JAWABAN No.

1B
DIAGRAM AON (ACTIVITY ON NODE)

0 5 5 15
0 5 14 24

A F
5 10

5 12 12 24
5 12 12 24

D G
7 12

5 13
6 14

E
8

0 4
8 12

B
4

0 6 13 23
8 14 14 24

C H
6 10

ANALISA JARINGAN

Aktivitas
Aktivitas Durasi ES EF LS LF TF
Sebelum
A D, E, F 5 0 5 0 5 0
B G 4 0 4 8 12 8
C H 6 0 6 8 14 8
D G 7 5 12 5 12 0
E H 8 5 13 6 14 1
F - 10 5 15 14 24 9
G - 12 12 24 12 24 0
H - 10 13 23 14 24 1
GANTT CHART

Waktu
Aktivitas Durasi
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
A 5
B 4

C 6

D 7

E 8
F 10

G 12

H 10
Period (days) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Aktivitas Kritis
Aktivitas Non Kritis
Total Float