
Datum 0.00
Basement Level 2500.00
G/F Hotel Lobby 7925.00
1/F Signature Gaming 14425.00
2/F Kitchen 17800.00
3/F GYM / SPA / POOL 21175.00
5/F MEP Floor 28300.00
a. It is the Project Teams responsibility to conduct and manage an adequate and thorough
Clash Detection process so that all major interferences between building components will
have been detected and resolve. It shall be the goal to reduce the number of changes during
construction due to major building interferences to zero before construction starts.
b. The BIM Managers shall assemble a composite BIM from all of the BIMs of each design
discipline for the purpose of performing a visual check of the building design for spatial and
system coordination. Vertical shafts should also be reviewed to ensure that adequate space
has been allocated for all of the vertical mechanical systems and that all of the shafts line up
floor to floor.
c. Coordination software (Navisworks or other approved software) shall be used for
assembling the various design BIMs to electronically identify, collectively coordinate
resolutions, and track and publish interference reports between all disciplines. The technical
disciplines shall be responsible for updating their BIMs to reflect the coordinated resolution.
d. The Project Team shall review the model and the Clash Reports in coordination meetings on
a regular as-needed basis throughout the design phases until all spatial and system
coordination issues have been resolved.
e. Internal Clash Resolution – The Design Team and Subcontractors who are responsible for
multiple scopes of work are expected to coordinate the clashes between those scopes prior
to providing those models to BIM Manager for spatial and system coordination.
f. Spatial Coordination – BIM models will be used to check physical clashes, conflicts and
critical dimensions between the different discipline designs to ensure no conflicts in the
design work.
DESIGN COORDINATION Design team and BIM coordinator Go through the major design improvement and modification by the design team
CLASH ANALYSIS REVIEW ALL BIM team leaders and design team Prepare
key member
the clash report in advance and to solve the clashes with related participants
BIM WORKSHOP ALL BIM team leaders and design team Finding
key member
issues of the shared models and discuss to workout solution
CPU Type intel® Pentium® 4 or AMD AthlonTM 3.0 GHZ (or higher) with SSE2 technology
Guidelines for whole project teams and for all individual discipline .
1. The certainty of data inter-operability between difference software platforms all BIM relate software,
rather than the specified software in this document, to be adopted in this project must be agreed in
writing by the project BIM manager prior to commence any work in the software
2. The usage of the software in this project shall be approved and agreed by all teams prior to
commencement of BIM work to ensure possession of required technical capability for model
manipulation and smooth data interoperability between different software platforms.
3. Before the commencement of the BIM work, the file format and version details for data exchange of
the software shall be agreed and consented.
4. Any upgrade on the mandated file formats shall be approved by clients and risk associated with
any upgrade shall be documented and acknowledged by project teams.
5. Team shall maintain their models in approved version of format of specified software.
6. Project BIM authoring tool shall be Industry Foundation Class (IFC) compliant as supported by all
major BIM authoring tools to allow data interoperability.
Keeping reliable backups is an important part of data management. Regular backups protect against
the risk of damage or loss due to hardware failure, software or media faults, viruses or hacking, power
failure, or even human errors.
- A date security protocol shall be maintained by each discipline company to prevent any possible data
corruption, computer virus infections, and data misuse or deliberate damage by project team members,
other employees or outside sources.
- Adequate user access right shall be established to prevent data loss or damage during file exchange,
maintenance, and archiving. BIM project data residing on network severs shall be subjected to regular
back-ups by IT Team.
- Frequency of the backup is not mandated, but it is recommended that frequency shall correspond to
quantity and frequency of change in the model.