You are on page 1of 125

DAFTAR SEWA P E R A L A T AN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI 03 2020
HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM
(Rp) (Rp)

1 Dump Truck 3 ton Jam 85,000 100,000

2 Dump Truck 9 ton Jam 110,000 115,000

3 Truk Bak Terbuka Engkel Jam 125,000 130,000

4 Truk Tanki Air Jam 280,000 290,000

5 Bulldozer 100 - 150 hp Jam 675,000 700,000

6 Motor Grader Jam 625,000 640,000


7 Wheel Loader Jam 270,000 280,000

8 Excavator Jam 650,000 660,000

9 Crane 35 ton Jam 550,000 600,000

10 Flat Bed Truck jam 430,000 440,000

11 Baby Roller / Pedestrian Jam 110,000 120,000


12 P.Tire Roller 8 - 10 ton Jam 500,000 550,000

13 Baby Roller jam 40,000 42,000

14 Vibrator Roller self 7 ton Jam 500,000 510,000

15 Pile Driver / Hammer jam 150,000 160,000

16 Water Pump Jam 40,000 42,500

17 Asphalt Sprayer Jam 135,000 140,000

18 Pick Up single cabin Jam 40,000 55,000

19 A M P Jam 5,500,000 5,600,000

20 Asphalt Finisher Jam 340,000 350,000

21 Concrete Vibrator Jam 55,000 60,000

22 Compressor Jam 310,000 320,000

23 Concrete Mixer 0,125m3 Jam 75,000 80,000

24 Concrete Cutter jam 37,500 40,000

25 Stamper Jam 40,000 45,000

26 Genset 5-25kva+bbm Jam 180,000 183,000

27 Alat Pengecat Marka Jam 300,000 310,000


28 Mesin Las jam 180,000 200,000

29 Stone Crusher jam 850,000 900,000

30 Truck Trailler trip 7,250,000 7,400,000


DAFTAR SEWA P E R A L A T AN

EDISI 03 2020

KET.
DAFTAR UPAH PEKERJA

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI 03 2020

HARGA
NO. URAIAN PEKERJA SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 105,000 115,000 16,429 16,429
2 Mandor Hr 130,000 145,000 20,714 20,714
3 Tukang listrik Hr 135,000 145,000 20,714 20,714
4 Tukang kayu Hr 135,000 145,000 20,714 20,714
5 Kep. tk. kayu Hr 140,000 150,000 21,429 21,429
6 Tukang batu Hr 135,000 145,000 20,714 20,714
7 Kep. tk. batu Hr 140,000 150,000 21,429 21,429
8 Tukang besi Hr 125,000 135,000 19,286 19,286
9 Kep. tk. besi Hr 140,000 150,000 21,429 21,429
10 T u k a n g c a t Hr 135,000 145,000 20,714 20,714
11 K e p . t k . c a t Hr 140,000 150,000 21,429 21,429
12 T u k a n g p l i t u r Hr 135,000 145,000 20,714 20,714
13 T u k a n g j a l a n Hr 105,000 115,000 16,429 16,429
14 T u k a n g g a l i Hr 105,000 115,000 16,429 16,429
15 Tukang masak aspal Hr 105,000 115,000 16,429 16,429
16 T k . l e i d e n g Hr 135,000 145,000 20,714 20,714
17 M a s i n i s Hr 175,000 200,000 28,571 28,571
18 P e m b . M a s i n i s Hr 125,000 150,000 21,429 21,429
19 P e n j a g a a p i Hr 105,000 115,000 16,429 16,429
20 P e n j a g a m a l a m Hr 105,000 115,000 16,429 16,429
21 Sopir Hr 175,000 200,000 28,571 28,571
22 Pembantu Sopir Hr 125,000 150,000 21,429 21,429

500669137.xls 125 utk


2,300,000 64,000

92,000

500669137.xls 125 utk


DAFTAR HARGA SATUAN BAHAN BANGUNAN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI 03 2020

HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 220,000 250,000
Bulat Belah m3 260,000 320,000
Pecah 10/15 m3 270,000 340,000
Pecah 5/7 m3 270,000 350,000
Pecah 3/5 m3 300,000 360,000
2 KERIKIL Timbun m3 180,000 200,000
Sawur / Koral m3 170,000 200,000
Beton 0,5/1 m3 310,000 380,000
Beton 1/2 m3 310,000 390,000
Beton 2/3 m3 320,000 380,000
Biasa m3 210,000 260,000
Tras Giling m3 280,000 320,000
3 BATU BATA ex lokal bh 520 580

4 PASIR Urug m3 160,000 220,000


Pasang m3 310,000 370,000
Beton m3 340,000 375,000
5 TANAH Padas m3 120,000 150,000
Liat m3 120,000 150,000
6 KAPUR Pasang m3 300,000 310,000
Semen Merah m3 200,000 200,000
7 PORTLAND CEMENT
Merk I 40 kg zak 46,000 48,000
Merk I 50 kg zak 56,000 57,500
Merk II 40 kg zak 45,500 47,000
Merk II 50 kg zak 56,000 57,000
Semen Putih 40 kg zak 85,000 90,000
Semen Putih 50 kg zak 95,000 102,000
Semen warna kg 12,000 15,000

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak 190,000 210,000

2 GENTENG BETON Genteng Beton Warna standard bh 6,400 7,200


Genteng Beton Warna Special bh 9,800 10,500
Genteng Beton Warna Khusus bh 14,800 15,200
Kerpus Beton Warna Standard bh 9,900 11,000
Kerpus Beton Warna Special bh 11,250 13,000
Kerpus Beton Warna Khusus bh 13,200 15,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
3 GENTENG TANAH LIAT
Vlaam/Plentong bh 2,300 2,600
Kodok bh 2,500 3,100
Kodok Glasur bh 4,250 4,350
Nok kerpus Kodok bh 6,500 6,800
Nok kerpus Kodok Glasur bh 8,000 12,000
Plentong super besar 18 bh/m2 bh 5,100 5,350
Nok kerpus plentong super bh 9,000 9,200
4 GENTENG KACA
Vlaam tebal 2 mm bh 13,000 15,000
Vlaam tebal 3 mm bh 15,000 17,000
Kodok tebal 2 mm bh 14,000 15,000
Kodok tebal 3 mm bh 15,000 17,500

5 ASBES GELOMBANG BESAR


. 200 cm X 102 cm X 5 mm bh 90,000 112,000
. 225 cm X 102 cm X 5 mm bh 99,000 123,000
. 250 cm X 102 cm X 5 mm bh 109,000 132,000
. 200 cm X 102 cm X 6 mm bh 120,000 144,000
. 225 cm X 102 cm X 6 mm bh 130,000 155,000
. 250 cm X 102 cm X 6 mm bh 140,000 160,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 42,500 55,000
. 180 cm X 105 cm X 4 mm bh 52,000 58,000
. 210 cm X 105 cm X 4 mm bh 60,000 81,000
. 240 cm X 105 cm X 4 mm bh 67,500 96,000
. 270 cm X 105 cm X 4 mm bh 75,000 104,000
. 300 cm X 105 cm X 4 mm bh 85,000 119,000
ONDULINE : 95 cm x 200cm x 0.3mm lbr 160,000 165,000
ONDUVILLA : 40cm x 106 cm x 0,3mm lbr 95,000 105,000
NOK Jabes nok
. Kerpus Genteng bh 31,000 40,000
. Stel Besar bh 44,000 50,000
. Paten Besar bh 43,000 47,000
Nokstel gelombang harflex
. Stel Besar bh 44,000 48,000
. Patent Besar bh 27,000 30,500
. Plat besar bh 50,000 55,000
NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cm x 50 cm x 0,3mm lbr 115,000 125,000
6 ASBES PLAT
. 100cm X 100 cm X 3 mm bh 15,500 17,000
. 100cm X 100 cm X 4 mm bh 16,000 20,000
. 50 cm X 200 cm X 3 mm bh 14,200 15,000
. 40 cm X 200 cm X 3 mm bh 14,000 14,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
FIBER PLAT uk. 100cm x 100cm x 4mm lbr 25,000 30,000
unt Plafond uk. 120cm x 240cm x 4mm lbr 75,000 80,000
uk. 122cm x 244cm x 4mm lbr 77,000 85,200
GRC BOARD uk.122cm x 244cm x 5mm lbr 100,000 112,000
uk.122cm x 244cm x 6mm lbr 130,000 135,000
uk.122cm x 244cm x 8mm lbr 199,500 201,500
uk.122cm x 244cm x 10mm lbr 255,000 260,000
7 FIBRE GLASS (JABES)
180 X 92 cm bh 56,000 61,000
200 X 92 cm bh 58,000 66,000
250 X 92 cm bh 67,000 74,000
180 X 105 cm bh 68,000 90,000
210 X 105 cm bh 70,000 105,000
250 X 105 cm bh 80,000 120,000
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 22,000 24,500
BJLS 0,20 lebar 55 cm m' 25,000 30,000
BJLS 0,28 lebar 55 cm m' 26,500 30,000
BJLS 0,30 lebar 55 cm m' 30,000 36,000
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 43,000 45,000
BJLS 0,20 panjang 180 cm lbr 48,000 55,000
BJLS 0,30 panjang 180 cm lbr 59,000 60,000
BJLS 0,40 panjang 180 cm lbr 69,000 72,000
III . B A H A N K A Y U
1 JATI Papan m3 28,000,000 29,000,000
Balok/pesagen m3 25,000,000 26,000,000
2 KAMPER Papan m3 8,700,000 8,800,000
Balok/pesagen m3 8,400,000 8,600,000
3 KRUING Papan m3 8,400,000 8,800,000
Balok/pesagen m3 6,500,000 6,800,000
4 MERANTI Papan m3 5,100,000 5,700,000
Balok/pesagen m3 5,000,000 5,400,000
5 LANAN Papan m3 3,290,000 3,300,000
Balok/pesagen m3 2,000,000 2,200,000
6 BENGKIRAI Papan m3 10,500,000 10,650,000
Balok/pesagen m3 9,400,000 9,900,000
7 DOLKEN Sedang 8 x 10 x 400 cm bt 21,000 24,000
Kecil 6 x 7 x 400 cm bt 18,000 21,000
Besar 10 x 12 x 400 cm bt 31,000 34,000
Kayu cetakan m3 2,200,000 2,700,000
Kayu bakar m3 150,000 170,000
Bambu bt 12,000 18,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
IV . BAHAN PENUTUP DINDING / LANTAI
1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 35,000 38,000
20 X 20 cm m2 34,000 37,000
PC warna 30 X 30 cm m2 40,000 48,000
20 X 20 cm m2 39,500 45,000
Teraso 30 X 30 cm m2 52,000 56,000
2 TEGEL PLINT
PC warna 10 X 20 cm bh 5,200 5,500
PC abu-abu 15 x 20 bh 5,100 6,000
3 UBIN PORSELIN
Lokal 11 X 11 putih dos 42,000 43,000
11 X 11 warna dos 45,000 46,000
Lokal 15 X 15 putih dos 45,000 47,500
15 X 15 warna dos 46,000 49,000
4 MOZAIK PORSELIN
10 X 20 cm m2 50,000 72,000
15 X 15 cm m2 55,000 73,000
20 X 20 cm m2 55,000 74,000
20 X 25 cm m2 56,000 74,000

5 Keramik 30 X 30 cm m2 67,000 78,000


20 X 20 cm m2 66,000 76,000
33 x 33 cm m2 66,000 78,000
25 x 25 cm m2 65,000 75,000
15 x 20 cm m2 68,000 75,000
2,250 2,500
6 Parquet Jati m2 260,000 310,000
7 Batu Paros m2 125,000 140,000
8 Batu Tempel Hitam m2 120,000 140,000
9 GRANITO 40 x 40 cm m2 220,000 250,000
30 x 30 cm m2 300,000 320,000
10 Marmer m2 475,000 480,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 39,000 40,000
Ø 20 cm - 100 cm bh 45,000 50,000
Ø 30 cm - 100 cm bh 64,500 80,000
Ø 50 cm - 100 cm bh 135,000 160,000
Ø 60 cm - 100 cm bh 185,000 215,000
Ø 70 cm - 100 cm bh 250,000 265,000
U 10 cm - 100 cm bh 30,000 32,500
U 15 cm - 100 cm bh 35,000 40,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
U 20 cm - 100 cm bh 39,000 45,000
U 30 cm - 100 cm bh 40,000 55,000
U 50 cm - 100 cm bh 65,000 80,000
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm bh 9,000 12,000
20 X 20 cm bh 12,500 16,000
25 X 25 cm bh 16,500 20,000
30 X 30 cm bh 19,000 22,000
15 X 25 cm bh 18,000 20,000
15 X 30 cm bh 20,000 22,000
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 10,200 12,000
besi beton prestress kg 14,000 14,500
besi beton ulir kg 13,200 13,500

2 BESI PLAT Besi Strip kg 14,000 14,250

3 BESI PROFIL Besi Profil kg 14,500 14,750


a BAJA RINGAN
GALVALUME lebar : 7,5cm tebal : 1mm btg 132,000 140,000 panj : 6 m
type CT 75 lebar : 7,5cm tebal : 0.75mm btg 103,000 115,000 panj : 6 m
lebar : 7,5cm tebal : 0,65mm btg 93,000 105,000 panj : 6 m
b type RT 12 tinggi : 3,5 cm, tebal : 0,45mm btg 48,000 62,500 panj : 6 m
type RT 10 tinggi : 3,0 cm, tebal : 0,45mm btg 42,000 55,000 panj : 6 m
c HOLLOW GALVANIS LIPAT
tinggi 2 cm; tebal : 0,3 mm btg 19,000 25,000 panj : 4 m
tinggi 4 cm; tebal : 0,3 mm btg 25,000 30,000 panj : 4 m
4 JARING - JARING BAJA
Diameter 4 - 15 kg 14,000 15,000
Diameter 6 - 15 kg 14,000 16,000
Kawat Bronjong kg 12,500 14,000
5 BESI SIKU L 40 X 40 X 4 btg 135,000 142,100
L 50 X 50 X 5 btg 217,500 220,500
L 60 X 60 X 6 btg 318,500 355,000

6 KAWAT - Ikat beton/bendrat kg 19,000 20,000


- Harmonika 12 X 45 mm m2 20,500 35,000
- Harmonika 12 X 24 mm m2 20,000 21,000
- Harmonika 14 X 30 mm m2 20,000 21,000
- Harmonika 14 X 35 mm m2 25,000 27,500
- Kawat Nyamuk Nylon m2 20,000 25,000
- Kawat Kasa m2 15,000 18,000
- Saringan pasir m2 19,000 20,000
- Kawat loket m2 17,000 18,500
- Kawat duri rol 110,000 140,000
- Kawat bronjong kg 25,000 26,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 28,000 31,000 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 34,000 36,500 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 49,000 55,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 60,000 70,000 panjang 4 m
Pipa PVC DN 63 ( 2" ) btg 85,000 105,000 panjang 4 m
Pipa PVC DN 90 ( 3" ) btg 165,000 185,000 panjang 4 m
Pipa PVC DN 110 ( 4" ) btg 270,000 280,000 panjang 4 m
Pipa PVC DN 160 ( 6" ) btg 530,000 550,000 panjang 4 m
Pipa PVC DN 200 ( 8" ) btg 900,000 1,050,000 panjang 4 m
Pipa PVC DN 250 ( 10" ) btg - - panjang 4 m
Pipa PVC DN 315 ( 12" ) btg - - panjang 4 m

2 Pipa Medium A Galvanis - SII


Pipa Medium Galvanis 0,50" btg 155,000 160,000 panjang 6 m
Pipa Medium Galvanis 0,75" btg 195,000 200,000 panjang 6 m
Pipa Medium Galvanis 1" btg 305,000 315,000 panjang 6 m
Pipa Medium Galvanis 1,25" btg 380,000 390,000 panjang 6 m
Pipa Medium Galvanis 1,50" btg 440,000 450,000 panjang 6 m
Pipa Medium Galvanis 2" btg 590,000 602,000 panjang 6 m
Pipa Medium Galvanis 2,50" btg 740,000 752,000 panjang 6 m
Pipa Medium Galvanis 3" btg 970,000 975,000 panjang 6 m
Pipa Medium Galvanis 4" btg 1,425,000 1,430,000 panjang 6 m
Pipa Medium Galvanis 5" btg 1,900,000 1,905,000 panjang 6 m
Pipa Medium Galvanis 6" btg - - panjang 6 m

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,800 6,500
30 X 60 lbr 13,200 14,500
60 X 120 lbr 42,000 46,000
List Kayu Profil m' 4,800 5,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 60,000 65,000
3 HARD BOARD-uk: 4'X 8' lbr 51,000 55,000
GYPROC uk.120cmx240cmx9mm lbr 60,000 65,000
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 65,000 75,000
. 120 X 240 X 3 mm lbr 80,000 95,000
. 90 X 210 X 4 mm lbr 65,000 85,000
. 90 X 210 X 9 mm lbr 115,000 125,000
. 90 X 210 X 12 mm lbr 135,000 170,000
. 90 X 210 X 15 mm lbr 200,000 240,000
. 90 X 210 X 18 mm lbr 295,000 310,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
Tripleks
. 120 X 240 X 3 mm lbr 50,000 61,500
. 120 X 240 X 4 mm lbr 65,000 70,000
. 120 X 240 X 6 mm lbr 75,000 86,000
Multipleks
. 120 X 240 X 9 mm lbr 110,000 130,000
. 120 X 240 X 12 mm lbr 165,000 180,000
. 120 X 240 X 15 mm lbr 190,000 210,000
. 120 X 240 X 18 mm lbr 215,000 250,000
Formika ukuran pintu lbr 70,000 75,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 30,000 32,000
Dempul plamur kg 25,000 30,000
Ambril/amplas lbr 4,100 5,000
Batu Apung kg 75,000 80,000
Cat dasar kg 40,000 42,500
. Emco kg 65,000 71,000
. Yunior 66 (nippon paint) kg 68,000 71,000
- Koas bh 17,500 20,000
. Deculux kg 67,000 75,000
. Siralax ons 20,000 21,000
. Spiritus ltr 15,000 18,000
. Plitur jadi ltr 65,000 71,000

2 TEMBOK
Kalkarium kg 4,500 5,000
Kapur sirih kg 4,250 4,750
Plamur kg 25,000 32,000
Cat Tembok kg 23,000 28,400
Sintex 5 kg 125,000 135,000
Danabride 5 kg 130,000 140,000
Catylac interior 5 kg 130,000 142,000
Mowilex 2,50 kg 285,000 350,000

3 BESI
Menie kg 25,000 36,000
Cat mengkilat kg 62,000 72,500
Cat kg 40,000 45,000
Thinner A ltr 16,000 20,000
Minyak cat ltr 20,000 22,000
Thinner Super ltr 17,500 35,000
Residu (teer/aspal) drum 60,000 67,500
Fibre glass (tanki air)
kapasitas 550 liter. bh 1,025,000 1,100,000
kapasitas 1100 liter. bh 1,625,000 1,700,000
Lem Aica Aibon kg 55,000 65,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 88,000 95,000
5 mm m2 100,000 105,000
2 ES KABUR 3 mm m2 110,000 115,000
5 mm m2 130,000 135,000
3 RAY BAND 3 mm m2 95,000 100,000
5 mm m2 105,000 110,000

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 5,250 5,500

SPLN LMK 1 X 2 1/2 mm2 m' 6,000 6,200

. 1X4 mm2 m' 6,600 7,750

1X6 mm2 m' 10,500 11,000

NYY :. 2 X 1 1/2 mm2 m' 11,000 11,500

PRIMA 2 X 2 1/2 mm2 m' 15,500 16,500

. 2X4 mm2 m' 28,000 29,500

2X6 mm2 m' 37,000 39,000

3 X 1 1/2 mm2 m' 14,500 16,700

3 X 2 1/2 mm2 m' 21,000 22,100

3X4 mm2 m' 35,600 39,000

3X6 mm2 m' 50,000 56,000

NYM :. 2 X 1 1/2 mm2 m' 8,000 8,500

PRIMA 2 X 2 1/2 mm2 m' 11,500 12,000

. 2X4 mm2 m' 22,500 24,000

3 X 1 1/2 mm2 m' 13,200 14,500

3 X 2 1/2 mm2 m' 21,050 23,400

3X4 mm2 m' 32,000 36,000

3X6 mm2 m' 45,000 49,000

2 SKAKELAR
Out bauw . Seri bh 25,000 35,000

. Engkel bh 20,000 22,000

In bauw . Seri bh 21,000 25,000

. Engkel bh 17,500 20,000

3 FUSE BOX (SEKERING KASA)


1 group bh 145,000 165,000

2 group bh 250,000 280,000

3 group bh 350,000 395,000

4 STEKER - Biasa bh 22,000 27,000

Arde bh 32,500 35,000

T Biasa bh 15,500 17,500

T dengan Arde bh 35,000 41,000


HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
5 FITING Flaon bh 17,000 25,000

Gantung bh 15,000 20,000

Kap bh 27,000 32,000

Kombinasi bh 31,000 38,000

6 STOP KONTAK - Arde Outbow putih bh 22,000 30,000

Arde Outbow hitam bh 30,000 35,000

Arde IB bh 35,000 40,000

Arde Putar bh 42,000 50,000

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh 100,000 125,000
2 X slag bh 165,000 200,000
Yale : 1 X slag bh 95,000 150,000
2 X slag bh 130,000 170,000
Kuda : 1 X slag bh 95,000 105,000
2 X slag bh 125,000 130,000

2 ENGSEL DAN GERENDEL


Engsel Angin bh 16,000 30,000
Kupu-kupu biasa bh 4,500 6,000
Nylon kupu-kupu bh 7,500 9,000
Espagnoled - dalam negeri bh 40,000 50,000
Grendel Tanam luar negeri bh 11,000 13,000
Grendel biasa bh 8,000 10,000
Kait Angin bh 17,500 20,000
Door Stop bh 275,000 350,000

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,600,000 1,850,000
2 KLOSET JONGKOK bh 145,000 160,000
3 WASTAFEL PEDESTAL bh 950,000 1,050,000
4 WASTAFEL MEJA OVAL bh 750,000 950,000
5 WASTAFEL GANTUNG BULAT bh 300,000 325,000
6 WASTAFEL GANTUNG SUDUT bh 250,000 310,000
7 WASTAFEL GANTUNG SUDUT KECIL bh 240,000 275,000
8 WASTAFEL BAK CUCI bh 150,000 165,000
9 TEMPAT SABUN GANTUNG bh 45,000 55,000
10 TEMPAT SABUN TANAM bh 22,500 25,000
11 LAIN - LAIN
Kran Air bh 27,500 45,000
Seal tape bh 4,000 4,500
Floor drain bh 35,000 42,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
XIV . ALAT PENGIKAT KAYU
1 PAKU - ukuran 1" s/d 4" kg 17,000 17,500
2 PAKU - payung kg 20,000 26,000
3 PAKU - sekrup kg 7,000 8,000
4 PAKU - beton kg 25,000 30,000
5 MUR BAUT (kuda-kuda) kg 13,000 14,000
6 ANGKUR BAUT bh 13,000 13,500
7 LEM KAYU bh 12,500 20,000
8 Tali Ijuk kg 35,000 37,000

XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 350,000 375,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 975,000 1,100,000
Fuji 250 watt bh 1,450,000 1,650,000
Shimizu . 100 watt bh 470,000 550,000
. 90 watt bh 350,000 425,000
Dab . 125 watt bh 400,000 420,000
. 175 watt bh 425,000 475,000

X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 85,000 95,000
Merah/hitam m2 90,000 105,000
2 HOLLAND Abu-abu m2 85,000 95,000
Merah/hitam m2 90,000 105,000
3 UNIDECOR Abu-abu m2 85,000 95,000
Merah/hitam m2 90,000 105,000
4 UNI Abu-abu m2 85,000 95,000
Merah/hitam m2 90,000 105,000
5 TRIHEX Abu-abu m2 85,000 95,000
Merah/hitam m2 90,000 105,000
6 OLYMPIA HEXA Abu-abu m2 85,000 95,000
7 HEXAGONAL Abu-abu m2 90,000 105,000
Merah/hitam m2 85,000 95,000
8 CASTLE Abu-abu m2 90,000 105,000
9 TRAPEZ Abu-abu m2 85,000 95,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 85,000 95,000
11 STANDARD GRASS BLOCK ABU-ABU BH 7,500 8,500
12 BATACO BH 4,100 5,500
13 KANSTEEN m' 27,000 32,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
XVII. L A I N - L A I N
1 KREI 25 MM m2 45,000 60,000
2 Sliding Pintu J4 bh 200,000 235,000
3 Naco per Daun bh 40,000 42,000
4 Rolling door Besi m2 325,000 335,000
Rolling door Almunium m2 275,000 290,000
5 Awning Almunium m2 225,000 250,000
6 Kusen Almunium 4" Putih m' 95,000 100,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,425,000 1,545,600

8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 950,000 1,100,000

9 KACA
Cermin tebal 5 mm m2 275,000 325,000

10 PAGAR BRC. Pagar BRC 90 A2 /lb 310,000 325,000


Pagar BRC 120 A2 /lb 375,000 390,000
11 LAIN-LAIN
Minyak Beton & bekisting ltr 9,000 10,000
Pintu Lipat Besi m2 400,000 425,000
Sunscreen Allumunim m2 350,000 400,000
Allumunium Foil m2 12,000 15,000
Soda api kg 13,000 15,000
Sabun kg 12,500 15,000
Air m3 20,000 25,000
Koas Alang-alang ikat 2,500 3,000
Solar (Industri) ltr 8,200 8,600
Premium (Industri) ltr 7,650 7,800
Pelumas ltr 37,000 45,000
Vynil 30x30 cm bh 6,200 6,500
DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016

SUMBER DATA : PASARAN BEBAS EDISI 03 2020


DAERAH : KOTA SEMARANG DAN SEKITAR

HARGA SATUAN PEKERJAAN


NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi 2,00
1 A.2.2.1.2 m' 717,172.50 767,849.50
m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 179,509.00 188,952.50

3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran m2 2,334,519.00 2,493,315.00

4 A.2.2.1.6 Pembuatan Rumah Jaga (Konstruksi Kayu) m2 1,818,960.00 1,930,225.00

5 A.2.2.1.7 Pembuatan Gudang Semen dan Peralatan m2 1,673,732.50 1,766,077.50

6 A.2.2.1.8 Pembuatan Bedeng Pekerja m2 2,064,425.00 2,205,390.00

7 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 18,700.00 20,625.00

8 A.2.2.1.10 Pembuatan Steger/Perancah dari Bambu m2 474,111.00 518,795.20

9 A.2.2.1.11 Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm bh 640,706.00 672,100.00

10 A.2.2.1.12 Pembuatan Jalan Sementara m2 189,255.00 218,817.50

11 A.2.2.1.13 Bongkaran Beton Bertulang m3 1,635,315.00 1,792,978.00

12 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah m3 774,757.50 848,639.00

13 A.2.2.1.15 Pagar Kawat Jaring Galvanis Panjang 240 cm m2 60,658.40 64,245.50


Pemasangan Pagar Panel Beton Pracetak 5 x 50 x
14 A.2.2.1.16 m2 327,387.50 359,169.25
240 cm

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 90,200.00 98,862.50

2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m m3 110,385.00 121,027.50

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m m3 130,856.00 143,511.50

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m m3 120,076.00 131,604.00

5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m m3 181,830.00 199,320.00

6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m m3 145,035.00 158,977.50

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m m2 6,490.00 7,122.50

8 A.2.3.1.8 MembuangTanah sejauh 30 m' m3 39,545.00 43,340.00


Pengurugan Kembali di hitung dari 1/3 kali koefisien
9 A.2.3.1.9 m3 21,633.33 23,741.67
Pekerjaan galian
10 A.2.3.1.10 Pemadatan Tanah (per 20 cm) m3 64,900.00 71,225.00

11 A.2.3.1.11 Urugan Pasir m3 247,280.00 329,945.00

12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL m3 472,571.00 532,125.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 m2 28,710.00 31,135.50
Resapan

14 A.2.3.1.14 Mengurug Sirtu Padat m3 270,050.00 299,612.50

500669137.xls 125/16 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP m3 1,084,215.00 1,246,547.50

2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP m3 1,046,815.00 1,209,312.50

3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 1,020,844.00 1,183,440.50


4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 1,002,606.00 1,165,279.50

5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP m3 977,559.00 1,140,320.50

6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 872,740.00 1,016,262.50
Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 956,747.00 1,113,403.50
PP
Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4
8 A.3.2.1.8 m3 936,738.00 1,094,164.50
PP
9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 592,020.00 726,874.50

Pasang Pondasi Siklop, 60% Beton Campuran 1PC :


10 A.3.2.1.10 m3 2,617,571.00 3,004,573.00
2PB : 3KR & 40% Batu Belah

11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm m3 1,029,193.00 1,150,308.50

IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum


1 A.4.1.1.1 m3 1,057,405.64 1,167,763.14
(12±2)cm, w/c = 0,87

Membuat Beton mutu f'c=9,8 Mpa (K125), slum


2 A.4.1.1.2 m3 1,086,527.42 1,197,987.97
(12±2)cm, w/c = 0,78

Membuat Beton mutu f'c=12,2 Mpa (K150), slum


3 A.4.1.1.3 m3 1,109,178.98 1,221,351.48
(12±2)cm, w/c = 0,72

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa


4 A.4.1.1.4 m3 973,927.31 1,078,162.70
(K100), slum (3-6)cm, w/c = 0,87

Membuat Beton mutu f'c=14,5 MPa (K175), slum


5 A.4.1.1.5 m3 1,136,044.29 1,249,215.96
(12±2)cm, w/c = 0,66

Membuat Beton mutu f'c=16,9 MPa (K200), slum


6 A.4.1.1.6 m3 1,161,708.63 1,275,610.58
(12±2)cm, w/c = 0,61

Membuat Beton mutu f'c=19,3 MPa (K225), slum


7 A.4.1.1.7 m3 1,181,099.77 1,295,921.44
(12±2)cm, w/c = 0,58

Membuat Beton mutu f'c=21,7 MPa (K250), slum


8 A.4.1.1.8 m3 1,193,855.99 1,308,836.54
(12±2)cm, w/c = 0,56

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa


9 A.4.1.1.9 m3 1,216,159.21 1,331,494.21
(K275), slum (12±2)cm, w/c = 0,53

Membuat Beton mutu f'c=26,4 MPa (K300), slum


10 A.4.1.1.10 m3 1,222,909.08 1,338,302.14
(12±2)cm, w/c = 0,52

Membuat Beton mutu f'c=28,8 MPa (K325), slum


11 A.4.1.1.11 m3 1,316,285.90 1,438,288.12
(12±2)cm, w/c = 0,49

Membuat Beton mutu f'c=31,2 MPa (K350), slum


12 A.4.1.1.12 m3 1,325,305.03 1,447,426.42
(12±2)cm, w/c = 0,48

500669137.xls 125/17 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir Kg 14,107.50 16,371.30

14 A.4.1.1.18 Kabel Presstresed Polos/strand Kg 17,818.90 18,527.85

15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh Kg 28,859.60 30,045.95

16 A.4.1.1.20 Memasang Bekisting untuk Pondasi m2 200,992.00 219,362.00


17 A.4.1.1.21 Memasang Bekisting untuk Sloof m2 211,992.00 231,462.00

18 A.4.1.1.22 Memasang Bekisting untuk Kolom m2 428,296.00 468,583.50

19 A.4.1.1.23 Memasang Bekisting untuk Balok m2 449,746.00 491,023.50

20 A.4.1.1.24 Memasang Bekisting untuk Lantai m2 520,696.00 574,183.50

21 A.4.1.1.25 Memasang Bekisting untuk Dinding m2 487,146.00 532,383.50

22 A.4.1.1.26 Memasang Bekisting untuk Tangga m2 405,801.00 443,833.50

23 A.4.1.1.27 Memasang Jembatan Cor m2 107,514.00 117,689.00

24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 92,455.00 102,817.00

25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 120,268.50 133,848.00

IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c


1 A.4.1.2.1 m2 90,898.06 99,955.10
14,5 Mpa, Slump (120 ± 20) mm K3

Pembuatan Lahan Produksi Tebal 10 cm Beton f'c =


2 A.4.1.2.2 m2 113,666.58 124,986.50
14,5 Mpa slum (120 ± 20 ) mm K3

Pembuatan Lahan Produksi Tebal 12 cm Beton


3 A.4.1.2.3 m2 132,464.10 145,678.40
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Lahan Produksi Tebal 15 cm Beton


4 A.4.1.2.4 m2 170,475.12 187,460.49
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Bekisting untuk Plat Beton Pra cetak (5


5 A.4.1.2.5 m2 128,430.66 137,870.62
kali Pakai)

Pembuatan Bekisting untuk Balok Beton Pra cetak


6 A.4.1.2.6 m2 48,083.00 50,634.60
(10 - 12 kali Pakai)

Pembuatan Bekisting untuk Kolom Beton Pra cetak


7 A.4.1.2.7 m2 42,208.00 44,484.60
(10 - 12 kali Pakai)

Pemasangan dan Membuka Bekisting untuk


8 A.4.1.2.8 bh 8,645.00 9,430.00
Komponen Plat Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


9 A.4.1.2.9 bh 14,045.00 15,310.00
Komponen Balok Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


10 A.4.1.2.10 bh 11,345.00 12,370.00
Komponen Kolom Beton Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


11 A.4.1.2.11 m3 78,309.00 76,985.00
Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


12 A.4.1.2.12 m3 80,536.50 79,170.00
Pracetak

Penuangan / Menebar Beton untuk Komponen


13 A.4.1.2.13 m3 72,314.00 71,125.00
Kolom Pracetak

500669137.xls 125/18 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
14 A.4.1.2.14 Ereksi Komponen Untuk Plat Pracetak bh 589,086.52 614,810.46

15 A.4.1.2.15 Ereksi Komponen Untuk Balok Pracetak bh 578,569.20 603,549.10

16 A.4.1.2.16 Ereksi Komponen Untuk Kolom Pracetak bh 831,139.54 872,219.92

17 A.4.1.2.17 Langsiran Komponen untuk Plat Pracetak (± 20 m) bh 162,420.94 169,740.12

18 A.4.1.2.18 Langsiran Komponen untuk Balok Pracetak (± 20 m) bh 126,522.44 130,178.62

19 A.4.1.2.19 Langsiran Komponen untuk Kolom Pracetak (± 20 m) bh 126,522.44 130,178.62

20 A.4.1.2.20 Bahan Grout Campuran m3 3,417,700.00 3,689,125.00

21 A.4.1.2.21 Bahan Grout Campuran (tidak Campuran) m3 3,061,300.00 3,368,750.00


22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 71,186.50 76,648.00

23 A.4.1.2.23 Pemasangan Bekisting Joint Pra Cetak ttk 142,249.80 152,036.50

24 A.4.1.2.24 Upah Pemasangan Joint dengan Sling ttk 62,920.00 68,183.50

HARGA SATUAN PEKERJAAN BESI &


V A.4.2.1
ALLUMUNIUM
1 A.4.2.1.1 Pemasangan Besi Profil Kg 35,535.50 37,287.25

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF Kg 29,590.00 31,152.00

3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) kg 106,359.00 123,172.50

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 m2 971,201.00 1,007,534.00
rangka baja Siku

5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 2,550.24 2,951.08

6 A.4.2.1.6 Pembuatan Rangka Jendela Besi Scuare Tube m2 283,393.88 315,478.46

7 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi m2 693,638.00 732,457.00

8 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door) m2 566,082.00 604,109.00

9 A.4.2.1.9 Pemasangan Sunscreen Allumunium m2 525,932.00 591,558.00

10 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 589,050.00 629,475.00


11 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium m' 132,214.50 140,062.45

12 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 556,419.60 590,682.40

13 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium m2 523,941.00 558,112.50

14 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds m2 204,864.00 218,746.00

15 A.4.2.1.15 Pemasangan Teralis Besi Strip (2x3) cm m2 649,559.35 703,144.75

16 A.4.2.1.16 Pemasangan Kawat Nyamuk m2 110,447.88 124,260.95

17 A.4.2.1.17 Pemasangan Jendela Nako & Tralis m2 148,423.00 160,429.50

Pemasangan Talang Datar / Jurai , Seng BJLS 28


18 A.4.2.1.18 m' 220,060.50 242,536.25
Lebar 90 cm

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


19 A.4.2.1.20 m2 133,309.00 143,148.50
Modul 60x120 cm dinding partisi

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


20 A.4.2.1.21 m2 170,764.00 183,546.00
Modul 60x60 cm dinding plafond

500669137.xls 125/19 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Atap Pelana Rangka Atap Baja Canal
21 A.4.2.1.22 m2 273,861.78 292,519.01
C dingin Profil C75

Pemasangan Atap Jurai Rangka Atap Baja Canal


22 A.4.2.1.23 m2 301,860.35 321,500.03
Dingin Profil C75

HARGA SATUAN PEKERJAAN PASANGAN


VI A.4.4.1
DINDING

Pemasangan Dinding Bata Merah ukuran (5x11x22)


1 A.4.4.1.1 m2 268,757.50 295,185.00
cm Tebal 1 bata Camp. 1SP: 2PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


2 A.4.4.1.2 m2 259,162.75 285,736.00
cm Tebal 1 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


3 A.4.4.1.3 m2 251,748.75 278,102.00
cm Tebal 1 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


4 A.4.4.1.4 m2 249,315.00 276,023.00
cm Tebal 1 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


5 A.4.4.1.5 m2 251,454.50 279,279.00
cm Tebal 1 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


6 A.4.4.1.6 m2 239,818.70 265,535.60
cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP

Pemasangan Dinding Bata Merah Ukuran


7 A.4.4.1.7 m2 130,154.75 143,082.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP

Pemasangan Dinding Bata Merah Ukuran


8 A.4.4.1.8 m2 125,043.05 137,850.90
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran


9 A.4.4.1.9 m2 122,435.50 135,283.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran


10 A.4.4.1.10 m2 120,815.20 133,695.10
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran


11 A.4.4.1.11 m2 120,458.80 133,527.90
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran


12 A.4.4.1.12 m2 118,497.50 131,532.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
Pemasangan Dinding Bata Merah Ukuran
13 A.4.4.1.13 (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : m2 120,917.50 134,007.50
10PP
Pemasangan Dinding Bata Merah Ukuran
14 A.4.4.1.14 m2 109,263.00 120,026.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP

Pemasangan Dinding Bata Merah Ukuran


15 A.4.4.1.15 m2 110,473.00 121,852.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


16 A.4.4.1.16 m2 412,328.40 471,997.90
3PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


17 A.4.4.1.17 m2 419,666.50 481,906.70
4PP

Pemasangan Dinding HB/CB 15, speci camp. 1SP :


18 A.4.4.1.18 m2 326,498.70 372,589.80
3PP

500669137.xls 125/20 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Dinding HB/CB 15, speci camp. 1SP :
19 A.4.4.1.19 m2 331,667.60 379,621.00
4PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


20 A.4.4.1.20 m2 256,003.00 305,422.70
3PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


21 A.4.4.1.21 m2 260,354.05 311,191.10
4PP

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 m2 376,035.00 482,707.50
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 m2 376,035.00 482,707.50
(12x11x24)cm Camp. 1SP : 4PP

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 m2 158,807.00 170,296.50
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Bata Ringan Tebal 7,5 cm


25 A.4.4.1.25 m2 350,032.54 375,287.06
dengan Mortar Siap Pakai

Pemasangan Dinding Bata Ringan Tebal 10 cm


26 A.4.4.1.26 m2 349,336.24 372,599.21
dengan Mortar Siap Pakai

VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

1 A.4.4.2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 86,448.56 93,719.78

2 A.4.4.2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 81,133.36 88,378.18

3 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 79,059.64 86,367.82

4 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 77,457.60 84,747.30

5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 76,803.76 84,167.38

6 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 76,173.24 83,560.62

7 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 75,907.04 83,334.02

8 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 75,640.84 83,107.42

Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15


9 A.4.4.2.9 m2 76,531.40 83,448.20
mm

Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15


10 A.4.4.2.10 m2 76,087.00 83,336.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15


11 A.4.4.2.11 m2 71,841.00 78,243.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15


12 A.4.4.2.12 m2 72,787.00 79,563.00
mm

13 A.4.4.2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 108,577.48 118,292.24

14 A.4.4.2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 80,323.20 87,696.60

15 A.4.4.2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 103,562.80 113,315.40

16 A.4.4.2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 102,804.68 112,677.84

17 A.4.4.2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 101,850.32 111,733.16

500669137.xls 125/21 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20
18 A.4.4.2.18 m2 101,112.00 110,264.00
mm

19 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm m2 46,262.26 50,958.38

Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10


20 A.4.4.2.20 m' 80,437.50 87,109.00
mm

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal


21 A.4.4.2.21 m' 121,368.50 131,626.00
10 mm

Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10


22 A.4.4.2.22 m' 121,368.50 131,626.00
mm

23 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp m2 60,695.80 66,086.90

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 m2 34,770.12 37,636.06
Merah

Pemasangan Finishing Siar Pasangan Dinding


25 A.4.4.2.25 m2 16,494.50 17,847.50
Conblock ekspose

Pemasangan Finishing Siar Pas.Batu Kali Adukan


26 A.4.4.2.26 m2 73,492.10 79,995.30
1Pc : 2Pp

27 A.4.4.2.27 Pemasangan Acian m2 45,031.25 48,785.00

28 A.4.4.2.28 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) m2 53,473.20 57,396.90

29 A.4.4.2.29 Pemasangan Acian dg Mortar Siap Pakai (MSP) m2 47,355.00 51,108.75

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3 dan DINDING

1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 120,838.50 132,402.00

2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 123,535.50 135,415.50

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 148,471.00 171,084.50

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 151,332.50 171,473.50

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 363,610.50 412,357.00

6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm m' 72,507.60 82,954.30

7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm m' 44,804.10 48,430.80

8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 263,525.35 314,185.30

Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20


9 A.4.4.3.33 m2 269,465.35 321,610.30
cm

10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 270,976.02 306,921.63

11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 270,544.00 304,583.50

12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 270,061.00 303,121.50

Pemasangan Lantai Keramik uk.10 x 33 cm, untuk


13 A.4.4.3.37 m2 497,480.50 552,046.00
variasi / border

14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 46,146.10 50,108.30

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 93,116.10 98,618.30

500669137.xls 125/22 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 96,031.10 101,533.30

17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 731,355.35 755,263.30

18 A.4.4.3.44 Pemasangan Lantai Karpet m2 214,335.00 228,035.50

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 479,820.00 556,682.50


20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 307,256.16 337,059.32

21 A.4.4.3.49 Pemasangan Dinding Porselen 10x20 cm m2 296,642.50 349,156.50

22 A.4.4.3.50 Pemasangan Dinding Porselen 20x20 cm m2 290,570.50 336,495.50

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm m2 296,642.50 349,156.50

24 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm m2 291,780.50 338,123.50


25 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 853,827.76 887,457.04

Pemasangan Dinding Batu Paros / Batu Tempel


26 A.4.4.3.58 m2 321,268.75 354,887.50
Hitam

27 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 165,394.90 178,057.00

28 A.4.4.3.60 Pemasangan Wallpaper Lebar 50 Cm m2 135,536.50 144,776.50

29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 62,931.00 67,177.00

30 A.4.4.3.64 Pemasangan Paving Block Natural Tebal 6 Cm m2 204,906.90 228,066.85

31 A.4.4.3.65 Pemasangan Paving Block Natural Tebal 8 Cm m2 272,562.40 299,319.35


32 A.4.4.3.66 Pemasangan Paving Block Berwarna Tebal 6 Cm m2 217,127.90 240,287.85

33 A.4.4.3.67 Pemasangan Paving Block Berwarna Tebal 8 Cm m2 284,783.40 311,540.35

HARGA SATUAN PEKERJAAN LANGIT-


IX A.4.5.1
LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m,


1 A.4.5.1.1 m2 34,452.00 37,515.50
tebal 4 mm, 5 mm & 6 mm

Pemasangan Langit-langit Akustik Ukuran (30x30)


2 A.4.5.1.2 m2 111,881.00 124,019.50
cm

Pemasangan Langit-langit Akustik Ukuran (30x60)


3 A.4.5.1.3 m2 113,806.00 124,520.00
cm

Pemasangan Langit-langit Akustik Ukuran (60x120)


4 A.4.5.1.4 m2 98,890.00 107,910.00
cm

Memasang Langit-langit Tripleks Uk (120x240) cm,


5 A.4.5.1.5 m2 56,028.50 60,500.00
Tebal 3 mm, 4 mm & 6 mm

Memasang Langit-langit Lambriziring Kayu Jati, tebal


6 A.4.5.1.6 m2 691,427.00 727,072.50
6 mm

Memasang Langit-langit Gypsu Board, Ukuran


7 A.4.5.1.7 m2 46,299.00 50,149.00
(120x240) tebal 9 mm

Memasang Langit-langit Akustik Uk (60x120) cm &


8 A.4.5.1.8 m2 269,582.50 293,012.50
Berikut Rangka Allumunium

9 A.4.5.1.9 List Langit-Langit Kayu Profil m1 20,130.00 21,571.00

500669137.xls 125/23 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
HARGA SATUAN PEKERJAAN PENUTUP
X A.4.5.2
ATAP
1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 94,011.50 104,951.00

2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur m2 147,713.50 153,158.50

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar m2 131,818.50 139,463.50

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong m' 123,673.00 133,628.00

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur m' 136,048.00 147,103.00

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar m' 139,898.00 150,183.00

7 A.4.5.2.7 Pemasangan Roof Light Fibreglass 90 x 180 m2 111,633.50 124,030.50


Pemasangan Atap Asbes Gelombang (2,50x0,92 m)
8 A.4.5.2.8 m2 71,054.50 79,106.50
x 5 mm

Pemasangan Atap Asbes Gelombang (2,25x0,92 m)


9 A.4.5.2.9 m2 72,600.00 80,976.50
x 5 mm

Pemasangan Atap Asbes Gelombang (2,00x0,92 m)


10 A.4.5.2.10 m2 72,930.00 81,636.50
x 5 mm

Pemasangan Atap Asbes Gelombang (1,80x0,92 m)


11 A.4.5.2.11 m2 80,190.00 84,474.50
x 5 mm

Pemasangan Atap Asbes Gelombang (3,00x1,05 m)


12 A.4.5.2.12 m2 63,415.00 79,139.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,70x1,05 m)


13 A.4.5.2.13 m2 65,340.00 81,372.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,40x1,05 m)


14 A.4.5.2.14 m2 63,360.00 79,788.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,10x1,05 m)


15 A.4.5.2.15 m2 64,350.00 78,765.50
x 4 mm

Pemasangan Atap Asbes Gelombang (1,50x1,05 m)


16 A.4.5.2.16 m2 68,090.00 81,724.50
x 4 mm

Pemasangan Atap Asbes Gelombang (3,00x1,08 m)


17 A.4.5.2.17 m2 72,611.00 76,059.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,70x1,08 m)


18 A.4.5.2.18 m2 75,966.00 79,524.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,40x1,08 m)


19 A.4.5.2.19 m2 72,798.00 76,884.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,10x1,08 m)


20 A.4.5.2.20 m2 73,810.00 78,061.50
x 6 mm

Pemasangan Atap Asbes Gelombang (1,80x1,08 m)


21 A.4.5.2.21 m2 77,715.00 81,603.50
x 6 mm

22 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 118,921.00 132,192.50


23 A.4.5.2.31 Pemasangan Atap Genteng Aspal m2 238,898.00 264,577.50

24 A.4.5.2.32 Pemasangan Atap Genteng Metal m2 100,760.00 115,665.00

25 A.4.5.2.34 Pemasangan Atap Sirap m2 127,732.00 139,425.00

500669137.xls 125/24 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
26 A.4.5.2.35 Pemasangan Nok Genteng Beton m' 145,464.00 159,582.50

27 A.4.5.2.36 Pemasangan Nok Genteng Aspal m' 143,830.50 153,912.00

28 A.4.5.2.37 Pemasangan Nok Genteng Metal m' 80,454.00 88,286.00

29 A.4.5.2.38 Pemasangan Nok Sirap m' 69,987.50 76,087.00


30 A.4.5.2.39 Pemasangan Atap Seng Gelombang m2 45,331.00 50,182.00

31 A.4.5.2.40 Pemasangan Atap Nok Seng m' 39,149.00 42,922.00

32 A.4.5.2.43 Pasang Allumunium Foil / Sisalation m2 40,524.00 46,376.00

XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U

Pembuatan & Pemasangan Kosen Pintu & Jendela


1 A.4.6.1.1 m3 34,587,575.00 36,143,387.50
Kayu klas I

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 m3 14,811,225.00 15,372,912.50
Kayu klas II atau III

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 m2 598,829.00 620,108.50
Kayu Klas II (Kayu Kamfer)

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 m2 598,829.00 620,108.50
Sederhana Kayu Klas III

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 m2 997,837.50 1,050,775.00
Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Kaca


6 A.4.6.1.6 m2 725,285.00 768,900.00
Kayu Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 m2 2,592,425.00 2,715,075.00
Kayu Klas I atau II (jati)

Pembuatan&Pemasangan Pintu kayu lapis


8 A.4.6.1.8 (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 m2 748,231.00 810,810.00
cm)

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 m2 815,408.00 882,865.50
rangka expose kayu klas I atau II

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 m2 2,303,895.00 2,407,075.00
Klas I atau II

Pembuatan & Pemasangan Pintu Teakwood


11 A.4.6.1.11 m2 1,337,666.00 1,428,157.50
Rangkap, Rangka Expose Kayu Klas I

Pembuatan & Pemasangan Pintu Teakwood


12 A.4.6.1.12 Rangkap Lapis Formika, Rangka expose Kayu Klas m2 873,180.00 942,271.00
II

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 m3 12,957,120.00 13,398,825.00
Konvensional Kayu I; II & III Bentang 6 meter

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 m3 37,451,865.00 39,101,507.50
Expose, Kayu Klas I

15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m3 11,925,540.00 12,288,815.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 m2 195,954.00 202,356.00
Klas II

500669137.xls 125/25 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Rangka Atap Genteng Beton, Kayu
17 A.4.6.1.17 m2 229,218.00 236,412.00
Klas II

18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II m2 167,486.00 173,547.00

Pemasangan Rangka Langit-langit (50x1,00) m,


19 A.4.6.1.19 m2 223,256.00 233,271.50
kayu Klas II atau III

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 m2 228,987.00 238,705.50
Klas II atau III

Pemasangan Listplank Uk. (3x20)cm Kayu klas I


21 A.4.6.1.21 m' 379,555.00 395,092.50
atau II

Pemasangan Listplank Uk. (3x30)cm Kayu klas I


22 A.4.6.1.22 m' 151,250.00 156,090.00
atau klas II

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 m2 353,749.00 367,218.50
Kayu klas II atau III

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 m2 422,939.00 459,948.50
Rangka Kayu Klas II

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 m2 432,795.00 470,222.50
Rangka Kayu Klas II

Pemasangan Dinding Lambriziring dari Papan Kelas


26 A.4.6.1.26 m2 587,235.00 624,030.00
I

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 m2 44,935.00 48,367.00
ukuran (120x240) cm

Pemasangan Dinding Bilik, Rangka Kayu Klas III


28 A.4.6.1.28 m2 140,490.24 159,775.00
atau IV

HARGA SATUAN PEKERJAAN KUNCI dan


XII A.4.6.2
KACA

1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa Buah 220,660.00 270,462.50

2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi Buah 180,455.00 246,606.25

3 A.4.6.2.4 Pemasangan Kunci Selinder Buah 218,955.00 268,606.25

4 A.4.6.2.5 Pemasangan Engsel Pintu Buah 35,640.00 39,393.75

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu Buah 23,210.00 26,262.50


6 A.4.6.2.7 Pemasangan Engsel Angin Buah 62,001.50 80,929.75

7 A.4.6.2.9 Pemasangan Kait Angin Buah 46,711.50 51,573.50

8 A.4.6.2.10 Pasang Door Closer Buah 390,582.50 479,723.75

9 A.4.6.2.11 Pemasangan Kunci Selot Buah 44,033.00 48,889.50

10 A.4.6.2.13 Pemasangan Door Stop Buah 320,116.50 403,944.75

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong Buah 325,699.00 372,168.50

12 A.4.6.2.15 Pemasangan Kunci Lemari Buah 57,798.40 63,869.85

13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm m2 132,904.75 143,367.13

14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m2 147,424.75 155,467.13


15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm m2 359,174.75 421,667.13

500669137.xls 125/26 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
HARGA SATUAN PEKERJAAN
XIII A.4.7.1
PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 m2 18,469.00 20,278.50
Lama

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 m2 18,441.50 20,278.50
dicat

Pengerokan Karat Cat Lama permukaan Baja dg


3 A.4.7.1.3 m2 19,156.50 21,076.00
cara manual

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


4 A.4.7.1.4 m2 50,182.00 54,048.50
Cat dasar, 2 Lp Cat Penutup)

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


5 A.4.7.1.5 m2 70,862.00 76,059.50
Cat dasar, 3 Lp Cat Penutup)

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 40,342.50 42,614.00


7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 62,766.00 69,516.70

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 13,563.00 14,906.38

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis m2 51,084.00 56,853.50

Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar


10 A.4.7.1.10 m2 23,712.70 27,388.90
2 Lap.Cat Penutup)

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 m2 16,684.80 19,015.70
Penutup)

12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium m2 11,041.80 11,962.50

13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih m2 20,222.40 22,244.75

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 m2 8,789.00 9,831.25
(pemeliharaan)

15 A.4.7.1.15 Pemasangan Wallpaper m2 93,747.50 105,228.75

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 36,030.50 39,833.75

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 m2 71,115.00 78,223.75
Perancah

HARGA SATUAN PEKERJAAN SANITASI


XIV A.5.1.1
DALAM GEDUNG

1 A.5.1.1.1 Pemasangan Closet Duduk / Mono Blok Unit 2,433,134.00 2,775,685.00

2 A.5.1.1.2 Pemasangan Closet Jongkok Porselen Unit 762,630.00 826,760.00

3 A.5.1.1.4 Pemasangan Urinoir Unit 805,200.00 866,690.00

4 A.5.1.1.5 Pemasangan Wastafel Unit 637,532.50 692,367.50

5 A.5.1.1.6 Pemasangan Bathcuip porselen Unit 1,122,016.50 1,197,966.00


6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3 Unit 1,489,950.00 1,618,650.00

7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,810,919.27 1,974,643.54

8 A.5.1.1.11 Pemasangan Bak Beton Bertulang Vol. 1 m3 Unit 6,916,390.02 7,900,488.06

9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 357,280.00 399,987.50

10 A.5.1.1.14 Pemasangan Floor Drain buah 56,760.00 66,412.50

500669137.xls 125/27 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Bak Kontrol Pas.Batu Bata 30x30
11 A.5.1.1.15 bh 528,033.00 579,694.50
tinggi 35 cm

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 bh 782,364.00 855,767.00
tinggi 50 cm

Pemasangan Bak Kontrol Pas.Batu Bata 60x60


13 A.5.1.1.17 bh 903,804.00 994,774.00
tinggi 60 cm

14 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½" m' 68,894.83 72,444.17

15 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 97,691.00 121,974.88


16 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾" m' 80,261.50 83,810.83

17 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1" m' 111,519.83 116,490.00

18 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ " m' 150,674.33 156,964.50

19 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3" m' 263,831.33 271,569.83

20 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4" m' 467,010.50 473,470.25

21 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½" m' 26,213.00 28,646.75

22 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾" m' 28,770.50 30,991.13

23 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1" m' 35,164.25 38,876.75

24 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½" m' 38,467.00 43,041.17


25 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2" m' 45,571.17 52,987.00

26 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3" m' 78,941.50 87,215.33

27 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4" m' 91,003.00 94,999.67

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


28 A.5.1.1.33 m' 85,481.00 94,204.00
20 cm

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


29 A.5.1.1.34 m' 41,327.00 46,997.50
15 cm

30 A.5.1.1.35 Pemasangan Pipa Beton Ø 15 - 20 cm m' 122,955.80 138,340.40

31 A.5.1.1.36 Pemasangan Pipa Beton Ø 30 - 100 cm m' 565,328.50 616,038.50

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 Pemasangan Lampu Titik 412,280.00 431,508.00

2 A.8.4.6.2 Pemasangan MCB buah 505,340.00 536,448.00

HARGA SATUAN PEKERJAAN


XVI A.8.4.1
PEMASANGAN PIPA

1 A.8.4.1.1 Pemasangan Pipa PVC Ø 63 mm m' 18,049.35 20,505.65

2 A.8.4.1.2 Pemasangan Pipa PVC Ø 90 mm m' 27,461.50 30,553.60

3 A.8.4.1.3 Pemasangan Pipa PVC Ø 110 mm m' 31,856.00 37,922.50

4 A.8.4.1.4 Pemasangan Pipa PVC Ø 150 mm m' 36,888.50 45,109.90

5 A.8.4.1.5 Pemasangan Pipa PVC Ø 200 mm m' 55,418.00 71,283.30

6 A.8.4.1.6 Pemasangan Pipa PVC Ø 250 mm m' 74,668.00 108,270.80

7 A.8.4.1.7 Pemasangan Pipa PVC Ø 300 mm m' 109,873.50 142,791.00

500669137.xls 125/28 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
8 A.8.4.1.8 Pemasangan Pipa PVC Ø 400 mm m' 208,076.00 273,119.00

9 A.8.4.1.9 Pemasangan Pipa PVC Ø 450 mm m' 385,198.00 438,817.50

10 A.8.4.1.10 Pemasangan Pipa PVC Ø 500 mm m' 474,507.00 494,965.90

11 A.8.4.1.11 Pemasangan Pipa PVC Ø 600 mm m' 554,042.50 593,708.50

12 A.8.4.1.12 Pemasangan Pipa PVC Ø 800 mm m' 800,431.50 857,851.50

13 A.8.4.1.13 Pemasangan Pipa PVC Ø 900 mm m' 1,035,490.50 1,094,262.40

14 A.8.4.1.14 Pemasangan Pipa PVC Ø 1.000 mm m' 1,193,054.50 1,250,109.30

15 A.8.4.1.15 Pemasangan Pipa PVC Ø 1.100 mm m' 1,311,986.50 1,405,809.90

16 A.8.4.1.16 Pemasangan Pipa PVC Ø 1.200 mm m' 1,408,907.50 1,506,497.30

17 A.8.4.1.17 Pemasangan Pipa HDPE Ø 63 mm m' 34,705.00 40,868.30

18 A.8.4.1.18 Pemasangan Pipa HDPE Ø 100 mm m' 46,871.00 53,138.80

19 A.8.4.1.19 Pemasangan Pipa HDPE Ø 125 mm m' 59,037.00 65,409.30

20 A.8.4.1.20 Pemasangan Pipa HDPE Ø 150 mm m' 84,331.50 90,995.30

21 A.8.4.1.21 Pemasangan Pipa HDPE Ø 200 mm m' 141,993.50 154,883.30

22 A.8.4.1.22 Pemasangan Pipa HDPE Ø 250 mm m' 176,132.00 184,138.90

23 A.8.4.1.23 Pemasangan Pipa HDPE Ø 300 mm m' 211,403.50 225,632.00

24 A.8.4.1.24 Pemasangan Pipa HDPE Ø 400 mm m' 280,846.50 297,444.40

25 A.8.4.1.25 Pemasangan Pipa HDPE Ø 450 mm m' 339,542.50 357,505.50

26 A.8.4.1.26 Pemasangan Pipa HDPE Ø 500 mm m' 420,997.50 451,398.20

27 A.8.4.1.27 Pemasangan Pipa HDPE Ø 600 mm m' 580,822.00 612,786.90

28 A.8.4.1.28 Pemasangan Pipa HDPE Ø 800 mm m' 903,402.50 948,360.60

29 A.8.4.1.29 Pemasangan Pipa HDPE Ø 900 mm m' 1,110,824.00 1,192,324.10

30 A.8.4.1.30 Pemasangan Pipa HDPE Ø 1.000 mm m' 1,340,630.50 1,400,653.10

31 A.8.4.1.31 Pemasangan Pipa HDPE Ø 1.100 mm m' 1,484,246.50 1,574,897.50

32 A.8.4.1.32 Pemasangan Pipa HDPE Ø 1.200 mm m' 1,711,022.50 1,812,522.80

33 A.8.4.1.33 Pemasangan Pipa GIP Ø 63 mm m' 86,751.50 95,749.50

34 A.8.4.1.34 Pemasangan Pipa GIP Ø 100 mm m' 102,703.33 116,380.00

35 A.8.4.1.35 Pemasangan Pipa GIP Ø 125 mm m' 116,193.00 132,577.50

36 A.8.4.1.36 Pemasangan Pipa GIP Ø 150 mm m' 134,473.17 152,830.33

37 A.8.4.1.37 Pemasangan Pipa GIP Ø 200 mm m' 203,731.00 230,101.67

38 A.8.4.1.38 Pemasangan Pipa GIP Ø 250 mm m' 243,232.00 275,130.17

39 A.8.4.1.39 Pemasangan Pipa GIP Ø 300 mm m' 272,508.50 302,732.83

40 A.8.4.1.40 Pemasangan Pipa GIP Ø 400 mm m' 349,946.67 375,607.83

41 A.8.4.1.41 Pemasangan Pipa GIP Ø 450 mm m' 396,962.50 432,509.00

42 A.8.4.1.42 Pemasangan Pipa GIP Ø 500 mm m' 453,838.00 491,507.50

43 A.8.4.1.43 Pemasangan Pipa GIP Ø 600 mm m' 446,891.50 481,987.00

500669137.xls 125/29 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
44 A.8.4.1.44 Pemasangan Pipa GIP Ø 800 mm m' 694,793.00 748,027.50

45 A.8.4.1.45 Pemasangan Pipa GIP Ø 900 mm m' 788,254.50 857,862.50

46 A.8.4.1.46 Pemasangan Pipa GIP Ø 1.000 mm m' 880,049.50 943,888.00

47 A.8.4.1.47 Pemasangan Pipa GIP Ø 1.100 mm m' 960,960.00 1,030,040.00

48 A.8.4.1.48 Pemasangan Pipa GIP Ø 1.200 mm m' 1,052,755.00 1,127,065.50

49 A.8.4.1.49 Pemasangan Pipa DCI Ø 100 mm m' 105,957.50 118,806.60

50 A.8.4.1.50 Pemasangan Pipa DCI Ø 125 mm m' 131,648.00 145,355.10

51 A.8.4.1.51 Pemasangan Pipa DCI Ø 150 mm m' 164,208.00 184,394.10

52 A.8.4.1.52 Pemasangan Pipa DCI Ø 200 mm m' 224,719.00 248,491.10

53 A.8.4.1.53 Pemasangan Pipa DCI Ø 250 mm m' 262,190.50 287,419.00

54 A.8.4.1.54 Pemasangan Pipa DCI Ø 300 mm m' 287,991.00 313,595.70

55 A.8.4.1.55 Pemasangan Pipa DCI Ø 400 mm m' 436,287.50 471,951.70

56 A.8.4.1.56 Pemasangan Pipa DCI Ø 450 mm m' 512,154.50 547,181.80

57 A.8.4.1.57 Pemasangan Pipa DCI Ø 500 mm m' 582,098.00 626,967.00

58 A.8.4.1.58 Pemasangan Pipa DCI Ø 600 mm m' 641,360.50 704,042.90

59 A.8.4.1.59 Pemasangan Pipa DCI Ø 800 mm m' 1,009,827.50 1,092,729.00

60 A.8.4.1.60 Pemasangan Pipa DCI Ø 900 mm m' 1,211,974.50 1,313,483.60

61 A.8.4.1.61 Pemasangan Pipa DCI Ø 1.000 mm m' 1,451,136.50 1,566,214.10

62 A.8.4.1.62 Pemasangan Pipa DCI Ø 1.100 mm m' 1,635,661.50 1,775,447.30

63 A.8.4.1.63 Pemasangan Pipa DCI Ø 1.200 mm m' 1,862,437.50 2,020,590.00

64 A.8.4.1.64 Pemasangan Baja PVC Ø 63 mm m' 92,878.50 101,401.30

65 A.8.4.1.65 Pemasangan Pipa Baja Ø 100 mm m' 106,188.50 117,549.30

66 A.8.4.1.66 Pemasangan Pipa Baja Ø 125 mm m' 119,988.00 131,827.30

67 A.8.4.1.67 Pemasangan Pipa Baja Ø 150 mm m' 135,058.00 151,088.30

68 A.8.4.1.68 Pemasangan Pipa Baja Ø 200 mm m' 210,584.00 232,620.30

69 A.8.4.1.69 Pemasangan Pipa Baja Ø 250 mm m' 266,453.00 297,146.30

70 A.8.4.1.70 Pemasangan Pipa Baja Ø 300 mm m' 302,665.00 329,178.30

71 A.8.4.1.71 Pemasangan Pipa Baja Ø 400 mm m' 459,382.00 498,242.80

72 A.8.4.1.72 Pemasangan Pipa Baja Ø 450 mm m' 475,502.50 519,853.40

73 A.8.4.1.73 Pemasangan Pipa Baja Ø 500 mm m' 536,178.50 600,044.50

74 A.8.4.1.74 Pemasangan Pipa Baja Ø 600 mm m' 560,345.50 615,376.30

75 A.8.4.1.75 Pemasangan Pipa Baja Ø 800 mm m' 914,078.00 999,917.60

76 A.8.4.1.76 Pemasangan Pipa Baja Ø 900 mm m' 1,041,606.50 1,128,748.50

77 A.8.4.1.77 Pemasangan Pipa Baja Ø 1.000 mm m' 1,187,879.00 1,288,673.10

78 A.8.4.1.78 Pemasangan Pipa Baja Ø 1.100 mm m' 1,323,740.00 1,431,919.50

79 A.8.4.1.79 Pemasangan Pipa Baja Ø 1.200 mm m' 1,461,685.50 1,577,442.90

500669137.xls 125/30 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp

HARGA SATUAN PEKERJAAN


XVII A.8.4.2
PEMOTONGAN PIPA

1 A.8.4.2.1 Pemotongan Pipa PVC Ø 63 mm bh 972.40 1,064.25

2 A.8.4.2.2 Pemotongan Pipa PVC Ø 90 mm bh 2,825.90 3,080.00

3 A.8.4.2.3 Pemotongan Pipa PVC Ø 110 mm bh 4,486.90 4,889.50

4 A.8.4.2.4 Pemotongan Pipa PVC Ø 150 mm bh 6,263.40 6,825.50

5 A.8.4.2.5 Pemotongan Pipa PVC Ø 200 mm bh 16,589.10 18,089.50

6 A.8.4.2.6 Pemotongan Pipa PVC Ø 250 mm bh 26,411.00 28,803.50

7 A.8.4.2.7 Pemotongan Pipa PVC Ø 300 mm bh 31,807.60 34,688.50

8 A.8.4.2.8 Pemotongan Pipa PVC Ø 400 mm bh 68,357.30 74,558.00

9 A.8.4.2.9 Pemotongan Pipa PVC Ø 450 mm bh 87,186.00 95,106.00

10 A.8.4.2.10 Pemotongan Pipa PVC Ø 500 mm bh 107,624.00 117,408.50

11 A.8.4.2.11 Pemotongan Pipa PVC Ø 600 mm bh 129,371.00 141,141.00

12 A.8.4.2.12 Pemasangan Pipa PVC Ø 800 mm bh 226,699.00 247,351.50

13 A.8.4.2.13 Pemotongan Pipa PVC Ø 900 mm bh 237,501.00 259,138.00

14 A.8.4.2.14 Pemotongan Pipa PVC Ø 1.000 mm bh 267,602.50 291,989.50

15 A.8.4.2.15 Pemotongan Pipa PVC Ø 1.100 mm bh 297,533.50 324,648.50

16 A.8.4.2.16 Pemotongan Pipa PVC Ø 1.200 mm bh 327,492.00 357,340.50

17 A.8.4.2.17 Pemotongan Pipa HDPE Ø 63 mm bh 4,258.10 4,690.40

18 A.8.4.2.18 Pemotongan Pipa HDPE Ø 100 mm bh 9,229.00 10,153.00

19 A.8.4.2.19 Pemotongan Pipa HDPE Ø 125 mm bh 12,650.00 13,909.50

20 A.8.4.2.20 Pemotongan Pipa HDPE Ø 150 mm bh 16,879.50 18,557.00

21 A.8.4.2.21 Pemotongan Pipa HDPE Ø 200 mm bh 28,198.50 30,965.00

22 A.8.4.2.22 Pemotongan Pipa HDPE Ø 250 mm bh 38,582.50 42,355.50

23 A.8.4.2.23 Pemotongan Pipa HDPE Ø 300 mm bh 48,999.50 53,779.00

24 A.8.4.2.24 Pemotongan Pipa HDPE Ø 400 mm bh 78,408.00 86,003.50

25 A.8.4.2.25 Pemotongan Pipa HDPE Ø 450 mm bh 94,292.00 103,405.50

26 A.8.4.2.26 Pemotongan Pipa HDPE Ø 500 mm bh 105,011.50 115,148.00

27 A.8.4.2.27 Pemotongan Pipa HDPE Ø 600 mm bh 133,567.50 146,448.50

28 A.8.4.2.28 Pemotongan Pipa HDPE Ø 800 mm bh 212,426.50 232,804.00

29 A.8.4.2.29 Pemotongan Pipa HDPE Ø 900 mm bh 289,415.50 317,042.00

30 A.8.4.2.30 Pemotongan Pipa HDPE Ø 1.000 mm bh 345,350.50 378,262.50

31 A.8.4.2.31 Pemotongan Pipa HDPE Ø 1.100 mm bh 380,490.00 416,751.50

32 A.8.4.2.32 Pemotongan Pipa HDPE Ø 1.200 mm bh 472,224.50 517,110.00

33 A.8.4.2.33 Pemotongan Pipa GIP Ø 63 mm bh 3,965.50 4,317.50

34 A.8.4.2.34 Pemotongan Pipa GIP Ø 100 mm bh 11,863.50 12,919.50

500669137.xls 125/31 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
35 A.8.4.2.35 Pemotongan Pipa GIP Ø 125 mm bh 18,744.00 20,410.50

36 A.8.4.2.36 Pemotongan Pipa GIP Ø 150 mm bh 26,790.50 29,172.00

37 A.8.4.2.37 Pemotongan Pipa GIP Ø 200 mm bh 69,377.00 75,548.00

38 A.8.4.2.38 Pemotongan Pipa GIP Ø 250 mm bh 96,778.00 105,385.50

39 A.8.4.2.39 Pemotongan Pipa GIP Ø 300 mm bh 102,784.00 111,925.00

40 A.8.4.2.40 Pemotongan Pipa GIP Ø 400 mm bh 150,617.50 164,015.50

41 A.8.4.2.41 Pemotongan Pipa GIP Ø 450 mm bh 173,063.00 188,457.50

42 A.8.4.2.42 Pemotongan Pipa GIP Ø 500 mm bh 176,242.00 191,917.00

43 A.8.4.2.43 Pemotongan Pipa GIP Ø 600 mm bh 192,071.00 209,154.00

44 A.8.4.2.44 Pemotongan Pipa GIP Ø 800 mm bh 319,715.00 348,155.50

45 A.8.4.2.45 Pemotongan Pipa GIP Ø 900 mm bh 361,168.50 393,294.00

46 A.8.4.2.46 Pemotongan Pipa GIP Ø 1.000 mm bh 402,737.50 438,559.00

47 A.8.4.2.47 Pemotongan Pipa GIP Ø 1.100 mm bh 444,163.50 483,664.50

48 A.8.4.2.48 Pemotongan Pipa GIP Ø 1.200 mm bh 486,018.50 529,248.50

49 A.8.4.2.49 Pemotongan Pipa DCI Ø 100 mm bh 11,313.50 12,370.60

50 A.8.4.2.50 Pemotongan Pipa DCI Ø 125 mm bh 17,886.00 19,563.50

51 A.8.4.2.51 Pemotongan Pipa DCI Ø 150 mm bh 25,602.50 28,007.10

52 A.8.4.2.52 Pemotongan Pipa DCI Ø 200 mm bh 58,998.50 64,556.80

53 A.8.4.2.53 Pemotongan Pipa DCI Ø 250 mm bh 76,752.50 83,986.10

54 A.8.4.2.54 Pemotongan Pipa DCI Ø 300 mm bh 82,445.00 90,214.30

55 A.8.4.2.55 Pemotongan Pipa DCI Ø 400 mm bh 151,783.50 166,101.10

56 A.8.4.2.56 Pemotongan Pipa DCI Ø 450 mm bh 183,271.00 200,543.20

57 A.8.4.2.57 Pemotongan Pipa DCI Ø 500 mm bh 211,288.00 231,185.90

58 A.8.4.2.58 Pemotongan Pipa DCI Ø 600 mm bh 211,288.00 231,185.90

59 A.8.4.2.59 Pemotongan Pipa DCI Ø 800 mm bh 417,879.00 457,149.00

60 A.8.4.2.60 Pemotongan Pipa DCI Ø 900 mm bh 541,706.00 592,588.70

61 A.8.4.2.61 Pemotongan Pipa DCI Ø 1.000 mm bh 646,156.50 706,834.70

62 A.8.4.2.62 Pemotongan Pipa DCI Ø 1.100 mm bh 760,116.50 831,481.20

63 A.8.4.2.63 Pemotongan Pipa DCI Ø 1.200 mm bh 883,817.00 966,781.20

64 A.8.4.2.64 Pemotongan pipa Baja Ø 63 mm bh 5,775.00 6,402.00

65 A.8.4.2.65 Pemotongan Pipa Baja Ø 100 mm bh 14,806.00 16,280.00

66 A.8.4.2.66 Pemotongan Pipa Baja Ø 125 mm bh 22,616.00 24,821.50

67 A.8.4.2.67 Pemotongan Pipa Baja Ø 150 mm bh 30,805.50 33,781.00

68 A.8.4.2.68 Pemotongan Pipa Baja Ø 200 mm bh 77,929.50 85,332.50

69 A.8.4.2.69 Pemotongan Pipa Baja Ø 250 mm bh 108,009.00 118,228.00

70 A.8.4.2.70 Pemotongan Pipa Baja Ø 300 mm bh 121,132.00 132,583.00

500669137.xls 125/32 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
71 A.8.4.2.71 Pemotongan Pipa Baja Ø 400 mm bh 233,145.00 255,106.50

72 A.8.4.2.72 Pemotongan Pipa Baja Ø 450 mm bh 219,785.50 240,493.00

73 A.8.4.2.73 Pemotongan Pipa Baja Ø 500 mm bh 236,874.00 259,198.50

74 A.8.4.2.74 Pemotongan Pipa Baja Ø 600 mm bh 252,318.00 276,083.50

75 A.8.4.2.75 Pemotongan Pipa Baja Ø 800 mm bh 423,978.50 463,853.50

76 A.8.4.2.76 Pemotongan Pipa Baja Ø 900 mm bh 479,869.50 524,991.50

77 A.8.4.2.77 Pemotongan Pipa Baja Ø 1.000 mm bh 536,057.50 586,454.00

78 A.8.4.2.78 Pemotongan Pipa Baja Ø 1.100 mm bh 592,064.00 647,718.50

79 A.8.4.2.79 Pemotongan Pipa Baja Ø 1.200 mm bh 648,252.00 709,181.00

HARGA SATUAN PEKERJAAN


XVIII A.8.4.3
PEMASANGAN AKSESORIS PIPA

1 A.8.4.3.1 Pemasangan Valve Ø 150 mm bh 347,776.00 390,439.50

2 A.8.4.3.2 Pemasangan Valve Ø 200 mm bh 435,484.50 483,747.00

3 A.8.4.3.3 Pemasangan Valve Ø 250 mm bh 491,584.50 534,567.00

4 A.8.4.3.4 Pemasangan Valve Ø 300 mm bh 578,600.00 638,000.00

5 A.8.4.3.5 Pemasangan Valve Ø 400 mm bh 1,013,276.00 1,105,219.50

6 A.8.4.3.6 Pemasangan Valve Ø 450 mm bh 1,068,276.00 1,160,219.50

7 A.8.4.3.7 Pemasangan Valve Ø 500 mm bh 1,239,700.00 1,342,000.00

8 A.8.4.3.8 Pemasangan Valve Ø 600 mm bh 813,615.00 874,830.00

9 A.8.4.3.9 Pemasangan Valve Ø 700 mm bh 929,676.00 989,719.50

10 A.8.4.3.10 Pemasangan Valve Ø 800 mm bh 1,057,490.50 1,129,513.00

11 A.8.4.3.11 Pemasangan Valve Ø 900 mm bh 1,141,684.50 1,218,437.00

12 A.8.4.3.12 Pemasangan Valve Ø 1.000 mm bh 1,415,672.50 1,497,540.00

13 A.8.4.3.13 Pemasangan Valve Ø 1.100 mm bh 1,558,150.00 1,647,800.00

14 A.8.4.3.14 Pemasangan Valve Ø 1.200 mm bh 1,591,150.00 1,691,800.00

15 A.8.4.3.15 Pemasangan Tee Ø 150 mm bh 35,194.50 40,486.60

16 A.8.4.3.16 Pemasangan Tee Ø 200 mm bh 60,951.00 70,441.80

17 A.8.4.3.17 Pemasangan Tee Ø 250 mm bh 94,506.50 106,015.80

18 A.8.4.3.18 Pemasangan Tee Ø 300 mm bh 133,023.00 147,543.00

19 A.8.4.3.19 Pemasangan Tee Ø 400 mm bh 188,914.00 207,427.00

20 A.8.4.3.20 Pemasangan Tee Ø 450 mm bh 233,359.50 253,869.00

21 A.8.4.3.21 Pemasangan Tee Ø 500 mm bh 267,905.00 290,631.00

22 A.8.4.3.22 Pemasangan Tee Ø 600 mm bh 340,659.00 374,094.60

23 A.8.4.3.23 Pemasangan Tee Ø 700 mm bh 410,707.00 443,080.00

24 A.8.4.3.24 Pemasangan Tee Ø 800 mm bh 469,590.00 511,878.40

25 A.8.4.3.25 Pemasangan Tee Ø 900 mm bh 542,465.00 589,591.20

500669137.xls 125/33 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
26 A.8.4.3.26 Pemasangan Tee Ø 1.000 mm bh 613,481.00 665,183.20

27 A.8.4.3.27 Pemasangan Tee Ø 1.100 mm bh 682,242.00 738,201.20

28 A.8.4.3.28 Pemasangan Tee Ø 1.200 mm bh 755,117.00 815,914.00

HARGA SATUAN PEKERJAAN


XIX A.8.4.4
PENYAMBUNGAN PIPA BARU KE PIPA LAMA

Penyambungan Pipa Baru ke Pipa yang ada Ø 80


1 A.8.4.4.1 bh 525,849.50 602,470.00
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


2 A.8.4.4.2 bh 560,961.50 694,883.20
100 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


3 A.8.4.4.3 bh 802,686.50 972,666.20
150 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


4 A.8.4.4.4 bh 1,011,411.50 1,228,449.20
200 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


5 A.8.4.4.5 bh 1,192,636.50 1,440,232.20
250 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


6 A.8.4.4.6 bh 1,362,861.50 1,641,015.20
300 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


7 A.8.4.4.7 bh 1,703,311.50 2,053,581.20
400 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


8 A.8.4.4.8 bh 1,879,036.50 2,265,364.20
450 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


9 A.8.4.4.9 bh 2,065,761.50 2,488,147.20
500 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


10 A.8.4.4.10 bh 2,406,211.50 2,900,713.20
600 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


11 A.8.4.4.11 bh 2,779,661.50 3,346,279.20
700 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


12 A.8.4.4.11 bh 3,109,111.50 3,758,845.20
800 mm

HARGA SATUAN PEKERJAAN


XX A.8.4.5
PENGETESAN
1 A.8.4.5.1 Pengetesan Pipa Ø 50 mm m' 1,583.23 1,714.24

2 A.8.4.5.2 Pengetesan Pipa Ø 75 mm m' 1,583.56 1,714.68

3 A.8.4.5.3 Pengetesan Pipa Ø 100 mm m' 1,584.22 1,715.56

4 A.8.4.5.4 Pengetesan Pipa Ø 150 mm m' 1,585.87 1,717.76

5 A.8.4.5.5 Pengetesan Pipa Ø 200 mm m' 1,588.02 1,720.62

6 A.8.4.5.6 Pengetesan Pipa Ø 250 mm m' 1,590.99 1,724.58

7 A.8.4.5.7 Pengetesan Pipa Ø 300 mm m' 1,594.62 1,729.42

8 A.8.4.5.8 Pengetesan Pipa Ø 400 mm m' 1,603.69 1,741.52

9 A.8.4.5.9 Pengetesan Pipa Ø 500 mm m' 1,608.97 1,748.56

10 A.8.4.5.10 Pengetesan Pipa Ø 600 mm m' 1,629.60 1,776.06

500669137.xls 125/34 hspk ok


DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016

SUMBER DATA : PASARAN BEBAS EDISI 03 2020


DAERAH : KOTA SEMARANG DAN SEKITAR

HARGA SATUAN PEKERJAAN


NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi 2,00
1 A.2.2.1.2 m' 717,172.50 767,849.50
m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 179,509.00 188,952.50

3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran m2 2,334,519.00 2,493,315.00

4 A.2.2.1.6 Pembuatan Rumah Jaga (Konstruksi Kayu) m2 1,818,960.00 1,930,225.00

5 A.2.2.1.7 Pembuatan Gudang Semen dan Peralatan m2 1,673,732.50 1,766,077.50

6 A.2.2.1.8 Pembuatan Bedeng Pekerja m2 2,064,425.00 2,205,390.00

7 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 18,700.00 20,625.00

8 A.2.2.1.10 Pembuatan Steger/Perancah dari Bambu m2 474,111.00 518,795.20


Pembuatan Kotak Adukan ukuran
9 A.2.2.1.11 bh 640,706.00 672,100.00
40cmx50cmx25cm
10 A.2.2.1.12 Pembuatan Jalan Sementara m2 189,255.00 218,817.50

11 A.2.2.1.13 Bongkaran Beton Bertulang m3 1,635,315.00 1,792,978.00

12 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah m3 774,757.50 848,639.00

13 A.2.2.1.15 Pagar Kawat Jaring Galvanis Panjang 240 cm m2 60,658.40 64,245.50


Pemasangan Pagar Panel Beton Pracetak 5 x 50 x
14 A.2.2.1.16 m2 327,387.50 359,169.25
240 cm

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 90,200.00 98,862.50

2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m m3 110,385.00 121,027.50

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m m3 130,856.00 143,511.50

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m m3 120,076.00 131,604.00

5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m m3 181,830.00 199,320.00

6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m m3 145,035.00 158,977.50

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m m2 6,490.00 7,122.50

8 A.2.3.1.8 MembuangTanah sejauh 30 m' m3 39,545.00 43,340.00


Pengurugan Kembali di hitung dari 1/3 kali koefisien
9 A.2.3.1.9 m3 21,633.33 23,741.67
Pekerjaan galian
10 A.2.3.1.10 Pemadatan Tanah (per 20 cm) m3 64,900.00 71,225.00

11 A.2.3.1.11 Urugan Pasir m3 247,280.00 329,945.00

12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL m3 472,571.00 532,125.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 m2 28,710.00 31,135.50
Resapan

14 A.2.3.1.14 Mengurug Sirtu Padat m3 270,050.00 299,612.50

500669137.xls 125/35 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP m3 1,084,215.00 1,246,547.50

2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP m3 1,046,815.00 1,209,312.50

3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 1,020,844.00 1,183,440.50

4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 1,002,606.00 1,165,279.50


5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP m3 977,559.00 1,140,320.50

6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 872,740.00 1,016,262.50
Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 956,747.00 1,113,403.50
PP
Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4
8 A.3.2.1.8 m3 936,738.00 1,094,164.50
PP
9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 592,020.00 726,874.50

Pasang Pondasi Siklop, 60% Beton Campuran


10 A.3.2.1.10 m3 2,617,571.00 3,004,573.00
1PC : 2PB : 3KR & 40% Batu Belah

11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm m3 1,029,193.00 1,150,308.50

IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum


1 A.4.1.1.1 m3 1,057,405.64 1,167,763.14
(12±2)cm, w/c = 0,87

Membuat Beton mutu f'c=9,8 Mpa (K125), slum


2 A.4.1.1.2 m3 1,086,527.42 1,197,987.97
(12±2)cm, w/c = 0,78

Membuat Beton mutu f'c=12,2 Mpa (K150), slum


3 A.4.1.1.3 m3 1,109,178.98 1,221,351.48
(12±2)cm, w/c = 0,72

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa


4 A.4.1.1.4 m3 973,927.31 1,078,162.70
(K100), slum (3-6)cm, w/c = 0,87

Membuat Beton mutu f'c=14,5 MPa (K175), slum


5 A.4.1.1.5 m3 1,136,044.29 1,249,215.96
(12±2)cm, w/c = 0,66

Membuat Beton mutu f'c=16,9 MPa (K200), slum


6 A.4.1.1.6 m3 1,161,708.63 1,275,610.58
(12±2)cm, w/c = 0,61

Membuat Beton mutu f'c=19,3 MPa (K225), slum


7 A.4.1.1.7 m3 1,181,099.77 1,295,921.44
(12±2)cm, w/c = 0,58

Membuat Beton mutu f'c=21,7 MPa (K250), slum


8 A.4.1.1.8 m3 1,193,855.99 1,308,836.54
(12±2)cm, w/c = 0,56

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa


9 A.4.1.1.9 m3 1,216,159.21 1,331,494.21
(K275), slum (12±2)cm, w/c = 0,53

Membuat Beton mutu f'c=26,4 MPa (K300), slum


10 A.4.1.1.10 m3 1,222,909.08 1,338,302.14
(12±2)cm, w/c = 0,52

Membuat Beton mutu f'c=28,8 MPa (K325), slum


11 A.4.1.1.11 m3 1,316,285.90 1,438,288.12
(12±2)cm, w/c = 0,49

Membuat Beton mutu f'c=31,2 MPa (K350), slum


12 A.4.1.1.12 m3 1,325,305.03 1,447,426.42
(12±2)cm, w/c = 0,48

500669137.xls 125/36 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir Kg 14,107.50 16,371.30

14 A.4.1.1.18 Kabel Presstresed Polos/strand Kg 17,818.90 18,527.85

15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh Kg 28,859.60 30,045.95

16 A.4.1.1.20 Memasang Bekisting untuk Pondasi m2 200,992.00 219,362.00

17 A.4.1.1.21 Memasang Bekisting untuk Sloof m2 211,992.00 231,462.00


18 A.4.1.1.22 Memasang Bekisting untuk Kolom m2 428,296.00 468,583.50

19 A.4.1.1.23 Memasang Bekisting untuk Balok m2 449,746.00 491,023.50

20 A.4.1.1.24 Memasang Bekisting untuk Lantai m2 520,696.00 574,183.50

21 A.4.1.1.25 Memasang Bekisting untuk Dinding m2 487,146.00 532,383.50

22 A.4.1.1.26 Memasang Bekisting untuk Tangga m2 405,801.00 443,833.50

23 A.4.1.1.27 Memasang Jembatan Cor m2 107,514.00 117,689.00

24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 92,455.00 102,817.00

25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 120,268.50 133,848.00

HARGA SATUAN PEKERJAAN BETON


IV A A.4.1.2
PRACETAK

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c


1 A.4.1.2.1 m2 90,898.06 99,955.10
14,5 Mpa, Slump (120 ± 20) mm K3

Pembuatan Lahan Produksi Tebal 10 cm Beton f'c =


2 A.4.1.2.2 m2 113,666.58 124,986.50
14,5 Mpa slum (120 ± 20 ) mm K3

Pembuatan Lahan Produksi Tebal 12 cm Beton


3 A.4.1.2.3 m2 132,464.10 145,678.40
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Lahan Produksi Tebal 15 cm Beton


4 A.4.1.2.4 m2 170,475.12 187,460.49
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Bekisting untuk Plat Beton Pra cetak (5


5 A.4.1.2.5 m2 128,430.66 137,870.62
kali Pakai)

Pembuatan Bekisting untuk Balok Beton Pra cetak


6 A.4.1.2.6 m2 48,083.00 50,634.60
(10 - 12 kali Pakai)

Pembuatan Bekisting untuk Kolom Beton Pra cetak


7 A.4.1.2.7 m2 42,208.00 44,484.60
(10 - 12 kali Pakai)

Pemasangan dan Membuka Bekisting untuk


8 A.4.1.2.8 bh 8,645.00 9,430.00
Komponen Plat Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


9 A.4.1.2.9 bh 14,045.00 15,310.00
Komponen Balok Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


10 A.4.1.2.10 bh 11,345.00 12,370.00
Komponen Kolom Beton Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


11 A.4.1.2.11 m3 78,309.00 76,985.00
Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


12 A.4.1.2.12 m3 80,536.50 79,170.00
Pracetak

Penuangan / Menebar Beton untuk Komponen


13 A.4.1.2.13 m3 72,314.00 71,125.00
Kolom Pracetak

500669137.xls 125/37 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
14 A.4.1.2.14 Ereksi Komponen Untuk Plat Pracetak bh 589,086.52 614,810.46

15 A.4.1.2.15 Ereksi Komponen Untuk Balok Pracetak bh 578,569.20 603,549.10

16 A.4.1.2.16 Ereksi Komponen Untuk Kolom Pracetak bh 831,139.54 872,219.92

17 A.4.1.2.17 Langsiran Komponen untuk Plat Pracetak (± 20 m) bh 162,420.94 169,740.12

18 A.4.1.2.18 Langsiran Komponen untuk Balok Pracetak (± 20 m) bh 126,522.44 130,178.62

Langsiran Komponen untuk Kolom Pracetak (± 20


19 A.4.1.2.19 bh 126,522.44 130,178.62
m)

20 A.4.1.2.20 Bahan Grout Campuran m3 3,417,700.00 3,689,125.00

21 A.4.1.2.21 Bahan Grout Campuran (tidak Campuran) m3 3,061,300.00 3,368,750.00

22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 71,186.50 76,648.00

23 A.4.1.2.23 Pemasangan Bekisting Joint Pra Cetak ttk 142,249.80 152,036.50

24 A.4.1.2.24 Upah Pemasangan Joint dengan Sling ttk 62,920.00 68,183.50

HARGA SATUAN PEKERJAAN BESI &


V A.4.2.1
ALLUMUNIUM
1 A.4.2.1.1 Pemasangan Besi Profil Kg 35,535.50 37,287.25

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF Kg 29,590.00 31,152.00

3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) kg 106,359.00 123,172.50

Pembuatan Pintu Besi Plat Baja tebal 2 mm


4 A.4.2.1.4 m2 971,201.00 1,007,534.00
rangkap, rangka baja Siku

5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 2,550.24 2,951.08

6 A.4.2.1.6 Pembuatan Rangka Jendela Besi Scuare Tube m2 283,393.88 315,478.46

7 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi m2 693,638.00 732,457.00


8 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door) m2 566,082.00 604,109.00

9 A.4.2.1.9 Pemasangan Sunscreen Allumunium m2 525,932.00 591,558.00

10 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 589,050.00 629,475.00

11 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium m' 132,214.50 140,062.45

12 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 556,419.60 590,682.40

13 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium m2 523,941.00 558,112.50

14 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds m2 204,864.00 218,746.00

15 A.4.2.1.15 Pemasangan Teralis Besi Strip (2x3) cm m2 649,559.35 703,144.75


16 A.4.2.1.16 Pemasangan Kawat Nyamuk m2 110,447.88 124,260.95

17 A.4.2.1.17 Pemasangan Jendela Nako & Tralis m2 148,423.00 160,429.50

Pemasangan Talang Datar / Jurai , Seng BJLS 28


18 A.4.2.1.18 m' 220,060.50 242,536.25
Lebar 90 cm

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


19 A.4.2.1.20 m2 133,309.00 143,148.50
Modul 60x120 cm dinding partisi

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


20 A.4.2.1.21 m2 170,764.00 183,546.00
Modul 60x60 cm dinding plafond

500669137.xls 125/38 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Atap Pelana Rangka Atap Baja Canal
21 A.4.2.1.22 m2 273,861.78 292,519.01
C dingin Profil C75

Pemasangan Atap Jurai Rangka Atap Baja Canal


22 A.4.2.1.23 m2 301,860.35 321,500.03
Dingin Profil C75

HARGA SATUAN PEKERJAAN PASANGAN


VI A.4.4.1
DINDING

Pemasangan Dinding Bata Merah ukuran (5x11x22)


1 A.4.4.1.1 m2 268,757.50 295,185.00
cm Tebal 1 bata Camp. 1SP: 2PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


2 A.4.4.1.2 m2 259,162.75 285,736.00
cm Tebal 1 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


3 A.4.4.1.3 m2 251,748.75 278,102.00
cm Tebal 1 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


4 A.4.4.1.4 m2 249,315.00 276,023.00
cm Tebal 1 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


5 A.4.4.1.5 m2 251,454.50 279,279.00
cm Tebal 1 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


6 A.4.4.1.6 m2 239,818.70 265,535.60
cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP

Pemasangan Dinding Bata Merah Ukuran


7 A.4.4.1.7 m2 130,154.75 143,082.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP

Pemasangan Dinding Bata Merah Ukuran


8 A.4.4.1.8 m2 125,043.05 137,850.90
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran


9 A.4.4.1.9 m2 122,435.50 135,283.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran


10 A.4.4.1.10 m2 120,815.20 133,695.10
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran


11 A.4.4.1.11 m2 120,458.80 133,527.90
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran


12 A.4.4.1.12 m2 118,497.50 131,532.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
Pemasangan Dinding Bata Merah Ukuran
13 A.4.4.1.13 (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : m2 120,917.50 134,007.50
10PP
Pemasangan Dinding Bata Merah Ukuran
14 A.4.4.1.14 m2 109,263.00 120,026.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP
Pemasangan Dinding Bata Merah Ukuran
15 A.4.4.1.15 (5x11x22)cm Tebal 1/2 Bata Camp. 1SM : 1KP : m2 110,473.00 121,852.50
2PP
Pemasangan Dinding HB/CB 20, speci camp. 1SP :
16 A.4.4.1.16 m2 412,328.40 471,997.90
3PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


17 A.4.4.1.17 m2 419,666.50 481,906.70
4PP

Pemasangan Dinding HB/CB 15, speci camp. 1SP :


18 A.4.4.1.18 m2 326,498.70 372,589.80
3PP

500669137.xls 125/39 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Dinding HB/CB 15, speci camp. 1SP :
19 A.4.4.1.19 m2 331,667.60 379,621.00
4PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


20 A.4.4.1.20 m2 256,003.00 305,422.70
3PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


21 A.4.4.1.21 m2 260,354.05 311,191.10
4PP

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 m2 376,035.00 482,707.50
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 m2 376,035.00 482,707.50
(12x11x24)cm Camp. 1SP : 4PP

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 m2 158,807.00 170,296.50
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Bata Ringan Tebal 7,5 cm


25 A.4.4.1.25 m2 350,032.54 375,287.06
dengan Mortar Siap Pakai

Pemasangan Dinding Bata Ringan Tebal 10 cm


26 A.4.4.1.26 m2 349,336.24 372,599.21
dengan Mortar Siap Pakai

VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A.4.4.2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 86,448.56 93,719.78
2 A.4.4.2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 81,133.36 88,378.18

3 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 79,059.64 86,367.82

4 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 77,457.60 84,747.30

5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 76,803.76 84,167.38

6 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 76,173.24 83,560.62

7 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 75,907.04 83,334.02

8 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 75,640.84 83,107.42

Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15


9 A.4.4.2.9 m2 76,531.40 83,448.20
mm

Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15


10 A.4.4.2.10 m2 76,087.00 83,336.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15


11 A.4.4.2.11 m2 71,841.00 78,243.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15


12 A.4.4.2.12 m2 72,787.00 79,563.00
mm

13 A.4.4.2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 108,577.48 118,292.24


14 A.4.4.2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 80,323.20 87,696.60

15 A.4.4.2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 103,562.80 113,315.40

16 A.4.4.2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 102,804.68 112,677.84

17 A.4.4.2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 101,850.32 111,733.16

500669137.xls 125/40 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20
18 A.4.4.2.18 m2 101,112.00 110,264.00
mm

19 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm m2 46,262.26 50,958.38

Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10


20 A.4.4.2.20 m' 80,437.50 87,109.00
mm

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal


21 A.4.4.2.21 m' 121,368.50 131,626.00
10 mm

Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10


22 A.4.4.2.22 m' 121,368.50 131,626.00
mm

23 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp m2 60,695.80 66,086.90

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 m2 34,770.12 37,636.06
Merah

Pemasangan Finishing Siar Pasangan Dinding


25 A.4.4.2.25 m2 16,494.50 17,847.50
Conblock ekspose

Pemasangan Finishing Siar Pas.Batu Kali Adukan


26 A.4.4.2.26 m2 73,492.10 79,995.30
1Pc : 2Pp

27 A.4.4.2.27 Pemasangan Acian m2 45,031.25 48,785.00

28 A.4.4.2.28 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) m2 53,473.20 57,396.90

29 A.4.4.2.29 Pemasangan Acian dg Mortar Siap Pakai (MSP) m2 47,355.00 51,108.75

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3 dan DINDING

Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30


1 A.4.4.3.2 m2 120,838.50 132,402.00
cm

Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20


2 A.4.4.3.3 m2 123,535.50 135,415.50
cm

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 148,471.00 171,084.50

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 151,332.50 171,473.50

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 363,610.50 412,357.00


6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm m' 72,507.60 82,954.30

7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm m' 44,804.10 48,430.80

8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 263,525.35 314,185.30

Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20


9 A.4.4.3.33 m2 269,465.35 321,610.30
cm

10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 270,976.02 306,921.63

11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 270,544.00 304,583.50

12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 270,061.00 303,121.50

Pemasangan Lantai Keramik uk.10 x 33 cm, untuk


13 A.4.4.3.37 m2 497,480.50 552,046.00
variasi / border

14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 46,146.10 50,108.30

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 93,116.10 98,618.30

500669137.xls 125/41 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 96,031.10 101,533.30

17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 731,355.35 755,263.30

18 A.4.4.3.44 Pemasangan Lantai Karpet m2 214,335.00 228,035.50

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 479,820.00 556,682.50

20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 307,256.16 337,059.32


21 A.4.4.3.49 Pemasangan Dinding Porselen 10x20 cm m2 296,642.50 349,156.50

22 A.4.4.3.50 Pemasangan Dinding Porselen 20x20 cm m2 290,570.50 336,495.50

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm m2 296,642.50 349,156.50

24 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm m2 291,780.50 338,123.50

25 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 853,827.76 887,457.04

Pemasangan Dinding Batu Paros / Batu Tempel


26 A.4.4.3.58 m2 321,268.75 354,887.50
Hitam

27 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 165,394.90 178,057.00

28 A.4.4.3.60 Pemasangan Wallpaper Lebar 50 Cm m2 135,536.50 144,776.50


29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 62,931.00 67,177.00

30 A.4.4.3.64 Pemasangan Paving Block Natural Tebal 6 Cm m2 204,906.90 228,066.85

31 A.4.4.3.65 Pemasangan Paving Block Natural Tebal 8 Cm m2 272,562.40 299,319.35

32 A.4.4.3.66 Pemasangan Paving Block Berwarna Tebal 6 Cm m2 217,127.90 240,287.85

33 A.4.4.3.67 Pemasangan Paving Block Berwarna Tebal 8 Cm m2 284,783.40 311,540.35

HARGA SATUAN PEKERJAAN LANGIT-


IX A.4.5.1
LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m,


1 A.4.5.1.1 m2 34,452.00 37,515.50
tebal 4 mm, 5 mm & 6 mm

Pemasangan Langit-langit Akustik Ukuran (30x30)


2 A.4.5.1.2 m2 111,881.00 124,019.50
cm

Pemasangan Langit-langit Akustik Ukuran (30x60)


3 A.4.5.1.3 m2 113,806.00 124,520.00
cm

Pemasangan Langit-langit Akustik Ukuran (60x120)


4 A.4.5.1.4 m2 98,890.00 107,910.00
cm

Memasang Langit-langit Tripleks Uk (120x240) cm,


5 A.4.5.1.5 m2 56,028.50 60,500.00
Tebal 3 mm, 4 mm & 6 mm

Memasang Langit-langit Lambriziring Kayu Jati,


6 A.4.5.1.6 m2 691,427.00 727,072.50
tebal 6 mm

Memasang Langit-langit Gypsu Board, Ukuran


7 A.4.5.1.7 m2 46,299.00 50,149.00
(120x240) tebal 9 mm

Memasang Langit-langit Akustik Uk (60x120) cm &


8 A.4.5.1.8 m2 269,582.50 293,012.50
Berikut Rangka Allumunium

9 A.4.5.1.9 List Langit-Langit Kayu Profil m1 20,130.00 21,571.00

500669137.xls 125/42 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
HARGA SATUAN PEKERJAAN PENUTUP
X A.4.5.2
ATAP
1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 94,011.50 104,951.00

2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur m2 147,713.50 153,158.50

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar m2 131,818.50 139,463.50

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong m' 123,673.00 133,628.00

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur m' 136,048.00 147,103.00

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar m' 139,898.00 150,183.00

7 A.4.5.2.7 Pemasangan Roof Light Fibreglass 90 x 180 m2 111,633.50 124,030.50


Pemasangan Atap Asbes Gelombang (2,50x0,92 m)
8 A.4.5.2.8 m2 71,054.50 79,106.50
x 5 mm

Pemasangan Atap Asbes Gelombang (2,25x0,92 m)


9 A.4.5.2.9 m2 72,600.00 80,976.50
x 5 mm

Pemasangan Atap Asbes Gelombang (2,00x0,92 m)


10 A.4.5.2.10 m2 72,930.00 81,636.50
x 5 mm

Pemasangan Atap Asbes Gelombang (1,80x0,92 m)


11 A.4.5.2.11 m2 80,190.00 84,474.50
x 5 mm

Pemasangan Atap Asbes Gelombang (3,00x1,05 m)


12 A.4.5.2.12 m2 63,415.00 79,139.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,70x1,05 m)


13 A.4.5.2.13 m2 65,340.00 81,372.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,40x1,05 m)


14 A.4.5.2.14 m2 63,360.00 79,788.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,10x1,05 m)


15 A.4.5.2.15 m2 64,350.00 78,765.50
x 4 mm

Pemasangan Atap Asbes Gelombang (1,50x1,05 m)


16 A.4.5.2.16 m2 68,090.00 81,724.50
x 4 mm

Pemasangan Atap Asbes Gelombang (3,00x1,08 m)


17 A.4.5.2.17 m2 72,611.00 76,059.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,70x1,08 m)


18 A.4.5.2.18 m2 75,966.00 79,524.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,40x1,08 m)


19 A.4.5.2.19 m2 72,798.00 76,884.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,10x1,08 m)


20 A.4.5.2.20 m2 73,810.00 78,061.50
x 6 mm

Pemasangan Atap Asbes Gelombang (1,80x1,08 m)


21 A.4.5.2.21 m2 77,715.00 81,603.50
x 6 mm

22 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 118,921.00 132,192.50

23 A.4.5.2.31 Pemasangan Atap Genteng Aspal m2 238,898.00 264,577.50

24 A.4.5.2.32 Pemasangan Atap Genteng Metal m2 100,760.00 115,665.00

25 A.4.5.2.34 Pemasangan Atap Sirap m2 127,732.00 139,425.00

500669137.xls 125/43 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
26 A.4.5.2.35 Pemasangan Nok Genteng Beton m' 145,464.00 159,582.50

27 A.4.5.2.36 Pemasangan Nok Genteng Aspal m' 143,830.50 153,912.00

28 A.4.5.2.37 Pemasangan Nok Genteng Metal m' 80,454.00 88,286.00

29 A.4.5.2.38 Pemasangan Nok Sirap m' 69,987.50 76,087.00

30 A.4.5.2.39 Pemasangan Atap Seng Gelombang m2 45,331.00 50,182.00


31 A.4.5.2.40 Pemasangan Atap Nok Seng m' 39,149.00 42,922.00

32 A.4.5.2.43 Pasang Allumunium Foil / Sisalation m2 40,524.00 46,376.00

XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U

Pembuatan & Pemasangan Kosen Pintu & Jendela


1 A.4.6.1.1 m3 34,587,575.00 36,143,387.50
Kayu klas I

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 m3 14,811,225.00 15,372,912.50
Kayu klas II atau III

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 m2 598,829.00 620,108.50
Kayu Klas II (Kayu Kamfer)

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 m2 598,829.00 620,108.50
Sederhana Kayu Klas III

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 m2 997,837.50 1,050,775.00
Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Kaca


6 A.4.6.1.6 m2 725,285.00 768,900.00
Kayu Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 m2 2,592,425.00 2,715,075.00
Kayu Klas I atau II (jati)

Pembuatan&Pemasangan Pintu kayu lapis


8 A.4.6.1.8 (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 m2 748,231.00 810,810.00
cm)

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 m2 815,408.00 882,865.50
rangka expose kayu klas I atau II

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 m2 2,303,895.00 2,407,075.00
Klas I atau II

Pembuatan & Pemasangan Pintu Teakwood


11 A.4.6.1.11 m2 1,337,666.00 1,428,157.50
Rangkap, Rangka Expose Kayu Klas I

Pembuatan & Pemasangan Pintu Teakwood


12 A.4.6.1.12 Rangkap Lapis Formika, Rangka expose Kayu Klas m2 873,180.00 942,271.00
II

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 m3 12,957,120.00 13,398,825.00
Konvensional Kayu I; II & III Bentang 6 meter

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 m3 37,451,865.00 39,101,507.50
Expose, Kayu Klas I

15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m3 11,925,540.00 12,288,815.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 m2 195,954.00 202,356.00
Klas II

500669137.xls 125/44 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Rangka Atap Genteng Beton, Kayu
17 A.4.6.1.17 m2 229,218.00 236,412.00
Klas II

18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II m2 167,486.00 173,547.00

Pemasangan Rangka Langit-langit (50x1,00) m,


19 A.4.6.1.19 m2 223,256.00 233,271.50
kayu Klas II atau III

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 m2 228,987.00 238,705.50
Klas II atau III

Pemasangan Listplank Uk. (3x20)cm Kayu klas I


21 A.4.6.1.21 m' 379,555.00 395,092.50
atau II

Pemasangan Listplank Uk. (3x30)cm Kayu klas I


22 A.4.6.1.22 m' 151,250.00 156,090.00
atau klas II

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 m2 353,749.00 367,218.50
Kayu klas II atau III

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 m2 422,939.00 459,948.50
Rangka Kayu Klas II

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 m2 432,795.00 470,222.50
Rangka Kayu Klas II

Pemasangan Dinding Lambriziring dari Papan Kelas


26 A.4.6.1.26 m2 587,235.00 624,030.00
I

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 m2 44,935.00 48,367.00
ukuran (120x240) cm

Pemasangan Dinding Bilik, Rangka Kayu Klas III


28 A.4.6.1.28 m2 140,490.24 159,775.00
atau IV

HARGA SATUAN PEKERJAAN KUNCI dan


XII A.4.6.2
KACA

1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa Buah 220,660.00 270,462.50


2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi Buah 180,455.00 246,606.25

3 A.4.6.2.4 Pemasangan Kunci Selinder Buah 218,955.00 268,606.25

4 A.4.6.2.5 Pemasangan Engsel Pintu Buah 35,640.00 39,393.75

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu Buah 23,210.00 26,262.50

6 A.4.6.2.7 Pemasangan Engsel Angin Buah 62,001.50 80,929.75

7 A.4.6.2.9 Pemasangan Kait Angin Buah 46,711.50 51,573.50

8 A.4.6.2.10 Pasang Door Closer Buah 390,582.50 479,723.75

9 A.4.6.2.11 Pemasangan Kunci Selot Buah 44,033.00 48,889.50


10 A.4.6.2.13 Pemasangan Door Stop Buah 320,116.50 403,944.75

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong Buah 325,699.00 372,168.50

12 A.4.6.2.15 Pemasangan Kunci Lemari Buah 57,798.40 63,869.85

13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm m2 132,904.75 143,367.13

14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m2 147,424.75 155,467.13

15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm m2 359,174.75 421,667.13

500669137.xls 125/45 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
HARGA SATUAN PEKERJAAN
XIII A.4.7.1
PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 m2 18,469.00 20,278.50
Lama

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 m2 18,441.50 20,278.50
dicat

Pengerokan Karat Cat Lama permukaan Baja dg


3 A.4.7.1.3 m2 19,156.50 21,076.00
cara manual

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


4 A.4.7.1.4 m2 50,182.00 54,048.50
Cat dasar, 2 Lp Cat Penutup)

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


5 A.4.7.1.5 m2 70,862.00 76,059.50
Cat dasar, 3 Lp Cat Penutup)

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 40,342.50 42,614.00

7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 62,766.00 69,516.70

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 13,563.00 14,906.38

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis m2 51,084.00 56,853.50

Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar


10 A.4.7.1.10 m2 23,712.70 27,388.90
2 Lap.Cat Penutup)

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 m2 16,684.80 19,015.70
Penutup)

12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium m2 11,041.80 11,962.50

13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih m2 20,222.40 22,244.75

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 m2 8,789.00 9,831.25
(pemeliharaan)

15 A.4.7.1.15 Pemasangan Wallpaper m2 93,747.50 105,228.75

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 36,030.50 39,833.75

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 m2 71,115.00 78,223.75
Perancah

HARGA SATUAN PEKERJAAN SANITASI


XIV A.5.1.1
DALAM GEDUNG

1 A.5.1.1.1 Pemasangan Closet Duduk / Mono Blok Unit 2,433,134.00 2,775,685.00

2 A.5.1.1.2 Pemasangan Closet Jongkok Porselen Unit 762,630.00 826,760.00

3 A.5.1.1.4 Pemasangan Urinoir Unit 805,200.00 866,690.00

4 A.5.1.1.5 Pemasangan Wastafel Unit 637,532.50 692,367.50

5 A.5.1.1.6 Pemasangan Bathcuip porselen Unit 1,122,016.50 1,197,966.00

6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3 Unit 1,489,950.00 1,618,650.00

7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,810,919.27 1,974,643.54

8 A.5.1.1.11 Pemasangan Bak Beton Bertulang Vol. 1 m3 Unit 6,916,390.02 7,900,488.06

9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 357,280.00 399,987.50
10 A.5.1.1.14 Pemasangan Floor Drain buah 56,760.00 66,412.50

500669137.xls 125/46 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Bak Kontrol Pas.Batu Bata 30x30
11 A.5.1.1.15 bh 528,033.00 579,694.50
tinggi 35 cm

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 bh 782,364.00 855,767.00
tinggi 50 cm

Pemasangan Bak Kontrol Pas.Batu Bata 60x60


13 A.5.1.1.17 bh 903,804.00 994,774.00
tinggi 60 cm

14 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½" m' 68,894.83 72,444.17

15 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 97,691.00 121,974.88

16 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾" m' 80,261.50 83,810.83

17 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1" m' 111,519.83 116,490.00

18 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ " m' 150,674.33 156,964.50


19 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3" m' 263,831.33 271,569.83

20 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4" m' 467,010.50 473,470.25

21 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½" m' 26,213.00 28,646.75

22 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾" m' 28,770.50 30,991.13

23 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1" m' 35,164.25 38,876.75

24 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½" m' 38,467.00 43,041.17

25 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2" m' 45,571.17 52,987.00

26 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3" m' 78,941.50 87,215.33


27 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4" m' 91,003.00 94,999.67

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


28 A.5.1.1.33 m' 85,481.00 94,204.00
20 cm

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


29 A.5.1.1.34 m' 41,327.00 46,997.50
15 cm

30 A.5.1.1.35 Pemasangan Pipa Beton Ø 15 - 20 cm m' 122,955.80 138,340.40

31 A.5.1.1.36 Pemasangan Pipa Beton Ø 30 - 100 cm m' 565,328.50 616,038.50

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 Pemasangan Lampu Titik 412,280.00 431,508.00

2 A.8.4.6.2 Pemasangan MCB buah 505,340.00 536,448.00

500669137.xls 125/47 hspk


DAFTAR HARGA SATUAN PEKERJAAN (AHSP) NO.28/PRT/M/2016
BIDANG CIPTA KARYA
SUMBER DATA : PASARAN BEBAS
D A E R A H : KOTA SEMARANG & SEKITAR
EDISI 03 2020

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
I A. 2.2.1 K.3 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi
1 A.2.2.1.2 1 m' 717,172.50 767,849.50
2,00 m
A TENAGA 80,400.00 86,900.00
L.01 0.2 OH Pekerja 105,000.00 115,000.00 21,000.00 23,000.00
L.02 0.4 OH Tukang Kayu 135,000.00 145,000.00 54,000.00 58,000.00
L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.02 OH Mandor 130,000.00 145,000.00 2,600.00 2,900.00
B BAHAN 571,575.00 611,145.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 26,250.00 30,000.00
2.5 Kg Portalnd Semen 1,150.00 1,200.00 2,875.00 3,000.00
1.2 Lbr Seng Gelombang 3" - 5" 48,000.00 55,000.00 57,600.00 66,000.00
0.005 m3 Pasir Beton 340,000.00 375,000.00 1,700.00 1,875.00
0.009 m3 Koral Beton 320,000.00 380,000.00 2,880.00 3,420.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 6,500,000.00 6,800,000.00 468,000.00 489,600.00
0.06 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 1,020.00 1,050.00
0.45 Kg Meni Besi 25,000.00 36,000.00 11,250.00 16,200.00
C PERALATAN
D Jumlah A + B + C 651,975.00 698,045.00
E Overhead & Profit (contah 10%) 10% 65,197.50 69,804.50
F Harga Satuan Pekerjaan (D+E) 717,172.50 767,849.50
Overhead & Profit (contah 10%)
2 A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank 179,509.00 188,952.50
A Tenaga 26,050.00 28,225.00
L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.1 OH Tukang Kayu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 137,140.00 143,550.00
0.012 m3 Kayu 5/7x 4m Kayu Kruing 6,500,000.00 6,800,000.00 78,000.00 81,600.00
0.02 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 340.00 350.00
0.007 m3 Kayu Papan 3/20 Kruing 8,400,000.00 8,800,000.00 58,800.00 61,600.00
C PERALATAN
D Jumlah A + B + C 163,190.00 171,775.00
E Overhead & Profit (contah 10%) 10% 16,319.00 17,177.50
F Harga Satuan Pekerjaan (D+E) 179,509.00 188,952.50

3 A.2.2.1.5 K.3 1 m2 Pembuatan Kantor Sementara dg Lantai Plesteran 2,334,519.00 2,493,315.00

A Tenaga 663,500.00 717,250.00


L.01 2 OH Pekerja 105,000.00 115,000.00 210,000.00 230,000.00
L.02 2 OH Tukang Kayu 135,000.00 145,000.00 270,000.00 290,000.00
L.02 1 OH Tukang Batu 135,000.00 145,000.00 135,000.00 145,000.00
L.03 0.3 OH Kepala Tukang 140,000.00 150,000.00 42,000.00 45,000.00
L.04 0.05 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00
B Bahan 1,458,790.00 1,549,400.00
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m 21,000.00 24,000.00 26,250.00 30,000.00
0.18 m3 Kayu 6,500,000.00 6,800,000.00 1,170,000.00 1,224,000.00
0.80 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 13,600.00 14,000.00
1.1 Kg Besi Strip 14,000.00 14,250.00 15,400.00 15,675.00
35 Kg Portland Sement 1,150.00 1,200.00 40,250.00 42,000.00
0.15 m3 Pasir pasang 310,000.00 370,000.00 46,500.00 55,500.00
0.1 m3 Pasir Beton 340,000.00 375,000.00 34,000.00 37,500.00
0.15 m3 Koral Beton 320,000.00 380,000.00 48,000.00 57,000.00
30 buah Batu bata Merah 520.00 580.00 15,600.00 17,400.00
0.25 Lbr Seng Plat 22,000.00 24,500.00 5,500.00 6,125.00
0.20 buah Jendela Naco 40,000.00 42,000.00 8,000.00 8,400.00
0.08 m2 Kaca Polos 88,000.00 95,000.00 7,040.00 7,600.00
0.15 buah Kunci Tanam 165,000.00 200,000.00 24,750.00 30,000.00
0.06 Lbr Plywood 4 mm 65,000.00 70,000.00 3,900.00 4,200.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 2,122,290.00 2,266,650.00
E Overhead & Profit (contah 10%) 10% 212,229.00 226,665.00
F Harga Satuan Pekerjaan (D+E) 2,334,519.00 2,493,315.00

4 A.2.2.1.6 K.3 1 m2 Pembuatan Rumah Jaga (Konstruksi Kayu) 1,818,960.00 1,930,225.00


A Tenaga 335,000.00 362,250.00
L.01 1 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00
L.02 1.50 OH Tukang Kayu 135,000.00 145,000.00 202,500.00 217,500.00
L.03 0.15 OH Kepala Tukang 140,000.00 150,000.00 21,000.00 22,500.00
L.04 0.05 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00
B Bahan 1,318,600.00 1,392,500.00
3.00 Btg Kayu Dolken Ø 8 - 10 / 4 m 21,000.00 24,000.00 63,000.00 72,000.00
0.18 m3 Kayu 6,500,000.00 6,800,000.00 1,170,000.00 1,224,000.00
0.80 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 13,600.00 14,000.00
1.50 Lbr Seng Gelombang 48,000.00 55,000.00 72,000.00 82,500.00
C PERALATAN
D Jumlah A + B + C 1,653,600.00 1,754,750.00
E Overhead & Profit (contah 10%) 10% 165,360.00 175,475.00
F Harga Satuan Pekerjaan (D+E) 1,818,960.00 1,930,225.00

5. A.2.2.1.7 K.3 1 m2 Pembuatan Gudang Semen dan Peralatan 1,673,732.50 1,766,077.50


A Tenaga 409,500.00 442,250.00
L.01 1 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00
L.02 2 OH Tukang Kayu 135,000.00 145,000.00 270,000.00 290,000.00
L.03 0.2 OH Kepala Tukang 140,000.00 150,000.00 28,000.00 30,000.00
L.04 0.05 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00
B Bahan 1,516,075.00 1,599,400.00
1.7 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 35,700.00 40,800.00
0.21 m3 Kayu 6,500,000.00 6,800,000.00 1,365,000.00 1,428,000.00
0.3 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 5,100.00 5,250.00
10.5 Kg Portland Semen 1,150.00 1,200.00 12,075.00 12,600.00
0.03 m3 Pasir Beton 340,000.00 375,000.00 10,200.00 11,250.00
0.05 m3 Koral Beton 320,000.00 380,000.00 16,000.00 19,000.00
1.5 Lbr Seng Gelombang 48,000.00 55,000.00 72,000.00 82,500.00
0.25 Lbr Seng Plat 22,000.00 24,500.00 5,500.00 6,125.00
C PERALATAN
D Jumlah A + B + C 1,521,575.00 1,605,525.00
E Overhead & Profit (contah 10%) 10% 152,157.50 160,552.50
F Harga Satuan Pekerjaan (D+E) 1,673,732.50 1,766,077.50

6. A.2.2.1.8 K.3 1 m2 Pembuatan Bedeng Pekerja 2,064,425.00 2,205,390.00


A Tenaga 409,500.00 442,250.00
L.01 1 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00
L.02 2 OH Tukang Kayu 135,000.00 145,000.00 270,000.00 290,000.00
L.03 0.2 OH Kepala Tukang 140,000.00 150,000.00 28,000.00 30,000.00
L.04 0.05 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00
B Bahan 1,467,250.00 1,562,650.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 26,250.00 30,000.00
0.186 m3 Kayu 6,500,000.00 6,800,000.00 1,209,000.00 1,264,800.00
0.30 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 5,100.00 5,250.00
18.00 Kg Portland Semen 1,150.00 1,200.00 20,700.00 21,600.00
0.03 m3 Pasir Beton 340,000.00 375,000.00 10,200.00 11,250.00
0.05 m3 Koral Beton 320,000.00 380,000.00 16,000.00 19,000.00
1.50 Lbr Seng Gelombang 48,000.00 55,000.00 72,000.00 82,500.00
1.35 Lbr Playwood 80,000.00 95,000.00 108,000.00 128,250.00
C PERALATAN
D Jumlah A + B + C 1,876,750.00 2,004,900.00
E Overhead & Profit (contah 10%) 10% 187,675.00 200,490.00
F Harga Satuan Pekerjaan (D+E) 2,064,425.00 2,205,390.00

7. A.2.2.1.9 K.3 1 m2 Membersihkan Lapangan dan Perataan 18,700.00 20,625.00


A Tenaga 17,000.00 18,750.00
L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.04 0.05 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00
B Bahan
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 17,000.00 18,750.00
E Overhead & Profit (contah 10%) 10% 1,700.00 1,875.00
F Harga Satuan Pekerjaan (D+E) 18,700.00 20,625.00

8 A.2.2.1.10 K.3 1 m2 Pembuatan Steger/Perancah dari Bambu 474,111.00 518,795.20


A Tenaga 409,500.00 442,250.00
L.01 1.00 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00
L.02 2.00 OH Tukang Kayu 135,000.00 145,000.00 270,000.00 290,000.00
L.03 0.20 OH Kepala Tukang 140,000.00 150,000.00 28,000.00 30,000.00
L.04 0.05 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00
B Bahan 21,510.00 29,382.00
1.250 Btg Bambu diameter 6 - 8 / 600 cm 12,000.00 18,000.00 15,000.00 22,500.00
0.186 Kg Tali Ijuk 35,000.00 37,000.00 6,510.00 6,882.00
C PERALATAN
D Jumlah A + B + C 431,010.00 471,632.00
E Overhead & Profit (contah 10%) 10% 43,101.00 47,163.20
F Harga Satuan Pekerjaan (D+E) 474,111.00 518,795.20

Pembuatan Kotak Adukan ukuran


9 A.2.2.1.11 1 bh 640,706.00 672,100.00
40cmx50cmx25cm
A Tenaga 44,700.00 48,000.00
L.02 0.30 OH Tukang Kayu 135,000.00 145,000.00 40,500.00 43,500.00
L.03 0.03 OH Kepala Tukang 140,000.00 150,000.00 4,200.00 4,500.00
B Bahan 537,760.00 563,000.00
0.036 m3 Kayu Papan Kelas III 8,400,000.00 8,800,000.00 302,400.00 316,800.00
0.036 m3 Kayu Balok Kelas III 6,500,000.00 6,800,000.00 234,000.00 244,800.00
0.080 kg Paku Biasa 17,000.00 17,500.00 1,360.00 1,400.00
C PERALATAN
D Jumlah A + B + C 582,460.00 611,000.00
E Overhead & Profit (contah 10%) 10% 58,246.00 61,100.00
F Harga Satuan Pekerjaan (D+E) 640,706.00 672,100.00

10 A.2.2.1.12 1 m2 Pembuatan Jalan Sementara 189,255.00 218,817.50


A Tenaga 105,650.00 115,725.00

L.01 1 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00

L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00


B. Bahan 66,400.00 83,200.00

0.150 m3 Batu Belah 260,000.00 320,000.00 39,000.00 48,000.00


0.090 m3 Batu Pecah 270,000.00 350,000.00 24,300.00 31,500.00

0.010 m3 Pasir Pasang 310,000.00 370,000.00 3,100.00 3,700.00

C PERALATAN
D Jumlah A + B + C 172,050.00 198,925.00
E Overhead & Profit (contah 10%) 10% 17,205.00 19,892.50
F Harga Satuan Pekerjaan (D+E) 189,255.00 218,817.50

11 A.2.2.1.13 1 m3 Bongkaran Beton Bertulang 1,635,315.00 1,792,978.00


A Tenaga 1,486,650.00 1,629,980.00
L.01 13.334 OH Pekerja 105,000.00 115,000.00 1,400,070.00 1,533,410.00
L.04 0.666 OH Mandor 130,000.00 145,000.00 86,580.00 96,570.00
B Bahan
C PERALATAN
D Jumlah A + B + C 1,486,650.00 1,629,980.00
E Overhead & Profit (contah 10%) 10% 148,665.00 162,998.00
F Harga Satuan Pekerjaan (D+E) 1,635,315.00 1,792,978.00

12 A.2.2.1.14 1 m3 Bongkaran Dinding Tembok Bata Merah 774,757.50 848,639.00


A Tenaga 704,325.00 771,490.00
L.01 6.667 OH Pekerja 105,000.00 115,000.00 700,035.00 766,705.00
L.04 0.033 OH Mandor 130,000.00 145,000.00 4,290.00 4,785.00
B Bahan
C PERALATAN
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
D Jumlah A + B + C 704,325.00 771,490.00
E Overhead & Profit (contah 10%) 10% 70,432.50 77,149.00
F Harga Satuan Pekerjaan (D+E) 774,757.50 848,639.00

13 A.2.2.1.15 1 m2 Pagar Kawat Jaring Galvanis Panjang 240 cm 60,658.40 64,245.50


A Tenaga 10,690.00 11,800.00

L.01 0.042 OH Pekerja 105,000.00 115,000.00 4,410.00 4,830.00


L.02 0.004 OH Tukang 135,000.00 145,000.00 540.00 580.00
L.03 0.002 OH Kepala Tukang 140,000.00 150,000.00 280.00 300.00
L.04 0.042 OH Mandor 130,000.00 145,000.00 5,460.00 6,090.00
B Bahan 44,454.00 46,605.00

0.1434 Lbr Kawat Jaring 310,000 325,000 44,454.00 46,605.00


C PERALATAN
D Jumlah A + B + C 55,144.00 58,405.00
E Overhead & Profit (contah 10%) 10% 5,514.40 5,840.50
F Harga Satuan Pekerjaan (D+E) 60,658.40 64,245.50

Pemasangan Pagar Panel Beton Pracetak 5 x 50 x


14 A.2.2.1.16 1 m2 327,387.50 359,169.25
240 cm
A Tenaga 60,400.00 65,805.00
L.01 0.375 OH Pekerja 105,000.00 115,000.00 39,375.00 43,125.00
L.02 0.125 OH Tukang Batu 135,000.00 145,000.00 16,875.00 18,125.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.019 OH Mandor 130,000.00 145,000.00 2,470.00 2,755.00
B Bahan 237,225.00 260,712.50
0.986 Lbr Panel Beton Pracetak 65,000.00 75,000.00 64,090.00 73,950.00
0.525 Btg Kolom Beton Pracetak 145,000.00 162,500.00 76,125.00 85,312.50
45.000 Kg Semen (SM) 1,150.00 1,200.00 51,750.00 54,000.00
0.146 m3 Koral 310,000.00 325,000.00 45,260.00 47,450.00
C PERALATAN
D Jumlah A + B + C 297,625.00 326,517.50
E Overhead & Profit (contah 10%) 10% 29,762.50 32,651.75
F Harga Satuan Pekerjaan (D+E) 327,387.50 359,169.25
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 1 m3 Menggali Tanah Biasa Sedalam 1 m 90,200.00 98,862.50


A TENAGA 82,000.00 89,875.00
L.01 0.75 OH Pekerja 105,000.00 115,000.00 78,750.00 86,250.00
L.04 0.025 OH Mandor 130,000.00 145,000.00 3,250.00 3,625.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 82,000.00 89,875.00
E Overhead & Profit (contah 10%) 10% 8,200.00 8,987.50
F Harga Satuan Pekerjaan (D+E) 90,200.00 98,862.50
Overhead & Profit (contah 10%)
2 A.2.3.1.2 1 m3 Menggali Tanah Biasa Sedalam 2 m 110,385.00 121,027.50
A TENAGA 100,350.00 110,025.00
L.01 0.90 OH Pekerja 105,000.00 115,000.00 94,500.00 103,500.00
L.04 0.045 OH Mandor 130,000.00 145,000.00 5,850.00 6,525.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 100,350.00 110,025.00
E Overhead & Profit (contah 10%) 10% 10,035.00 11,002.50
F Harga Satuan Pekerjaan (D+E) 110,385.00 121,027.50

3 A.2.3.1.3 1 m3 Menggali Tanah Biasa Sedalam 3 m 130,856.00 143,511.50


A TENAGA 118,960.00 130,465.00
L.01 1.05 OH Pekerja 105,000.00 115,000.00 110,250.00 120,750.00
L.04 0.067 OH Mandor 130,000.00 145,000.00 8,710.00 9,715.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 118,960.00 130,465.00
E Overhead & Profit (contah 10%) 10% 11,896.00 13,046.50
F Harga Satuan Pekerjaan (D+E) 130,856.00 143,511.50

4 A.2.3.1.4 1 m3 Menggali Tanah Keras Sedalam 1 m 120,076.00 131,604.00


TENAGA 109,160.00 119,640.00
L.01 1.000 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00
L.04 0.032 OH Mandor 130,000.00 145,000.00 4,160.00 4,640.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 109,160.00 119,640.00
E Overhead & Profit (contah 10%) 10% 10,916.00 11,964.00
F Harga Satuan Pekerjaan (D+E) 120,076.00 131,604.00

5 A.2.3.1.5 1 m3 Menggali Tanah Cadas Sedalam 1 m 181,830.00 199,320.00


A TENAGA 165,300.00 181,200.00
L.01 1.50 OH Pekerja 105,000.00 115,000.00 157,500.00 172,500.00
L.04 0.060 OH Mandor 130,000.00 145,000.00 7,800.00 8,700.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 165,300.00 181,200.00
E Overhead & Profit (contah 10%) 10% 16,530.00 18,120.00
F Harga Satuan Pekerjaan (D+E) 181,830.00 199,320.00

6 A.2.3.1.6 1 m3 Menggali Tanah Lumpur Sedalam 1 m 145,035.00 158,977.50


A TENAGA 131,850.00 144,525.00
L.01 1.200 OH Pekerja 105,000.00 115,000.00 126,000.00 138,000.00
L.04 0.045 OH Mandor 130,000.00 145,000.00 5,850.00 6,525.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 131,850.00 144,525.00
E Overhead & Profit (contah 10%) 10% 13,185.00 14,452.50
F Harga Satuan Pekerjaan (D+E) 145,035.00 158,977.50

7 A.2.3.1.7 1 m2 Mengerjakan Striping Tebing Setinggi 1 m 6,490.00 7,122.50


A TENAGA 5,900.00 6,475.00
L.01 0.05 OH Pekerja 105,000.00 115,000.00 5,250.00 5,750.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 5,900.00 6,475.00
E Overhead & Profit (contah 10%) 10% 590.00 647.50
F Harga Satuan Pekerjaan (D+E) 6,490.00 7,122.50

8 A.2.3.1.8 1 m3 MembuangTanah sejauh 30 m' 39,545.00 43,340.00


A TENAGA 35,950.00 39,400.00
L.01 0.330 OH Pekerja 105,000.00 115,000.00 34,650.00 37,950.00
L.04 0.010 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00

file:///conversion/tmp/scratch/500669137.xls 125/52 2-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B BAHAN
C PERALATAN
D Jumlah A + B + C 35,950.00 39,400.00
E Overhead & Profit (contah 10%) 10% 3,595.00 3,940.00
F Harga Satuan Pekerjaan (D+E) 39,545.00 43,340.00

Pengurugan Kembali di hitung dari 1/3 kali koefisien


9 A.2.3.1.9 1 m3 21,633.33 23,741.67
Pekerjaan galian
A TENAGA 59,000.00 64,750.00
L.01 0.50 OH Pekerja 105,000.00 115,000.00 52,500.00 57,500.00
L.04 0.050 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 59,000.00 64,750.00
E Overhead & Profit (contah 10%) 10% 5,900.00 6,475.00
F Harga Satuan Pekerjaan (D+E) 64,900.00 71,225.00

10 A.2.3.1.10 1 m3 Pemadatan Tanah (per 20 cm) 64,900.00 71,225.00


A TENAGA 59,000.00 64,750.00
L.01 0.5 OH Pekerja 105,000.00 115,000.00 52,500.00 57,500.00
L.04 0.05 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 59,000.00 64,750.00
E Overhead & Profit (contah 10%) 10% 5,900.00 6,475.00
F Harga Satuan Pekerjaan (D+E) 64,900.00 71,225.00

11 A.2.3.1.11 1 m3 Urugan Pasir 247,280.00 329,945.00


A TENAGA 32,800.00 35,950.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.04 0.01 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00
B BAHAN 192,000.00 264,000.00
1.2 m3 Pasir Urug 160,000.00 220,000.00 192,000.00 264,000.00
C PERALATAN
D Jumlah A + B + C 224,800.00 299,950.00
E Overhead & Profit (contah 10%) 10% 22,480.00 29,995.00
F Harga Satuan Pekerjaan (D+E) 247,280.00 329,945.00

12 A.2.3.1.12 1 m3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 472,571.00 532,125.00


A TENAGA 154,000.00 167,600.00
L.01 0.800 OH Pekerja 105,000.00 115,000.00 84,000.00 92,000.00
L.02 0.400 OH Tukang Batu 135,000.00 145,000.00 54,000.00 58,000.00
L.03 0.04 OH Kepala Tukang 140,000.00 150,000.00 5,600.00 6,000.00
L.04 0.080 OH Mandor 130,000.00 145,000.00 10,400.00 11,600.00
B BAHAN 275,610.00 316,150.00
0.135 m3 Pasir Pasang 310,000.00 370,000.00 41,850.00 49,950.00
0.400 m3 Kapur Padam 300,000.00 310,000.00 120,000.00 124,000.00
0.948 m3 Tanah Liat 120,000.00 150,000.00 113,760.00 142,200.00
C PERALATAN
D Jumlah A + B + C 429,610.00 483,750.00
E Overhead & Profit (contah 10%) 10% 42,961.00 48,375.00
F Harga Satuan Pekerjaan (D+E) 472,571.00 532,125.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 1 m2 28,710.00 31,135.50
Resapan
A TENAGA 17,700.00 19,425.00
0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B BAHAN 8,400.00 8,880.00
6.00 kg Ijuk 1,400.00 1,480.00 8,400.00 8,880.00
C PERALATAN
D Jumlah A + B + C 26,100.00 28,305.00
E Overhead & Profit (contah 10%) 10% 2,610.00 2,830.50
F Harga Satuan Pekerjaan (D+E) 28,710.00 31,135.50

14 A.2.3.1.14 1 m3 Mengurug Sirtu Padat 270,050.00 299,612.50


A TENAGA 29,500.00 32,375.00
0.25 OH Pekerja 105,000.00 115,000.00 26,250.00 28,750.00
0.025 OH Mandor 130,000.00 145,000.00 3,250.00 3,625.00
B BAHAN 216,000.00 240,000.00
1.2 m3 Sirtu 180,000.00 200,000.00 216,000.00 240,000.00
C PERALATAN
D Jumlah A + B + C 245,500.00 272,375.00
E Overhead & Profit (contah 10%) 10% 24,550.00 27,237.50
F Harga Satuan Pekerjaan (D+E) 270,050.00 299,612.50

file:///conversion/tmp/scratch/500669137.xls 125/53 2-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 1 m3 Pemasangan Pondasi Batu Belah 1SP : 3 PP 1,084,215.00 1,246,547.50
A TENAGA 279,000.00 303,375.00
L.01 1.5 OH Pekerja 105,000.00 115,000.00 157,500.00 172,500.00
L.02 0.750 OH Tukang Batu 135,000.00 145,000.00 101,250.00 108,750.00
L.03 0.075 OH Kepala Tukang 140,000.00 150,000.00 10,500.00 11,250.00
L.04 0.075 OH Mandor 130,000.00 145,000.00 9,750.00 10,875.00
B BAHAN 706,650.00 829,850.00
1.2 m3 Batu Belah 15/20 270,000.00 340,000.00 324,000.00 408,000.00
202 Kg Portland Sement 1,150.00 1,200.00 232,300.00 242,400.00
0.485 m3 Pasir Pasang 310,000.00 370,000.00 150,350.00 179,450.00
C PERALATAN
D Jumlah A + B + C 985,650.00 1,133,225.00
E Overhead & Profit (contoh 10%) 10% 98,565.00 113,322.50
F Harga Satuan Pekerjaan (D+E) 1,084,215.00 1,246,547.50
Overhead & Profit (contoh 10%)
2 A.3.2.1.2 1 m3 Pemasangan Pondasi Batu Belah 1SP : 4 PP 1,046,815.00 1,209,312.50
A TENAGA 279,000.00 303,375.00
L.01 1.5 OH Pekerja 105,000.00 115,000.00 157,500.00 172,500.00
L.02 0.750 OH Tukang Batu 135,000.00 145,000.00 101,250.00 108,750.00
L.03 0.075 OH Kepala Tukang 140,000.00 150,000.00 10,500.00 11,250.00
L.04 0.075 OH Mandor 130,000.00 145,000.00 9,750.00 10,875.00
B BAHAN 672,650.00 796,000.00
1.2 m3 Batu Belah 15/20 270,000.00 340,000.00 324,000.00 408,000.00
163 Kg Portland Sement 1,150.00 1,200.00 187,450.00 195,600.00
0.52 m3 Pasir Pasang 310,000.00 370,000.00 161,200.00 192,400.00
C PERALATAN
D Jumlah A + B + C 951,650.00 1,099,375.00
E Overhead & Profit (contoh 10%) 10% 95,165.00 109,937.50
F Harga Satuan Pekerjaan (D+E) 1,046,815.00 1,209,312.50

3 A.3.2.1.3 1 m3 Pemasangan Pondasi Batu Belah 1SP : 5 PP 1,020,844.00 1,183,440.50


A TENAGA 279,000.00 303,375.00
L.01 1.5 OH Pekerja 105,000.00 115,000.00 157,500.00 172,500.00
L.02 0.750 OH Tukang Batu 135,000.00 145,000.00 101,250.00 108,750.00
L.03 0.075 OH Kepala Tukang 140,000.00 150,000.00 10,500.00 11,250.00
L.04 0.075 OH Mandor 130,000.00 145,000.00 9,750.00 10,875.00
B BAHAN 649,040.00 772,480.00
1.2 m3 Batu Belah 15/20 270,000.00 340,000.00 324,000.00 408,000.00
136 Kg Portland Sement 1,150.00 1,200.00 156,400.00 163,200.00
0.544 m3 Pasir Pasang 310,000.00 370,000.00 168,640.00 201,280.00
C PERALATAN
D Jumlah A + B + C 928,040.00 1,075,855.00
E Overhead & Profit (contoh 10%) 10% 92,804.00 107,585.50
F Harga Satuan Pekerjaan (D+E) 1,020,844.00 1,183,440.50

4 A.3.2.1.4 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 1,002,606.00 1,165,279.50


A TENAGA 279,000.00 303,375.00
L.01 1.5 OH Pekerja 105,000.00 115,000.00 157,500.00 172,500.00
L.02 0.750 OH Tukang Batu 135,000.00 145,000.00 101,250.00 108,750.00
L.03 0.075 OH Kepala Tukang 140,000.00 150,000.00 10,500.00 11,250.00
L.04 0.075 OH Mandor 130,000.00 145,000.00 9,750.00 10,875.00
B BAHAN 632,460.00 755,970.00
1.2 m3 Batu Belah 15/20 270,000.00 340,000.00 324,000.00 408,000.00
117 Kg Portland Sement 1,150.00 1,200.00 134,550.00 140,400.00
0.561 m3 Pasir Pasang 310,000.00 370,000.00 173,910.00 207,570.00
C PERALATAN
D Jumlah A + B + C 911,460.00 1,059,345.00
E Overhead & Profit (contoh 10%) 10% 91,146.00 105,934.50
F Harga Satuan Pekerjaan (D+E) 1,002,606.00 1,165,279.50

5 A.3.2.1.5 1 m3 Pemasangan Pondasi Batu Belah 1SP : 8 PP 977,559.00 1,140,320.50


A Tenaga 279,000.00 303,375.00
L.01 1.5 OH Pekerja 105,000.00 115,000.00 157,500.00 172,500.00
L.02 0.750 OH Tukang Batu 135,000.00 145,000.00 101,250.00 108,750.00
L.03 0.075 OH Kepala Tukang 140,000.00 150,000.00 10,500.00 11,250.00
L.04 0.075 OH Mandor 130,000.00 145,000.00 9,750.00 10,875.00
B Bahan 609,690.00 733,280.00
1.2 m3 Batu Belah 15/20 270,000.00 340,000.00 324,000.00 408,000.00
91 Kg Portland Sement 1,150.00 1,200.00 104,650.00 109,200.00
0.584 m3 Pasir Pasang 310,000.00 370,000.00 181,040.00 216,080.00

file:///conversion/tmp/scratch/500669137.xls 125/54 3-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 888,690.00 1,036,655.00
E Overhead & Profit (contoh 10%) 10% 88,869.00 103,665.50
F Harga Satuan Pekerjaan (D+E) 977,559.00 1,140,320.50

6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 872,740.00 1,016,262.50
A Tenaga 279,000.00 303,375.00
L.01 1.5 OH Pekerja 105,000.00 115,000.00 157,500.00 172,500.00
L.02 0.750 OH Tukang Batu 135,000.00 145,000.00 101,250.00 108,750.00
L.03 0.075 OH Kepala Tukang 140,000.00 150,000.00 10,500.00 11,250.00
L.04 0.075 OH Mandor 130,000.00 145,000.00 9,750.00 10,875.00
B Bahan 514,400.00 620,500.00
1.2 m3 Batu Belah 15/20 270,000.00 340,000.00 324,000.00 408,000.00
0.17 m3 Kapur Pasang (KP) 300,000.00 310,000.00 51,000.00 52,700.00
0.17 Kg Semen Merah (SM) 200,000.00 200,000.00 34,000.00 34,000.00
0.340 m3 Pasir Pasang 310,000.00 370,000.00 105,400.00 125,800.00
C PERALATAN
D Jumlah A + B + C 793,400.00 923,875.00
E Overhead & Profit (contoh 10%) 10% 79,340.00 92,387.50
F Harga Satuan Pekerjaan (D+E) 872,740.00 1,016,262.50

7 A.3.2.1.7 1 m3 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP 956,747.00 1,113,403.50


A Tenaga 279,000.00 303,375.00
L.01 1.5 OH Pekerja 105,000.00 115,000.00 157,500.00 172,500.00
L.02 0.750 OH Tukang Batu 135,000.00 145,000.00 101,250.00 108,750.00
L.03 0.075 OH Kepala Tukang 140,000.00 150,000.00 10,500.00 11,250.00
L.04 0.075 OH Mandor 130,000.00 145,000.00 9,750.00 10,875.00
B Bahan 590,770.00 708,810.00
1.2 m3 Batu Belah 15/20 270,000.00 340,000.00 324,000.00 408,000.00
61 kg Portland Sement 1,150.00 1,200.00 70,150.00 73,200.00
0.147 m3 Kapur Pasang 300,000.00 310,000.00 44,100.00 45,570.00
0.492 m3 Pasir Pasang 310,000.00 370,000.00 152,520.00 182,040.00
C PERALATAN
D Jumlah A + B + C 869,770.00 1,012,185.00
E Overhead & Profit (contoh 10%) 10% 86,977.00 101,218.50
F Harga Satuan Pekerjaan (D+E) 956,747.00 1,113,403.50

8 A.3.2.1.8 1 m3 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP 936,738.00 1,094,164.50


A Tenaga 279,000.00 303,375.00
L.01 1.5 OH Pekerja 105,000.00 115,000.00 157,500.00 172,500.00
L.02 0.750 OH Tukang Batu 135,000.00 145,000.00 101,250.00 108,750.00
L.03 0.075 OH Kepala Tukang 140,000.00 150,000.00 10,500.00 11,250.00
L.04 0.075 OH Mandor 130,000.00 145,000.00 9,750.00 10,875.00
B Bahan 572,580.00 691,320.00
1.2 m3 Batu Belah 15/20 270,000.00 340,000.00 324,000.00 408,000.00
41 kg Portland Sement 1,150.00 1,200.00 47,150.00 49,200.00
0.131 m3 Kapur Pasang 300,000.00 310,000.00 39,300.00 40,610.00
0.523 m3 Pasir 310,000.00 370,000.00 162,130.00 193,510.00
C PERALATAN
D Jumlah A + B + C 851,580.00 994,695.00
E Overhead & Profit (contoh 10%) 10% 85,158.00 99,469.50
F Harga Satuan Pekerjaan (D+E) 936,738.00 1,094,164.50

9 A.3.2.1.9 1 m3 Pemasang Batu Kosong/Anstamping 592,020.00 726,874.50


A Tenaga 145,080.00 157,755.00
L.01 0.78 OH Pekerja 105,000.00 115,000.00 81,900.00 89,700.00
L.02 0.39 OH Tukang Batu 135,000.00 145,000.00 52,650.00 56,550.00
L.03 0.039 OH Kepala Tukang 140,000.00 150,000.00 5,460.00 5,850.00
L.04 0.039 OH Mandor 130,000.00 145,000.00 5,070.00 5,655.00
B Bahan 393,120.00 503,040.00
1.2 m3 Batu Belah 15/20 270,000.00 340,000.00 324,000.00 408,000.00
0.432 m3 Pasir Urug 160,000.00 220,000.00 69,120.00 95,040.00
C PERALATAN
D Jumlah A + B + C 538,200.00 660,795.00
E Overhead & Profit (contoh 10%) 10% 53,820.00 66,079.50
F Harga Satuan Pekerjaan (D+E) 592,020.00 726,874.50

file:///conversion/tmp/scratch/500669137.xls 125/55 3-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pasang Pondasi Siklop, 60% Beton Campuran 1PC : 2PB :
10 A.3.2.1.10 1 m3 2,617,571.00 3,004,573.00
3KR & 40% Batu Belah
A Tenaga 503,150.00 548,750.00
L.01 3.4 OH Pekerja 105,000.00 115,000.00 357,000.00 391,000.00
L.02 0.85 OH Tukang Batu 135,000.00 145,000.00 114,750.00 123,250.00
L.03 0.085 OH Kepala Tukang 140,000.00 150,000.00 11,900.00 12,750.00
L.04 0.15 OH Mandor 130,000.00 145,000.00 19,500.00 21,750.00
B Bahan 1,876,460.00 2,182,680.00
0.480 m3 Batu Belah 15/20 cm 270,000.00 340,000.00 129,600.00 163,200.00
126 Kg Besi Beton 10,200.00 12,000.00 1,285,200.00 1,512,000.00
194 Kg Portland Semen 1,150.00 1,200.00 223,100.00 232,800.00
0.312 m3 Pasir Beton 340,000.00 375,000.00 106,080.00 117,000.00
0.468 m3 Koral Beton 210,000.00 260,000.00 98,280.00 121,680.00
1.8 Kg Kawat Beton 19,000.00 20,000.00 34,200.00 36,000.00
C PERALATAN
D Jumlah A + B + C 2,379,610.00 2,731,430.00
E Overhead & Profit (contoh 10%) 10% 237,961.00 273,143.00
F Harga Satuan Pekerjaan (D+E) 2,617,571.00 3,004,573.00

11 A.3.2.1.11 1 m3 Pasang Pondasi Sumuran diameter 100 cm 1,029,193.00 1,150,308.50


A Tenaga 386,670.00 421,255.00
L.01 2.40 OH Pekerja 105,000.00 115,000.00 252,000.00 276,000.00
L.02 0.8 OH Tukang Batu 135,000.00 145,000.00 108,000.00 116,000.00
L.03 0.08 OH Kepala Tukang 140,000.00 150,000.00 11,200.00 12,000.00
L.04 0.119 OH Mandor 130,000.00 145,000.00 15,470.00 17,255.00
B Bahan 548,960.00 624,480.00
0.45 m3 Batu Belah 15/20 cm 270,000.00 340,000.00 121,500.00 153,000.00
194 Kg Portland Semen 1,150.00 1,200.00 223,100.00 232,800.00
0.312 m3 Pasir Beton 340,000.00 375,000.00 106,080.00 117,000.00
0.468 m3 Koral Beton 210,000.00 260,000.00 98,280.00 121,680.00
C PERALATAN
D Jumlah A + B + C 935,630.00 1,045,735.00
E Overhead & Profit (contoh 10%) 10% 93,563.00 104,573.50
F Harga Satuan Pekerjaan (D+E) 1,029,193.00 1,150,308.50

file:///conversion/tmp/scratch/500669137.xls 125/56 3-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c


1 A.4.1.1.1 1 m3 1,057,405.64 1,167,763.14
= 0,87
A Tenaga 225,085.00 245,860.00
L.01 1.65 OH Pekerja 105,000.00 115,000.00 173,250.00 189,750.00
L.02 0.275 OH Tukang Batu 135,000.00 145,000.00 37,125.00 39,875.00
L.03 0.028 OH Kepala Tukang 140,000.00 150,000.00 3,920.00 4,200.00
L.04 0.083 OH Mandor 130,000.00 145,000.00 10,790.00 12,035.00
B Bahan 736,192.86 815,742.86
247 Kg Portland Semen 1,150.00 1,200.00 284,050.00 296,400.00
869 Kg Pasir Beton 242.86 267.86 211,042.86 232,767.86
999 Kg Kerikil (maksimum 30 mm) 237.04 281.48 236,800.00 281,200.00
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 961,277.86 1,061,602.86
E Overhead & Profit (contoh 10%) 10% 96,127.79 106,160.29
F Harga Satuan Pekerjaan (D+E) 1,057,405.64 1,167,763.14
10%
Overhead & Profit (contoh 10%)
Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c
2 A.4.1.1.2 1 m3 1,086,527.42 1,197,987.97
= 0,78
A Tenaga 225,085.00 245,860.00
L.01 1.650 OH Pekerja 105,000.00 115,000.00 173,250.00 189,750.00
L.02 0.275 OH Tukang Batu 135,000.00 145,000.00 37,125.00 39,875.00
L.03 0.028 OH Kepala Tukang 140,000.00 150,000.00 3,920.00 4,200.00
L.04 0.083 OH Mandor 130,000.00 145,000.00 10,790.00 12,035.00
B Bahan 762,667.20 843,219.97
276 Kg Portland Semen 1,150.00 1,200.00 317,400.00 331,200.00
828 kg Pasir Beton 242.86 267.86 201,085.71 221,785.71
1,012 kg Kerikil (maksimum 30 mm) 237.04 281.48 239,881.48 284,859.26
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 987,752.20 1,089,079.97
E Overhead & Profit (contoh 10%) 10% 98,775.22 108,908.00
F Harga Satuan Pekerjaan (D+E) 1,086,527.42 1,197,987.97

Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm,


3 A.4.1.1.3 1 m3 1,109,178.98 1,221,351.48
w/c = 0,72
A Tenaga 225,085.00 245,860.00
L.01 1.650 OH Pekerja 105,000.00 115,000.00 173,250.00 189,750.00
L.02 0.275 OH Tukang Batu 135,000.00 145,000.00 37,125.00 39,875.00
L.03 0.028 OH Kepala Tukang 140,000.00 150,000.00 3,920.00 4,200.00
L.04 0.083 OH Mandor 130,000.00 145,000.00 10,790.00 12,035.00
B Bahan 783,259.52 864,459.52
299 Kg Portland Semen 1,150.00 1,200.00 343,850.00 358,800.00
799 kg Pasir Beton 242.86 267.86 194,042.86 214,017.86
1,017 kg Kerikil (maksimum 30 mm) 237.04 281.48 241,066.67 286,266.67
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,008,344.52 1,110,319.52
E Overhead & Profit (contoh 10%) 10% 100,834.45 111,031.95
F Harga Satuan Pekerjaan (D+E) 1,109,178.98 1,221,351.48

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum


4 A.4.1.1.4 1.00 m3 973,927.31 1,078,162.70
(3-6)cm, w/c = 0,87
A Tenaga 156,580.00 170,870.00
L.01 1.200 OH Pekerja 105,000.00 115,000.00 126,000.00 138,000.00
L.02 0.200 OH Tukang Batu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.020 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
B Bahan 728,808.47 809,277.91
230 Kg Portland Semen 1,150.00 1,200.00 264,500.00 276,000.00
893 kg Pasir Beton 242.86 267.86 216,871.43 239,196.43
1,027 kg Kerikil (maksimum 30 mm) 237.04 281.48 243,437.04 289,081.48
200 ltr Air 20.00 25.00 4,000.00 5,000.00
C PERALATAN
D Jumlah A + B + C 885,388.47 980,147.91
E Overhead & Profit (contoh 10%) 10% 88,538.85 98,014.79
F Harga Satuan Pekerjaan (D+E) 973,927.31 1,078,162.70

Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,


5 A.4.1.1.5 1 m3 1,136,044.29 1,249,215.96
w/c = 0,66
A Tenaga 225,085.00 245,860.00
L.01 1.65 OH Pekerja 105,000.00 115,000.00 173,250.00 189,750.00
L.02 0.275 OH Tukang Batu 135,000.00 145,000.00 37,125.00 39,875.00
L.03 0.028 OH Kepala Tukang 140,000.00 150,000.00 3,920.00 4,200.00
L.04 0.083 OH Mandor 130,000.00 145,000.00 10,790.00 12,035.00

file:///conversion/tmp/scratch/500669137.xls 125/57 4-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 807,682.54 889,790.87
326 Kg Portland Semen 1,150.00 1,200.00 374,900.00 391,200.00
760 Kg Pasir Beton 242.86 267.86 184,571.43 203,571.43
1,029 Kg Kerikil (maksimum 30 mm) 237.04 281.48 243,911.11 289,644.44
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,032,767.54 1,135,650.87
E Overhead & Profit (contoh 10%) 10% 103,276.75 113,565.09
F Harga Satuan Pekerjaan (D+E) 1,136,044.29 1,249,215.96

Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm,


6 A.4.1.1.6 1 m3 1,161,708.63 1,275,610.58
w/c = 0,61
A Tenaga 225,085.00 245,860.00
L.01 1.650 OH Pekerja 105,000.00 115,000.00 173,250.00 189,750.00
L.02 0.275 OH Tukang Batu 135,000.00 145,000.00 37,125.00 39,875.00
L.03 0.028 OH Kepala Tukang 140,000.00 150,000.00 3,920.00 4,200.00
L.04 0.083 OH Mandor 130,000.00 145,000.00 10,790.00 12,035.00
B Bahan 831,013.76 913,785.98
352 Kg Portland Semen 1,150.00 1,200.00 404,800.00 422,400.00
731 Kg Pasir Beton 242.86 267.86 177,528.57 195,803.57
1,031 Kg Kerikil (maksimum 30 mm) 237.04 281.48 244,385.19 290,207.41
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,056,098.76 1,159,645.98
E Overhead & Profit (contoh 10%) 10% 105,609.88 115,964.60
F Harga Satuan Pekerjaan (D+E) 1,161,708.63 1,275,610.58

Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm,


7 A.4.1.1.7 1 m3 1,181,099.77 1,295,921.44
w/c = 0,58
A Tenaga 225,085.00 245,860.00
L.01 1.650 OH Pekerja 105,000.00 115,000.00 173,250.00 189,750.00
L.02 0.275 OH Tukang Batu 135,000.00 145,000.00 37,125.00 39,875.00
L.03 0.028 OH Kepala Tukang 140,000.00 150,000.00 3,920.00 4,200.00
L.04 0.083 OH Mandor 130,000.00 145,000.00 10,790.00 12,035.00
B Bahan 848,642.06 932,250.40
371 Kg Portland Semen 1,150.00 1,200.00 426,650.00 445,200.00
698 Kg Pasir Beton 242.86 267.86 169,514.29 186,964.29
1,047 Kg Kerikil (maksimum 30 mm) 237.04 281.48 248,177.78 294,711.11
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,073,727.06 1,178,110.40
E Overhead & Profit (contoh 10%) 10% 107,372.71 117,811.04
F Harga Satuan Pekerjaan (D+E) 1,181,099.77 1,295,921.44

Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm,


8 A.4.1.1.8 1 m3 1,193,855.99 1,308,836.54
w/c = 0,56
A Tenaga 225,085.00 245,860.00
L.01 1.650 OH Pekerja 105,000.00 115,000.00 173,250.00 189,750.00
L.02 0.275 OH Tukang Batu 135,000.00 145,000.00 37,125.00 39,875.00
L.03 0.028 OH Kepala Tukang 140,000.00 150,000.00 3,920.00 4,200.00
L.04 0.083 OH Mandor 130,000.00 145,000.00 10,790.00 12,035.00
B Bahan 860,238.62 943,991.40
384 Kg Portland Semen 1,150.00 1,200.00 441,600.00 460,800.00
692 Kg Pasir Beton 242.86 267.86 168,057.14 185,357.14
1,039 Kg Kerikil (maksimum 30 mm) 237.04 281.48 246,281.48 292,459.26
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,085,323.62 1,189,851.40
E Overhead & Profit (contoh 10%) 10% 108,532.36 118,985.14
F Harga Satuan Pekerjaan (D+E) 1,193,855.99 1,308,836.54

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum


9 A.4.1.1.9 1 m3 1,216,159.21 1,331,494.21
(12±2)cm, w/c = 0,53
A Tenaga 225,085.00 245,860.00
L.01 1.650 OH Pekerja 105,000.00 115,000.00 173,250.00 189,750.00
L.02 0.275 OH Tukang Batu 135,000.00 145,000.00 37,125.00 39,875.00
L.03 0.028 OH Kepala Tukang 140,000.00 150,000.00 3,920.00 4,200.00
L.04 0.083 OH Mandor 130,000.00 145,000.00 10,790.00 12,035.00
B Bahan 880,514.29 964,589.29
406 Kg Portland Semen 1,150.00 1,200.00 466,900.00 487,200.00
684 kg Pasir Beton 242.86 267.86 166,114.29 183,214.29
1,026 kg Kerikil (maksimum 30 mm) 237.04 281.48 243,200.00 288,800.00
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,105,599.29 1,210,449.29
E Overhead & Profit (contoh 10%) 10% 110,559.93 121,044.93
F Harga Satuan Pekerjaan (D+E) 1,216,159.21 1,331,494.21

file:///conversion/tmp/scratch/500669137.xls 125/58 4-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm,
10 A.4.1.1.10 1 m3 1,222,909.08 1,338,302.14
w/c = 0,52
A Tenaga 225,085.00 245,860.00
L.01 1.650 OH Pekerja 105,000.00 115,000.00 173,250.00 189,750.00
L.02 0.275 OH Tukang Batu 135,000.00 145,000.00 37,125.00 39,875.00
L.03 0.028 OH Kepala Tukang 140,000.00 150,000.00 3,920.00 4,200.00
L.04 0.083 OH Mandor 130,000.00 145,000.00 10,790.00 12,035.00
B Bahan 886,650.53 970,778.31
413 Kg Portland Semen 1,150.00 1,200.00 474,950.00 495,600.00
681 Kg Pasir Beton 242.86 267.86 165,385.71 182,410.71
1,021 Kg Kerikil (maksimum 30 mm) 237.04 281.48 242,014.81 287,392.59
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,111,735.53 1,216,638.31
E Overhead & Profit (contoh 10%) 10% 111,173.55 121,663.83
F Harga Satuan Pekerjaan (D+E) 1,222,909.08 1,338,302.14

Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm,


11 A.4.1.1.11 1 m3 1,316,285.90 1,438,288.12
w/c = 0,49
A Tenaga 286,300.00 312,725.00
L.01 2.1 OH Pekerja 105,000.00 115,000.00 220,500.00 241,500.00
L.02 0.35 OH Tukang Batu 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.105 OH Mandor 130,000.00 145,000.00 13,650.00 15,225.00
B Bahan 910,323.54 994,809.66
439 Kg Portland Semen 1,150.00 1,200.00 504,850.00 526,800.00
670 Kg Pasir Beton 242.86 267.86 162,714.29 179,464.29
1,006 Kg Kerikil (maksimum 30 mm) 237.04 281.48 238,459.26 283,170.37
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,196,623.54 1,307,534.66
E Overhead & Profit (contoh 10%) 10% 119,662.35 130,753.47
F Harga Satuan Pekerjaan (D+E) 1,316,285.90 1,438,288.12

Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm,


12 A.4.1.1.12 1 m3 1,325,305.03 1,447,426.42
w/c = 0,48
A Tenaga 286,300.00 312,725.00
L.01 2.10 OH Pekerja 105,000.00 115,000.00 220,500.00 241,500.00
L.02 0.350 OH Tukang Batu 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.105 OH Mandor 130,000.00 145,000.00 13,650.00 15,225.00
B Bahan 918,522.75 1,003,117.20
448 Kg Portland Semen 1,150.00 1,200.00 515,200.00 537,600.00
667 Kg Pasir Beton 242.86 267.86 161,985.71 178,660.71
1,000 Kg Kerikil (maksimum 30 mm) 237.04 281.48 237,037.04 281,481.48
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,204,822.75 1,315,842.20
E Overhead & Profit (contoh 10%) 10% 120,482.28 131,584.22
F Harga Satuan Pekerjaan (D+E) 1,325,305.03 1,447,426.42

13 A.4.1.1.17 10 Kg Pembesian dg Besi Polos atau Besi Ulir 141,075.00 163,713.00


A Tenaga 18,300.00 19,830.00
L.01 0.07 OH Pekerja 105,000.00 115,000.00 7,350.00 8,050.00
L.02 0.07 OH Tukang Besi 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.004 OH Mandor 130,000.00 145,000.00 520.00 580.00
B Bahan 109,950.00 129,000.00
10.50 Kg Besi Beton (polos/ulir) 10,200.00 12,000.00 107,100.00 126,000.00
0.150 Kg Kawat Beton 19,000.00 20,000.00 2,850.00 3,000.00
C PERALATAN
D Jumlah A + B + C 128,250.00 148,830.00
E Overhead & Profit (contoh 10%) 10% 12,825.00 14,883.00
F Harga Satuan Pekerjaan (D+E) 141,075.00 163,713.00

14 A.4.1.1.18 10 Kg Kabel Presstresed Polos/strand 178,189.00 185,278.50


A Tenaga 13,090.00 14,185.00
L.01 0.05 OH Pekerja 105,000.00 115,000.00 5,250.00 5,750.00
L.02 0.05 OH Tukang Besi 135,000.00 145,000.00 6,750.00 7,250.00
L.03 0.005 OH Kepala Tukang 140,000.00 150,000.00 700.00 750.00
L.04 0.003 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 148,900.00 154,250.00
10.5 Kg Besi presstred polos 14,000.00 14,500.00 147,000.00 152,250.00
0.1 Kg Kawat Beton 19,000.00 20,000.00 1,900.00 2,000.00

file:///conversion/tmp/scratch/500669137.xls 125/59 4-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 161,990.00 168,435.00
E Overhead & Profit (contoh 10%) 10% 16,199.00 16,843.50
F Harga Satuan Pekerjaan (D+E) 178,189.00 185,278.50

15 A.4.1.1.19 10 Kg Jaring Kawat baja/Wire Mesh 288,596.00 300,459.50


A Tenaga 6,410.00 6,945.00
L.01 0.025 OH Pekerja 105,000.00 115,000.00 2,625.00 2,875.00
L.02 0.025 OH Tukang Besi 135,000.00 145,000.00 3,375.00 3,625.00
L.03 0.002 OH Kepala Tukang 140,000.00 150,000.00 280.00 300.00
L.04 0.001 OH Mandor 130,000.00 145,000.00 130.00 145.00
B Bahan 255,950.00 266,200.00
10.20 Kg Jaring Kawat Baja dilas 25,000.00 26,000.00 255,000.00 265,200.00
0.05 Kg Kawat Beton 19,000.00 20,000.00 950.00 1,000.00
C PERALATAN
D Jumlah A + B + C 262,360.00 273,145.00
E Overhead & Profit (contoh 10%) 10% 26,236.00 27,314.50
F Harga Satuan Pekerjaan (D+E) 288,596.00 300,459.50

16 A.4.1.1.20 1 m2 Memasang Bekisting untuk Pondasi 200,992.00 219,362.00


A Tenaga 96,720.00 105,170.00
L.01 0.52 OH Pekerja 105,000.00 115,000.00 54,600.00 59,800.00
L.02 0.26 OH Tukang Kayu 135,000.00 145,000.00 35,100.00 37,700.00
L.03 0.026 OH Kepala Tukang 140,000.00 150,000.00 3,640.00 3,900.00
L.04 0.026 OH Mandor 130,000.00 145,000.00 3,380.00 3,770.00
B Bahan 86,000.00 94,250.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.3 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 5,100.00 5,250.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 182,720.00 199,420.00
E Overhead & Profit (contoh 10%) 10% 18,272.00 19,942.00
F Harga Satuan Pekerjaan (D+E) 200,992.00 219,362.00

17 A.4.1.1.21 1 m2 Memasang Bekisting untuk Sloof 211,992.00 231,462.00


A Tenaga 96,720.00 105,170.00
L.01 0.52 OH Pekerja 105,000.00 115,000.00 54,600.00 59,800.00
L.02 0.26 OH Tukang Kayu 135,000.00 145,000.00 35,100.00 37,700.00
L.03 0.026 OH Kepala Tukang 140,000.00 150,000.00 3,640.00 3,900.00
L.04 0.026 OH Mandor 130,000.00 145,000.00 3,380.00 3,770.00
B Bahan 96,000.00 105,250.00
0.045 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 90,000.00 99,000.00
0.3 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 5,100.00 5,250.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 192,720.00 210,420.00
E Overhead & Profit (contoh 10%) 10% 19,272.00 21,042.00
F Harga Satuan Pekerjaan (D+E) 211,992.00 231,462.00

18 A.4.1.1.22 1 m2 Memasang Bekisting untuk Kolom 428,296.00 468,583.50


A Tenaga 122,760.00 133,485.00
L.01 0.66 OH Pekerja 105,000.00 115,000.00 69,300.00 75,900.00
L.02 0.33 OH Tukang Kayu 135,000.00 145,000.00 44,550.00 47,850.00
L.03 0.033 OH Kepala Tukang 140,000.00 150,000.00 4,620.00 4,950.00
L.04 0.033 OH Mandor 130,000.00 145,000.00 4,290.00 4,785.00
B Bahan 266,600.00 292,500.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 6,800.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II 6,500,000.00 6,800,000.00 97,500.00 102,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 130,000.00 38,500.00 45,500.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 389,360.00 425,985.00
E Overhead & Profit (contoh 10%) 10% 38,936.00 42,598.50
F Harga Satuan Pekerjaan (D+E) 428,296.00 468,583.50

19 A.4.1.1.23 1 m2 Memasang Bekisting untuk Balok 449,746.00 491,023.50


A Tenaga 122,760.00 133,485.00
L.01 0.66 OH Pekerja 105,000.00 115,000.00 69,300.00 75,900.00
L.02 0.33 OH Tukang Kayu 135,000.00 145,000.00 44,550.00 47,850.00
L.03 0.033 OH Kepala Tukang 140,000.00 150,000.00 4,620.00 4,950.00
L.04 0.033 OH Mandor 130,000.00 145,000.00 4,290.00 4,785.00

file:///conversion/tmp/scratch/500669137.xls 125/60 4-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 286,100.00 312,900.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 6,800.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.018 m3 Balok Kayu Klas II 6,500,000.00 6,800,000.00 117,000.00 122,400.00
0.35 Lbr Plywood tebal 9mm 110,000.00 130,000.00 38,500.00 45,500.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 408,860.00 446,385.00
E Overhead & Profit (contoh 10%) 10% 40,886.00 44,638.50
F Harga Satuan Pekerjaan (D+E) 449,746.00 491,023.50

20 A.4.1.1.24 1 m2 Memasang Bekisting untuk Lantai 520,696.00 574,183.50


A Tenaga 122,760.00 133,485.00
L.01 0.66 OH Pekerja 105,000.00 115,000.00 69,300.00 75,900.00
L.02 0.33 OH Tukang Kayu 135,000.00 145,000.00 44,550.00 47,850.00
L.03 0.033 OH Kepala Tukang 140,000.00 150,000.00 4,620.00 4,950.00
L.04 0.033 OH Mandor 130,000.00 145,000.00 4,290.00 4,785.00
B Bahan 350,600.00 388,500.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 6,800.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II (Borneo) 6,500,000.00 6,800,000.00 97,500.00 102,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 130,000.00 38,500.00 45,500.00
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 126,000.00 144,000.00
C PERALATAN
D Jumlah A + B + C 473,360.00 521,985.00
E Overhead & Profit (contoh 10%) 10% 47,336.00 52,198.50
F Harga Satuan Pekerjaan (D+E) 520,696.00 574,183.50

21 A.4.1.1.25 1 m2 Memasang Bekisting untuk Dinding 487,146.00 532,383.50


A Tenaga 122,760.00 133,485.00
L.01 0.66 OH Pekerja 105,000.00 115,000.00 69,300.00 75,900.00
L.02 0.33 OH Tukang Kayu 135,000.00 145,000.00 44,550.00 47,850.00
L.03 0.033 OH Kepala Tukang 140,000.00 150,000.00 4,620.00 4,950.00
L.04 0.033 OH Mandor 130,000.00 145,000.00 4,290.00 4,785.00
B Bahan 320,100.00 350,500.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 6,800.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.02 m3 Balok Kayu Klas II 6,500,000.00 6,800,000.00 130,000.00 136,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 130,000.00 38,500.00 45,500.00
3 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 63,000.00 72,000.00
4 Buah Formite/Penjaga jarak / Spacer (alat bantu) 5,000.00 5,500.00 20,000.00 22,000.00
C PERALATAN
D Jumlah A + B + C 442,860.00 483,985.00
E Overhead & Profit (contoh 10%) 10% 44,286.00 48,398.50
F Harga Satuan Pekerjaan (D+E) 487,146.00 532,383.50

22 A.4.1.1.26 1 m2 Memasang Bekisting untuk Tangga 405,801.00 443,833.50


A Tenaga 122,760.00 133,485.00
L.01 0.66 OH Pekerja 105,000.00 115,000.00 69,300.00 75,900.00
L.02 0.33 OH Tukang Kayu 135,000.00 145,000.00 44,550.00 47,850.00
L.03 0.033 OH Kepala Tukang 140,000.00 150,000.00 4,620.00 4,950.00
L.04 0.033 OH Mandor 130,000.00 145,000.00 4,290.00 4,785.00
B Bahan 246,150.00 270,000.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 6,800.00 7,000.00
0.15 Ltr Minyak Bekisting 9,000.00 10,000.00 1,350.00 1,500.00
0.015 m3 Balok Kayu Klas II 6,500,000.00 6,800,000.00 97,500.00 102,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 130,000.00 38,500.00 45,500.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 368,910.00 403,485.00
E Overhead & Profit (contoh 10%) 10% 36,891.00 40,348.50
F Harga Satuan Pekerjaan (D+E) 405,801.00 443,833.50

23 A.4.1.1.27 1 m2 Memasang Jembatan Cor 107,514.00 117,689.00


A Tenaga 24,240.00 26,410.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.02 0.05 OH Tukang Kayu 135,000.00 145,000.00 6,750.00 7,250.00
L.03 0.005 OH Kepala Tukang 140,000.00 150,000.00 700.00 750.00
L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 73,500.00 80,580.00
0.0264 m3 Kayu Terentang 2,000,000.00 2,200,000.00 52,800.00 58,080.00
0.6 kg Paku Biasa 2" - 5" 17,000.00 17,500.00 10,200.00 10,500.00
0.5 m3 Dolken Kayu Galam diameter 8 - 10 / 4 m 21,000.00 24,000.00 10,500.00 12,000.00

file:///conversion/tmp/scratch/500669137.xls 125/61 4-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 97,740.00 106,990.00
E Overhead & Profit (contoh 10%) 10% 9,774.00 10,699.00
F Harga Satuan Pekerjaan (D+E) 107,514.00 117,689.00

24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 92,455.00 102,817.00
A Tenaga 28,810.00 31,405.00
L.01 0.180 OH Pekerja 105,000.00 115,000.00 18,900.00 20,700.00
L.02 0.020 OH Tukang batu 135,000.00 145,000.00 2,700.00 2,900.00
L.02 0.020 OH Tukang Kayu 135,000.00 145,000.00 2,700.00 2,900.00
L.02 0.020 OH Tukang Besi 125,000.00 135,000.00 2,500.00 2,700.00
L.03 0.006 OH Kepala Tukang 140,000.00 150,000.00 840.00 900.00
L.04 0.009 OH Mandor 130,000.00 145,000.00 1,170.00 1,305.00
B Bahan 55,240.00 62,065.00
0.002 m3 Kayu Klas III 3,290,000.00 3,300,000.00 6,580.00 6,600.00
0.01 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 170.00 175.00
3.0 Kg Besi Beton Polos 10,200.00 12,000.00 30,600.00 36,000.00
0.45 Kg Kawat Beton 19,000.00 20,000.00 8,550.00 9,000.00
4.0 Kg Portland Semen 1,150.00 1,200.00 4,600.00 4,800.00
0.006 m3 Pasir Beton 340,000.00 375,000.00 2,040.00 2,250.00
0.009 m3 Kerikil 300,000.00 360,000.00 2,700.00 3,240.00
C PERALATAN
D Jumlah A + B + C 84,050.00 93,470.00
E Overhead & Profit (contoh 10%) 10% 8,405.00 9,347.00
F Harga Satuan Pekerjaan (D+E) 92,455.00 102,817.00

25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 120,268.50 133,848.00
A Tenaga 47,570.00 51,855.00
L.01 0.297 OH Pekerja 105,000.00 115,000.00 31,185.00 34,155.00
L.02 0.033 OH Tukang batu 135,000.00 145,000.00 4,455.00 4,785.00
L.02 0.033 OH Tukang Kayu 135,000.00 145,000.00 4,455.00 4,785.00
L.02 0.033 OH Tukang Besi 125,000.00 135,000.00 4,125.00 4,455.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 61,765.00 69,825.00
0.003 m3 Kayu Klas III 3,290,000.00 3,300,000.00 9,870.00 9,900.00
0.02 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 340.00 350.00
3.6 Kg Besi Beton Polos 10,200.00 12,000.00 36,720.00 43,200.00
0.05 Kg Kawat Beton 19,000.00 20,000.00 950.00 1,000.00
5.5 Kg Portland Semen 1,150.00 1,200.00 6,325.00 6,600.00
0.009 m3 Pasir Beton 340,000.00 375,000.00 3,060.00 3,375.00
0.015 m3 Kerikil 300,000.00 360,000.00 4,500.00 5,400.00
C PERALATAN
D Jumlah A + B + C 109,335.00 121,680.00
E Overhead & Profit (contoh 10%) 10% 10,933.50 12,168.00
F Harga Satuan Pekerjaan (D+E) 120,268.50 133,848.00

file:///conversion/tmp/scratch/500669137.xls 125/62 4-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
UNTUK PRODUKSI PRACETAK BISA DILAKUKAN DI PABRIK (COR DI PLANT) ATAU DI LAPANGAN (CAST IN PLACE). INDEKS YANG ADA DALAM PEDOMAN INI
HANYA UNTUK PEKERJAAN PRODUKSI YANG DILAKUKAN DI LAPANGAN, TERUTAMA UNTUK ANALISA CETAKAN (BEKISTING) PRACETAK BAIK UNTUK
KOMPONEN KOLOM, BALOK DAN PELAT.

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c 14,5 Mpa,


1 A.4.1.2.1 1 m2 90,898.06 99,955.10
Slump (120 ± 20) mm K3
A Tenaga 18,020.00 19,685.00
L.01 0.132 OH Pekerja 105,000.00 115,000.00 13,860.00 15,180.00
L.02 0.022 OH Tukang Batu 135,000.00 145,000.00 2,970.00 3,190.00
L.03 0.002 OH Kepala Tukang 140,000.00 150,000.00 280.00 300.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 64,614.60 71,183.27
26.080 Kg Portland Semen 1,150.00 1,200.00 29,992.00 31,296.00
60.800 Kg Pasir Beton 242.86 267.86 14,765.71 16,285.71
82.320 Kg Kerikil (maksimum 30 mm) 237.04 281.48 19,512.89 23,171.56
17.200 ltr Air 20.00 25.00 344.00 430.00
C PERALATAN
D Jumlah A + B + C 82,634.60 90,868.27
E Overhead & Profit (contoh 10%) 10% 8,263.46 9,086.83
F Harga Satuan Pekerjaan (D+E) 90,898.06 99,955.10
10%
Overhead & Profit (contoh 10%)
Pembuatan Lahan Produksi Tebal 10 cm Beton f'c = 14,5 Mpa
2 A.4.1.2.2 1 m2 113,666.58 124,986.50
slum (120 ± 20 ) mm K3
A Tenaga 22,565.00 24,645.00
L.01 0.165 OH Pekerja 105,000.00 115,000.00 17,325.00 18,975.00
L.02 0.028 OH Tukang Batu 135,000.00 145,000.00 3,780.00 4,060.00
L.03 0.003 OH Kepala Tukang 140,000.00 150,000.00 420.00 450.00
L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 80,768.25 88,979.09
32.60 Kg Portland Semen 1,150.00 1,200.00 37,490.00 39,120.00
76.00 kg Pasir Beton 242.86 267.86 18,457.14 20,357.14
102.90 kg Kerikil (maksimum 30 mm) 237.04 281.48 24,391.11 28,964.44
21.50 ltr Air 20.00 25.00 430.00 537.50
C PERALATAN
D Jumlah A + B + C 103,333.25 113,624.09
E Overhead & Profit (contoh 10%) 10% 10,333.33 11,362.41
F Harga Satuan Pekerjaan (D+E) 113,666.58 124,986.50

Pembuatan Lahan Produksi Tebal 12 cm Beton f'c=14,5 Mpa,


3 A.4.1.2.3 1 m2 132,464.10 145,678.40
slum (120±20)mm, K3
A Tenaga 23,500.00 25,660.00
L.01 0.165 OH Pekerja 105,000.00 115,000.00 17,325.00 18,975.00
L.02 0.033 OH Tukang Batu 135,000.00 145,000.00 4,455.00 4,785.00
L.03 0.003 OH Kepala Tukang 140,000.00 150,000.00 420.00 450.00
L.04 0.010 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00
B Bahan 96,921.90 106,774.90
39.120 Kg Portland Semen 1,150.00 1,200.00 44,988.00 46,944.00
91.200 kg Pasir Beton 242.86 267.86 22,148.57 24,428.57
123.480 kg Kerikil (maksimum 30 mm) 237.04 281.48 29,269.33 34,757.33
25.800 ltr Air 20.00 25.00 516.00 645.00
C PERALATAN
D Jumlah A + B + C 120,421.90 132,434.90
E Overhead & Profit (contoh 10%) 10% 12,042.19 13,243.49
F Harga Satuan Pekerjaan (D+E) 132,464.10 145,678.40

Pembuatan Lahan Produksi Tebal 15 cm Beton f'c=14,5 Mpa,


4 A.4.1.2.4 1.00 m2 170,475.12 187,460.49
slum (120±20)mm, K3
A Tenaga 33,825.00 36,950.00
L.01 0.248 OH Pekerja 105,000.00 115,000.00 26,040.00 28,520.00
L.02 0.041 OH Tukang Batu 135,000.00 145,000.00 5,535.00 5,945.00
L.03 0.004 OH Kepala Tukang 140,000.00 150,000.00 560.00 600.00
L.04 0.013 OH Mandor 130,000.00 145,000.00 1,690.00 1,885.00
B Bahan 121,152.38 133,468.63
48.900 Kg Portland Semen 1,150.00 1,200.00 56,235.00 58,680.00
114.000 kg Pasir Beton 242.86 267.86 27,685.71 30,535.71
154.350 kg Kerikil (maksimum 30 mm) 237.04 281.48 36,586.67 43,446.67
32.250 ltr Air 20.00 25.00 645.00 806.25
C PERALATAN
D Jumlah A + B + C 154,977.38 170,418.63
E Overhead & Profit (contoh 10%) 10% 15,497.74 17,041.86
F Harga Satuan Pekerjaan (D+E) 170,475.12 187,460.49

Pembuatan Bekisting untuk Plat Beton Pra cetak (5 kali


5 A.4.1.2.5 1 m2 128,430.66 137,870.62
Pakai)
A Tenaga 12,245.00 13,170.00
L.01 0.007 OH Pekerja 105,000.00 115,000.00 735.00 805.00
L.02 0.076 OH Tukang Batu 135,000.00 145,000.00 10,260.00 11,020.00
L.03 0.008 OH Kepala Tukang 140,000.00 150,000.00 1,120.00 1,200.00
L.04 0.001 OH Mandor 130,000.00 145,000.00 130.00 145.00

file:///conversion/tmp/scratch/500669137.xls 125/63 4a-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 104,510.14 112,166.93
0.008 m3 Lantai Kerja Tebal 10 cm 97,392.73 107,816.27 779.14 862.53
9.394 Kg Besi Hollow (50x50x3) mm 5,500.00 6,000.00 51,667.00 56,364.00
0.005 m3 Kayu Kaso 5/7 6,500,000.00 6,800,000.00 32,500.00 34,000.00
0.080 lbr Phenol film 12 mm 125,000.00 130,000.00 10,000.00 10,400.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
3.882 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 7,764.00 8,540.40
C PERALATAN
D Jumlah A + B + C 116,755.14 125,336.93
E Overhead & Profit (contoh 10%) 10% 11,675.51 12,533.69
F Harga Satuan Pekerjaan (D+E) 128,430.66 137,870.62

Pembuatan Bekisting untuk Balok Beton Pra cetak (10 - 12


6 A.4.1.2.6 1 m2 48,083.00 50,634.60
kali Pakai)
A Tenaga 6,240.00 6,715.00
L.01 0.004 OH Pekerja 105,000.00 115,000.00 420.00 460.00
L.02 0.038 OH Tukang Batu 135,000.00 145,000.00 5,130.00 5,510.00
L.03 0.004 OH Kepala Tukang 140,000.00 150,000.00 560.00 600.00
L.04 0.001 OH Mandor 130,000.00 145,000.00 130.00 145.00
B Bahan 41,843.00 43,919.60
0.046 Kg Paku (5 s/d 7) cm 17,000.00 17,500.00 782.00 805.00
0.005 m3 Kayu Kaso 5/7 6,500,000.00 6,800,000.00 32,500.00 34,000.00
0.043 lbr Phenol film 12 mm 125,000.00 130,000.00 5,375.00 5,590.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.693 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 1,386.00 1,524.60
C PERALATAN
D Jumlah A + B + C 48,083.00 50,634.60
E Overhead & Profit (contoh 10%) 10% 4,808.30 5,063.46
F Harga Satuan Pekerjaan (D+E) 52,891.30 55,698.06

Pembuatan Bekisting untuk Kolom Beton Pra cetak (10 - 12


7 A.4.1.2.7 1 m2 42,208.00 44,484.60
kali Pakai)
A Tenaga 6,240.00 6,715.00
L.01 0.004 OH Pekerja 105,000.00 115,000.00 420.00 460.00
L.02 0.038 OH Tukang Batu 135,000.00 145,000.00 5,130.00 5,510.00
L.03 0.004 OH Kepala Tukang 140,000.00 150,000.00 560.00 600.00
L.04 0.001 OH Mandor 130,000.00 145,000.00 130.00 145.00
B Bahan 35,968.00 37,769.60
0.046 Kg Paku (5 s/d 7) cm 17,000.00 17,500.00 782.00 805.00
0.004 m3 Kayu Kaso 5/7 6,500,000.00 6,800,000.00 26,000.00 27,200.00
0.048 lbr Phenol film 12 mm 125,000.00 130,000.00 6,000.00 6,240.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.693 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 1,386.00 1,524.60
C PERALATAN
D Jumlah A + B + C 42,208.00 44,484.60
E Overhead & Profit (contoh 10%) 10% 4,220.80 4,448.46
F Harga Satuan Pekerjaan (D+E) 46,428.80 48,933.06

Pemasangan dan Membuka Bekisting untuk Komponen Plat


8 A.4.1.2.8 1 bh 8,645.00 9,430.00
Beton Pracetak
A Tenaga 8,645.00 9,430.00
L.01 0.053 OH Pekerja 105,000.00 115,000.00 5,565.00 6,095.00
L.02 0.018 OH Tukang Batu 135,000.00 145,000.00 2,430.00 2,610.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan
C PERALATAN
D Jumlah A + B + C 8,645.00 9,430.00
E Overhead & Profit (contoh 10%) 10% 864.50 943.00
F Harga Satuan Pekerjaan (D+E) 9,509.50 10,373.00

Pemasangan dan Membuka Bekisting untuk Komponen


9 A.4.1.2.9 1 bh 14,045.00 15,310.00
Balok Beton Pracetak
A Tenaga 14,045.00 15,310.00
L.01 0.089 OH Pekerja 105,000.00 115,000.00 9,345.00 10,235.00
L.02 0.030 OH Tukang Batu 135,000.00 145,000.00 4,050.00 4,350.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan
C PERALATAN
D Jumlah A + B + C 14,045.00 15,310.00
E Overhead & Profit (contoh 10%) 10% 1,404.50 1,531.00
F Harga Satuan Pekerjaan (D+E) 15,449.50 16,841.00

file:///conversion/tmp/scratch/500669137.xls 125/64 4a-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan dan Membuka Bekisting untuk Komponen
10 A.4.1.2.10 1 bh 11,345.00 12,370.00
Kolom Beton Pracetak
A Tenaga 11,345.00 12,370.00
L.01 0.071 OH Pekerja 105,000.00 115,000.00 7,455.00 8,165.00
L.02 0.024 OH Tukang Batu 135,000.00 145,000.00 3,240.00 3,480.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan
C PERALATAN
D Jumlah A + B + C 11,345.00 12,370.00
E Overhead & Profit (contoh 10%) 10% 1,134.50 1,237.00
F Harga Satuan Pekerjaan (D+E) 12,479.50 13,607.00

11 A.4.1.2.11 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 78,309.00 76,985.00

A Tenaga 71,190.00 76,985.00


L.01 0.064 OH Pekerja 105,000.00 115,000.00 6,720.00 7,360.00
L.02 0.244 OH Tukang Batu 135,000.00 145,000.00 32,940.00 35,380.00
L.02 0.128 OH Tukang Vibrator 135,000.00 145,000.00 17,280.00 18,560.00
L.03 0.034 OH Kapala Tukang 140,000.00 150,000.00 4,760.00 5,100.00
L.04 0.073 OH Mandor 130,000.00 145,000.00 9,490.00 10,585.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 71,190.00 76,985.00
E Overhead & Profit (contoh 10%) 10% 7,119.00 7,698.50
F Harga Satuan Pekerjaan (D+E) 78,309.00 84,683.50

12 A.4.1.2.12 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 80,536.50 79,170.00

A Tenaga 73,215.00 79,170.00


L.01 0.069 OH Pekerja 105,000.00 115,000.00 7,245.00 7,935.00
L.02 0.242 OH Tukang Batu 135,000.00 145,000.00 32,670.00 35,090.00
L.02 0.138 OH Tukang Vibrator 135,000.00 145,000.00 18,630.00 20,010.00
L.03 0.037 OH Kapala Tukang 140,000.00 150,000.00 5,180.00 5,550.00
L.04 0.073 OH Mandor 130,000.00 145,000.00 9,490.00 10,585.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 73,215.00 79,170.00
E Overhead & Profit (contoh 10%) 10% 7,321.50 7,917.00
F Harga Satuan Pekerjaan (D+E) 80,536.50 87,087.00

Penuangan / Menebar Beton untuk Komponen Kolom


13 A.4.1.2.13 1 m3 72,314.00 71,125.00
Pracetak
A Tenaga 65,740.00 71,125.00
L.01 0.061 OH Pekerja 105,000.00 115,000.00 6,405.00 7,015.00
L.02 0.213 OH Tukang Batu 135,000.00 145,000.00 28,755.00 30,885.00
L.02 0.122 OH Tukang Vibrator 135,000.00 145,000.00 16,470.00 17,690.00
L.03 0.033 OH Kapala Tukang 140,000.00 150,000.00 4,620.00 4,950.00
L.04 0.073 OH Mandor 130,000.00 145,000.00 9,490.00 10,585.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 65,740.00 71,125.00
E Overhead & Profit (contoh 10%) 10% 6,574.00 7,112.50
F Harga Satuan Pekerjaan (D+E) 72,314.00 78,237.50

14 A.4.1.2.14 1 bh Ereksi Komponen Untuk Plat Pracetak 589,086.52 614,810.46


A Tenaga 54,940.00 59,965.00
L.08 0.067 OH Operator Crane 175,000.00 200,000.00 11,725.00 13,400.00
L.09 0.067 OH Pembantu Operator Crane 135,000.00 145,000.00 9,045.00 9,715.00
L.01 0.067 OH Pekerja 105,000.00 115,000.00 7,035.00 7,705.00
L.02 0.067 OH Tukang Batu 135,000.00 145,000.00 9,045.00 9,715.00
L.02 0.134 OH Tukang Ereksi 135,000.00 145,000.00 18,090.00 19,430.00
L.03 0.067 OH Kepala Tukang 140,000.00 150,000.00 9,380.00 10,050.00
L.04 0.067 OH Mandor 130,000.00 145,000.00 8,710.00 9,715.00
B Bahan 54,743.20 57,413.60
6.676 Ltr Solar 8,200.00 8,600.00 54,743.20 57,413.60
C PERALATAN 425,850.00 441,540.00
0.067 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 304,850.00 309,540.00
1.100 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 121,000.00 132,000.00
D Jumlah A + B + C 535,533.20 558,918.60
E Overhead & Profit (contoh 10%) 10% 53,553.32 55,891.86
F Harga Satuan Pekerjaan (D+E) 589,086.52 614,810.46

file:///conversion/tmp/scratch/500669137.xls 125/65 4a-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Indek Kenaikan Lantai Ereksi Komponen untuk Plat Pracetak
Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Plat Ereksi Plat

1 1.0000 13 1.114
2 1.0000 14 1.134

3 1.0000 15 1.155

4 1.0000 16 1.176
5 1.0000 17 1.197

6 1.0000 18 1.219
7 1.0000 19 1.241

8 1.0180 20 1.264
9 1.0370 21 1.287

10 1.0550 22 1.310
11 1.0750 23 1.334

12 1.0940 24 1.358

15 A.4.1.2.15 1 bh Ereksi Komponen Untuk Balok Pracetak 578,569.20 603,549.10


A Tenaga 50,020.00 54,595.00
L.08 0.061 OH Operator Crane 175,000.00 200,000.00 10,675.00 12,200.00
L.09 0.061 OH Pembantu Operator Crane 135,000.00 145,000.00 8,235.00 8,845.00
L.01 0.061 OH Pekerja 105,000.00 115,000.00 6,405.00 7,015.00
L.02 0.061 OH Tukang Batu 135,000.00 145,000.00 8,235.00 8,845.00
L.02 0.122 OH Tukang Ereksi 135,000.00 145,000.00 16,470.00 17,690.00
L.03 0.061 OH Kepala Tukang 140,000.00 150,000.00 8,540.00 9,150.00
L.04 0.061 OH Mandor 130,000.00 145,000.00 7,930.00 8,845.00
B Bahan 50,102.00 52,546.00
6.110 Ltr Solar 8,200.00 8,600.00 50,102.00 52,546.00
C PERALATAN 425,850.00 441,540.00
0.067 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 304,850.00 309,540.00
1.100 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 121,000.00 132,000.00
D Jumlah A + B + C 525,972.00 548,681.00
E Overhead & Profit (contoh 10%) 10% 52,597.20 54,868.10
F Harga Satuan Pekerjaan (D+E) 578,569.20 603,549.10

Indek Kenaikan Lantai Ereksi Komponen untuk Balok Pracetak


Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Balok Ereksi Balok
1 1.0000 13 1.068

2 1.0000 14 1.080
3 1.0000 15 1.092

4 1.0000 16 1.104
5 1.0000 17 1.116

6 1.0000 18 1.129
7 1.0000 19 1.141

8 1.0110 20 1.154
9 1.0220 21 1.166

10 1.0340 22 1.179

11 1.0450 23 1.192
12 1.0570 24 1.206

16 A.4.1.2.16 1 bh Ereksi Komponen Untuk Kolom Pracetak 831,139.54 872,219.92


A Tenaga 68,060.00 74,285.00
L.08 0.083 OH Operator Crane 175,000.00 200,000.00 14,525.00 16,600.00
L.09 0.083 OH Pembantu Operator Crane 135,000.00 145,000.00 11,205.00 12,035.00
L.01 0.083 OH Pekerja 105,000.00 115,000.00 8,715.00 9,545.00
L.02 0.083 OH Tukang Batu 135,000.00 145,000.00 11,205.00 12,035.00
L.02 0.166 OH Tukang Ereksi 135,000.00 145,000.00 22,410.00 24,070.00
L.03 0.083 OH Kepala Tukang 140,000.00 150,000.00 11,620.00 12,450.00
L.04 0.083 OH Mandor 130,000.00 145,000.00 10,790.00 12,035.00
B Bahan 67,871.40 71,182.20
8.277 Ltr Solar 8,200.00 8,600.00 67,871.40 71,182.20
C PERALATAN 619,650.00 647,460.00
0.083 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 377,650.00 383,460.00
2.200 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 242,000.00 264,000.00
D Jumlah A + B + C 755,581.40 792,927.20
E Overhead & Profit (contoh 10%) 10% 75,558.14 79,292.72
F Harga Satuan Pekerjaan (D+E) 831,139.54 872,219.92

file:///conversion/tmp/scratch/500669137.xls 125/66 4a-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Indek Kenaikan Lantai Ereksi Komponen untuk Balok Pracetak
Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Balok Ereksi Balok

1 1.0000 13 1.162
2 1.0000 14 1.191

3 1.0000 15 1.221

4 1.0000 16 1.252
5 1.0000 17 1.284

6 1.0000 18 1.318
7 1.0000 19 1.350

8 1.0250 20 1.384
9 1.0510 21 1.419

10 1.0780 22 1.455
11 1.1050 23 1.492

12 1.1330 24 1.530

17 A.4.1.2.17 1 bh Langsiran Komponen untuk Plat Pracetak (± 20 m) 162,420.94 169,740.12


A Tenaga 45,650.00 50,215.00
L.08 0.083 OH Operator Crane 175,000.00 200,000.00 14,525.00 16,600.00
L.09 0.083 OH Pembantu Operator Crane 135,000.00 145,000.00 11,205.00 12,035.00
L.01 0.083 OH Pekerja 105,000.00 115,000.00 8,715.00 9,545.00
L.02 0.083 OH Tukang Batu 135,000.00 145,000.00 11,205.00 12,035.00
B Bahan 15,555.40 16,314.20
1.897 Ltr Solar 8,200.00 8,600.00 15,555.40 16,314.20
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 147,655.40 154,309.20
E Overhead & Profit (contoh 10%) 10% 14,765.54 15,430.92
F Harga Satuan Pekerjaan (D+E) 162,420.94 169,740.12

18 A.4.1.2.18 1 bh Langsiran Komponen untuk Balok Pracetak (± 20 m) 126,522.44 130,178.62


A Tenaga 13,015.00 14,250.00
L.08 0.019 OH Operator Crane 175,000.00 200,000.00 3,325.00 3,800.00
L.09 0.019 OH Pembantu Operator Crane 135,000.00 145,000.00 2,565.00 2,755.00
L.01 0.019 OH Pekerja 105,000.00 115,000.00 1,995.00 2,185.00
L.02 0.038 OH Tukang Batu 135,000.00 145,000.00 5,130.00 5,510.00
B Bahan 15,555.40 16,314.20
1.897 Ltr Solar 8,200.00 8,600.00 15,555.40 16,314.20
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 115,020.40 118,344.20
E Overhead & Profit (contoh 10%) 10% 11,502.04 11,834.42
F Harga Satuan Pekerjaan (D+E) 126,522.44 130,178.62

19 A.4.1.2.19 1 bh Langsiran Komponen untuk Kolom Pracetak (± 20 m) 126,522.44 130,178.62


A Tenaga 13,015.00 14,250.00
L.08 0.019 OH Operator Crane 175,000.00 200,000.00 3,325.00 3,800.00
L.09 0.019 OH Pembantu Operator Crane 135,000.00 145,000.00 2,565.00 2,755.00
L.01 0.019 OH Pekerja 105,000.00 115,000.00 1,995.00 2,185.00
L.02 0.038 OH Tukang Batu 135,000.00 145,000.00 5,130.00 5,510.00
B Bahan 15,555.40 16,314.20
1.897 Ltr Solar 8,200.00 8,600.00 15,555.40 16,314.20
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 115,020.40 118,344.20
E Overhead & Profit (contoh 10%) 10% 11,502.04 11,834.42
F Harga Satuan Pekerjaan (D+E) 126,522.44 130,178.62

20 A.4.1.2.20 1 m3 Bahan Grout Campuran 3,417,700.00 3,689,125.00


A Tenaga - -

B Bahan 3,107,000.00 3,353,750.00


1,200 Kg Semen Grout 1,500.00 1,650.00 1,800,000.00 1,980,000.00
650 kg Screening 2,000.00 2,100.00 1,300,000.00 1,365,000.00
350 Ltr Air 20.00 25.00 7,000.00 8,750.00
C PERALATAN - -
D Jumlah A + B + C 3,107,000.00 3,353,750.00
E Overhead & Profit (contoh 10%) 10% 310,700.00 335,375.00
F Harga Satuan Pekerjaan (D+E) 3,417,700.00 3,689,125.00

file:///conversion/tmp/scratch/500669137.xls 125/67 4a-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
21 A.4.1.2.21 1 m3 Bahan Grout Campuran (tidak Campuran) 3,061,300.00 3,368,750.00
A Tenaga - -

B Bahan 2,783,000.00 3,062,500.00


1,850 Kg Semen Grout 1,500.00 1,650.00 2,775,000.00 3,052,500.00
400 Ltr Air 20.00 25.00 8,000.00 10,000.00
C PERALATAN - -
D Jumlah A + B + C 2,783,000.00 3,062,500.00
E Overhead & Profit (contoh 10%) 10% 278,300.00 306,250.00
F Harga Satuan Pekerjaan (D+E) 3,061,300.00 3,368,750.00

22 A.4.1.2.22 1 ttk Upah Pekerjaan Gruot pada Joint Beton Pra Cetak 71,186.50 76,648.00
A Tenaga 64,715.00 69,680.00
L.02 0.367 OH Tukang Batu 135,000.000 145,000.000 49,545.000 53,215.000
L.03 0.074 OH Kepala Tukang 140,000.000 150,000.000 10,360.000 11,100.000
L.04 0.037 OH Mandor 130,000.000 145,000.000 4,810.000 5,365.000

B Bahan - -

C PERALATAN - -
D Jumlah A + B + C 64,715.00 69,680.00
E Overhead & Profit (contoh 10%) 10% 6,471.50 6,968.00
F Harga Satuan Pekerjaan (D+E) 71,186.50 76,648.00

23 A.4.1.2.23 1 ttk Pemasangan Bekisting Joint Pra Cetak 142,249.80 152,036.50


A Tenaga 38,030.00 41,195.00
L.01 0.147 OH Pekerja 105,000.00 115,000.00 15,435.000 16,905.000
L.02 0.147 OH Tukang Batu 135,000.000 145,000.000 19,845.000 21,315.000
L.03 0.015 OH Kepala Tukang 140,000.000 150,000.000 2,100.000 2,250.000
L.04 0.005 OH Mandor 130,000.000 145,000.000 650.000 725.000
B Bahan 91,288.00 97,020.00
0.012 m3 Kayu Kaso 5/7 6,500,000.00 6,800,000.00 78,000.00 81,600.00
0.004 m3 Papan Cor 2,200,000.00 2,700,000.00 8,800.00 10,800.00
0.264 Kg Paku (5 s/d 7) cm 17,000.00 17,500.00 4,488.00 4,620.00
C PERALATAN - -
D Jumlah A + B + C 129,318.00 138,215.00
E Overhead & Profit (contoh 10%) 10% 12,931.80 13,821.50
F Harga Satuan Pekerjaan (D+E) 142,249.80 152,036.50

24 A.4.1.2.24 1 ttk Upah Pemasangan Joint dengan Sling 62,920.00 68,183.50


A Tenaga 57,200.00 61,985.00
L.01 0.220 OH Pekerja 105,000.00 115,000.00 23,100.000 25,300.000
L.02 0.022 OH Tukang Batu 135,000.000 145,000.000 2,970.000 3,190.000
L.02 0.220 OH Tukang Besi 135,000.000 145,000.000 29,700.000 31,900.000
L.04 0.011 OH Mandor 130,000.000 145,000.000 1,430.000 1,595.000
B Bahan

C PERALATAN - -
D Jumlah A + B + C 57,200.00 61,985.00
E Overhead & Profit (contoh 10%) 10% 5,720.00 6,198.50
F Harga Satuan Pekerjaan (D+E) 62,920.00 68,183.50

file:///conversion/tmp/scratch/500669137.xls 125/68 4a-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

V A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 1 Kg Pemasangan Besi Profil 35,535.50 37,287.25
A Tenaga 15,630.00 16,935.00
L.01 0.06 OH Pekerja 105,000.00 115,000.00 6,300.00 6,900.00
L.02 0.06 OH Tukang Besi 135,000.00 145,000.00 8,100.00 8,700.00
L.03 0.006 OH Kepala Tukang 140,000.00 150,000.00 840.00 900.00
L.04 0.003 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 16,675.00 16,962.50
1.15 Kg Besi Profil 14,500.00 14,750.00 16,675.00 16,962.50
C PERALATAN
D Jumlah A + B + C 32,305.00 33,897.50
E Overhead & Profit (contoh 10%) 10% 3,230.50 3,389.75
F Harga Satuan Pekerjaan (D+E) 35,535.50 37,287.25

2 A.4.2.1.2 1 Kg Pemasangan Rangka Kuda-kuda Baja IWF 29,590.00 31,152.00


A Tenaga 15,630.00 16,935.00
L.01 0.06 OH Pekerja 105,000.00 115,000.00 6,300.00 6,900.00
L.02 0.06 OH Tukang Besi 135,000.00 145,000.00 8,100.00 8,700.00
L.03 0.006 OH Kepala Tukang 140,000.00 150,000.00 840.00 900.00
L.04 0.003 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 11,270.00 11,385.00
1.15 kg Besi Baja IWF 9,800.00 9,900.00 11,270.00 11,385.00
C PERALATAN
D Jumlah A + B + C 26,900.00 28,320.00
E Overhead & Profit (contoh 10%) 10% 2,690.00 2,832.00
F Harga Satuan Pekerjaan (D+E) 29,590.00 31,152.00

3 A.4.2.1.3 100 kg Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) 106,359.00 123,172.50


A Tenaga 24,790.00 26,875.00
L.01 0.100 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.100 OH Tukang Besi 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.001 OH Kepala Tukang 140,000.00 150,000.00 140.00 150.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 11,900.00 13,100.00
1 ltr Solar 8,200.00 8,600.00 8,200.00 8,600.00
0.1 ltr Minyak Pelumas 37,000.00 45,000.00 3,700.00 4,500.00
C PERALATAN 60,000 72,000
0.800 jam Sewa Alat 75,000 90,000 60,000 72,000
D Jumlah A + B + C 96,690.00 111,975.00
E Overhead & Profit (contoh 10%) 10% 9,669.00 11,197.50
F Harga Satuan Pekerjaan (D+E) 106,359.00 123,172.50

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 1 m2 971,201.00 1,007,534.00
rangka baja Siku
A Tenaga 273,460.00 296,290.00
L.01 1.05 OH Pekerja 105,000.00 115,000.00 110,250.00 120,750.00
L.02 1.05 OH Tukang Besi 135,000.00 145,000.00 141,750.00 152,250.00
L.03 0.105 OH Kepala Tukang 140,000.00 150,000.00 14,700.00 15,750.00
L.04 0.052 OH Mandor 130,000.00 145,000.00 6,760.00 7,540.00
B Bahan 609,450.00 619,650.00
15 Kg Besi Siku L.30.30.3 9,800.00 9,900.00 147,000.00 148,500.00
32.8 Kg Besi Plat Baja 14,000.00 14,250.00 459,200.00 467,400.00
0.05 Kg Kawat Las 65,000.00 75,000.00 3,250.00 3,750.00
C PERALATAN
D Jumlah A + B + C 882,910.00 915,940.00
E Overhead & Profit (contoh 10%) 10% 88,291.00 91,594.00
F Harga Satuan Pekerjaan (D+E) 971,201.00 1,007,534.00

5 A.4.2.1.5 10 cm Pengerjaan Pengelasan dengan Las Listrik 25,502.40 29,510.80


A Tenaga 7,440.00 8,090.00
L.01 0.04 OH Pekerja 105,000.00 115,000.00 4,200.00 4,600.00
L.02 0.02 OH Tukang Besi 135,000.00 145,000.00 2,700.00 2,900.00
L.03 0.002 OH Kepala Tukang 140,000.00 150,000.00 280.00 300.00
L.04 0.002 OH Mandor 130,000.00 145,000.00 260.00 290.00
B Bahan 2,994.00 3,438.00
0.04 kg Kawat Las 65,000.00 75,000.00 2,600.00 3,000.00
0.03 ltr Solar 8,200.00 8,600.00 246.00 258.00
0.004 ltr Minyak Pelumas 37,000.00 45,000.00 148.00 180.00

file:///conversion/tmp/scratch/500669137.xls 125/69 5-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

C PERALATAN 12,750 15,300


0.170 jam Sewa Alat 75,000 90,000 12,750 15,300
D Jumlah A + B + C 23,184.00 26,828.00
E Overhead & Profit (contoh 10%) 10% 2,318.40 2,682.80
F Harga Satuan Pekerjaan (D+E) 25,502.40 29,510.80

6 A.4.2.1.6 1 m2 Pembuatan Rangka Jendela Besi Scuare Tube 283,393.88 315,478.46


A Tenaga 169,260.00 183,390.00
L.01 0.65 OH Pekerja 105,000.00 115,000.00 68,250.00 74,750.00
L.02 0.65 OH Tukang Las Biasa 135,000.00 145,000.00 87,750.00 94,250.00
L.03 0.065 OH Kepala Tukang 140,000.00 150,000.00 9,100.00 9,750.00
L.04 0.032 OH Mandor 130,000.00 145,000.00 4,160.00 4,640.00
B Bahan 88,370.80 103,408.60
4.760 m' Besi Scuare tube 5,000.00 6,000.00 23,800.00 28,560.00
4.522 m' Besi List Kaca 1 x 1 cm 3,000.00 3,500.00 13,566.00 15,827.00
20.000 cm Pengelasan 2,550.24 2,951.08 51,004.80 59,021.60
C PERALATAN
D Jumlah A + B + C 257,630.80 286,798.60
E Overhead & Profit (contoh 10%) 10% 25,763.08 28,679.86
F Harga Satuan Pekerjaan (D+E) 283,393.88 315,478.46

7 A.4.2.1.7 1 m2 Pemasangan Pintu Rolling Door Besi 693,638.00 732,457.00


A Tenaga 305,580.00 330,870.00
L.01 1.2 OH Pekerja 105,000.00 115,000.00 126,000.00 138,000.00
L.02 1.2 OH Tukang Besi 135,000.00 145,000.00 162,000.00 174,000.00
L.03 0.12 OH Kepala Tukang 140,000.00 150,000.00 16,800.00 18,000.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
B Bahan 325,000.00 335,000.00
1 m2 Pintu Gulung Besi 325,000.00 335,000.00 325,000.00 335,000.00
C PERALATAN
D Jumlah A + B + C 630,580.00 665,870.00
E Overhead & Profit (contoh 10%) 10% 63,058.00 66,587.00
F Harga Satuan Pekerjaan (D+E) 693,638.00 732,457.00

8 A.4.2.1.8 1 m2 Pemasangan Pintu Lipat (Folding Door) 566,082.00 604,109.00


A Tenaga 114,620.00 124,190.00
L.01 0.44 OH Pekerja 105,000.00 115,000.00 46,200.00 50,600.00
L.02 0.44 OH Tukang Besi 135,000.00 145,000.00 59,400.00 63,800.00
L.03 0.044 OH Kepala Tukang 140,000.00 150,000.00 6,160.00 6,600.00
L.04 0.022 OH Mandor 130,000.00 145,000.00 2,860.00 3,190.00
B Bahan 400,000.00 425,000.00
1 m2 Pintu Lipat 400,000.00 425,000.00 400,000.00 425,000.00
C PERALATAN
D Jumlah A + B + C 514,620.00 549,190.00
E Overhead & Profit (contoh 10%) 10% 51,462.00 54,919.00
F Harga Satuan Pekerjaan (D+E) 566,082.00 604,109.00

9 A.4.2.1.9 1 m2 Pemasangan Sunscreen Allumunium 525,932.00 591,558.00


A Tenaga 128,120.00 137,780.00
L.01 0.08 OH Pekerja 105,000.00 115,000.00 8,400.00 9,200.00
L.02 0.8 OH Tukang Besi 135,000.00 145,000.00 108,000.00 116,000.00
L.03 0.08 OH Kepala Tukang 140,000.00 150,000.00 11,200.00 12,000.00
L.04 0.004 OH Mandor 130,000.00 145,000.00 520.00 580.00
B Bahan 350,000.00 400,000.00
1 m2 Sunscreen Allumunium 350,000.00 400,000.00 350,000.00 400,000.00
C PERALATAN
D Jumlah A + B + C 478,120.00 537,780.00
E Overhead & Profit (contoh 10%) 10% 47,812.00 53,778.00
F Harga Satuan Pekerjaan (D+E) 525,932.00 591,558.00

10 A.4.2.1.10 1 m2 Pemasangan Rolling Door Allumunium 589,050.00 629,475.00


A Tenaga 260,500.00 282,250.00
L.01 1 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00
L.02 1 OH Tukang Besi 135,000.00 145,000.00 135,000.00 145,000.00
L.03 0.1 OH Kepala Tukang 140,000.00 150,000.00 14,000.00 15,000.00
L.04 0.05 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00

file:///conversion/tmp/scratch/500669137.xls 125/70 5-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 275,000.00 290,000.00


1 m2 Rolling Allumunium 275,000.00 290,000.00 275,000.00 290,000.00
C PERALATAN
D Jumlah A + B + C 535,500.00 572,250.00
E Overhead & Profit (contoh 10%) 10% 53,550.00 57,225.00
F Harga Satuan Pekerjaan (D+E) 589,050.00 629,475.00

11 A.4.2.1.11 1 m' Pemasangan Kusen Pintu Allumunium 132,214.50 140,062.45


A Tenaga 11,195.00 12,129.50
L.01 0.043 OH Pekerja 105,000.00 115,000.00 4,515.00 4,945.00
L.02 0.043 OH Tukang Besi 135,000.00 145,000.00 5,805.00 6,235.00
L.03 0.0043 OH Kepala Tukang 140,000.00 150,000.00 602.00 645.00
L.04 0.0021 OH Mandor 130,000.00 145,000.00 273.00 304.50
B Bahan 109,000.00 115,200.00
1.1 m' Profil Allumunium 95,000.00 100,000.00 104,500.00 110,000.00
2 buah Skrup Fixer 750.00 800.00 1,500.00 1,600.00
0.06 Tube Sealant 50,000.00 60,000.00 3,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 120,195.00 127,329.50
E Overhead & Profit (contoh 10%) 10% 12,019.50 12,732.95
F Harga Satuan Pekerjaan (D+E) 132,214.50 140,062.45

12 A.4.2.1.12 1 m2 Pemasangan Pintu Allumunium Strip Lebar 8 cm 556,419.60 590,682.40


A Tenaga 22,136.00 23,984.00
L.01 0.085 OH Pekerja 105,000.00 115,000.00 8,925.00 9,775.00
L.02 0.085 OH Tukang Besi 135,000.00 145,000.00 11,475.00 12,325.00
L.03 0.0085 OH Kepala Tukang 140,000.00 150,000.00 1,190.00 1,275.00
L.04 0.0042 OH Mandor 130,000.00 145,000.00 546.00 609.00
B Bahan 483,700.00 513,000.00
4.4 m' Profil Allumunium 95,000.00 100,000.00 418,000.00 440,000.00
14.6 m' Allumunium Strip 4,500.00 5,000.00 65,700.00 73,000.00
C PERALATAN
D Jumlah A + B + C 505,836.00 536,984.00
E Overhead & Profit (contoh 10%) 10% 50,583.60 53,698.40
F Harga Satuan Pekerjaan (D+E) 556,419.60 590,682.40

13 A.4.2.1.13 1 m2 Pemasangan Pintu Kaca Rangka Allumunium 523,941.00 558,112.50


A Tenaga 22,310.00 24,175.00
L.01 0.085 OH Pekerja 105,000.00 115,000.00 8,925.00 9,775.00
L.02 0.085 OH Tukang Besi 135,000.00 145,000.00 11,475.00 12,325.00
L.03 0.009 OH Kepala Tukang 140,000.00 150,000.00 1,260.00 1,350.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 454,000.00 483,200.00
4.4 m' Pintu Allumunium 95,000.00 100,000.00 418,000.00 440,000.00
4.5 m' Profil Kaca 5,000.00 6,000.00 22,500.00 27,000.00
0.27 tube Sealant 50,000.00 60,000.00 13,500.00 16,200.00
C PERALATAN
D Jumlah A + B + C 476,310.00 507,375.00
E Overhead & Profit (contoh 10%) 10% 47,631.00 50,737.50
F Harga Satuan Pekerjaan (D+E) 523,941.00 558,112.50

14 A.4.2.1.14 1 m2 Pemasangan Venetions Blinds & Vertical Blinds 204,864.00 218,746.00


A Tenaga 91,240.00 98,860.00
L.01 0.35 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 0.35 OH Tukang Besi 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00
B Bahan 95,000.00 100,000.00
1 m2 Venetions Blinds atau Vertical Blinds (tirai) 95,000.00 100,000.00 95,000.00 100,000.00
C PERALATAN
D Jumlah A + B + C 186,240.00 198,860.00
E Overhead & Profit (contoh 10%) 10% 18,624.00 19,886.00
F Harga Satuan Pekerjaan (D+E) 204,864.00 218,746.00

15 A.4.2.1.15 1 m2 Pemasangan Teralis Besi Strip (2x3) cm 649,559.35 703,144.75


A Tenaga 434,970.00 471,285.00
L.01 1.67 OH Pekerja 105,000.00 115,000.00 175,350.00 192,050.00
L.02 1.67 OH Tukang Las 135,000.00 145,000.00 225,450.00 242,150.00
L.03 0.167 OH Kepala Tukang 140,000.00 150,000.00 23,380.00 25,050.00
L.04 0.083 OH Mandor 130,000.00 145,000.00 10,790.00 12,035.00

file:///conversion/tmp/scratch/500669137.xls 125/71 5-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 155,538.50 167,937.50


6.177 kg Besi Strip 14,000.00 14,250.00 86,478.00 88,022.25
27.08 cm Pengelasan 2,550.24 2,951.08 69,060.50 79,915.25
C PERALATAN
D Jumlah A + B + C 590,508.50 639,222.50
E Overhead & Profit (contoh 10%) 10% 59,050.85 63,922.25
F Harga Satuan Pekerjaan (D+E) 649,559.35 703,144.75

16 A.4.2.1.16 1 m2 Pemasangan Kawat Nyamuk 110,447.88 124,260.95


A Tenaga 26,050.00 28,225.00
L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.1 OH Tukang 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 74,357.17 84,739.50
1.1 m2 Kawat Nyamuk nylon 20,000.00 25,000.00 22,000.00 27,500.00
11.11 cm Pengelasan 2,550.24 2,951.08 28,333.17 32,786.50
1.716 kg Baja Strip (0,2x2) cm 14,000.00 14,250.00 24,024.00 24,453.00
C PERALATAN
D Jumlah A + B + C 100,407.17 112,964.50
E Overhead & Profit (contoh 10%) 10% 10,040.72 11,296.45
F Harga Satuan Pekerjaan (D+E) 110,447.88 124,260.95

17 A.4.2.1.17 1 m2 Pemasangan Jendela Nako & Tralis 148,423.00 160,429.50


A Tenaga 50,930.00 55,145.00
L.01 0.2 OH Pekerja 105,000.00 115,000.00 21,000.00 23,000.00
L.02 0.2 OH Tukang Kayu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.001 OH Mandor 130,000.00 145,000.00 130.00 145.00
B Bahan 84,000.00 90,700.00
1.1 m2 Jendela Nako 40,000.00 42,000.00 44,000.00 46,200.00
10 buah Paku Skrup 1 - 2,5 cm 500.00 600.00 5,000.00 6,000.00
7 m' Besi Strip 5,000.00 5,500.00 35,000.00 38,500.00
C PERALATAN
D Jumlah A + B + C 134,930.00 145,845.00
E Overhead & Profit (contoh 10%) 10% 13,493.00 14,584.50
F Harga Satuan Pekerjaan (D+E) 148,423.00 160,429.50

Pemasangan Talang Datar / Jurai , Seng BJLS 28 Lebar 90


18 A.4.2.1.18 1 m' 220,060.50 242,536.25
cm
A Tenaga 79,800.00 86,200.00
L.01 0.20 OH Pekerja 105,000.00 115,000.00 21,000.00 23,000.00
L.02 0.4 OH Tukang Kayu 135,000.00 145,000.00 54,000.00 58,000.00
L.03 0.025 OH Kepala Tukang 140,000.00 150,000.00 3,500.00 3,750.00
L.04 0.01 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00
B Bahan 120,255.00 134,287.50
1.05 Lbr Seng Plaat 22,000.00 24,500.00 23,100.00 25,725.00
0.015 Kg Paku Biasa 1 - 2,5 cm 17,000.00 17,500.00 255.00 262.50
0.019 m3 Kayu Papan Klas II atau III 5,100,000.00 5,700,000.00 96,900.00 108,300.00
C PERALATAN
D Jumlah A + B + C 200,055.00 220,487.50
E Overhead & Profit (contoh 10%) 10% 20,005.50 22,048.75
F Harga Satuan Pekerjaan (D+E) 220,060.50 242,536.25

Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat


19 A.4.2.1.19 1 m' 89,320.00 96,987.00
BJLS 30 Lebar 45 cm
A Tenaga 50,930.00 55,145.00
L.01 0.20 OH Pekerja 105,000.00 115,000.00 21,000.00 23,000.00
L.02 0.20 OH Tukang Kayu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.001 OH Mandor 130,000.00 145,000.00 130.00 145.00
B Bahan 30,270.00 33,025.00
1.05 Lbr Seng Plaat 22,000.00 24,500.00 23,100.00 25,725.00
0.01 Kg Paku Biasa 1 - 2,5 cm 17,000.00 17,500.00 170.00 175.00
0.5 Kg Besi strip 14,000.00 14,250.00 7,000.00 7,125.00
C PERALATAN
D Jumlah A + B + C 81,200.00 88,170.00
E Overhead & Profit (contoh 10%) 10% 8,120.00 8,817.00
F Harga Satuan Pekerjaan (D+E) 89,320.00 96,987.00

file:///conversion/tmp/scratch/500669137.xls 125/72 5-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


20 A.4.2.1.20 1 m2 133,309.00 143,148.50
60x120 cm dinding partisi
A Tenaga 65,190.00 70,635.00
L.01 0.250 OH Pekerja 105,000.00 115,000.00 26,250.00 28,750.00
L.02 0.250 OH Tukang Besi 135,000.00 145,000.00 33,750.00 36,250.00
L.03 0.025 OH Kepala Tukang 140,000.00 150,000.00 3,500.00 3,750.00
L.04 0.013 OH Mandor 130,000.00 145,000.00 1,690.00 1,885.00
B Bahan 56,000.00 59,500.00
3.50 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 28,000.00 29,750.00
1.00 **) Assesoris (perkuatan; las dll) 28,000.00 29,750.00 28,000.00 29,750.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 121,190.00 130,135.00
E Overhead & Profit (contoh 10%) 10% 12,119.00 13,013.50
F Harga Satuan Pekerjaan (D+E) 133,309.00 143,148.50

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


21 A.4.2.1.21 1 m2 170,764.00 183,546.00
60x60 cm dinding plafond
A Tenaga 91,240.00 98,860.00
L.01 0.350 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 0.350 OH Tukang Besi 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00
B Bahan 64,000.00 68,000.00
4.00 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 32,000.00 34,000.00
1.00 **) Assesoris (perkuatan; las dll) 32,000.00 34,000.00 32,000.00 34,000.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 155,240.00 166,860.00
E Overhead & Profit (contoh 10%) 10% 15,524.00 16,686.00
F Harga Satuan Pekerjaan (D+E) 170,764.00 183,546.00

Pemasangan Atap Pelana Rangka Atap Baja Canal C


22 A.4.2.1.22 1 m2 273,861.78 292,519.01
dingin Profil C75
A Tenaga 191,190.00 207,155.00
L.01 0.734 OH Pekerja 105,000.00 115,000.00 77,070.00 84,410.00
L.02 0.734 OH Tukang Besi 135,000.00 145,000.00 99,090.00 106,430.00
L.03 0.073 OH Kepala Tukang 140,000.00 150,000.00 10,220.00 10,950.00
L.04 0.037 OH Mandor 130,000.00 145,000.00 4,810.00 5,365.00
B Bahan 53,331.00 54,250.50
3.065 kg Baja Ringan Canal Dingin C75 14,500.00 14,750.00 44,442.50 45,208.75
C PERALATAN 4,444.25 4,520.88
10 % Peralatan *) harga bahan 44,442.50 45,208.75 4,444.25 4,520.88
D Jumlah A + B + C 248,965.25 265,926.38
E Overhead & Profit (contoh 10%) 10% 24,896.53 26,592.64
F Harga Satuan Pekerjaan (D+E) 273,861.78 292,519.01

Pemasangan Atap Jurai Rangka Atap Baja Canal Dingin


23 A.4.2.1.23 1 m2 301,860.35 321,500.03
Profil C75
A Tenaga 198,076.00 214,614.00
L.01 0.7604 OH Pekerja 105,000.00 115,000.00 79,842.00 87,446.00
L.02 0.7604 OH Tukang Besi 135,000.00 145,000.00 102,654.00 110,258.00
L.03 0.0760 OH Kepala Tukang 140,000.00 150,000.00 10,640.00 11,400.00
L.04 0.0380 OH Mandor 130,000.00 145,000.00 4,940.00 5,510.00
B Bahan 70,470.00 71,685.00
4.05 kg Baja Ringan Canal Dingin C75 14,500.00 14,750.00 58,725.00 59,737.50
C PERALATAN 5,872.50 5,973.75
10 % Peralatan *) harga bahan 58,725.00 59,737.50 5,872.50 5,973.75
D Jumlah A + B + C 274,418.50 292,272.75
E Overhead & Profit (contoh 10%) 10% 27,441.85 29,227.28
F Harga Satuan Pekerjaan (D+E) 301,860.35 321,500.03

file:///conversion/tmp/scratch/500669137.xls 125/73 5-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


Pemasangan Dinding Bata Merah ukuran (5x11x22) cm
1 A.4.4.1.1 1 m2 268,757.50 295,185.00
Tebal 1 bata Camp. 1SP: 2PP
A Tenaga 96,700.00 105,350.00
L.01 0.6 OH Pekerja 105,000.00 115,000.00 63,000.00 69,000.00
L.02 0.2 OH Tukang Batu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang Batu 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.03 OH Mandor 130,000.00 145,000.00 3,900.00 4,350.00
B Bahan 147,625.00 163,000.00
140 Buah Bata Merah 520.00 580.00 72,800.00 81,200.00
43.5 Kg Portland Semen (PC) 1,150.00 1,200.00 50,025.00 52,200.00
0.08 m3 Pasir Pasang (PP) 310,000.00 370,000.00 24,800.00 29,600.00
C PERALATAN
D Jumlah A + B + C 244,325.00 268,350.00
E Overhead & Profit (contoh 10%) 10% 24,432.50 26,835.00
F Harga Satuan Pekerjaan (D+E) 268,757.50 295,185.00
Overhead & Profit (contoh 10%)
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
2 A.4.4.1.2 1 m2 259,162.75 285,736.00
Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga 96,700.00 105,350.00
L.01 0.6 OH Pekerja 105,000.00 115,000.00 63,000.00 69,000.00
L.02 0.2 OH Tukang Batu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang Batu 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.03 OH Mandor 130,000.00 145,000.00 3,900.00 4,350.00
B Bahan 138,902.50 154,410.00
140 Buah Bata Merah 520.00 580.00 72,800.00 81,200.00
32.95 Kg Portland Semen (PC) 1,150.00 1,200.00 37,892.50 39,540.00
0.091 m3 Pasir Pasang (PP) 310,000.00 370,000.00 28,210.00 33,670.00
C PERALATAN
D Jumlah A + B + C 235,602.50 259,760.00
E Overhead & Profit (contoh 10%) 10% 23,560.25 25,976.00
F Harga Satuan Pekerjaan (D+E) 259,162.75 285,736.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


3 A.4.4.1.3 1 m2 251,748.75 278,102.00
Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga 96,700.00 105,350.00
L.01 0.6 OH Pekerja 105,000.00 115,000.00 63,000.00 69,000.00
L.02 0.2 OH Tukang Batu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang Batu 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.03 OH Mandor 130,000.00 145,000.00 3,900.00 4,350.00
B Bahan 132,162.50 147,470.00
140 Buah Bata Merah 520.00 580.00 72,800.00 81,200.00
26.55 Kg Portland Semen (PC) 1,150.00 1,200.00 30,532.50 31,860.00
0.093 m3 Pasir Pasang (PP) 310,000.00 370,000.00 28,830.00 34,410.00
C PERALATAN
D Jumlah A + B + C 228,862.50 252,820.00
E Overhead & Profit (contoh 10%) 10% 22,886.25 25,282.00
F Harga Satuan Pekerjaan (D+E) 251,748.75 278,102.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


4 A.4.4.1.4 1 m2 249,315.00 276,023.00
Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga 96,700.00 105,350.00
L.01 0.6 OH Pekerja 105,000.00 115,000.00 63,000.00 69,000.00
L.02 0.2 OH Tukang Batu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang Batu 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.03 OH Mandor 130,000.00 145,000.00 3,900.00 4,350.00
B Bahan 129,950.00 145,580.00
140 Buah Bata Merah 520.00 580.00 72,800.00 81,200.00
22.2 Kg Portland Semen (PC) 1,150.00 1,200.00 25,530.00 26,640.00
0.102 m3 Pasir Pasang (PP) 310,000.00 370,000.00 31,620.00 37,740.00
C PERALATAN
D Jumlah A + B + C 226,650.00 250,930.00
E Overhead & Profit (contoh 10%) 10% 22,665.00 25,093.00
F Harga Satuan Pekerjaan (D+E) 249,315.00 276,023.00

file:///conversion/tmp/scratch/500669137.xls 125/74 6-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
5 A.4.4.1.5 1 m2 251,454.50 279,279.00
Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga 96,700.00 105,350.00
L.01 0.6 OH Pekerja 105,000.00 115,000.00 63,000.00 69,000.00
L.02 0.2 OH Tukang Batu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang Batu 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.03 OH Mandor 130,000.00 145,000.00 3,900.00 4,350.00
B Bahan 131,895.00 148,540.00
140 Buah Bata Merah 520.00 580.00 72,800.00 81,200.00
18.5 Kg Portland Semen (PC) 1,150.00 1,200.00 21,275.00 22,200.00
0.122 m3 Pasir Pasang (PP) 310,000.00 370,000.00 37,820.00 45,140.00
C PERALATAN
D Jumlah A + B + C 228,595.00 253,890.00
E Overhead & Profit (contoh 10%) 10% 22,859.50 25,389.00
F Harga Satuan Pekerjaan (D+E) 251,454.50 279,279.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


6 A.4.4.1.6 1 m2 239,818.70 265,535.60
Tebal 1 Bata Camp. 1SP : 3 KP :10PP
A Tenaga 96,700.00 105,350.00
L.01 0.6 OH Pekerja 105,000.00 115,000.00 63,000.00 69,000.00
L.02 0.2 OH Tukang Batu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang Batu 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.03 OH Mandor 130,000.00 145,000.00 3,900.00 4,350.00
B Bahan 121,317.00 136,046.00
140 Buah Bata Merah 520.00 580.00 72,800.00 81,200.00
10.08 Kg Portland Semen (PC) 1,150.00 1,200.00 11,592.00 12,096.00
0.0925 m3 Pasir Pasang (PP) 310,000.00 370,000.00 28,675.00 34,225.00
0.0275 m3 Kapur Pasang (KP) 300,000.00 310,000.00 8,250.00 8,525.00
C PERALATAN
D Jumlah A + B + C 218,017.00 241,396.00
E Overhead & Profit (contoh 10%) 10% 21,801.70 24,139.60
F Harga Satuan Pekerjaan (D+E) 239,818.70 265,535.60

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


7 A.4.4.1.7 1 m2 130,154.75 143,082.50
Tebal 1/2 Bata Camp. 1SP : 2PP
A Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 69,972.50 77,400.00
70 Buah Bata Merah 5 x 11 x 22 520.00 580.00 36,400.00 40,600.00
18.95 Kg Portland Semen 1,150.00 1,200.00 21,792.50 22,740.00
0.038 m3 Pasir Pasang 310,000.00 370,000.00 11,780.00 14,060.00
C PERALATAN
D Jumlah A + B + C 118,322.50 130,075.00
E Overhead & Profit (contoh 10%) 10% 11,832.25 13,007.50
F Harga Satuan Pekerjaan (D+E) 130,154.75 143,082.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


8 A.4.4.1.8 1 m2 125,043.05 137,850.90
Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 65,325.50 72,644.00
70 Buah Bata Merah 5 x 11 x 22 520.00 580.00 36,400.00 40,600.00
14.37 Kg Portland Semen 1,150.00 1,200.00 16,525.50 17,244.00
0.04 m3 Pasir Pasang 310,000.00 370,000.00 12,400.00 14,800.00

file:///conversion/tmp/scratch/500669137.xls 125/75 6-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 113,675.50 125,319.00
E Overhead & Profit (contoh 10%) 10% 11,367.55 12,531.90
F Harga Satuan Pekerjaan (D+E) 125,043.05 137,850.90

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


9 A.4.4.1.9 1 m2 122,435.50 135,283.50
Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 62,955.00 70,310.00
70 Buah Bata Merah 5 x 11 x 22 520.00 580.00 36,400.00 40,600.00
11.50 Kg Portland Semen 1,150.00 1,200.00 13,225.00 13,800.00
0.043 m3 Pasir Pasang 310,000.00 370,000.00 13,330.00 15,910.00
C PERALATAN
D Jumlah A + B + C 111,305.00 122,985.00
E Overhead & Profit (contoh 10%) 10% 11,130.50 12,298.50
F Harga Satuan Pekerjaan (D+E) 122,435.50 135,283.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


10 A.4.4.1.10 1 m2 120,815.20 133,695.10
Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 61,482.00 68,866.00
70 Buah Bata Merah 5 x 11 x 22 520.00 580.00 36,400.00 40,600.00
9.68 Kg Portland Semen 1,150.00 1,200.00 11,132.00 11,616.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 109,832.00 121,541.00
E Overhead & Profit (contoh 10%) 10% 10,983.20 12,154.10
F Harga Satuan Pekerjaan (D+E) 120,815.20 133,695.10

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


11 A.4.4.1.11 1 m2 120,458.80 133,527.90
Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 61,158.00 68,714.00
70 Buah Bata Merah 5 x 11 x 22 520.00 580.00 36,400.00 40,600.00
8.32 Kg Portland Semen 1,150.00 1,200.00 9,568.00 9,984.00
0.049 m3 Pasir Pasang 310,000.00 370,000.00 15,190.00 18,130.00
C PERALATAN
D Jumlah A + B + C 109,508.00 121,389.00
E Overhead & Profit (contoh 10%) 10% 10,950.80 12,138.90
F Harga Satuan Pekerjaan (D+E) 120,458.80 133,527.90

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


12 A.4.4.1.12 1 m2 118,497.50 131,532.50
Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 59,375.00 66,900.00
70 Buah Bata Merah 5 x 11 x 22 520.00 580.00 36,400.00 40,600.00
6.50 Kg Portland Semen 1,150.00 1,200.00 7,475.00 7,800.00
0.05 m3 Pasir Pasang 310,000.00 370,000.00 15,500.00 18,500.00

file:///conversion/tmp/scratch/500669137.xls 125/76 6-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 107,725.00 119,575.00
E Overhead & Profit (contoh 10%) 10% 10,772.50 11,957.50
F Harga Satuan Pekerjaan (D+E) 118,497.50 131,532.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


13 A.4.4.1.13 1 m2 120,917.50 134,007.50
Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP
A Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 61,575.00 69,150.00
70 Buah Bata Merah 5 x 11 x 22 520.00 580.00 36,400.00 40,600.00
4.5 Kg Portland Semen 1,150.00 1,200.00 5,175.00 5,400.00
0.05 m3 Pasir Pasang 310,000.00 370,000.00 15,500.00 18,500.00
0.015 m3 Kapur Padam 300,000.00 310,000.00 4,500.00 4,650.00
C PERALATAN
D Jumlah A + B + C 109,925.00 121,825.00
E Overhead & Profit (contoh 10%) 10% 10,992.50 12,182.50
F Harga Satuan Pekerjaan (D+E) 120,917.50 134,007.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


14 A.4.4.1.14 1 m2 109,263.00 120,026.50
Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP
A Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 50,980.00 56,440.00
70 Buah Bata Merah 5 x 11 x 22 520.00 580.00 36,400.00 40,600.00
0.018 m3 Semen Merah 200,000.00 200,000.00 3,600.00 3,600.00
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
0.018 m3 Kapur Padam 300,000.00 310,000.00 5,400.00 5,580.00
C PERALATAN
D Jumlah A + B + C 99,330.00 109,115.00
E Overhead & Profit (contoh 10%) 10% 9,933.00 10,911.50
F Harga Satuan Pekerjaan (D+E) 109,263.00 120,026.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


15 A.4.4.1.15 1 m2 110,473.00 121,852.50
Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP
A Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 52,080.00 58,100.00
70 Buah Bata Merah 5 x 11 x 22 520.00 580.00 36,400.00 40,600.00
0.014 m3 Semen Merah 200,000.00 200,000.00 2,800.00 2,800.00
0.028 m3 Pasir Pasang 310,000.00 370,000.00 8,680.00 10,360.00
0.014 m3 Kapur Padam 300,000.00 310,000.00 4,200.00 4,340.00
C PERALATAN
D Jumlah A + B + C 100,430.00 110,775.00
E Overhead & Profit (contoh 10%) 10% 10,043.00 11,077.50
F Harga Satuan Pekerjaan (D+E) 110,473.00 121,852.50

16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 412,328.40 471,997.90
A Tenaga 61,440.00 66,860.00
L.01 0.350 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 0.150 OH Tukang Batu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00

file:///conversion/tmp/scratch/500669137.xls 125/77 6-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 313,404.00 362,229.00
12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
30.320 kg PC 1,150.00 1,200.00 34,868.00 36,384.00
0.728 m3 Pasir Pasang 310,000.00 370,000.00 225,680.00 269,360.00
0.280 kg Besi Angkur Ø 8 mm 10,200.00 12,000.00 2,856.00 3,360.00
C PERALATAN
D Jumlah A + B + C 374,844.00 429,089.00
E Overhead & Profit (contoh 10%) 10% 37,484.40 42,908.90
F Harga Satuan Pekerjaan (D+E) 412,328.40 471,997.90

17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 419,666.50 481,906.70
A Tenaga 61,440.00 66,860.00
L.01 0.350 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 0.150 OH Tukang Batu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00

B Bahan 320,075.00 371,237.00


12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
24.260 kg PC 1,150.00 1,200.00 27,899.00 29,112.00
0.772 m3 Pasir Pasang 310,000.00 370,000.00 239,320.00 285,640.00
0.280 kg Besi Angkur Ø 8 mm 10,200.00 12,000.00 2,856.00 3,360.00
C PERALATAN
D Jumlah A + B + C 381,515.00 438,097.00
E Overhead & Profit (contoh 10%) 10% 38,151.50 43,809.70
F Harga Satuan Pekerjaan (D+E) 419,666.50 481,906.70

18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 326,498.70 372,589.80
A Tenaga 53,560.00 58,320.00
L.01 0.320 OH Pekerja 105,000.00 115,000.00 33,600.00 36,800.00
L.02 0.120 OH Tukang Batu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.016 OH Mandor 130,000.00 145,000.00 2,080.00 2,320.00
B Bahan 243,257.00 280,398.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
22.740 kg PC 1,150.00 1,200.00 26,151.00 27,288.00
0.550 m3 Pasir Pasang 310,000.00 370,000.00 170,500.00 203,500.00
0.280 kg Besi Angkur Ø 8 mm 10,200.00 12,000.00 2,856.00 3,360.00
C PERALATAN
D Jumlah A + B + C 296,817.00 338,718.00
E Overhead & Profit (contoh 10%) 10% 29,681.70 33,871.80
F Harga Satuan Pekerjaan (D+E) 326,498.70 372,589.80

19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 331,667.60 379,621.00
A Tenaga 53,560.00 58,320.00
L.01 0.320 OH Pekerja 105,000.00 115,000.00 33,600.00 36,800.00
L.02 0.120 OH Tukang Batu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.016 OH Mandor 130,000.00 145,000.00 2,080.00 2,320.00
B Bahan 247,956.00 286,790.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
18.200 kg PC 1,150.00 1,200.00 20,930.00 21,840.00
0.582 m3 Pasir Pasang 310,000.00 370,000.00 180,420.00 215,340.00
0.280 kg Besi Angkur Ø 8 mm 10,200.00 12,000.00 2,856.00 3,360.00
C PERALATAN
D Jumlah A + B + C 301,516.00 345,110.00
E Overhead & Profit (contoh 10%) 10% 30,151.60 34,511.00
F Harga Satuan Pekerjaan (D+E) 331,667.60 379,621.00

20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 256,003.00 305,422.70
A Tenaga 48,350.00 52,675.00
L.01 0.300 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.100 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.010 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00

file:///conversion/tmp/scratch/500669137.xls 125/78 6-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 184,380.00 224,982.00
12.500 buah Batako 4,100.00 5,500.00 51,250.00 68,750.00
15.160 kg PC 1,150.00 1,200.00 17,434.00 18,192.00
0.364 m3 Pasir Pasang 310,000.00 370,000.00 112,840.00 134,680.00
0.280 kg Besi Angkur Ø 8 mm 10,200.00 12,000.00 2,856.00 3,360.00
C PERALATAN
D Jumlah A + B + C 232,730.00 277,657.00
E Overhead & Profit (contoh 10%) 10% 23,273.00 27,765.70
F Harga Satuan Pekerjaan (D+E) 256,003.00 305,422.70

21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 260,354.05 311,191.10
A Tenaga 48,350.00 52,675.00
L.01 0.300 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.100 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.010 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00

B Bahan 188,335.50 230,226.00


12.500 buah Batako 4,100.00 5,500.00 51,250.00 68,750.00
12.130 kg PC 1,150.00 1,200.00 13,949.50 14,556.00
0.388 m3 Pasir Pasang 310,000.00 370,000.00 120,280.00 143,560.00
0.280 kg Besi Angkur Ø 8 mm 10,200.00 12,000.00 2,856.00 3,360.00
C PERALATAN
D Jumlah A + B + C 236,685.50 282,901.00
E Overhead & Profit (contoh 10%) 10% 23,668.55 28,290.10
F Harga Satuan Pekerjaan (D+E) 260,354.05 311,191.10

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 1 m2 376,035.00 482,707.50
(12x11x24)cm Camp. 1SP : 3PP
A Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 293,500.00 386,150.00
30 Buah Terawang / Roster 9,000.00 12,000.00 270,000.00 360,000.00
11 kg Portland Semen 1,150.00 1,200.00 12,650.00 13,200.00
0.035 m3 Pasir Pasang 310,000.00 370,000.00 10,850.00 12,950.00
C PERALATAN
D Jumlah A + B + C 341,850.00 438,825.00
E Overhead & Profit (contoh 10%) 10% 34,185.00 43,882.50
F Harga Satuan Pekerjaan (D+E) 376,035.00 482,707.50

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 1 m2 376,035.00 482,707.50
(12x11x24)cm Camp. 1SP : 4PP
A Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 293,500.00 386,150.00
30 Buah Terawang / Roster 9,000.00 12,000.00 270,000.00 360,000.00
11 kg Portland Semen 1,150.00 1,200.00 12,650.00 13,200.00
0.035 m3 Pasir Pasang 310,000.00 370,000.00 10,850.00 12,950.00
C PERALATAN
D Jumlah A + B + C 341,850.00 438,825.00
E Overhead & Profit (contoh 10%) 10% 34,185.00 43,882.50
F Harga Satuan Pekerjaan (D+E) 376,035.00 482,707.50

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 1 m2 158,807.00 170,296.50
(12x11x24)cm Camp. 1SP : 3PP
m2 Tenaga 48,350.00 52,675.00
L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.1 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00

file:///conversion/tmp/scratch/500669137.xls 125/79 6-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
OH Bahan 96,020.00 102,140.00
70 Buah Bata Roster 1,000.00 1,050.00 70,000.00 73,500.00
14 kg Portland Semen 1,150.00 1,200.00 16,100.00 16,800.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00
C PERALATAN
D Jumlah A + B + C 144,370.00 154,815.00
E Overhead & Profit (contoh 10%) 10% 14,437.00 15,481.50
F Harga Satuan Pekerjaan (D+E) 158,807.00 170,296.50

Pemasangan Dinding Bata Ringan Tebal 7,5 cm dengan


25 A.4.4.1.25 1 m2 350,032.54 375,287.06
Mortar Siap Pakai
m2 Tenaga 0.075 264,440.00 285,485.00
L.01 0.67 OH Pekerja 0.12 725000 105,000.00 115,000.00 70,350.00 77,050.00
L.02 1.3 OH Tukang Batu 1 6525 135,000.00 145,000.00 175,500.00 188,500.00
L.03 0.13 OH Kepala Tukang 13.3333333333333 140,000.00 150,000.00 18,200.00 19,500.00
L.04 0.003 OH Mandor 111.111111111111 130,000.00 145,000.00 390.00 435.00
OH Bahan 53,771.40 55,685.05
8.40 Buah Bata Ringan Tebal 7,5 cm 90000 6,300.00 6,525.00 52,920.00 54,810.00
0.473 kg Mortar Siap Pakai 1,800.00 1,850.00 851.40 875.05

C PERALATAN
D Jumlah A + B + C 318,211.40 341,170.05
E Overhead & Profit (contoh 10%) 10% 31,821.14 34,117.01
F Harga Satuan Pekerjaan (D+E) 350,032.54 375,287.06

Pemasangan Dinding Bata Ringan Tebal 10 cm dengan


26 A.4.4.1.26 1 m2 349,336.24 372,599.21
Mortar Siap Pakai
m2 Tenaga 0.075 248,165.00 268,050.00
L.01 0.671 OH Pekerja 0.12 700000 105,000.00 115,000.00 70,455.00 77,165.00
L.02 1.300 OH Tukang Batu 0.1 8400 135,000.00 145,000.00 175,500.00 188,500.00
L.03 0.013 OH Kepala Tukang 10 140,000.00 150,000.00 1,820.00 1,950.00
L.04 0.003 OH Mandor 83.3333333333333 130,000.00 145,000.00 390.00 435.00
OH Bahan 69,413.40 70,676.55
8.40 Buah Bata Ringan Tebal 10 cm 90000 8,250.00 8,400.00 69,300.00 70,560.00
0.063 kg Mortar Siap Pakai 1,800.00 1,850.00 113.40 116.55

C PERALATAN
D Jumlah A + B + C 317,578.40 338,726.55
E Overhead & Profit (contoh 10%) 10% 31,757.84 33,872.66
F Harga Satuan Pekerjaan (D+E) 349,336.24 372,599.21

file:///conversion/tmp/scratch/500669137.xls 125/80 6-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.1 1 m2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm 86,448.56 93,719.78
A Tenaga 55,800.00 60,675.00
L.01 0.3 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00

L.02 0.15 OH Tukang batu 135,000.00 145,000.00 20,250.00 21,750.00

L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00

L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00


B Bahan 22,789.60 24,524.80
15.504 Kg Portland Semen 1,150.00 1,200.00 17,829.60 18,604.80
0.016 m3 Pasir Pasang 310,000.00 370,000.00 4,960.00 5,920.00
C PERALATAN
D Jumlah A + B + C 78,589.60 85,199.80
E Overhead & Profit (contoh 10%) 10% 7,858.96 8,519.98
F Harga Satuan Pekerjaan (D+E) 86,448.56 93,719.78
Overhead & Profit (contoh 10%)
2 A.4.4.2.2 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm 81,133.36 88,378.18
A Tenaga 55,800.00 60,675.00
L.01 0.3 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00

L.02 0.15 OH Tukang batu 135,000.00 145,000.00 20,250.00 21,750.00

L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00


L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 17,957.60 19,668.80
10.224 Kg Portland Semen 1,150.00 1,200.00 11,757.60 12,268.80
0.020 m3 Pasir Pasang 310,000.00 370,000.00 6,200.00 7,400.00
C PERALATAN
D Jumlah A + B + C 73,757.60 80,343.80
E Overhead & Profit (contoh 10%) 10% 7,375.76 8,034.38
F Harga Satuan Pekerjaan (D+E) 81,133.36 88,378.18

3 A.4.4.2.3 1 m2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 79,059.64 86,367.82


A Tenaga 55,800.00 60,675.00

L.01 0.3 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00

L.02 0.15 OH Tukang batu 135,000.00 145,000.00 20,250.00 21,750.00

L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00


L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 16,072.40 17,841.20
7.776 Kg Portland Semen 1,150.00 1,200.00 8,942.40 9,331.20
0.023 m3 Pasir Pasang 310,000.00 370,000.00 7,130.00 8,510.00
C PERALATAN
D Jumlah A + B + C 71,872.40 78,516.20
E Overhead & Profit (contoh 10%) 10% 7,187.24 7,851.62
F Harga Satuan Pekerjaan (D+E) 79,059.64 86,367.82

4 A.4.4.2.4 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm 77,457.60 84,747.30


A Tenaga 55,800.00 60,675.00

L.01 0.3 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00


L.02 0.15 OH Tukang batu 135,000.00 145,000.00 20,250.00 21,750.00

L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00

L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00


B Bahan 14,616.00 16,368.00
6.240 Kg Portland Semen 1,150.00 1,200.00 7,176.00 7,488.00
0.024 m3 Pasir Pasang 310,000.00 370,000.00 7,440.00 8,880.00
C PERALATAN
D Jumlah A + B + C 70,416.00 77,043.00
E Overhead & Profit (contoh 10%) 10% 7,041.60 7,704.30
F Harga Satuan Pekerjaan (D+E) 77,457.60 84,747.30

5 A.4.4.2.5 1 m2 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm 76,803.76 84,167.38


A Tenaga 55,800.00 60,675.00
L.01 0.3 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.15 OH Tukang batu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 14,021.60 15,840.80
5.184 Kg Portland Semen 1,150.00 1,200.00 5,961.60 6,220.80
0.026 m3 Pasir Pasang 310,000.00 370,000.00 8,060.00 9,620.00
C PERALATAN
D Jumlah A + B + C 69,821.60 76,515.80
E Overhead & Profit (contoh 10%) 10% 6,982.16 7,651.58
F Harga Satuan Pekerjaan (D+E) 76,803.76 84,167.38

file:///conversion/tmp/scratch/500669137.xls 125/81 7-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.4.2.6 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 76,173.24 83,560.62
Tenaga 55,800.00 60,675.00

L.01 0.3 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00

L.02 0.15 OH Tukang batu 135,000.00 145,000.00 20,250.00 21,750.00

L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00

L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00


Bahan 13,448.40 15,289.20
4.416 Kg Portland Semen 1,150.00 1,200.00 5,078.40 5,299.20
0.027 m3 Pasir Pasang 310,000.00 370,000.00 8,370.00 9,990.00
C PERALATAN
D Jumlah A + B + C 69,248.40 75,964.20
E Overhead & Profit (contoh 10%) 10% 6,924.84 7,596.42
F Harga Satuan Pekerjaan (D+E) 76,173.24 83,560.62

7 A.4.4.2.7 1 m2 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm 75,907.04 83,334.02


A Tenaga 55,800.00 60,675.00

L.01 0.3 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00

L.02 0.15 OH Tukang batu 135,000.00 145,000.00 20,250.00 21,750.00

L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00

L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00


B Bahan 13,206.40 15,083.20
3.936 Kg Portland Semen 1,150.00 1,200.00 4,526.40 4,723.20
0.028 m3 Pasir Pasang 310,000.00 370,000.00 8,680.00 10,360.00
C PERALATAN
D Jumlah A + B + C 69,006.40 75,758.20
E Overhead & Profit (contoh 10%) 10% 6,900.64 7,575.82
F Harga Satuan Pekerjaan (D+E) 75,907.04 83,334.02

8 A.4.4.2.8 1 m2 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm 75,640.84 83,107.42


A Tenaga 55,800.00 60,675.00

L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00

L.02 0.15 OH Tukang batu 135,000.00 145,000.00 20,250.00 21,750.00


L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 12,964.40 14,877.20
3.456 Kg Portland Semen 1,150.00 1,200.00 3,974.40 4,147.20
0.029 m3 Pasir Pasang 310,000.00 370,000.00 8,990.00 10,730.00
C PERALATAN
D Jumlah A + B + C 68,764.40 75,552.20
E Overhead & Profit (contoh 10%) 10% 6,876.44 7,555.22
F Harga Satuan Pekerjaan (D+E) 75,640.84 83,107.42

9 A.4.4.2.9 1 m2 Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15 mm 76,531.40 83,448.20


A Tenaga 58,020.00 63,210.00

L.01 0.36 OH Pekerja 105,000.00 115,000.00 37,800.00 41,400.00


L.02 0.12 OH Tukang batu 135,000.00 145,000.00 16,200.00 17,400.00

L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00

L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00


B Bahan 11,554.00 12,652.00
5.760 Kg Portland Semen 1,150.00 1,200.00 6,624.00 6,912.00
0.003 m3 Kapur Pasang 300,000.00 310,000.00 900.00 930.00
0.013 m3 Pasir Pasang 310,000.00 370,000.00 4,030.00 4,810.00
C PERALATAN
D Jumlah A + B + C 69,574.00 75,862.00
E Overhead & Profit (contoh 10%) 10% 6,957.40 7,586.20
F Harga Satuan Pekerjaan (D+E) 76,531.40 83,448.20

10 A.4.4.2.10 1 m2 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm 76,087.00 83,336.00


A Tenaga 58,020.00 63,210.00
L.01 0.36 OH Pekerja 105,000.00 115,000.00 37,800.00 41,400.00
L.02 0.12 OH Tukang batu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00
B Bahan 11,150.00 12,550.00
3 kg Portland Semen 1,150.00 1,200.00 3,450.00 3,600.00
0.005 m3 Kapur Padam 300,000.00 310,000.00 1,500.00 1,550.00
0.020 m3 Pasir Pasang 310,000.00 370,000.00 6,200.00 7,400.00
C PERALATAN
D Jumlah A + B + C 69,170.00 75,760.00
E Overhead & Profit (contoh 10%) 10% 6,917.00 7,576.00
F Harga Satuan Pekerjaan (D+E) 76,087.00 83,336.00

file:///conversion/tmp/scratch/500669137.xls 125/82 7-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.4.2.11 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm 71,841.00 78,243.00
A Tenaga 58,020.00 63,210.00

L.01 0.36 OH Pekerja 105,000.00 115,000.00 37,800.00 41,400.00

L.02 0.12 OH Tukang batu 135,000.00 145,000.00 16,200.00 17,400.00

L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00

L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00


B Bahan 7,290.00 7,920.00
0.009 m3 Semen Merah 200,000.00 200,000.00 1,800.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.009 m3 Pasir Pasang 310,000.00 370,000.00 2,790.00 3,330.00
C PERALATAN
D Jumlah A + B + C 65,310.00 71,130.00
E Overhead & Profit (contoh 10%) 10% 6,531.00 7,113.00
F Harga Satuan Pekerjaan (D+E) 71,841.00 78,243.00

12 A.4.4.2.12 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm 72,787.00 79,563.00


A Tenaga 58,020.00 63,210.00

L.01 0.36 OH Pekerja 105,000.00 115,000.00 37,800.00 41,400.00

L.02 0.12 OH Tukang batu 135,000.00 145,000.00 16,200.00 17,400.00

L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00

L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00


B Bahan 8,150.00 9,120.00
0.007 m3 Semen Merah 200,000.00 200,000.00 1,400.00 1,400.00
0.007 m3 Kapur Padam 300,000.00 310,000.00 2,100.00 2,170.00
0.015 m3 Pasir Pasang 310,000.00 370,000.00 4,650.00 5,550.00
C PERALATAN
D Jumlah A + B + C 66,170.00 72,330.00
E Overhead & Profit (contoh 10%) 10% 6,617.00 7,233.00
F Harga Satuan Pekerjaan (D+E) 72,787.00 79,563.00

13 A.4.4.2.13 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm 108,577.48 118,292.24


A Tenaga 74,660.00 81,190.00

L.01 0.40 OH Pekerja 105,000.00 115,000.00 42,000.00 46,000.00

L.02 0.20 OH Tukang batu 135,000.00 145,000.00 27,000.00 29,000.00

L.03 0.020 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00

L.04 0.022 OH Mandor 130,000.00 145,000.00 2,860.00 3,190.00


B Bahan 24,046.80 26,348.40
13.632 kg Portland Semen 1,150.00 1,200.00 15,676.80 16,358.40
0.027 m3 Pasir Pasang 310,000.00 370,000.00 8,370.00 9,990.00
C PERALATAN
D Jumlah A + B + C 98,706.80 107,538.40
E Overhead & Profit (contoh 10%) 10% 9,870.68 10,753.84
F Harga Satuan Pekerjaan (D+E) 108,577.48 118,292.24

14 A.4.4.2.14 1 m2 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm 80,323.20 87,696.60


A Tenaga 58,790.00 63,785.00
L.01 0.26 OH Pekerja 105,000.00 115,000.00 27,300.00 29,900.00
L.02 0.2 OH Tukang batu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.013 OH Mandor 130,000.00 145,000.00 1,690.00 1,885.00
B Bahan 21,533.20 23,911.60
10.368 Kg Portland Semen 1,150.00 1,200.00 11,923.20 12,441.60
0.031 m3 Pasir Pasang 310,000.00 370,000.00 9,610.00 11,470.00
C PERALATAN
D Jumlah A + B + C 82,013.20 89,581.60
E Overhead & Profit (contoh 10%) 10% 8,201.32 8,958.16
F Harga Satuan Pekerjaan (D+E) 90,214.52 98,539.76

15 A.4.4.2.15 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm 103,562.80 113,315.40


A Tenaga 74,660.00 81,190.00

L.01 0.40 OH Pekerja 105,000.00 115,000.00 42,000.00 46,000.00

L.02 0.20 OH Tukang batu 135,000.00 145,000.00 27,000.00 29,000.00


L.03 0.020 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00

L.04 0.022 OH Mandor 130,000.00 145,000.00 2,860.00 3,190.00


B Bahan 19,488.00 21,824.00
8.320 kg Portland Semen 1,150.00 1,200.00 9,568.00 9,984.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00

file:///conversion/tmp/scratch/500669137.xls 125/83 7-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 94,148.00 103,014.00
E Overhead & Profit (contoh 10%) 10% 9,414.80 10,301.40
F Harga Satuan Pekerjaan (D+E) 103,562.80 113,315.40

16 A.4.4.2.16 1 m2 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm 102,804.68 112,677.84


A Tenaga 74,660.00 81,190.00

L.01 0.400 OH Pekerja 105,000.00 115,000.00 42,000.00 46,000.00

L.02 0.200 OH Tukang batu 135,000.00 145,000.00 27,000.00 29,000.00

L.03 0.020 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00

L.04 0.022 OH Mandor 130,000.00 145,000.00 2,860.00 3,190.00


B Bahan 18,798.80 21,244.40
6.912 Kg Portland Semen 1,150.00 1,200.00 7,948.80 8,294.40
0.035 m3 Pasir Pasang 310,000.00 370,000.00 10,850.00 12,950.00
C PERALATAN
D Jumlah A + B + C 93,458.80 102,434.40
E Overhead & Profit (contoh 10%) 10% 9,345.88 10,243.44
F Harga Satuan Pekerjaan (D+E) 102,804.68 112,677.84

17 A.4.4.2.17 1 m2 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm 101,850.32 111,733.16


A Tenaga 74,660.00 81,190.00

L.01 0.40 OH Pekerja 105,000.00 115,000.00 42,000.00 46,000.00

L.02 0.2 OH Tukang batu 135,000.00 145,000.00 27,000.00 29,000.00

L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00


L.04 0.022 OH Mandor 130,000.00 145,000.00 2,860.00 3,190.00
B Bahan 17,931.20 20,385.60
5.888 Kg Portland Semen 1,150.00 1,200.00 6,771.20 7,065.60
0.036 m3 Pasir Pasang 310,000.00 370,000.00 11,160.00 13,320.00
C PERALATAN
D Jumlah A + B + C 92,591.20 101,575.60
E Overhead & Profit (contoh 10%) 10% 9,259.12 10,157.56
F Harga Satuan Pekerjaan (D+E) 101,850.32 111,733.16

18 A.4.4.2.18 1 m2 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm 101,112.00 110,264.00


A Tenaga 81,840.00 88,990.00

L.01 0.440 OH Pekerja 105,000.00 115,000.00 46,200.00 50,600.00

L.02 0.22 OH Tukang batu 135,000.00 145,000.00 29,700.00 31,900.00

L.03 0.022 OH Kepala Tukang 140,000.00 150,000.00 3,080.00 3,300.00

L.04 0.022 OH Mandor 130,000.00 145,000.00 2,860.00 3,190.00


B Bahan 10,080.00 11,250.00
0.009 m3 Semen Merah 200,000.00 200,000.00 1,800.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
C PERALATAN
D Jumlah A + B + C 91,920.00 100,240.00
E Overhead & Profit (contoh 10%) 10% 9,192.00 10,024.00
F Harga Satuan Pekerjaan (D+E) 101,112.00 110,264.00

19 A.4.4.2.19 1 m2 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm 46,262.26 50,958.38


A Tenaga 28,035.00 30,485.00

L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00


L.02 0.075 OH Tukang batu 135,000.00 145,000.00 10,125.00 10,875.00

L.03 0.008 OH Kepala Tukang 140,000.00 150,000.00 1,120.00 1,200.00


L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 14,021.60 15,840.80
5.184 Kg Portland Semen 1,150.00 1,200.00 5,961.60 6,220.80
0.026 m3 Pasir Pasang 310,000.00 370,000.00 8,060.00 9,620.00
C PERALATAN
D Jumlah A + B + C 42,056.60 46,325.80
E Overhead & Profit (contoh 10%) 10% 4,205.66 4,632.58
F Harga Satuan Pekerjaan (D+E) 46,262.26 50,958.38

20 A.4.4.2.20 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm 80,437.50 87,109.00

A Tenaga 68,520.00 73,780.00

L.01 0.080 OH Pekerja 105,000.00 115,000.00 8,400.00 9,200.00

L.02 0.40 OH Tukang batu 135,000.00 145,000.00 54,000.00 58,000.00

L.03 0.040 OH Kepala Tukang 140,000.00 150,000.00 5,600.00 6,000.00

L.04 0.004 OH Mandor 130,000.00 145,000.00 520.00 580.00

file:///conversion/tmp/scratch/500669137.xls 125/84 7-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 4,605.00 5,410.00
0.5 Kg Portland Semen 1,150.00 1,200.00 575.00 600.00
0.013 m3 Pasir Pasang 310,000.00 370,000.00 4,030.00 4,810.00
C PERALATAN
D Jumlah A + B + C 73,125.00 79,190.00
E Overhead & Profit (contoh 10%) 10% 7,312.50 7,919.00
F Harga Satuan Pekerjaan (D+E) 80,437.50 87,109.00

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal 10


21 A.4.4.2.21 1 m' 121,368.50 131,626.00
mm
A Tenaga 83,835.00 91,160.00
L.01 0.450 OH Pekerja 105,000.00 115,000.00 47,250.00 51,750.00
L.02 0.225 OH Tukang batu 135,000.00 145,000.00 30,375.00 32,625.00
L.03 0.023 OH Kepala Tukang 140,000.00 150,000.00 3,220.00 3,450.00
L.04 0.023 OH Mandor 130,000.00 145,000.00 2,990.00 3,335.00
B Bahan 26,500.00 28,500.00
10 Kg Portland Semen 1,150.00 1,200.00 11,500.00 12,000.00
15 Kg Batu Granit 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 110,335.00 119,660.00
E Overhead & Profit (contoh 10%) 10% 11,033.50 11,966.00
F Harga Satuan Pekerjaan (D+E) 121,368.50 131,626.00

22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 121,368.50 131,626.00

A Tenaga 83,835.00 91,160.00


L.01 0.450 OH Pekerja 105,000.00 115,000.00 47,250.00 51,750.00
L.02 0.225 OH Tukang batu 135,000.00 145,000.00 30,375.00 32,625.00
L.03 0.023 OH Kepala Tukang 140,000.00 150,000.00 3,220.00 3,450.00
L.04 0.023 OH Mandor 130,000.00 145,000.00 2,990.00 3,335.00
B Bahan 26,500.00 28,500.00
10 Kg Portland Semen 1,150.00 1,200.00 11,500.00 12,000.00
15 m3 Batu Traso 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 110,335.00 119,660.00
E Overhead & Profit (contoh 10%) 10% 11,033.50 11,966.00
F Harga Satuan Pekerjaan (D+E) 121,368.50 131,626.00

23 A.4.4.2.23 1 m2 Pemasangan Plesteran Ciprat 1Pc : 2 Pp 60,695.80 66,086.90


Tenaga 48,350.00 52,675.00

L.01 0.30 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00

L.02 0.1 OH Tukang batu 135,000.00 145,000.00 13,500.00 14,500.00

L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00

L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00


Bahan 6,828.00 7,404.00
4.32 Kg Portland Semen 1,150.00 1,200.00 4,968.00 5,184.00
0.006 m3 Pasir Pasang 310,000.00 370,000.00 1,860.00 2,220.00
C PERALATAN
D Jumlah A + B + C 55,178.00 60,079.00
E Overhead & Profit (contoh 10%) 10% 5,517.80 6,007.90
F Harga Satuan Pekerjaan (D+E) 60,695.80 66,086.90

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 1 m2 34,770.12 37,636.06
Merah
A Tenaga 28,035.00 30,485.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00

L.02 0.075 OH Tukang batu 135,000.00 145,000.00 10,125.00 10,875.00

L.03 0.008 OH Kepala Tukang 140,000.00 150,000.00 1,120.00 1,200.00


L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 3,574.20 3,729.60
3.108 Kg Portland Semen 1,150.00 1,200.00 3,574.20 3,729.60
C PERALATAN
D Jumlah A + B + C 31,609.20 34,214.60
E Overhead & Profit (contoh 10%) 10% 3,160.92 3,421.46
F Harga Satuan Pekerjaan (D+E) 34,770.12 37,636.06

file:///conversion/tmp/scratch/500669137.xls 125/85 7-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Finishing Siar Pasangan Dinding Conblock
25 A.4.4.2.25 1 m2 16,494.50 17,847.50
ekspose
A Tenaga 13,155.00 14,305.00
L.01 0.070 OH Pekerja 105,000.00 115,000.00 7,350.00 8,050.00

L.02 0.035 OH Tukang batu 135,000.00 145,000.00 4,725.00 5,075.00

L.03 0.004 OH Kepala Tukang 140,000.00 150,000.00 560.00 600.00

L.04 0.004 OH Mandor 130,000.00 145,000.00 520.00 580.00


B Bahan 1,840.00 1,920.00
1.600 Kg Portland Semen 1,150.00 1,200.00 1,840.00 1,920.00
C PERALATAN
D Jumlah A + B + C 14,995.00 16,225.00
E Overhead & Profit (contoh 10%) 10% 1,499.50 1,622.50
F Harga Satuan Pekerjaan (D+E) 16,494.50 17,847.50

Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc :


26 A.4.4.2.26 1 m2 73,492.10 79,995.30
2Pp
Tenaga 55,800.00 60,675.00

L.01 0.3 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00

L.02 0.15 OH Tukang batu 135,000.00 145,000.00 20,250.00 21,750.00

L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00

L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00


Bahan 11,011.00 12,048.00
6.34 Kg Portland Semen 1,150.00 1,200.00 7,291.00 7,608.00
0.012 m3 Pasir Pasang 310,000.00 370,000.00 3,720.00 4,440.00
C PERALATAN
D Jumlah A + B + C 66,811.00 72,723.00
E Overhead & Profit (contoh 10%) 10% 6,681.10 7,272.30
F Harga Satuan Pekerjaan (D+E) 73,492.10 79,995.30

27 A.4.4.2.27 1 m2 Pemasangan Acian 45,031.25 48,785.00

Tenaga 37,200.00 40,450.00


L.01 0.20 OH Pekerja 105,000.00 115,000.00 21,000.00 23,000.00
L.02 0.10 OH Tukang batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.010 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.010 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00
Bahan 3,737.50 3,900.00
3.25 Kg Portland Semen 1,150.00 1,200.00 3,737.50 3,900.00
C PERALATAN
D Jumlah A + B + C 40,937.50 44,350.00
E Overhead & Profit (contoh 10%) 10% 4,093.75 4,435.00
F Harga Satuan Pekerjaan (D+E) 45,031.25 48,785.00

28 A.4.4.2.28 1 m2 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) 53,473.20 57,396.90

Tenaga 37,200.00 40,450.00


L.01 0.20 OH Pekerja 105,000.00 115,000.00 21,000.00 23,000.00
L.02 0.10 OH Tukang batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.010 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.010 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00
Bahan 11,412.00 11,729.00
6.34 Kg Portland Semen 1,800.00 1,850.00 11,412.00 11,729.00
C PERALATAN
D Jumlah A + B + C 48,612.00 52,179.00
E Overhead & Profit (contoh 10%) 10% 4,861.20 5,217.90
F Harga Satuan Pekerjaan (D+E) 53,473.20 57,396.90

29 A.4.4.2.29 1 m2 Pemasangan Acian dg Mortar Siap Pakai (MSP) 47,355.00 51,108.75


Tenaga 37,200.00 40,450.00
L.01 0.20 OH Pekerja 105,000.00 115,000.00 21,000.00 23,000.00
L.02 0.10 OH Tukang batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.010 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.010 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00
Bahan 5,850.00 6,012.50
3.25 Kg Mortar Siap Pakai 1,800.00 1,850.00 5,850.00 6,012.50
C PERALATAN
D Jumlah A + B + C 43,050.00 46,462.50
E Overhead & Profit (contoh 10%) 10% 4,305.00 4,646.25
F Harga Satuan Pekerjaan (D+E) 47,355.00 51,108.75

file:///conversion/tmp/scratch/500669137.xls 125/86 7-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3
dan DINDING

1 A.4.4.3.2 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm 120,838.50 132,402.00


A Tenaga 46,635.00 50,710.00
L.01 0.25 OH Pekerja 105,000.00 115,000.00 26,250.00 28,750.00
L.02 0.125 OH Tukang Batu 135,000.00 145,000.00 16,875.00 18,125.00
L.03 0.013 OH Kepala Tukang 140,000.00 150,000.00 1,820.00 1,950.00
L.04 0.013 OH Mandor 130,000.00 145,000.00 1,690.00 1,885.00
B Bahan 63,218.18 69,655.45
11.87 Buah Ubin Abu-abu 30x30 cm 11.1111 3,181.82 3,454.55 37,768.18 41,005.45
10.0 Kg Portland Semen 0.3 1,150.00 1,200.00 11,500.00 12,000.00
0.0450 m3 Pasir Pasang 0.09 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN

D Jumlah A + B + C 109,853.18 120,365.45


E Overhead & Profit (contoh 10%) 10% 10,985.32 12,036.55
F Harga Satuan Pekerjaan (D+E) 120,838.50 132,402.00

2 A.4.4.3.3 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm 123,535.50 135,415.50


A Tenaga 50,355.00 54,755.00
L.01 0.27 OH Pekerja 105,000.00 115,000.00 28,350.00 31,050.00
L.02 0.135 OH Tukang Batu 135,000.00 145,000.00 18,225.00 19,575.00
L.03 0.014 OH Kepala Tukang 140,000.00 150,000.00 1,960.00 2,100.00
L.04 0.014 OH Mandor 130,000.00 145,000.00 1,820.00 2,030.00
B Bahan 61,950.00 68,350.00
26.5 Buah Ubin Abu-abu 20x20 cm 1,360.00 1,480.00 36,040.00 39,220.00
10.4 Kg Portland Semen 1,150.00 1,200.00 11,960.00 12,480.00
0.0450 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 112,305.00 123,105.00
E Overhead & Profit (contoh 10%) 10% 11,230.50 12,310.50
F Harga Satuan Pekerjaan (D+E) 123,535.50 135,415.50

3 A.4.4.3.5 1 m2 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm 148,471.00 171,084.50


A Tenaga 48,360.00 52,585.00
L.01 0.26 OH Pekerja 105,000.00 115,000.00 27,300.00 29,900.00
L.02 0.130 OH Tukang Batu 135,000.00 145,000.00 17,550.00 18,850.00
L.03 0.013 OH Kepala Tukang 140,000.00 150,000.00 1,820.00 1,950.00
L.04 0.013 OH Mandor 130,000.00 145,000.00 1,690.00 1,885.00
B Bahan 86,613.64 102,946.36
11.87 Buah Ubin Warna 30x30 cm 3,636.36 4,363.64 43,163.64 51,796.36
10.0 Kg Portland Semen 1,150.00 1,200.00 11,500.00 12,000.00
1.50 Kg Semen warna 12,000.00 15,000.00 18,000.00 22,500.00
0.0450 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 134,973.64 155,531.36
E Overhead & Profit (contoh 10%) 10% 13,497.36 15,553.14
F Harga Satuan Pekerjaan (D+E) 148,471.00 171,084.50

4 A.4.4.3.6 1 m2 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm 151,332.50 171,473.50


A Tenaga 50,355.00 54,755.00
L.01 0.27 OH Pekerja 105,000.00 115,000.00 28,350.00 31,050.00
L.02 0.135 OH Tukang Batu 135,000.00 145,000.00 18,225.00 19,575.00
L.03 0.014 OH Kepala Tukang 140,000.00 150,000.00 1,960.00 2,100.00
L.04 0.014 OH Mandor 130,000.00 145,000.00 1,820.00 2,030.00
B Bahan 87,220.00 101,130.00
26.5 Buah Ubin Warna 20x20 cm 1,580.00 1,800.00 41,870.00 47,700.00
10.4 Kg Portland Semen 1,150.00 1,200.00 11,960.00 12,480.00
1.62 Kg Semen warna 12,000.00 15,000.00 19,440.00 24,300.00
0.0450 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 137,575.00 155,885.00
E Overhead & Profit (contoh 10%) 10% 13,757.50 15,588.50
F Harga Satuan Pekerjaan (D+E) 151,332.50 171,473.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.4.3.9 1 m2 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 363,610.50 412,357.00
A Tenaga 46,635.00 50,710.00
L.01 0.250 OH Pekerja 105,000.00 115,000.00 26,250.00 28,750.00
L.02 0.125 OH Tukang Batu 135,000.00 145,000.00 16,875.00 18,125.00
L.03 0.013 OH Kepala Tukang 140,000.00 150,000.00 1,820.00 1,950.00
L.04 0.013 OH Mandor 130,000.00 145,000.00 1,690.00 1,885.00
B Bahan 283,920.00 324,160.00
6.63 Buah Ubin Granito 40x40 cm 0.4 36,666.67 41,666.67 243,100.00 276,250.00

9.8 Kg Portland Semen 0.16 1,150.00 1,200.00 11,270.00 11,760.00


1.300 Kg Semen warna 6.25 12,000.00 15,000.00 15,600.00 19,500.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 330,555.00 374,870.00
E Overhead & Profit (contoh 10%) 10% 33,055.50 37,487.00
F Harga Satuan Pekerjaan (D+E) 363,610.50 412,357.00

6 A.4.4.3.16 1 m' Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm 72,507.60 82,954.30

A Tenaga 23,510.00 25,475.00


L.01 0.090 OH Pekerja 105,000.00 115,000.00 9,450.00 10,350.00
L.02 0.090 OH Tukang Batu 135,000.00 145,000.00 12,150.00 13,050.00
L.03 0.009 OH Kepala Tukang 140,000.00 150,000.00 1,260.00 1,350.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 42,406.00 49,938.00
5.30 Buah Ubin Plin Pc Abu-abu 15x20 cm 5,100.00 6,000.00 27,030.00 31,800.00
1.2 Kg Portland Semen 1,150.00 1,200.00 1,426.00 1,488.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 65,916.00 75,413.00
E Overhead & Profit (contoh 10%) 10% 6,591.60 7,541.30
F Harga Satuan Pekerjaan (D+E) 72,507.60 82,954.30

7 A.4.4.3.19 1 m' Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm 44,804.10 48,430.80


A Tenaga 23,510.00 25,475.00
L.01 0.090 OH Pekerja 105,000.00 115,000.00 9,450.00 10,350.00
L.02 0.090 OH Tukang Batu 135,000.00 145,000.00 12,150.00 13,050.00
L.03 0.009 OH Kepala Tukang 140,000.00 150,000.00 1,260.00 1,350.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 17,221.00 18,553.00
2.65 Buah Ubin Plin Pc SWarna 15x20 cm 5,200.00 5,500.00 13,780.00 14,575.00
1.14 Kg Portland Semen 1,150.00 1,200.00 1,311.00 1,368.00
0.100 Kg Semen Warna 12,000.00 15,000.00 1,200.00 1,500.00
0.003 m3 Pasir Pasang 310,000.00 370,000.00 930.00 1,110.00
C PERALATAN
D Jumlah A + B + C 40,731.00 44,028.00
E Overhead & Profit (contoh 10%) 10% 4,073.10 4,402.80
F Harga Satuan Pekerjaan (D+E) 44,804.10 48,430.80

8 A.4.4.3.32 1 m2 Pemasangan Lantai Keramik 10x 20 cm 263,525.35 314,185.30


A Tenaga 130,200.00 141,575.00
L.01 0.70 OH Pekerja 105,000.00 115,000.00 73,500.00 80,500.00
L.02 0.350 OH Tukang Batu 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.035 OH Mandor 130,000.00 145,000.00 4,550.00 5,075.00
B Bahan 109,368.50 144,048.00
53.00 Buah Keramik 10 x 20 cm 1,000.00 1,440.00 53,000.00 76,320.00

8.19 Kg Portland Semen 1,150.00 1,200.00 9,418.50 9,828.00


2.75 Kg Semen Warna 12,000.00 15,000.00 33,000.00 41,250.00
0.0450 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 239,568.50 285,623.00
E Overhead & Profit (contoh 10%) 10% 23,956.85 28,562.30
F Harga Satuan Pekerjaan (D+E) 263,525.35 314,185.30
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

9 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm 269,465.35 321,610.30

A Tenaga 130,200.00 141,575.00


L.01 0.70 OH Pekerja 105,000.00 115,000.00 73,500.00 80,500.00
L.02 0.350 OH Tukang Batu 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.035 OH Mandor 130,000.00 145,000.00 4,550.00 5,075.00
B Bahan 114,768.50 150,798.00
106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm 500.00 720.00 53,000.00 76,320.00
8.19 Kg Portland Semen 1,150.00 1,200.00 9,418.50 9,828.00
3.20 Kg Semen Warna 12,000.00 15,000.00 38,400.00 48,000.00
0.0450 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 244,968.50 292,373.00
E Overhead & Profit (contoh 10%) 10% 24,496.85 29,237.30

F Harga Satuan Pekerjaan (D+E) 269,465.35 321,610.30

10 A.4.4.3.34 1 m2 Pemasangan Lantai Keramik 33 x 33 cm 270,976.02 306,921.63


A Tenaga 130,200.00 141,575.00
L.01 0.70 OH Pekerja 105,000.00 115,000.00 73,500.00 80,500.00
L.02 0.35 OH Tukang Batu 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.035 OH Mandor 130,000.00 145,000.00 4,550.00 5,075.00
B Bahan 116,141.83 137,444.67

10 Buah Ubin Keramik 33 x 33 cm 7,333.33 8,666.67 73,333.33 86,666.67


8.19 Kg Portland Semen 1,150.00 1,200.00 9,418.50 9,828.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
1.62 Kg Semen Warna 12,000.00 15,000.00 19,440.00 24,300.00
C PERALATAN
D Jumlah A + B + C 246,341.83 279,019.67
E Overhead & Profit (contoh 10%) 10% 24,634.18 27,901.97
F Harga Satuan Pekerjaan (D+E) 270,976.02 306,921.63

11 A.4.4.3.35 1 m2 Pemasangan Lantai Keramik 30 x 30 cm 270,544.00 304,583.50


A Tenaga 130,200.00 141,575.00
L.01 0.70 OH Pekerja 105,000.00 115,000.00 73,500.00 80,500.00
L.02 0.35 OH Tukang Batu 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.035 OH Mandor 130,000.00 145,000.00 4,550.00 5,075.00
B Bahan 115,749.09 135,319.09
11.87 Buah Ubin Keramik 30 x 30 cm 6,090.91 7,090.91 72,299.09 84,169.09
10.00 Kg Portland Semen 1,150.00 1,200.00 11,500.00 12,000.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
1.50 Kg Semen Warna 12,000.00 15,000.00 18,000.00 22,500.00
C PERALATAN
D Jumlah A + B + C 245,949.09 276,894.09
E Overhead & Profit (contoh 10%) 10% 24,594.91 27,689.41
F Harga Satuan Pekerjaan (D+E) 270,544.00 304,583.50

12 A.4.4.3.36 1 m2 Pemasangan Lantai Keramik 20 x 20 cm 270,061.00 303,121.50


A Tenaga 130,200.00 141,575.00
L.01 0.70 OH Pekerja 105,000.00 115,000.00 73,500.00 80,500.00
L.02 0.35 OH Tukang Batu 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.035 OH Mandor 130,000.00 145,000.00 4,550.00 5,075.00
B Bahan 115,310.00 133,990.00
26.5 Buah Ubin Keramik 20 x 20 cm 2,640.00 3,040.00 69,960.00 80,560.00
10.40 Kg Portland Semen 1,150.00 1,200.00 11,960.00 12,480.00
1.62 Kg Semen Warna 12,000.00 15,000.00 19,440.00 24,300.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 245,510.00 275,565.00
E Overhead & Profit (contoh 10%) 10% 24,551.00 27,556.50
F Harga Satuan Pekerjaan (D+E) 270,061.00 303,121.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Lantai Keramik uk.10 x 33 cm, untuk
13 A.4.4.3.37 1 m2 497,480.50 552,046.00
variasi / border
A Tenaga 193,095.00 209,900.00
L.01 1.05 OH Pekerja 105,000.00 115,000.00 110,250.00 120,750.00
L.02 0.525 OH Tukang Batu 135,000.00 145,000.00 70,875.00 76,125.00
L.03 0.053 OH Kepala Tukang 140,000.00 150,000.00 7,420.00 7,950.00
L.04 0.035 OH Mandor 130,000.00 145,000.00 4,550.00 5,075.00
B Bahan 259,160.00 291,960.00
33.0 Buah Ubin Keramik 5,500.00 6,000.00 181,500.00 198,000.00
9.80 Kg Portland Semen 1,150.00 1,200.00 11,270.00 11,760.00
4.37 Kg Semen Warna 12,000.00 15,000.00 52,440.00 65,550.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
C PERALATAN
D Jumlah A + B + C 452,255.00 501,860.00
E Overhead & Profit (contoh 10%) 10% 45,225.50 50,186.00
F Harga Satuan Pekerjaan (D+E) 497,480.50 552,046.00

14 A.4.4.3.39 1 m' Pemasangan Plint Keramik Ukuran 10x20 cm 46,146.10 50,108.30


A Tenaga 23,510.00 25,475.00
L.01 0.09 OH Pekerja 105,000.00 115,000.00 9,450.00 10,350.00
L.02 0.09 OH Tukang Batu 135,000.00 145,000.00 12,150.00 13,050.00
L.03 0.009 OH Kepala Tukang 140,000.00 150,000.00 1,260.00 1,350.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 18,441.00 20,078.00
5.3 Buah Ubin Keramik 3,000.00 3,250.00 15,900.00 17,225.00
1.14 Kg Portland Semen 1,150.00 1,200.00 1,311.00 1,368.00
0.003 m3 Pasir Pasang 310,000.00 370,000.00 930.00 1,110.00
0.025 Kg Semen Warna 12,000.00 15,000.00 300.00 375.00
C PERALATAN
D Jumlah A + B + C 41,951.00 45,553.00
E Overhead & Profit (contoh 10%) 10% 4,195.10 4,555.30
F Harga Satuan Pekerjaan (D+E) 46,146.10 50,108.30

15 A.4.4.3.40 1 m' Pemasangan Plint Keramik Ukuran 10x10 cm 93,116.10 98,618.30


A Tenaga 23,510.00 25,475.00
L.01 0.09 OH Pekerja 105,000.00 115,000.00 9,450.00 10,350.00
L.02 0.09 OH Tukang Batu 135,000.00 145,000.00 12,150.00 13,050.00
L.03 0.009 OH Kepala Tukang 140,000.00 150,000.00 1,260.00 1,350.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 61,141.00 64,178.00
10.6 Buah Ubin Keramik 5,500.00 5,750.00 58,300.00 60,950.00
1.14 Kg Portland Semen 1,150.00 1,200.00 1,311.00 1,368.00
0.003 m3 Pasir Pasang 310,000.00 370,000.00 930.00 1,110.00
0.05 Kg Semen Warna 12,000.00 15,000.00 600.00 750.00
C PERALATAN
D Jumlah A + B + C 84,651.00 89,653.00
E Overhead & Profit (contoh 10%) 10% 8,465.10 8,965.30
F Harga Satuan Pekerjaan (D+E) 93,116.10 98,618.30

16 A.4.4.3.41 1 m' Pemasangan Plint Keramik Ukuran 5x20 cm 96,031.10 101,533.30


A Tenaga 23,510.00 25,475.00
L.01 0.09 OH Pekerja 105,000.00 115,000.00 9,450.00 10,350.00
L.02 0.09 OH Tukang Batu 135,000.00 145,000.00 12,150.00 13,050.00
L.03 0.009 OH Kepala Tukang 140,000.00 150,000.00 1,260.00 1,350.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 63,791.00 66,828.00
10.6 Buah Ubin Keramik 5,750.00 6,000.00 60,950.00 63,600.00
1.14 Kg Portland Semen 1,150.00 1,200.00 1,311.00 1,368.00
0.003 m3 Pasir Pasang 310,000.00 370,000.00 930.00 1,110.00
0.05 Kg Semen Warna 12,000.00 15,000.00 600.00 750.00
C PERALATAN
D Jumlah A + B + C 87,301.00 92,303.00
E Overhead & Profit (contoh 10%) 10% 8,730.10 9,230.30
F Harga Satuan Pekerjaan (D+E) 96,031.10 101,533.30
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
17 A.4.4.3.43 1 m2 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm 731,355.35 755,263.30
A Tenaga 130,200.00 141,575.00
L.01 0.7 OH Pekerja 105,000.00 115,000.00 73,500.00 80,500.00
L.02 0.35 OH Tukang Batu 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.035 OH Mandor 130,000.00 145,000.00 4,550.00 5,075.00
B Bahan 534,668.50 545,028.00
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
8.19 kg Portland Semen 1,150.00 1,200.00 9,418.50 9,828.00
0.045 m3 Pasir Pasang 310,000.00 370,000.00 13,950.00 16,650.00
0.65 kg Semen Warna 12,000.00 15,000.00 7,800.00 9,750.00
C PERALATAN
D Jumlah A + B + C 664,868.50 686,603.00
E Overhead & Profit (contoh 10%) 10% 66,486.85 68,660.30
F Harga Satuan Pekerjaan (D+E) 731,355.35 755,263.30

18 A.4.4.3.44 1 m2 Pemasangan Lantai Karpet 214,335.00 228,035.50


A Tenaga 44,350.00 48,055.00
L.01 0.17 OH Pekerja 105,000.00 115,000.00 17,850.00 19,550.00
L.02 0.17 OH Tukang Batu 135,000.00 145,000.00 22,950.00 24,650.00
L.03 0.017 OH Kepala Tukang 140,000.00 150,000.00 2,380.00 2,550.00
L.04 0.009 OH Mandor 130,000.00 145,000.00 1,170.00 1,305.00
B Bahan 150,500.00 159,250.00
1.05 m2 Karpet 125,000.00 130,000.00 131,250.00 136,500.00
0.35 kg Lem 55,000.00 65,000.00 19,250.00 22,750.00
C PERALATAN
D Jumlah A + B + C 194,850.00 207,305.00
E Overhead & Profit (contoh 10%) 10% 19,485.00 20,730.50
F Harga Satuan Pekerjaan (D+E) 214,335.00 228,035.50

19 A.4.4.3.46 1 m2 Pemasangan Lantai Parquet Jati 479,820.00 556,682.50


A Tenaga 130,200.00 141,575.00
L.01 0.70 OH Pekerja 105,000.00 115,000.00 73,500.00 80,500.00
L.02 0.35 OH Tukang Batu 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.035 OH Mandor 130,000.00 145,000.00 4,550.00 5,075.00
B Bahan 306,000.00 364,500.00
1.05 m2 Parquet Jati 260,000.00 310,000.00 273,000.00 325,500.00
0.6 Kg Lem Vynil 55,000.00 65,000.00 33,000.00 39,000.00
C PERALATAN
D Jumlah A + B + C 436,200.00 506,075.00
E Overhead & Profit (contoh 10%) 10% 43,620.00 50,607.50
F Harga Satuan Pekerjaan (D+E) 479,820.00 556,682.50

20 A.4.4.3.48 1 m2 Pemasangan Dinding Porselen 11 x 11 cm 307,256.16 337,059.32


A Tenaga 186,000.00 202,250.00
L.01 1.00 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00
L.02 0.50 OH Tukang Batu 135,000.00 145,000.00 67,500.00 72,500.00
L.03 0.050 OH Kepala Tukang 140,000.00 150,000.00 7,000.00 7,500.00
L.04 0.050 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00
B Bahan 93,323.78 104,167.56
86 bh Porselen 512.20 524.39 44,048.78 45,097.56
9.30 Kg Portland Semen 82.6446 1,150.00 1,200.00 10,695.00 11,160.00

2.750 Kg Semen Warna 0.0121 12,000.00 15,000.00 33,000.00 41,250.00

0.018 m3 Pasir Pasang 0.11 310,000.00 370,000.00 5,580.00 6,660.00


C PERALATAN
D Jumlah A + B + C 279,323.78 306,417.56
E Overhead & Profit (contoh 10%) 10% 27,932.38 30,641.76
F Harga Satuan Pekerjaan (D+E) 307,256.16 337,059.32

21 A.4.4.3.49 1 m2 Pemasangan Dinding Porselen 10x20 cm 296,642.50 349,156.50


A Tenaga 167,400.00 182,025.00
L.01 0.9 OH Pekerja 105,000.00 115,000.00 94,500.00 103,500.00
L.02 0.45 OH Tukang Batu 135,000.00 145,000.00 60,750.00 65,250.00
L.03 0.045 OH Kepala Tukang 140,000.00 150,000.00 6,300.00 6,750.00
L.04 0.045 OH Mandor 130,000.00 145,000.00 5,850.00 6,525.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 102,275.00 135,390.00
53 Buah Keramik 1,000.00 1,440.00 53,000.00 76,320.00
9.3 Kg Portland Semen 1,150.00 1,200.00 10,695.00 11,160.00
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
2.75 Kg Semen Warna 12,000.00 15,000.00 33,000.00 41,250.00
C PERALATAN
D Jumlah A + B + C 269,675.00 317,415.00
E Overhead & Profit (contoh 10%) 10% 26,967.50 31,741.50
F Harga Satuan Pekerjaan (D+E) 296,642.50 349,156.50

22 A.4.4.3.50 1 m2 Pemasangan Dinding Porselen 20x20 cm 290,570.50 336,495.50


A Tenaga 167,400.00 182,025.00
L.01 0.9 OH Pekerja 105,000.00 115,000.00 94,500.00 103,500.00
L.02 0.45 OH Tukang Batu 135,000.00 145,000.00 60,750.00 65,250.00
L.03 0.045 OH Kepala Tukang 140,000.00 150,000.00 6,300.00 6,750.00
L.04 0.045 OH Mandor 130,000.00 145,000.00 5,850.00 6,525.00
B Bahan 96,755.00 123,880.00
26.0 Buah Keramik 2,200.00 2,960.00 57,200.00 76,960.00
9.3 Kg Portland Semen 1,150.00 1,200.00 10,695.00 11,160.00
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
1.94 Kg Semen Warna 12,000.00 15,000.00 23,280.00 29,100.00
C PERALATAN
D Jumlah A + B + C 264,155.00 305,905.00
E Overhead & Profit (contoh 10%) 10% 26,415.50 30,590.50
F Harga Satuan Pekerjaan (D+E) 290,570.50 336,495.50

23 A.4.4.3.53 1 m2 Pemasangan Dinding Keramik 10x20 cm 296,642.50 349,156.50


A Tenaga 167,400.00 182,025.00
L.01 0.9 OH Pekerja 105,000.00 115,000.00 94,500.00 103,500.00
L.02 0.45 OH Tukang Batu 135,000.00 145,000.00 60,750.00 65,250.00
L.03 0.045 OH Kepala Tukang 140,000.00 150,000.00 6,300.00 6,750.00
L.04 0.045 OH Mandor 130,000.00 145,000.00 5,850.00 6,525.00
B Bahan 102,275.00 135,390.00
53.0 Buah Keramik 1,000.00 1,440.00 53,000.00 76,320.00
9.3 Kg Portland Semen 1,150.00 1,200.00 10,695.00 11,160.00
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
2.75 Kg Semen Warna 12,000.00 15,000.00 33,000.00 41,250.00
C PERALATAN
D Jumlah A + B + C 269,675.00 317,415.00
E Overhead & Profit (contoh 10%) 10% 26,967.50 31,741.50
F Harga Satuan Pekerjaan (D+E) 296,642.50 349,156.50

24 A.4.4.3.54 1 m2 Pemasangan Dinding Keramik 20x20 cm 291,780.50 338,123.50


A Tenaga 167,400.00 182,025.00
L.01 0.9 OH Pekerja 105,000.00 115,000.00 94,500.00 103,500.00
L.02 0.45 OH Tukang Batu 135,000.00 145,000.00 60,750.00 65,250.00
L.03 0.045 OH Kepala Tukang 140,000.00 150,000.00 6,300.00 6,750.00
L.04 0.045 OH Mandor 130,000.00 145,000.00 5,850.00 6,525.00
B Bahan 97,855.00 125,360.00
26.5 Buah Keramik 2,200.00 2,960.00 58,300.00 78,440.00
9.3 Kg Portland Semen 1,150.00 1,200.00 10,695.00 11,160.00
0.018 m3 Pasir Pasang 310,000.00 370,000.00 5,580.00 6,660.00
1.94 Kg Semen Warna 12,000.00 15,000.00 23,280.00 29,100.00
C PERALATAN
D Jumlah A + B + C 265,255.00 307,385.00
E Overhead & Profit (contoh 10%) 10% 26,525.50 30,738.50
F Harga Satuan Pekerjaan (D+E) 291,780.50 338,123.50

25 A.4.4.3.55 1 m2 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm 853,827.76 887,457.04


A Tenaga 241,800.00 262,925.00
L.01 1.3 OH Pekerja 105,000.00 115,000.00 136,500.00 149,500.00
L.02 0.65 OH Tukang Batu 135,000.00 145,000.00 87,750.00 94,250.00
L.03 0.065 OH Kepala Tukang 140,000.00 150,000.00 9,100.00 9,750.00
L.04 0.065 OH Mandor 130,000.00 145,000.00 8,450.00 9,425.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 534,407.05 543,854.13
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
3.003 buah Paku 12 cm 350.00 375.00 1,051.05 1,126.13
12.44 kg Portlan Semen 1,150.00 1,200.00 14,306.00 14,928.00
0.025 m3 Pasir Pasang 310,000.00 370,000.00 7,750.00 9,250.00
0.65 kg Semen Warna 12,000.00 15,000.00 7,800.00 9,750.00
C PERALATAN
D Jumlah A + B + C 776,207.05 806,779.13
E Overhead & Profit (contoh 10%) 10% 77,620.71 80,677.91
F Harga Satuan Pekerjaan (D+E) 853,827.76 887,457.04

26 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 321,268.75 354,887.50

A Tenaga 130,200.00 141,575.00


L.01 0.70 OH Pekerja 105,000.00 115,000.00 73,500.00 80,500.00
L.02 0.35 OH Tukang Batu 135,000.00 145,000.00 47,250.00 50,750.00
L.03 0.035 OH Kepala Tukang 140,000.00 150,000.00 4,900.00 5,250.00
L.04 0.035 OH Mandor 130,000.00 145,000.00 4,550.00 5,075.00
B Bahan 161,862.50 181,050.00
1.10 m2 Batu Paros 125,000.00 140,000.00 137,500.00 154,000.00
11.75 Kg Portland Semen 1,150.00 1,200.00 13,512.50 14,100.00
0.035 m3 Pasir Pasang 310,000.00 370,000.00 10,850.00 12,950.00
C PERALATAN
D Jumlah A + B + C 292,062.50 322,625.00
E Overhead & Profit (contoh 10%) 10% 29,206.25 32,262.50
F Harga Satuan Pekerjaan (D+E) 321,268.75 354,887.50

27 A.4.4.3.59 1 m2 Pemasangan Lantai Vynil uk.30 x 30 cm 165,394.90 178,057.00


A Tenaga 63,015.00 68,465.00
L.01 0.35 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 0.175 OH Tukang Batu 135,000.00 145,000.00 23,625.00 25,375.00
L.03 0.017 OH Kepala Tukang 140,000.00 150,000.00 2,380.00 2,550.00
L.04 0.002 OH Mandor 130,000.00 145,000.00 260.00 290.00
B Bahan 87,344.00 93,405.00
11.87 bh Vynil 30x30cm 6,200.00 6,500.00 73,594.00 77,155.00
0.25 kg Lem 55,000.00 65,000.00 13,750.00 16,250.00

C PERALATAN
D Jumlah A + B + C 150,359.00 161,870.00
E Overhead & Profit (contoh 10%) 10% 15,035.90 16,187.00
F Harga Satuan Pekerjaan (D+E) 165,394.90 178,057.00

28 A.4.4.3.60 1 m2 Pemasangan Wallpaper Lebar 50 Cm 135,536.50 144,776.50


A Tenaga 63,015.00 68,465.00
L.01 0.35 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 0.175 OH Tukang Batu 135,000.00 145,000.00 23,625.00 25,375.00
L.03 0.017 OH Kepala Tukang 140,000.00 150,000.00 2,380.00 2,550.00
L.04 0.002 OH Mandor 130,000.00 145,000.00 260.00 290.00
B Bahan 60,200.00 63,150.00
2.2 m' Wallpaper 26,000.00 27,000.00 57,200.00 59,400.00
0.25 kg Lem 12,000.00 15,000.00 3,000.00 3,750.00
C PERALATAN
D Jumlah A + B + C 123,215.00 131,615.00
E Overhead & Profit (contoh 10%) 10% 12,321.50 13,161.50
F Harga Satuan Pekerjaan (D+E) 135,536.50 144,776.50

29 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 62,931.00 67,177.00
Tenaga 31,260.00 33,870.00
L.01 0.12 OH Pekerja 105,000.00 115,000.00 12,600.00 13,800.00
L.02 0.12 OH Tukang Batu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
Bahan 25,950.00 27,200.00
0.003 m3 Papan Kayu Klas II 8,400,000.00 8,800,000.00 25,200.00 26,400.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 57,210.00 61,070.00
E Overhead & Profit (contoh 10%) 10% 5,721.00 6,107.00
F Harga Satuan Pekerjaan (D+E) 62,931.00 67,177.00

30 A.4.4.3.64 1 m2 Pemasangan Paving Block Natural Tebal 6 Cm 204,906.90 228,066.85


Tenaga 100,919.00 108,938.50
L.01 0.25 OH Pekerja 105,000.00 115,000.00 26,250.00 28,750.00
L.02 0.5 OH Tukang Batu 135,000.00 145,000.00 67,500.00 72,500.00
L.03 0.05 OH Kepala Tukang 140,000.00 150,000.00 7,000.00 7,500.00
L.04 0.0013 OH Mandor 130,000.00 145,000.00 169.00 188.50
Bahan 77,600.00 89,450.00
1.01 m2 Paving Block Tebal 6 Cm 60,000.00 70,000.00 60,600.00 70,700.00
0.05 m3 Pasir Beton 340,000.00 375,000.00 17,000.00 18,750.00
C PERALATAN 7,760.00 8,945.00
10 % Peralatan 77,600.00 89,450.00 7,760.00 8,945.00
D Jumlah A + B + C 186,279.00 207,333.50
E Overhead & Profit (contoh 10%) 10% 18,627.90 20,733.35
F Harga Satuan Pekerjaan (D+E) 204,906.90 228,066.85

31 A.4.4.3.65 1 m2 Pemasangan Paving Block Natural Tebal 8 Cm 272,562.40 299,319.35


Tenaga 127,169.00 137,688.50
L.01 0.5 OH Pekerja 105,000.00 115,000.00 52,500.00 57,500.00
L.02 0.5 OH Tukang Batu 135,000.00 145,000.00 67,500.00 72,500.00
L.03 0.05 OH Kepala Tukang 140,000.00 150,000.00 7,000.00 7,500.00
L.04 0.0013 OH Mandor 130,000.00 145,000.00 169.00 188.50
Bahan 109,650.00 122,200.00
1.01 m2 Paving Block Tebal 8 Cm 85,000.00 95,000.00 85,850.00 95,950.00
0.07 m3 Pasir Beton 340,000.00 375,000.00 23,800.00 26,250.00
C PERALATAN 10,965.00 12,220.00
10 % Peralatan 109,650.00 122,200.00 10,965.00 12,220.00
D Jumlah A + B + C 247,784.00 272,108.50
E Overhead & Profit (contoh 10%) 10% 24,778.40 27,210.85
F Harga Satuan Pekerjaan (D+E) 272,562.40 299,319.35

32 A.4.4.3.66 1 m2 Pemasangan Paving Block Berwarna Tebal 6 Cm 217,127.90 240,287.85


Tenaga 100,919.00 108,938.50
L.01 0.25 OH Pekerja 105,000.00 115,000.00 26,250.00 28,750.00
L.02 0.5 OH Tukang Batu 135,000.00 145,000.00 67,500.00 72,500.00
L.03 0.05 OH Kepala Tukang 140,000.00 150,000.00 7,000.00 7,500.00
L.04 0.0013 OH Mandor 130,000.00 145,000.00 169.00 188.50
Bahan 87,700.00 99,550.00
1.01 m2 Paving Block Berwarna Tebal 6 Cm 70,000.00 80,000.00 70,700.00 80,800.00
0.05 m3 Pasir Beton 340,000.00 375,000.00 17,000.00 18,750.00
C PERALATAN 8,770.00 9,955.00
10 % Peralatan 87,700.00 99,550.00 8,770.00 9,955.00
D Jumlah A + B + C 197,389.00 218,443.50
E Overhead & Profit (contoh 10%) 10% 19,738.90 21,844.35
F Harga Satuan Pekerjaan (D+E) 217,127.90 240,287.85

33 A.4.4.3.67 1 m2 Pemasangan Paving Block Berwarna Tebal 8 Cm 284,783.40 311,540.35


Tenaga 127,169.00 137,688.50
L.01 0.5 OH Pekerja 105,000.00 115,000.00 52,500.00 57,500.00
L.02 0.5 OH Tukang Batu 135,000.00 145,000.00 67,500.00 72,500.00
L.03 0.05 OH Kepala Tukang 140,000.00 150,000.00 7,000.00 7,500.00
L.04 0.0013 OH Mandor 130,000.00 145,000.00 169.00 188.50
Bahan 119,750.00 132,300.00
1.01 m2 Paving Block Tebal Berwarna 8 Cm 95,000.00 105,000.00 95,950.00 106,050.00
0.07 m3 Pasir Beton 340,000.00 375,000.00 23,800.00 26,250.00
C PERALATAN 11,975.00 13,230.00
10 % Peralatan 119,750.00 132,300.00 11,975.00 13,230.00
D Jumlah A + B + C 258,894.00 283,218.50
E Overhead & Profit (contoh 10%) 10% 25,889.40 28,321.85
F Harga Satuan Pekerjaan (D+E) 284,783.40 311,540.35
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4


1 A.4.5.1.1 1 m2 34,452.00 37,515.50
mm, 5 mm & 6 mm

A Tenaga 14,100.00 15,230.00


L.01 0.03 OH Pekerja 105,000.00 115,000.00 3,150.00 3,450.00
L.02 0.07 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.004 OH Mandor 130,000.00 145,000.00 520.00 580.00
B Bahan 17,220.00 18,875.00
1.1 Lbr Plat Asbes 15,500.00 17,000.00 17,050.00 18,700.00
0.01 Kg Paku 17,000.00 17,500.00 170.00 175.00
C PERALATAN
D Jumlah A + B + C 31,320.00 34,105.00
E Overhead & Profit (contoh 10%) 10% 3,132.00 3,410.50
F Harga Satuan Pekerjaan (D+E) 34,452.00 37,515.50
Overhead & Profit (contoh 10%)
2 A.4.5.1.2 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm 111,881.00 124,019.50
A Tenaga 31,260.00 33,870.00
L.01 0.12 OH Pekerja 105,000.00 115,000.00 12,600.00 13,800.00
L.02 0.12 OH Tukang Kayu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
B Bahan 70,450.00 78,875.00
12.0 Lbr Akustik Uk.30 x 30 cm 5,800.00 6,500.00 69,600.00 78,000.00
0.05 Kg Paku 17,000.00 17,500.00 850.00 875.00
C PERALATAN
D Jumlah A + B + C 101,710.00 112,745.00
E Overhead & Profit (contoh 10%) 10% 10,171.00 11,274.50
F Harga Satuan Pekerjaan (D+E) 111,881.00 124,019.50

3 A.4.5.1.3 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x60) cm 113,806.00 124,520.00


A Tenaga 26,050.00 28,225.00
L.01 0.10 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.10 OH Tukang Kayu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 77,410.00 84,975.00
5.80 Lbr Akustik 13,200.00 14,500.00 76,560.00 84,100.00
0.05 Kg Paku 17,000.00 17,500.00 850.00 875.00
C PERALATAN
D Jumlah A + B + C 103,460.00 113,200.00
E Overhead & Profit (contoh 10%) 10% 10,346.00 11,320.00
F Harga Satuan Pekerjaan (D+E) 113,806.00 124,520.00

4 A.4.5.1.4 1 m2 Pemasangan Langit-langit Akustik Ukuran (60x120) cm 98,890.00 107,910.00


A Tenaga 26,050.00 28,225.00
L.01 0.10 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.10 OH Tukang Kayu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 63,850.00 69,875.00
1.50 Lbr Akustik 42,000.00 46,000.00 63,000.00 69,000.00
0.05 Kg Paku 17,000.00 17,500.00 850.00 875.00
C PERALATAN
D Jumlah A + B + C 89,900.00 98,100.00
E Overhead & Profit (contoh 10%) 10% 8,990.00 9,810.00
F Harga Satuan Pekerjaan (D+E) 98,890.00 107,910.00

Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3


5 A.4.5.1.5 1 m2 56,028.50 60,500.00
mm, 4 mm & 6 mm

A Tenaga 26,050.00 28,225.00


L.01 0.10 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.10 OH Tukang Kayu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00

file:///conversion/tmp/scratch/500669137.xls 125/95 9-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 24,885.00 26,775.00
0.375 Lbr Tripleks (4 mm) 65,000.00 70,000.00 24,375.00 26,250.00
0.03 Kg Paku Tripleks 17,000.00 17,500.00 510.00 525.00
C PERALATAN
D Jumlah A + B + C 50,935.00 55,000.00
E Overhead & Profit (contoh 10%) 10% 5,093.50 5,500.00
F Harga Satuan Pekerjaan (D+E) 56,028.50 60,500.00

6 A.4.5.1.6 1 m2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm 691,427.00 727,072.50


A Tenaga 208,400.00 225,800.00
L.01 0.8 OH Pekerja 105,000.00 115,000.00 84,000.00 92,000.00
L.02 0.8 OH Tukang Kayu 135,000.00 145,000.00 108,000.00 116,000.00
L.03 0.08 OH Kepala Tukang 140,000.00 150,000.00 11,200.00 12,000.00
L.04 0.04 OH Mandor 130,000.00 145,000.00 5,200.00 5,800.00
B Bahan 420,170.00 435,175.00
0.015 m3 Kayu Jati,Papan 28,000,000.00 29,000,000.00 420,000.00 435,000.00
0.01 Kg Paku 17,000.00 17,500.00 170.00 175.00
C PERALATAN
D Jumlah A + B + C 628,570.00 660,975.00
E Overhead & Profit (contoh 10%) 10% 62,857.00 66,097.50
F Harga Satuan Pekerjaan (D+E) 691,427.00 727,072.50

Memasang Langit-langit Gypsu Board, Ukuran (120x240)


7 A.4.5.1.7 1 m2 46,299.00 50,149.00
tebal 9 mm

A Tenaga 18,600.00 20,225.00


L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.05 OH Tukang Kayu 135,000.00 145,000.00 6,750.00 7,250.00
L.03 0.005 OH Kepala Tukang 140,000.00 150,000.00 700.00 750.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 23,490.00 25,365.00
0.364 Lbr Gypsum Board 60,000.00 65,000.00 21,840.00 23,660.00
0.11 Kg Paku Sekrup 15,000.00 15,500.00 1,650.00 1,705.00
C PERALATAN
D Jumlah A + B + C 42,090.00 45,590.00
E Overhead & Profit (contoh 10%) 10% 4,209.00 4,559.00
F Harga Satuan Pekerjaan (D+E) 46,299.00 50,149.00

Memasang Langit-langit Akustik Uk (60x120) cm & Berikut


8 A.4.5.1.8 1 m2 269,582.50 293,012.50
Rangka Allumunium

A Tenaga 130,250.00 141,125.00


L.01 0.5 OH Pekerja 105,000.00 115,000.00 52,500.00 57,500.00
L.02 0.5 OH Tukang Kayu 135,000.00 145,000.00 67,500.00 72,500.00
L.03 0.05 OH Kepala Tukang 140,000.00 150,000.00 7,000.00 7,500.00
L.04 0.025 OH Mandor 130,000.00 145,000.00 3,250.00 3,625.00
B Bahan 114,825.00 125,250.00
3.6 m' Profil Allumunium "T" 7,500.00 8,500.00 27,000.00 30,600.00
0.15 kg Kawat Ø 4 mm 15,000.00 17,000.00 2,250.00 2,550.00
1.05 bh Ramset 21,500.00 22,000.00 22,575.00 23,100.00
1.5 lmb Akustik 60 x 120 cm 42,000.00 46,000.00 63,000.00 69,000.00
C PERALATAN
D Jumlah A + B + C 245,075.00 266,375.00
E Overhead & Profit (contoh 10%) 10% 24,507.50 26,637.50
F Harga Satuan Pekerjaan (D+E) 269,582.50 293,012.50

9 A.4.5.1.9 1 m1 List Langit-Langit Kayu Profil 20,130.00 21,571.00


A Tenaga 13,090.00 14,185.00
L.01 0.05 OH Pekerja 105,000.00 115,000.00 5,250.00 5,750.00
L.02 0.05 OH Tukang Kayu 135,000.00 145,000.00 6,750.00 7,250.00
L.03 0.005 OH Kepala Tukang 140,000.00 150,000.00 700.00 750.00
L.04 0.003 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 5,210.00 5,425.00
1.05 m1 List Kayu Profil 4,800.00 5,000.00 5,040.00 5,250.00
0.01 Kg Paku 17,000.00 17,500.00 170.00 175.00
C PERALATAN
D Jumlah A + B + C 18,300.00 19,610.00
E Overhead & Profit (contoh 10%) 10% 1,830.00 1,961.00
F Harga Satuan Pekerjaan (D+E) 20,130.00 21,571.00

file:///conversion/tmp/scratch/500669137.xls 125/96 9-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
X A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP
1 A.4.5.2.1 1 m2 Pemasangan Atap Genteng Plentong Kecil 94,011.50 104,951.00
A Tenaga 27,965.00 30,410.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.02 0.075 OH Tukang Kayu 135,000.00 145,000.00 10,125.00 10,875.00
L.03 0.0075 OH Kepala Tukang 140,000.00 150,000.00 1,050.00 1,125.00
L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 57,500.00 65,000.00
25 Buah Genteng Plentong 2,300.00 2,600.00 57,500.00 65,000.00
C PERALATAN
D Jumlah A + B + C 85,465.00 95,410.00
E Overhead & Profit (contoh 10%) 10% 8,546.50 9,541.00
F Harga Satuan Pekerjaan (D+E) 94,011.50 104,951.00
Overhead & Profit (contoh 10%)
2 A.4.5.2.2 1 m2 Pemasangan Atap Genteng Kodok / Glasur 147,713.50 153,158.50
A Tenaga 28,035.00 30,485.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.02 0.075 OH Tukang Kayu 135,000.00 145,000.00 10,125.00 10,875.00
L.03 0.008 OH Kepala Tukang 140,000.00 150,000.00 1,120.00 1,200.00
L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 106,250.00 108,750.00
25 Buah Genteng Kodok / Glasur 4,250.00 4,350.00 106,250.00 108,750.00
C PERALATAN
D Jumlah A + B + C 134,285.00 139,235.00
E Overhead & Profit (contoh 10%) 10% 13,428.50 13,923.50
F Harga Satuan Pekerjaan (D+E) 147,713.50 153,158.50

3 A.4.5.2.3 1 m2 Pemasangan Atap Genteng Plentong Super / Besar 131,818.50 139,463.50


A Tenaga 28,035.00 30,485.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.02 0.075 OH Tukang Kayu 135,000.00 145,000.00 10,125.00 10,875.00
L.03 0.008 OH Kepala Tukang 140,000.00 150,000.00 1,120.00 1,200.00
L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 91,800.00 96,300.00
12 Buah Genteng Plentong Super / Besar 7,650.00 8,025.00 91,800.00 96,300.00
C PERALATAN
D Jumlah A + B + C 119,835.00 126,785.00
E Overhead & Profit (contoh 10%) 10% 11,983.50 12,678.50
F Harga Satuan Pekerjaan (D+E) 131,818.50 139,463.50

4 A.4.5.2.4 1 m' Pemasangan Genteng Bubung Plentong 123,673.00 133,628.00


A Tenaga 72,060.00 78,290.00
L.01 0.4 OH Pekerja 105,000.00 115,000.00 42,000.00 46,000.00
L.02 0.2 OH Tukang Kayu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.002 OH Mandor 130,000.00 145,000.00 260.00 290.00
B Bahan 40,370.00 43,190.00
5 Buah Genteng Bubung Plentong 4,250.00 4,350.00 21,250.00 21,750.00
8 Kg Portland Semen 1,150.00 1,200.00 9,200.00 9,600.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00
C PERALATAN
D Jumlah A + B + C 112,430.00 121,480.00
E Overhead & Profit (contoh 10%) 10% 11,243.00 12,148.00
F Harga Satuan Pekerjaan (D+E) 123,673.00 133,628.00

file:///conversion/tmp/scratch/500669137.xls 125/97 10-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.5.2.5 1 m' Pemasangan Genteng Bubung Kodok / Glasur 136,048.00 147,103.00
A Tenaga 72,060.00 78,290.00
L.01 0.4 OH Pekerja 105,000.00 115,000.00 42,000.00 46,000.00
L.02 0.2 OH Tukang Kayu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.002 OH Mandor 130,000.00 145,000.00 260.00 290.00
B Bahan 51,620.00 55,440.00
5 Buah Genteng Bubung Kodok / Glasur 6,500.00 6,800.00 32,500.00 34,000.00
8 Kg Portland Semen 1,150.00 1,200.00 9,200.00 9,600.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00
C PERALATAN
D Jumlah A + B + C 123,680.00 133,730.00
E Overhead & Profit (contoh 10%) 10% 12,368.00 13,373.00
F Harga Satuan Pekerjaan (D+E) 136,048.00 147,103.00

6 A.4.5.2.6 1 m' Pemasangan Genteng Bubung Plentong Besar 139,898.00 150,183.00


A Tenaga 72,060.00 78,290.00
L.01 0.4 OH Pekerja 105,000.00 115,000.00 42,000.00 46,000.00
L.02 0.2 OH Tukang Kayu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.002 OH Mandor 130,000.00 145,000.00 260.00 290.00
B Bahan 55,120.00 58,240.00
4 Buah Genteng Bubung Plentong Besar 9,000.00 9,200.00 36,000.00 36,800.00
8 Kg Portland Semen 1,150.00 1,200.00 9,200.00 9,600.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00
C PERALATAN
D Jumlah A + B + C 127,180.00 136,530.00
E Overhead & Profit (contoh 10%) 10% 12,718.00 13,653.00
F Harga Satuan Pekerjaan (D+E) 139,898.00 150,183.00

7 A.4.5.2.7 1 m2 Pemasangan Roof Light Fibreglass 90 x 180 111,633.50 124,030.50


A Tenaga 25,635.00 27,880.00
L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.067 OH Tukang Kayu 135,000.00 145,000.00 9,045.00 9,715.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 75,850.00 84,875.00
0.6 Lbr Rooflight 90 x 180 125,000.00 140,000.00 75,000.00 84,000.00
0.05 Kg Paku Biasa 17,000.00 17,500.00 850.00 875.00
C PERALATAN
D Jumlah A + B + C 101,485.00 112,755.00
E Overhead & Profit (contoh 10%) 10% 10,148.50 11,275.50
F Harga Satuan Pekerjaan (D+E) 111,633.50 124,030.50

Pemasangan Atap Asbes Gelombang (2,50x0,92 m) x 5


8 A.4.5.2.8 1 m2 71,054.50 79,106.50
mm

A Tenaga 26,985.00 29,335.00


L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.075 OH Tukang Kayu 135,000.00 145,000.00 10,125.00 10,875.00
L.03 0.008 OH Kepala Tukang 140,000.00 150,000.00 1,120.00 1,200.00
L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 37,610.00 42,580.00
0.5 Lbr Asbes Gelombang 71,500.00 81,200.00 35,750.00 40,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 64,595.00 71,915.00
E Overhead & Profit (contoh 10%) 10% 6,459.50 7,191.50
F Harga Satuan Pekerjaan (D+E) 71,054.50 79,106.50

file:///conversion/tmp/scratch/500669137.xls 125/98 10-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5
9 A.4.5.2.9 1 m2 72,600.00 80,976.50
mm

A Tenaga 26,040.00 28,315.00


L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.07 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 39,960.00 45,300.00
0.6 Lbr Asbes Gelombang 63,500.00 72,200.00 38,100.00 43,320.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 66,000.00 73,615.00
E Overhead & Profit (contoh 10%) 10% 6,600.00 7,361.50
F Harga Satuan Pekerjaan (D+E) 72,600.00 80,976.50

Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5


10 A.4.5.2.10 1 m2 72,930.00 81,636.50
mm

A Tenaga 26,040.00 28,315.00


L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.07 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 40,260.00 45,900.00
0.6 Lbr Asbes Gelombang 64,000.00 73,200.00 38,400.00 43,920.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 66,300.00 74,215.00
E Overhead & Profit (contoh 10%) 10% 6,630.00 7,421.50
F Harga Satuan Pekerjaan (D+E) 72,930.00 81,636.50

Pemasangan Atap Asbes Gelombang (1,80x0,92 m) x 5


11 A.4.5.2.11 1 m2 80,190.00 84,474.50
mm

A Tenaga 26,040.00 28,315.00


L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.07 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 46,860.00 48,480.00
0.75 Lbr Asbes Gelombang 60,000.00 62,000.00 45,000.00 46,500.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 72,900.00 76,795.00
E Overhead & Profit (contoh 10%) 10% 7,290.00 7,679.50
F Harga Satuan Pekerjaan (D+E) 80,190.00 84,474.50

Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4


12 A.4.5.2.12 1 m2 63,415.00 79,139.50
mm
A Tenaga 26,040.00 28,315.00
L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.07 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 31,610.00 43,630.00
0.35 Lbr Asbes Gelombang 85,000.00 119,000.00 29,750.00 41,650.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 57,650.00 71,945.00
E Overhead & Profit (contoh 10%) 10% 5,765.00 7,194.50
F Harga Satuan Pekerjaan (D+E) 63,415.00 79,139.50

file:///conversion/tmp/scratch/500669137.xls 125/99 10-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,70x1,05 m) x 4
13 A.4.5.2.13 1 m2 65,340.00 81,372.50
mm
A Tenaga 26,040.00 28,315.00
L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.07 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 33,360.00 45,660.00
0.42 Lbr Asbes Gelombang 75,000.00 104,000.00 31,500.00 43,680.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 59,400.00 73,975.00
E Overhead & Profit (contoh 10%) 10% 5,940.00 7,397.50
F Harga Satuan Pekerjaan (D+E) 65,340.00 81,372.50

Pemasangan Atap Asbes Gelombang (2,40x1,05 m) x 4


14 A.4.5.2.14 1 m2 63,360.00 79,788.50
mm
A Tenaga 26,040.00 28,315.00
L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.070 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 31,560.00 44,220.00
0.44 Lbr Asbes Gelombang 67,500.00 96,000.00 29,700.00 42,240.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 57,600.00 72,535.00
E Overhead & Profit (contoh 10%) 10% 5,760.00 7,253.50
F Harga Satuan Pekerjaan (D+E) 63,360.00 79,788.50

Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4


15 A.4.5.2.15 1 m2 64,350.00 78,765.50
mm
A Tenaga 26,040.00 28,315.00
L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.070 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 32,460.00 43,290.00
0.51 Lbr Asbes Gelombang 60,000.00 81,000.00 30,600.00 41,310.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 58,500.00 71,605.00
E Overhead & Profit (contoh 10%) 10% 5,850.00 7,160.50
F Harga Satuan Pekerjaan (D+E) 64,350.00 78,765.50

Pemasangan Atap Asbes Gelombang (1,50x1,05 m) x 4


16 A.4.5.2.16 1 m2 68,090.00 81,724.50
mm
A Tenaga 26,040.00 28,315.00
L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.070 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 35,860.00 45,980.00
0.80 Lbr Asbes Gelombang 42,500.00 55,000.00 34,000.00 44,000.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 61,900.00 74,295.00
E Overhead & Profit (contoh 10%) 10% 6,190.00 7,429.50
F Harga Satuan Pekerjaan (D+E) 68,090.00 81,724.50

Pemasangan Atap Asbes Gelombang (3,00x1,08 m) x 6


17 A.4.5.2.17 1 m2 72,611.00 76,059.50
mm
A Tenaga 26,040.00 28,315.00
L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.07 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 39,970.00 40,830.00
0.37 Lbr Asbes Gelombang 103,000.00 105,000.00 38,110.00 38,850.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00

file:///conversion/tmp/scratch/500669137.xls 125/100 10-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 66,010.00 69,145.00
E Overhead & Profit (contoh 10%) 10% 6,601.00 6,914.50
F Harga Satuan Pekerjaan (D+E) 72,611.00 76,059.50

Pemasangan Atap Asbes Gelombang (2,70x1,08 m) x 6


18 A.4.5.2.18 1 m2 75,966.00 79,524.50
mm
A Tenaga 26,040.00 28,315.00
L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.07 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 43,020.00 43,980.00
0.42 Lbr Asbes Gelombang 98,000.00 100,000.00 41,160.00 42,000.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 69,060.00 72,295.00
E Overhead & Profit (contoh 10%) 10% 6,906.00 7,229.50
F Harga Satuan Pekerjaan (D+E) 75,966.00 79,524.50

Pemasangan Atap Asbes Gelombang (2,40x1,08 m) x 6


19 A.4.5.2.19 1 m2 72,798.00 76,884.50
mm
A Tenaga 26,040.00 28,315.00
L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.070 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 40,140.00 41,580.00
0.44 Lbr Asbes Gelombang 87,000.00 90,000.00 38,280.00 39,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 66,180.00 69,895.00
E Overhead & Profit (contoh 10%) 10% 6,618.00 6,989.50
F Harga Satuan Pekerjaan (D+E) 72,798.00 76,884.50

Pemasangan Atap Asbes Gelombang (2,10x1,08 m) x 6


20 A.4.5.2.20 1 m2 73,810.00 78,061.50
mm
A Tenaga 26,040.00 28,315.00
L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.070 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 41,060.00 42,650.00
0.49 Lbr Asbes Gelombang 80,000.00 83,000.00 39,200.00 40,670.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 67,100.00 70,965.00
E Overhead & Profit (contoh 10%) 10% 6,710.00 7,096.50
F Harga Satuan Pekerjaan (D+E) 73,810.00 78,061.50

Pemasangan Atap Asbes Gelombang (1,80x1,08 m) x 6


21 A.4.5.2.21 1 m2 77,715.00 81,603.50
mm
A Tenaga 26,040.00 28,315.00
L.01 0.14 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.070 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 44,610.00 45,870.00
0.57 Lbr Asbes Gelombang 75,000.00 77,000.00 42,750.00 43,890.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 70,650.00 74,185.00
E Overhead & Profit (contoh 10%) 10% 7,065.00 7,418.50
F Harga Satuan Pekerjaan (D+E) 77,715.00 81,603.50

file:///conversion/tmp/scratch/500669137.xls 125/101 10-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
22 A.4.5.2.30 1 m2 Pemasangan Atap Genteng Beton 118,921.00 132,192.50
A Tenaga 37,200.00 40,450.00
L.01 0.2 OH Pekerja 105,000.00 115,000.00 21,000.00 23,000.00
L.02 0.1 OH Tukang Kayu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.01 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00
B Bahan 70,910.00 79,725.00
11 Lbr Genteng Beton Standrad 6,400.00 7,200.00 70,400.00 79,200.00
0.03 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 510.00 525.00
C PERALATAN
D Jumlah A + B + C 108,110.00 120,175.00
E Overhead & Profit (contoh 10%) 10% 10,811.00 12,017.50
F Harga Satuan Pekerjaan (D+E) 118,921.00 132,192.50

23 A.4.5.2.31 1 m2 Pemasangan Atap Genteng Aspal 238,898.00 264,577.50


A Tenaga 63,220.00 68,400.00
L.01 0.2 OH Pekerja 105,000.00 115,000.00 21,000.00 23,000.00
L.02 0.3 OH Tukang Kayu 135,000.00 145,000.00 40,500.00 43,500.00
L.03 0.003 OH Kepala Tukang 140,000.00 150,000.00 420.00 450.00
L.04 0.01 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00
B Bahan 153,960.00 172,125.00
6.9 Buah Genteng Aspal 18,000.00 20,000.00 124,200.00 138,000.00
0.35 lbr Plywood 6 mm 75,000.00 86,000.00 26,250.00 30,100.00
0.03 kg Paku Biasa 2" - 5" 17,000.00 17,500.00 510.00 525.00
0.50 buah Plastic Aerotor 6,000.00 7,000.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 217,180.00 240,525.00
E Overhead & Profit (contoh 10%) 10% 21,718.00 24,052.50
F Harga Satuan Pekerjaan (D+E) 238,898.00 264,577.50

24 A.4.5.2.32 1 m2 Pemasangan Atap Genteng Metal 100,760.00 115,665.00


A Tenaga 37,200.00 40,450.00
L.01 0.2 OH Pekerja 105,000.00 115,000.00 21,000.00 23,000.00
L.02 0.1 OH Tukang Kayu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.01 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00
B Bahan 54,400.00 64,700.00
1.02 m2 Genteng Metal 50,000.00 60,000.00 51,000.00 61,200.00
0.20 Kg Paku Biasa Ø ½" - 1" 17,000.00 17,500.00 3,400.00 3,500.00
C PERALATAN
D Jumlah A + B + C 91,600.00 105,150.00
E Overhead & Profit (contoh 10%) 10% 9,160.00 10,515.00
F Harga Satuan Pekerjaan (D+E) 100,760.00 115,665.00

25 A.4.5.2.34 1 m2 Pemasangan Atap Sirap 127,732.00 139,425.00


A Tenaga 55,720.00 60,250.00
L.01 0.166 OH Pekerja 105,000.00 115,000.00 17,430.00 19,090.00
L.02 0.25 OH Tukang Kayu 135,000.00 145,000.00 33,750.00 36,250.00
L.03 0.025 OH Kepala Tukang 140,000.00 150,000.00 3,500.00 3,750.00
L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 60,400.00 66,500.00
30 Lbr Genteng Sirap 1,900.00 2,100.00 57,000.00 63,000.00
0.2 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 3,400.00 3,500.00
C PERALATAN
D Jumlah A + B + C 116,120.00 126,750.00
E Overhead & Profit (contoh 10%) 10% 11,612.00 12,675.00
F Harga Satuan Pekerjaan (D+E) 127,732.00 139,425.00

26 A.4.5.2.35 1 m' Pemasangan Nok Genteng Beton 145,464.00 159,582.50


A Tenaga 74,400.00 80,900.00
L.01 0.4 OH Pekerja 105,000.00 115,000.00 42,000.00 46,000.00
L.02 0.2 OH Tukang Kayu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.02 OH Mandor 130,000.00 145,000.00 2,600.00 2,900.00
B Bahan 57,840.00 64,175.00
3.5 Buah Nok Genteng Beton 9,900.00 11,000.00 34,650.00 38,500.00
0.05 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 850.00 875.00
10.8 Kg Portland Semen 1,150.00 1,200.00 12,420.00 12,960.00
0.032 m3 Pasir Pasang 310,000.00 370,000.00 9,920.00 11,840.00
1 Kg Semen Warna 12,000.00 15,000.00 12,000.00 15,000.00

file:///conversion/tmp/scratch/500669137.xls 125/102 10-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 132,240.00 145,075.00
E Overhead & Profit (contoh 10%) 10% 13,224.00 14,507.50
F Harga Satuan Pekerjaan (D+E) 145,464.00 159,582.50

27 A.4.5.2.36 1 m' Pemasangan Nok Genteng Aspal 143,830.50 153,912.00


A Tenaga 51,155.00 55,245.00
L.01 0.125 OH Pekerja 105,000.00 115,000.00 13,125.00 14,375.00
L.02 0.250 OH Tukang Kayu 135,000.00 145,000.00 33,750.00 36,250.00
L.03 0.025 OH Kepala Tukang 140,000.00 150,000.00 3,500.00 3,750.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
B Bahan 79,600.00 84,675.00
2.0 Buah Nok Genteng Aspal 28,000.00 30,000.00 56,000.00 60,000.00
0.05 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 850.00 875.00
0.0035 m3 Balok Kayu 6,500,000.00 6,800,000.00 22,750.00 23,800.00
C PERALATAN
D Jumlah A + B + C 130,755.00 139,920.00
E Overhead & Profit (contoh 10%) 10% 13,075.50 13,992.00
F Harga Satuan Pekerjaan (D+E) 143,830.50 153,912.00

28 A.4.5.2.37 1 m' Pemasangan Nok Genteng Metal 80,454.00 88,286.00


A Tenaga 50,290.00 54,635.00
L.01 0.250 OH Pekerja 105,000.00 115,000.00 26,250.00 28,750.00
L.02 0.150 OH Tukang Kayu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.013 OH Mandor 130,000.00 145,000.00 1,690.00 1,885.00
B Bahan 22,850.00 25,625.00
1.1 Buah Nok Genteng 20,000.00 22,500.00 22,000.00 24,750.00
0.05 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 850.00 875.00

C PERALATAN
D Jumlah A + B + C 73,140.00 80,260.00
E Overhead & Profit (contoh 10%) 10% 7,314.00 8,026.00
F Harga Satuan Pekerjaan (D+E) 80,454.00 88,286.00

29 A.4.5.2.38 1 m' Pemasangan Nok Sirap 69,987.50 76,087.00


A Tenaga 51,155.00 55,245.00
L.01 0.125 OH Pekerja 105,000.00 115,000.00 13,125.00 14,375.00
L.02 0.25 OH Tukang Kayu 135,000.00 145,000.00 33,750.00 36,250.00
L.03 0.025 OH Kepala Tukang 140,000.00 150,000.00 3,500.00 3,750.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
B Bahan 12,470.00 13,925.00
0.4 Lbr Seng Plaat 3" x 6" BJLS 28 26,500.00 30,000.00 10,600.00 12,000.00
0.06 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 1,020.00 1,050.00
0.05 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 850.00 875.00

C PERALATAN
D Jumlah A + B + C 63,625.00 69,170.00
E Overhead & Profit (contoh 10%) 10% 6,362.50 6,917.00
F Harga Satuan Pekerjaan (D+E) 69,987.50 76,087.00

30 A.4.5.2.39 1 m2 Pemasangan Atap Seng Gelombang 45,331.00 50,182.00


A Tenaga 22,320.00 24,270.00
L.01 0.12 OH Pekerja 105,000.00 115,000.00 12,600.00 13,800.00
L.02 0.06 OH Tukang Kayu 135,000.00 145,000.00 8,100.00 8,700.00
L.03 0.006 OH Kepala Tukang 140,000.00 150,000.00 840.00 900.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
B Bahan 18,890.00 21,350.00
0.7 Lbr Seng Gelombang 3" x 6" BJLS 28 26,500.00 30,000.00 18,550.00 21,000.00
0.02 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 340.00 350.00
C PERALATAN
D Jumlah A + B + C 41,210.00 45,620.00
E Overhead & Profit (contoh 10%) 10% 4,121.00 4,562.00
F Harga Satuan Pekerjaan (D+E) 45,331.00 50,182.00

file:///conversion/tmp/scratch/500669137.xls 125/103 10-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
31 A.4.5.2.40 1 m' Pemasangan Atap Nok Seng 39,149.00 42,922.00
A Tenaga 26,960.00 29,320.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.02 0.07 OH Tukang Kayu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
B Bahan 8,630.00 9,700.00
0.3 Lbr Seng Plaat 3" x 6" BJLS 28 26,500.00 30,000.00 7,950.00 9,000.00
0.04 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 680.00 700.00
C PERALATAN
D Jumlah A + B + C 35,590.00 39,020.00
E Overhead & Profit (contoh 10%) 10% 3,559.00 3,902.00
F Harga Satuan Pekerjaan (D+E) 39,149.00 42,922.00

32 A.4.5.2.43 1 m2 Pasang Allumunium Foil / Sisalation 40,524.00 46,376.00


A Tenaga 24,240.00 26,410.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.02 0.05 OH Tukang Kayu 135,000.00 145,000.00 6,750.00 7,250.00
L.03 0.005 OH Kepala Tukang 140,000.00 150,000.00 700.00 750.00
L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 12,600.00 15,750.00
1.05 m2 Sisalation / Allumunium Foil 12,000.00 15,000.00 12,600.00 15,750.00
C PERALATAN
D Jumlah A + B + C 36,840.00 42,160.00
E Overhead & Profit (contoh 10%) 10% 3,684.00 4,216.00
F Harga Satuan Pekerjaan (D+E) 40,524.00 46,376.00

file:///conversion/tmp/scratch/500669137.xls 125/104 10-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
Pembuatan & Pemasangan Kosen Pintu & Jendela
1 A.4.6.1.1 1 m3 34,587,575.00 36,143,387.50
Kayu klas I
A Tenaga 3,909,500.00 4,215,750.00
L.01 7 OH Pekerja 105,000.00 115,000.00 735,000.00 805,000.00
L.02 21 OH Tukang Kayu 135,000.00 145,000.00 2,835,000.00 3,045,000.00
L.03 2.10 OH Kepala Tukang 140,000.00 150,000.00 294,000.00 315,000.00
L.04 0.35 OH Mandor 130,000.00 145,000.00 45,500.00 50,750.00
B Bahan 27,533,750.00 28,641,875.00
1.1 m3 Kayu Klas I (Jati) , Balok 25,000,000.00 26,000,000.00 27,500,000.00 28,600,000.00
1.25 kg Paku Biasa 2" - 5 " 17,000.00 17,500.00 21,250.00 21,875.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 31,443,250.00 32,857,625.00
E Overhead & Profit (contoh 10%) 10% 3,144,325.00 3,285,762.50
F Harga Satuan Pekerjaan (D+E) 34,587,575.00 36,143,387.50

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 1 m3 14,811,225.00 15,372,912.50
Kayu klas II atau III
Tenaga 3,351,000.00 3,613,500.00
L.01 6.00 OH Pekerja 105,000.00 115,000.00 630,000.00 690,000.00
L.02 18.00 OH Tukang Kayu 135,000.00 145,000.00 2,430,000.00 2,610,000.00
L.03 1.80 OH Kepala Tukang 140,000.00 150,000.00 252,000.00 270,000.00
L.04 0.30 OH Mandor 130,000.00 145,000.00 39,000.00 43,500.00
Bahan 10,113,750.00 10,361,875.00
1.2 m3 Kayu Klas II (Kamfer) , Balok 8,400,000.00 8,600,000.00 10,080,000.00 10,320,000.00
1.25 kg Paku Biasa 2" - 5 " 17,000.00 17,500.00 21,250.00 21,875.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 13,464,750.00 13,975,375.00
E Overhead & Profit (contoh 10%) 10% 1,346,475.00 1,397,537.50
F Harga Satuan Pekerjaan (D+E) 14,811,225.00 15,372,912.50

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 1 m2 598,829.00 620,108.50
Kayu Klas II (Kayu Kamfer)
A Tenaga 195,540.00 210,860.00
L.01 0.35 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 1.05 OH Tukang Kayu 135,000.00 145,000.00 141,750.00 152,250.00
L.03 0.105 OH Kepala Tukang 140,000.00 150,000.00 14,700.00 15,750.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00
B Bahan 348,850.00 352,875.00
0.040 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 348,000.00 352,000.00
0.05 Kg Paku Biasa 2" - 5 " 17,000.00 17,500.00 850.00 875.00
C PERALATAN
D Jumlah A + B + C 544,390.00 563,735.00
E Overhead & Profit (contoh 10%) 10% 54,439.00 56,373.50
F Harga Satuan Pekerjaan (D+E) 598,829.00 620,108.50

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 1 m2 598,829.00 620,108.50
Sederhana Kayu Klas III
Tenaga 195,540.00 210,860.00
L.01 0.35 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 1.05 OH Tukang Kayu 135,000.00 145,000.00 141,750.00 152,250.00
L.03 0.105 OH Kepala Tukang 140,000.00 150,000.00 14,700.00 15,750.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00
Bahan 348,850.00 352,875.00
0.040 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 348,000.00 352,000.00
0.05 Kg Paku Biasa 2" - 5 " 17,000.00 17,500.00 850.00 875.00
C PERALATAN
D Jumlah A + B + C 544,390.00 563,735.00
E Overhead & Profit (contoh 10%) 10% 54,439.00 56,373.50
F Harga Satuan Pekerjaan (D+E) 598,829.00 620,108.50

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 1 m2 997,837.50 1,050,775.00
Klas I atau II
A Tenaga 558,500.00 602,250.00
L.01 1.00 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00
L.02 3.00 OH Tukang Kayu 135,000.00 145,000.00 405,000.00 435,000.00
L.03 0.30 OH Kepala Tukang 140,000.00 150,000.00 42,000.00 45,000.00
L.04 0.05 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00
B Bahan 348,625.00 353,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 348,000.00 352,000.00
0.050 kg Lem Kayu 12,500.00 20,000.00 625.00 1,000.00
C PERALATAN
D Jumlah A + B + C 907,125.00 955,250.00
E Overhead & Profit (contoh 10%) 10% 90,712.50 95,525.00
F Harga Satuan Pekerjaan (D+E) 997,837.50 1,050,775.00

file:///conversion/tmp/scratch/500669137.xls 125/105 11-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu & Jendela Kaca
6 A.4.6.1.6 1 m2 725,285.00 768,900.00
Kayu Klas I atau II
A Tenaga 446,800.00 481,800.00
L.01 0.800 OH Pekerja 105,000.00 115,000.00 84,000.00 92,000.00
L.02 2.400 OH Tukang Kayu 135,000.00 145,000.00 324,000.00 348,000.00
L.03 0.240 OH Kepala Tukang 140,000.00 150,000.00 33,600.00 36,000.00
L.04 0.040 OH Mandor 130,000.00 145,000.00 5,200.00 5,800.00
B Bahan 212,550.00 217,200.00
0.024 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 208,800.00 211,200.00
0.300 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
C PERALATAN
D Jumlah A + B + C 659,350.00 699,000.00
E Overhead & Profit (contoh 10%) 10% 65,935.00 69,900.00
F Harga Satuan Pekerjaan (D+E) 725,285.00 768,900.00

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 1 m2 2,592,425.00 2,715,075.00
Kayu Klas I atau II (jati)
A Tenaga 558,500.00 602,250.00
L.01 1 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00
L.02 3 OH Tukang Kayu 135,000.00 145,000.00 405,000.00 435,000.00
L.03 0.3 OH Kepala Tukang 140,000.00 150,000.00 42,000.00 45,000.00
L.04 0.05 OH Mandor 130,000.00 145,000.00 6,500.00 7,250.00
B Bahan 1,798,250.00 1,866,000.00
0.064 m3 Kayu Klas I (Jati), papan 28,000,000.00 29,000,000.00 1,792,000.00 1,856,000.00
0.5 kg Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
C PERALATAN
D Jumlah A + B + C 2,356,750.00 2,468,250.00
E Overhead & Profit (contoh 10%) 10% 235,675.00 246,825.00
F Harga Satuan Pekerjaan (D+E) 2,592,425.00 2,715,075.00

Pembuatan&Pemasangan Pintu kayu lapis (Plywood)


8 A.4.6.1.8 1 m2 748,231.00 810,810.00
Rangkap rangka Kayu Klas II (lbr s/d 90 cm)

A Tenaga 390,950.00 421,575.00


L.01 0.700 OH Pekerja 105,000.00 115,000.00 73,500.00 80,500.00
L.02 2.100 OH Tukang Kayu 135,000.00 145,000.00 283,500.00 304,500.00
L.03 0.210 OH Kepala Tukang 140,000.00 150,000.00 29,400.00 31,500.00
L.04 0.035 OH Mandor 130,000.00 145,000.00 4,550.00 5,075.00
B Bahan 289,260.00 315,525.00
0.025 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 217,500.00 220,000.00
0.030 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 510.00 525.00
0.500 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 85,000.00 65,000.00 85,000.00
C PERALATAN
D Jumlah A + B + C 680,210.00 737,100.00
E Overhead & Profit (contoh 10%) 10% 68,021.00 73,710.00
F Harga Satuan Pekerjaan (D+E) 748,231.00 810,810.00

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 1 m2 815,408.00 882,865.50
rangka expose kayu klas I atau II
A Tenaga 446,800.00 481,800.00
L.01 0.800 OH Pekerja 105,000.00 115,000.00 84,000.00 92,000.00
L.02 2.400 OH Tukang Kayu 135,000.00 145,000.00 324,000.00 348,000.00
L.03 0.240 OH Kepala Tukang 140,000.00 150,000.00 33,600.00 36,000.00
L.04 0.040 OH Mandor 130,000.00 145,000.00 5,200.00 5,800.00
B Bahan 294,480.00 320,805.00
0.0256 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 222,720.00 225,280.00
0.03 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 510.00 525.00
0.5 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 85,000.00 65,000.00 85,000.00
C PERALATAN
D Jumlah A + B + C 741,280.00 802,605.00
E Overhead & Profit (contoh 10%) 10% 74,128.00 80,260.50
F Harga Satuan Pekerjaan (D+E) 815,408.00 882,865.50

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 1 m2 2,303,895.00 2,407,075.00
Klas I atau II
A Tenaga 411,900.00 445,625.00
L.01 0.670 OH Pekerja 105,000.00 115,000.00 70,350.00 77,050.00
L.02 2.000 OH Tukang Kayu 135,000.00 145,000.00 270,000.00 290,000.00
L.03 0.200 OH Kepala Tukang 140,000.00 150,000.00 28,000.00 30,000.00
L.04 0.335 OH Mandor 130,000.00 145,000.00 43,550.00 48,575.00
B Bahan 1,682,550.00 1,742,625.00
0.06 m3 Kayu Klas I (Jati), papan 28,000,000.00 29,000,000.00 1,680,000.00 1,740,000.00
0.15 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 2,550.00 2,625.00
C PERALATAN
D Jumlah A + B + C 2,094,450.00 2,188,250.00
E Overhead & Profit (contoh 10%) 10% 209,445.00 218,825.00
F Harga Satuan Pekerjaan (D+E) 2,303,895.00 2,407,075.00

file:///conversion/tmp/scratch/500669137.xls 125/106 11-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu Teakwood
11 A.4.6.1.11 1 m2 1,337,666.00 1,428,157.50
Rangkap, Rangka Expose Kayu Klas I
A Tenaga 446,800.00 481,800.00
L.01 0.80 OH Pekerja 105,000.00 115,000.00 84,000.00 92,000.00
L.02 2.40 OH Tukang Kayu 135,000.00 145,000.00 324,000.00 348,000.00
L.03 0.24 OH Kepala Tukang 140,000.00 150,000.00 33,600.00 36,000.00
L.04 0.04 OH Mandor 130,000.00 145,000.00 5,200.00 5,800.00
B Bahan 769,260.00 816,525.00
0.025 m3 Kayu Klas I (Jati), papan 28,000,000.00 29,000,000.00 700,000.00 725,000.00
0.03 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 510.00 525.00
0.3 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 85,000.00 65,000.00 85,000.00
C PERALATAN
D Jumlah A + B + C 1,216,060.00 1,298,325.00
E Overhead & Profit (contoh 10%) 10% 121,606.00 129,832.50
F Harga Satuan Pekerjaan (D+E) 1,337,666.00 1,428,157.50

Pembuatan & Pemasangan Pintu Teakwood Rangkap


12 A.4.6.1.12 1 m2 873,180.00 942,271.00
Lapis Formika, Rangka expose Kayu Klas II

A Tenaga 474,790.00 511,985.00


L.01 0.850 OH Pekerja 105,000.00 115,000.00 89,250.00 97,750.00
L.02 2.550 OH Tukang Kayu 135,000.00 145,000.00 344,250.00 369,750.00
L.03 0.255 OH Kepala Tukang 140,000.00 150,000.00 35,700.00 38,250.00
L.04 0.043 OH Mandor 130,000.00 145,000.00 5,590.00 6,235.00
B Bahan 319,010.00 344,625.00
0.025 m3 Kayu Klas II (Kamfer), papan 8,700,000.00 8,800,000.00 217,500.00 220,000.00
0.03 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 510.00 525.00
0.08 kg Lem Kayu 12,500.00 20,000.00 1,000.00 1,600.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 85,000.00 65,000.00 85,000.00
0.5 Lbr Formika 70,000.00 75,000.00 35,000.00 37,500.00
C PERALATAN
D Jumlah A + B + C 793,800.00 856,610.00
E Overhead & Profit (contoh 10%) 10% 79,380.00 85,661.00
F Harga Satuan Pekerjaan (D+E) 873,180.00 942,271.00

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 1 m3 12,957,120.00 13,398,825.00
Konvensional Kayu I; II & III Bentang 6 meter
A Tenaga 2,234,000.00 2,409,000.00
L.01 4 OH Pekerja 105,000.00 115,000.00 420,000.00 460,000.00
L.02 12 OH Tukang Kayu 135,000.00 145,000.00 1,620,000.00 1,740,000.00
L.03 1.2 OH Kepala Tukang 140,000.00 150,000.00 168,000.00 180,000.00
L.04 0.2 OH Mandor 130,000.00 145,000.00 26,000.00 29,000.00
B Bahan 9,545,200.00 9,771,750.00
1.1 m3 Kayu Kamfer, balok 8,400,000.00 8,600,000.00 9,240,000.00 9,460,000.00
15 Kg Besi Strip 14,000.00 14,250.00 210,000.00 213,750.00
5.6 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 95,200.00 98,000.00
C PERALATAN
D Jumlah A + B + C 11,779,200.00 12,180,750.00
E Overhead & Profit (contoh 10%) 10% 1,177,920.00 1,218,075.00
F Harga Satuan Pekerjaan (D+E) 12,957,120.00 13,398,825.00

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 1 m3 37,451,865.00 39,101,507.50
Expose, Kayu Klas I
A Tenaga 3,741,950.00 4,035,075.00
L.01 6.7 OH Pekerja 105,000.00 115,000.00 703,500.00 770,500.00
L.02 20.1 OH Tukang Kayu 135,000.00 145,000.00 2,713,500.00 2,914,500.00
L.03 2.01 OH Kepala Tukang 140,000.00 150,000.00 281,400.00 301,500.00
L.04 0.335 OH Mandor 130,000.00 145,000.00 43,550.00 48,575.00
B Bahan 30,305,200.00 31,511,750.00
1.2 m3 Kayu Klas I (jati), balok 25,000,000.00 26,000,000.00 30,000,000.00 31,200,000.00
15 Kg Besi Strip 14,000.00 14,250.00 210,000.00 213,750.00
5.6 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 95,200.00 98,000.00
C PERALATAN
D Jumlah A + B + C 34,047,150.00 35,546,825.00
E Overhead & Profit (contoh 10%) 10% 3,404,715.00 3,554,682.50
F Harga Satuan Pekerjaan (D+E) 37,451,865.00 39,101,507.50

15 A.4.6.1.15 1 m3 Pemasangan konstruksi Gording, Kayu Klas II 11,925,540.00 12,288,815.00


A Tenaga 1,340,400.00 1,445,400.00
L.01 2.4 OH Pekerja 105,000.00 115,000.00 252,000.00 276,000.00
L.02 7.2 OH Tukang Kayu 135,000.00 145,000.00 972,000.00 1,044,000.00
L.03 0.72 OH Kepala Tukang 140,000.00 150,000.00 100,800.00 108,000.00
L.04 0.12 OH Mandor 130,000.00 145,000.00 15,600.00 17,400.00

file:///conversion/tmp/scratch/500669137.xls 125/107 11-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 9,501,000.00 9,726,250.00
1.1 m3 Kayu Klas I (Kamfer), balok 8,400,000.00 8,600,000.00 9,240,000.00 9,460,000.00
15 Kg Besi Strip 14,000.00 14,250.00 210,000.00 213,750.00
3 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 51,000.00 52,500.00
C PERALATAN
D Jumlah A + B + C 10,841,400.00 11,171,650.00
E Overhead & Profit (contoh 10%) 10% 1,084,140.00 1,117,165.00
F Harga Satuan Pekerjaan (D+E) 11,925,540.00 12,288,815.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 1 m2 195,954.00 202,356.00
Klas II
A Tenaga 26,050.00 28,225.00
L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.1 OH Tukang Kayu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 152,090.00 155,735.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 8,400,000.00 8,600,000.00 117,600.00 120,400.00
0.0036 m3 Reng (2x3) cm 8,400,000.00 8,600,000.00 30,240.00 30,960.00
0.25 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 4,250.00 4,375.00
C PERALATAN
D Jumlah A + B + C 178,140.00 183,960.00
E Overhead & Profit (contoh 10%) 10% 17,814.00 18,396.00
F Harga Satuan Pekerjaan (D+E) 195,954.00 202,356.00

Pemasangan Rangka Atap Genteng Beton, Kayu


17 A.4.6.1.17 1 m2 229,218.00 236,412.00
Klas II
A Tenaga 26,050.00 28,225.00
L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.1 OH Tukang Kayu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 182,330.00 186,695.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 8,400,000.00 8,600,000.00 117,600.00 120,400.00
0.0072 m3 Reng (2x3) cm 8,400,000.00 8,600,000.00 60,480.00 61,920.00
0.25 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 4,250.00 4,375.00
C PERALATAN
D Jumlah A + B + C 208,380.00 214,920.00
E Overhead & Profit (contoh 10%) 10% 20,838.00 21,492.00
F Harga Satuan Pekerjaan (D+E) 229,218.00 236,412.00

18 A.4.6.1.18 1 m2 Pemasangan Rangka Atap Sirap, Kayu Klas II 167,486.00 173,547.00


A Tenaga 31,260.00 33,870.00
L.01 0.12 OH Pekerja 105,000.00 115,000.00 12,600.00 13,800.00
L.02 0.12 OH Tukang Kayu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
B Bahan 121,000.00 123,900.00
0.014 m3 Kayu Klas II (Kamfer), balok 8,400,000.00 8,600,000.00 117,600.00 120,400.00
0.2 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 3,400.00 3,500.00
C PERALATAN
D Jumlah A + B + C 152,260.00 157,770.00
E Overhead & Profit (contoh 10%) 10% 15,226.00 15,777.00
F Harga Satuan Pekerjaan (D+E) 167,486.00 173,547.00

Pemasangan Rangka Langit-langit (50x1,00) m, kayu


19 A.4.6.1.19 1 m2 223,256.00 233,271.50
Klas II atau III
A Tenaga 70,200.00 76,125.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.02 0.30 OH Tukang Kayu 135,000.00 145,000.00 40,500.00 43,500.00
L.03 0.030 OH Kepala Tukang 140,000.00 150,000.00 4,200.00 4,500.00
L.04 0.075 OH Mandor 130,000.00 145,000.00 9,750.00 10,875.00
B Bahan 132,760.00 135,940.00
0.0154 m3 Kayu Klas II (Kamfer), balok 8,400,000.00 8,600,000.00 129,360.00 132,440.00
0.2 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 3,400.00 3,500.00
C PERALATAN
D Jumlah A + B + C 202,960.00 212,065.00
E Overhead & Profit (contoh 10%) 10% 20,296.00 21,206.50
F Harga Satuan Pekerjaan (D+E) 223,256.00 233,271.50

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 1 m2 228,987.00 238,705.50
Klas II atau III
A Tenaga 67,000.00 72,450.00
L.01 0.2 OH Pekerja 105,000.00 115,000.00 21,000.00 23,000.00
L.02 0.3 OH Tukang Kayu 135,000.00 145,000.00 40,500.00 43,500.00
L.03 0.03 OH Kepala Tukang 140,000.00 150,000.00 4,200.00 4,500.00
L.04 0.01 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00

file:///conversion/tmp/scratch/500669137.xls 125/108 11-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 141,170.00 144,555.00
0.0163 m3 Kayu Klas II (Kamfer), balok 8,400,000.00 8,600,000.00 136,920.00 140,180.00
0.25 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 4,250.00 4,375.00
C PERALATAN
D Jumlah A + B + C 208,170.00 217,005.00
E Overhead & Profit (contoh 10%) 10% 20,817.00 21,700.50
F Harga Satuan Pekerjaan (D+E) 228,987.00 238,705.50

Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau


21 A.4.6.1.21 1 m' 379,555.00 395,092.50
II
A Tenaga 40,950.00 44,225.00
L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.2 OH Tukang Kayu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.020 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 304,100.00 314,950.00
0.0108 m3 Kayu klas I (Jati), papan 28,000,000.00 29,000,000.00 302,400.00 313,200.00
0.10 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 1,700.00 1,750.00
C PERALATAN
D Jumlah A + B + C 345,050.00 359,175.00
E Overhead & Profit (contoh 10%) 10% 34,505.00 35,917.50
F Harga Satuan Pekerjaan (D+E) 379,555.00 395,092.50

Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau


22 A.4.6.1.22 1 m' 151,250.00 156,090.00
klas II
A Tenaga 40,950.00 44,225.00
L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.2 OH Tukang Kayu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 96,550.00 97,675.00
0.011 m3 Kayu klas II (Kamfer), papan 8,700,000.00 8,800,000.00 95,700.00 96,800.00
0.05 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 850.00 875.00
C PERALATAN
D Jumlah A + B + C 137,500.00 141,900.00
E Overhead & Profit (contoh 10%) 10% 13,750.00 14,190.00
F Harga Satuan Pekerjaan (D+E) 151,250.00 156,090.00

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 1 m2 353,749.00 367,218.50
Kayu klas II atau III
A Tenaga 83,840.00 90,410.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.02 0.45 OH Tukang Kayu 135,000.00 145,000.00 60,750.00 65,250.00
L.03 0.045 OH Kepala Tukang 140,000.00 150,000.00 6,300.00 6,750.00
L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 237,750.00 243,425.00
0.028 m3 Kayu klas II (Kamfer), balok 8,400,000.00 8,600,000.00 235,200.00 240,800.00
0.15 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 2,550.00 2,625.00
C PERALATAN
D Jumlah A + B + C 321,590.00 333,835.00
E Overhead & Profit (contoh 10%) 10% 32,159.00 33,383.50
F Harga Satuan Pekerjaan (D+E) 353,749.00 367,218.50

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 1 m2 422,939.00 459,948.50
Rangka Kayu Klas II
A Tenaga 83,840.00 90,410.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.02 0.45 OH Tukang Kayu 135,000.00 145,000.00 60,750.00 65,250.00
L.03 0.045 OH Kepala Tukang 140,000.00 150,000.00 6,300.00 6,750.00
L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 300,650.00 327,725.00
0.028 m3 Kayu klas II (Kamfer), balok 8,400,000.00 8,600,000.00 235,200.00 240,800.00
0.15 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 2,550.00 2,625.00
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm 65,000.00 85,000.00 55,900.00 73,100.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 384,490.00 418,135.00
E Overhead & Profit (contoh 10%) 10% 38,449.00 41,813.50
F Harga Satuan Pekerjaan (D+E) 422,939.00 459,948.50

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 1 m2 432,795.00 470,222.50
Rangka Kayu Klas II
A Tenaga 92,800.00 99,750.00
L.01 0.020 OH Pekerja 105,000.00 115,000.00 2,100.00 2,300.00
L.02 0.600 OH Tukang Kayu 135,000.00 145,000.00 81,000.00 87,000.00
L.03 0.060 OH Kepala Tukang 140,000.00 150,000.00 8,400.00 9,000.00
L.04 0.010 OH Mandor 130,000.00 145,000.00 1,300.00 1,450.00

file:///conversion/tmp/scratch/500669137.xls 125/109 11-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 300,650.00 327,725.00
0.028 m3 Kayu klas II (Kamfer), balok 8,400,000.00 8,600,000.00 235,200.00 240,800.00
0.15 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 2,550.00 2,625.00
0.86 Lbr Plywood 120 x 240 cm tebal 4mm 65,000.00 85,000.00 55,900.00 73,100.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 393,450.00 427,475.00
E Overhead & Profit (contoh 10%) 10% 39,345.00 42,747.50
F Harga Satuan Pekerjaan (D+E) 432,795.00 470,222.50

26 A.4.6.1.26 1 m2 Pemasangan Dinding Lambriziring dari Papan Kelas I 587,235.00 624,030.00

A Tenaga 335,100.00 361,350.00


L.01 0.6 OH Pekerja 105,000.00 115,000.00 63,000.00 69,000.00
L.02 1.8 OH Tukang Kayu 135,000.00 145,000.00 243,000.00 261,000.00
L.03 0.18 OH Kepala Tukang 140,000.00 150,000.00 25,200.00 27,000.00
L.04 0.03 OH Mandor 130,000.00 145,000.00 3,900.00 4,350.00
B Bahan 198,750.00 205,950.00
0.007 m3 Kayu klas I (Jati), papan 28,000,000.00 29,000,000.00 196,000.00 203,000.00
0.1 Kg Paku Biasa 2" - 5" 17,000.00 17,500.00 1,700.00 1,750.00
0.15 Kg Paku Sekrup 3,5" 7,000.00 8,000.00 1,050.00 1,200.00
C PERALATAN
D Jumlah A + B + C 533,850.00 567,300.00
E Overhead & Profit (contoh 10%) 10% 53,385.00 56,730.00
F Harga Satuan Pekerjaan (D+E) 587,235.00 624,030.00

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 1 m2 44,935.00 48,367.00
ukuran (120x240) cm
A Tenaga 14,000.00 15,095.00
L.01 0.025 OH Pekerja 105,000.00 115,000.00 2,625.00 2,875.00
L.02 0.075 OH Tukang Kayu 135,000.00 145,000.00 10,125.00 10,875.00
L.03 0.0080 OH Kepala Tukang 140,000.00 150,000.00 1,120.00 1,200.00
L.04 0.0010 OH Mandor 130,000.00 145,000.00 130.00 145.00
B Bahan 26,850.00 28,875.00
0.4 Lbr Plywood (120 X 240) cm x 4mm 65,000.00 70,000.00 26,000.00 28,000.00
0.05 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 850.00 875.00
C PERALATAN
D Jumlah A + B + C 40,850.00 43,970.00
E Overhead & Profit (contoh 10%) 10% 4,085.00 4,397.00
F Harga Satuan Pekerjaan (D+E) 44,935.00 48,367.00

Pemasangan Dinding Bilik, Rangka Kayu Klas III atau


28 A.4.6.1.28 1 m2 140,490.24 159,775.00
IV
A Tenaga 18,600.00 20,225.00
L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.05 OH Tukang Kayu 135,000.00 145,000.00 6,750.00 7,250.00
L.03 0.005 OH Kepala Tukang 140,000.00 150,000.00 700.00 750.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 109,118.40 125,025.00
1.500 m2 Bilik Bambu 25,000.00 30,000.00 37,500.00 45,000.00
0.014 m3 Kayu Klas III (Meranti) 5,100,000.00 5,700,000.00 71,400.00 79,800.00
0.012 Kg Paku Biasa 1/2" - 1" 17,000.00 17,500.00 204.00 210.00
0.003 m' List Kayu 2/4 4,800.00 5,000.00 14.40 15.00
C PERALATAN
D Jumlah A + B + C 127,718.40 145,250.00
E Overhead & Profit (contoh 10%) 10% 12,771.84 14,525.00
F Harga Satuan Pekerjaan (D+E) 140,490.24 159,775.00

file:///conversion/tmp/scratch/500669137.xls 125/110 11-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
1 A.4.6.2.2 1 Buah Pemasangan Kunci Tanam Biasa 220,660.00 270,462.50
A Tenaga 70,600.00 75,875.00
L.01 0.01 OH Pekerja 105,000.00 115,000.00 1,050.00 1,150.00
L.02 0.5 OH Tukang Kayu 135,000.00 145,000.00 67,500.00 72,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 130,000.00 170,000.00
1 Buah Kunci Tanam Biasa 130,000.00 170,000.00 130,000.00 170,000.00
C PERALATAN
D Jumlah A + B + C 200,600.00 245,875.00
E Overhead & Profit (contoh 10%) 10% 20,060.00 24,587.50
F Harga Satuan Pekerjaan (D+E) 220,660.00 270,462.50
Overhead & Profit (contoh 10%)
2 A.4.6.2.3 1 Buah Pemasangan Kunci Kamar Mandi 180,455.00 246,606.25
A Tenaga 69,050.00 74,187.50
L.01 0.005 OH Pekerja 105,000.00 115,000.00 525.00 575.00
L.02 0.5 OH Tukang Kayu 135,000.00 145,000.00 67,500.00 72,500.00
L.03 0.005 OH Kepala Tukang 140,000.00 150,000.00 700.00 750.00
L.04 0.0025 OH Mandor 130,000.00 145,000.00 325.00 362.50
B Bahan 95,000.00 150,000.00
1 Buah Kunci Tanam Kamar Mandi 95,000.00 150,000.00 95,000.00 150,000.00
C PERALATAN
D Jumlah A + B + C 164,050.00 224,187.50
E Overhead & Profit (contoh 10%) 10% 16,405.00 22,418.75
F Harga Satuan Pekerjaan (D+E) 180,455.00 246,606.25

3 A.4.6.2.4 1 Buah Pemasangan Kunci Selinder 218,955.00 268,606.25


A Tenaga 69,050.00 74,187.50
L.01 0.005 OH Pekerja 105,000.00 115,000.00 525.00 575.00
L.02 0.5 OH Tukang Kayu 135,000.00 145,000.00 67,500.00 72,500.00
L.03 0.005 OH Kepala Tukang 140,000.00 150,000.00 700.00 750.00
L.04 0.0025 OH Mandor 130,000.00 145,000.00 325.00 362.50
B Bahan 130,000.00 170,000.00
1 Buah Kunci Selinder 130,000.00 170,000.00 130,000.00 170,000.00
C PERALATAN
D Jumlah A + B + C 199,050.00 244,187.50
E Overhead & Profit (contoh 10%) 10% 19,905.00 24,418.75
F Harga Satuan Pekerjaan (D+E) 218,955.00 268,606.25

4 A.4.6.2.5 1 Buah Pemasangan Engsel Pintu 35,640.00 39,393.75


A Tenaga 24,900.00 26,812.50
L.01 0.015 OH Pekerja 105,000.00 115,000.00 1,575.00 1,725.00
L.02 0.15 OH Tukang Kayu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.0075 OH Mandor 130,000.00 145,000.00 975.00 1,087.50
B Bahan 7,500.00 9,000.00
1 Buah Engsel pintu 7,500.00 9,000.00 7,500.00 9,000.00
C PERALATAN
D Jumlah A + B + C 32,400.00 35,812.50
E Overhead & Profit (contoh 10%) 10% 3,240.00 3,581.25
F Harga Satuan Pekerjaan (D+E) 35,640.00 39,393.75

5 A.4.6.2.6 1 Buah Pemasangan Engsel Jendela Kupu-kupu 23,210.00 26,262.50


A Tenaga 16,600.00 17,875.00
L.01 0.01 OH Pekerja 105,000.00 115,000.00 1,050.00 1,150.00
L.02 0.1 OH Tukang Kayu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 4,500.00 6,000.00
1 Buah Engsel Jendela 4,500.00 6,000.00 4,500.00 6,000.00
C PERALATAN
D Jumlah A + B + C 21,100.00 23,875.00
E Overhead & Profit (contoh 10%) 10% 2,110.00 2,387.50
F Harga Satuan Pekerjaan (D+E) 23,210.00 26,262.50

file:///conversion/tmp/scratch/500669137.xls 125/111 12-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.6.2.7 1 Buah Pemasangan Engsel Angin 62,001.50 80,929.75
A Tenaga 40,365.00 43,572.50
L.01 0.10 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.02 0.20 OH Tukang Kayu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.0005 OH Mandor 130,000.00 145,000.00 65.00 72.50
B Bahan 16,000.00 30,000.00
1 Buah Engsel Angin 16,000.00 30,000.00 16,000.00 30,000.00
C PERALATAN
D Jumlah A + B + C 56,365.00 73,572.50
E Overhead & Profit (contoh 10%) 10% 5,636.50 7,357.25
F Harga Satuan Pekerjaan (D+E) 62,001.50 80,929.75

7 A.4.6.2.9 1 Buah Pemasangan Kait Angin 46,711.50 51,573.50


A Tenaga 24,965.00 26,885.00
L.01 0.015 OH Pekerja 105,000.00 115,000.00 1,575.00 1,725.00
L.02 0.15 OH Tukang Kayu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.008 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 17,500.00 20,000.00
1 Buah Kait Angin 17,500.00 20,000.00 17,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 42,465.00 46,885.00
E Overhead & Profit (contoh 10%) 10% 4,246.50 4,688.50
F Harga Satuan Pekerjaan (D+E) 46,711.50 51,573.50

8 A.4.6.2.10 1 Buah Pasang Door Closer 390,582.50 479,723.75


A Tenaga 80,075.00 86,112.50
L.01 0.05 OH Pekerja 105,000.00 115,000.00 5,250.00 5,750.00
L.02 0.5 OH Tukang Kayu 135,000.00 145,000.00 67,500.00 72,500.00
L.03 0.05 OH Kepala Tukang 140,000.00 150,000.00 7,000.00 7,500.00
L.04 0.0025 OH Mandor 130,000.00 145,000.00 325.00 362.50
B Bahan 275,000.00 350,000.00
1 Buah Door Closer 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 355,075.00 436,112.50
E Overhead & Profit (contoh 10%) 10% 35,507.50 43,611.25
F Harga Satuan Pekerjaan (D+E) 390,582.50 479,723.75

9 A.4.6.2.11 1 Buah Pemasangan Kunci Selot 44,033.00 48,889.50


A Tenaga 32,030.00 34,445.00
L.01 0.02 OH Pekerja 105,000.00 115,000.00 2,100.00 2,300.00
L.02 0.2 OH Tukang Kayu 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.02 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.001 OH Mandor 130,000.00 145,000.00 130.00 145.00
B Bahan 8,000.00 10,000.00
1 Buah Kunci Selot 8,000.00 10,000.00 8,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 40,030.00 44,445.00
E Overhead & Profit (contoh 10%) 10% 4,003.00 4,444.50
F Harga Satuan Pekerjaan (D+E) 44,033.00 48,889.50

10 A.4.6.2.13 1 Buah Pemasangan Door Stop 320,116.50 403,944.75


A Tenaga 16,015.00 17,222.50
L.01 0.01 OH Pekerja 105,000.00 115,000.00 1,050.00 1,150.00
L.02 0.1 OH Tukang Kayu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.0005 OH Mandor 130,000.00 145,000.00 65.00 72.50
B Bahan 275,000.00 350,000.00
1 Buah Door Stop 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 291,015.00 367,222.50
E Overhead & Profit (contoh 10%) 10% 29,101.50 36,722.25
F Harga Satuan Pekerjaan (D+E) 320,116.50 403,944.75

file:///conversion/tmp/scratch/500669137.xls 125/112 12-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.6.2.14 1 Buah Pemasangan Rel Pintu Dorong 325,699.00 372,168.50
A Tenaga 96,090.00 103,335.00
L.01 0.06 OH Pekerja 105,000.00 115,000.00 6,300.00 6,900.00
L.02 0.6 OH Tukang Kayu 135,000.00 145,000.00 81,000.00 87,000.00
L.03 0.06 OH Kepala Tukang 140,000.00 150,000.00 8,400.00 9,000.00
L.04 0.003 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 200,000.00 235,000.00
1 Buah Rel Pintu Dorong 200,000.00 235,000.00 200,000.00 235,000.00
C PERALATAN
D Jumlah A + B + C 296,090.00 338,335.00
E Overhead & Profit (contoh 10%) 10% 29,609.00 33,833.50
F Harga Satuan Pekerjaan (D+E) 325,699.00 372,168.50

12 A.4.6.2.15 1 Buah Pemasangan Kunci Lemari 57,798.40 63,869.85


A Tenaga 40,044.00 43,063.50
L.01 0.025 OH Pekerja 105,000.00 115,000.00 2,625.00 2,875.00
L.02 0.25 OH Tukang Kayu 135,000.00 145,000.00 33,750.00 36,250.00
L.03 0.025 OH Kepala Tukang 140,000.00 150,000.00 3,500.00 3,750.00
L.04 0.00130 OH Mandor 130,000.00 145,000.00 169.00 188.50
B Bahan 12,500.00 15,000.00
1 Buah Kunci Lemari 12,500.00 15,000.00 12,500.00 15,000.00
C PERALATAN
D Jumlah A + B + C 52,544.00 58,063.50
E Overhead & Profit (contoh 10%) 10% 5,254.40 5,806.35
F Harga Satuan Pekerjaan (D+E) 57,798.40 63,869.85

13 A.4.6.2.16 1 m2 Pemasangan Kaca tebal 3 mm 132,904.75 143,367.13


A Tenaga 24,022.50 25,833.75
L.01 0.015 OH Pekerja 105,000.00 115,000.00 1,575.00 1,725.00
L.02 0.15 OH Tukang Kayu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.00075 OH Mandor 130,000.00 145,000.00 97.50 108.75
B Bahan 96,800.00 104,500.00
1.1 m2 Kaca tebal 3mm 88,000.00 95,000.00 96,800.00 104,500.00
C PERALATAN
D Jumlah A + B + C 120,822.50 130,333.75
E Overhead & Profit (contoh 10%) 10% 12,082.25 13,033.38
F Harga Satuan Pekerjaan (D+E) 132,904.75 143,367.13

14 A.4.6.2.17 1 m2 Pemasangan Kaca tebal 5 mm 147,424.75 155,467.13


A Tenaga 24,022.50 25,833.75
L.01 0.015 OH Pekerja 105,000.00 115,000.00 1,575.00 1,725.00
L.02 0.15 OH Tukang Kayu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.00075 OH Mandor 130,000.00 145,000.00 97.50 108.75
B Bahan 110,000.00 115,500.00
1.1 m2 Kaca tebal 5mm 100,000.00 105,000.00 110,000.00 115,500.00
C PERALATAN
D Jumlah A + B + C 134,022.50 141,333.75
E Overhead & Profit (contoh 10%) 10% 13,402.25 14,133.38
F Harga Satuan Pekerjaan (D+E) 147,424.75 155,467.13

15 A.4.6.2.18 1 m2 Pemasangan Kaca Cermin tebal 5 mm 359,174.75 421,667.13


A Tenaga 24,022.50 25,833.75
L.01 0.015 OH Pekerja 105,000.00 115,000.00 1,575.00 1,725.00
L.02 0.15 OH Tukang Kayu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.00075 OH Mandor 130,000.00 145,000.00 97.50 108.75
B Bahan 302,500.00 357,500.00
1.1 m2 Kaca Cermin 275,000.00 325,000.00 302,500.00 357,500.00
C PERALATAN
D Jumlah A + B + C 326,522.50 383,333.75
E Overhead & Profit (contoh 10%) 10% 32,652.25 38,333.38
F Harga Satuan Pekerjaan (D+E) 359,174.75 421,667.13

file:///conversion/tmp/scratch/500669137.xls 125/113 12-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 1 m2 18,469.00 20,278.50
Lama
A Tenaga 16,140.00 17,685.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.04 0.0030 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 650.00 750.00
0.05 Kg Soda Api 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 16,790.00 18,435.00
E Overhead & Profit (contoh 10%) 10% 1,679.00 1,843.50
F Harga Satuan Pekerjaan (D+E) 18,469.00 20,278.50

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 1 m2 18,441.50 20,278.50
dicat
A Tenaga 16,140.00 17,685.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.04 0.0030 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 625.00 750.00
0.05 Kg Sabun 12,500.00 15,000.00 625.00 750.00
C PERALATAN
D Jumlah A + B + C 16,765.00 18,435.00
E Overhead & Profit (contoh 10%) 10% 1,676.50 1,843.50
F Harga Satuan Pekerjaan (D+E) 18,441.50 20,278.50

Pengerokan Karat Cat Lama permukaan Baja dg cara


3 A.4.7.1.3 1 m2 19,156.50 21,076.00
manual
A Tenaga 16,790.00 18,410.00
L.01 0.15 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.04 0.0080 OH Mandor 130,000.00 145,000.00 1,040.00 1,160.00
B Bahan 625.00 750.00
0.05 Kg Sabun 12,500.00 15,000.00 625.00 750.00
C PERALATAN
D Jumlah A + B + C 17,415.00 19,160.00
E Overhead & Profit (contoh 10%) 10% 1,741.50 1,916.00
F Harga Satuan Pekerjaan (D+E) 19,156.50 21,076.00

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


4 A.4.7.1.4 1 m2 50,182.00 54,048.50
dasar, 2 Lp Cat Penutup)
A Tenaga 9,795.00 10,690.00
L.01 0.070 OH Pekerja 105,000.00 115,000.00 7,350.00 8,050.00
L.02 0.009 OH Tukang Cat 135,000.00 145,000.00 1,215.00 1,305.00
L.03 0.006 OH Kepala Tukang 140,000.00 150,000.00 840.00 900.00
L.04 0.003 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 35,825.00 38,445.00
0.2000 kg Cat Menie 30,000.00 32,000.00 6,000.00 6,400.00
0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00
0.1700 kg Cat Dasar 40,000.00 42,500.00 6,800.00 7,225.00
0.2600 kg Cat Penutup 68,000.00 71,000.00 17,680.00 18,460.00
0.0100 bh Kuas 17,500.00 20,000.00 175.00 200.00
0.0300 kg Pengencer 20,000.00 22,000.00 600.00 660.00
0.2000 lbr Amplas 4,100.00 5,000.00 820.00 1,000.00
C PERALATAN
D Jumlah A + B + C 45,620.00 49,135.00
E Overhead & Profit (contoh 10%) 10% 4,562.00 4,913.50
F Harga Satuan Pekerjaan (D+E) 50,182.00 54,048.50

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


5 A.4.7.1.5 1 m2 70,862.00 76,059.50
dasar, 3 Lp Cat Penutup)
A Tenaga 22,475.00 24,310.00
L.01 0.070 OH Pekerja 105,000.00 115,000.00 7,350.00 8,050.00
L.02 0.105 OH Tukang Cat 135,000.00 145,000.00 14,175.00 15,225.00
L.03 0.004 OH Kepala Tukang 140,000.00 150,000.00 560.00 600.00
L.04 0.003 OH Mandor 130,000.00 145,000.00 390.00 435.00

file:///conversion/tmp/scratch/500669137.xls 125/114 13-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 41,945.00 44,835.00
0.2000 kg Cat Menie 30,000.00 32,000.00 6,000.00 6,400.00
0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00
0.1700 kg Cat Dasar 40,000.00 42,500.00 6,800.00 7,225.00
0.3500 kg Cat Penutup 68,000.00 71,000.00 23,800.00 24,850.00
0.0100 bh Kuas 17,500.00 20,000.00 175.00 200.00
0.0300 kg Pengencer 20,000.00 22,000.00 600.00 660.00
0.2000 lbr Amplas 4,100.00 5,000.00 820.00 1,000.00
C PERALATAN
D Jumlah A + B + C 64,420.00 69,145.00
E Overhead & Profit (contoh 10%) 10% 6,442.00 6,914.50
F Harga Satuan Pekerjaan (D+E) 70,862.00 76,059.50

6 A.4.7.1.6 1 m2 Pelaburan Bidang Kayu dg Teak Oil 40,342.50 42,614.00


A Tenaga 21,915.00 23,620.00
L.01 0.04 OH Pekerja 105,000.00 115,000.00 4,200.00 4,600.00
L.02 0.063 OH Tukang Cat 135,000.00 145,000.00 8,505.00 9,135.00
L.03 0.063 OH Kepala Tukang 140,000.00 150,000.00 8,820.00 9,450.00
L.04 0.0030 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 14,760.00 15,120.00
0.36 Ltr Teak Oil 41,000.00 42,000.00 14,760.00 15,120.00
C PERALATAN
D Jumlah A + B + C 36,675.00 38,740.00
E Overhead & Profit (contoh 10%) 10% 3,667.50 3,874.00
F Harga Satuan Pekerjaan (D+E) 40,342.50 42,614.00

7 A.4.7.1.7 1 m2 Pelaburan Bidang Kayu dg Politur 62,766.00 69,516.70


A Tenaga 14,930.00 16,135.00
L.01 0.04 OH Pekerja 105,000.00 115,000.00 4,200.00 4,600.00
L.02 0.06 OH Tukang Cat 135,000.00 145,000.00 8,100.00 8,700.00
L.03 0.016 OH Kepala Tukang 140,000.00 150,000.00 2,240.00 2,400.00
L.04 0.0030 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 42,130.00 47,062.00
0.15 Ltr Politur 65,000.00 71,000.00 9,750.00 10,650.00
0.372 Ltr Politur Jadi 65,000.00 71,000.00 24,180.00 26,412.00
2 Lbr Ampelas 4,100.00 5,000.00 8,200.00 10,000.00
C PERALATAN
D Jumlah A + B + C 57,060.00 63,197.00
E Overhead & Profit (contoh 10%) 10% 5,706.00 6,319.70
F Harga Satuan Pekerjaan (D+E) 62,766.00 69,516.70

8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 13,563.00 14,906.38
A Tenaga 11,280.00 12,370.00
L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
B Bahan 1,050.00 1,181.25
0.35 Ltr Residu atau Ter 3,000.00 3,375.00 1,050.00 1,181.25
C PERALATAN
D Jumlah A + B + C 12,330.00 13,551.25
E Overhead & Profit (contoh 10%) 10% 1,233.00 1,355.13
F Harga Satuan Pekerjaan (D+E) 13,563.00 14,906.38

9 A.4.7.1.9 1 m2 Pelaburan Bidang Kayu dg Vernis 51,084.00 56,853.50


A Tenaga 41,030.00 44,435.00
L.01 0.16 OH Pekerja 105,000.00 115,000.00 16,800.00 18,400.00
L.02 0.16 OH Tukang Cat 135,000.00 145,000.00 21,600.00 23,200.00
L.03 0.016 OH Kepala Tukang 140,000.00 150,000.00 2,240.00 2,400.00
L.04 0.0030 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 5,410.00 7,250.00
0.15 Ltr Vernis 25,000.00 35,000.00 3,750.00 5,250.00
0.05 Ltr Dempul 25,000.00 30,000.00 1,250.00 1,500.00
0.1 Lbr Ampelas 4,100.00 5,000.00 410.00 500.00
C PERALATAN
D Jumlah A + B + C 46,440.00 51,685.00
E Overhead & Profit (contoh 10%) 10% 4,644.00 5,168.50
F Harga Satuan Pekerjaan (D+E) 51,084.00 56,853.50

file:///conversion/tmp/scratch/500669137.xls 125/115 13-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2
10 A.4.7.1.10 1 m2 23,712.70 27,388.90
Lap.Cat Penutup)
A Tenaga 11,877.00 12,815.00
L.01 0.02 OH Pekerja 105,000.00 115,000.00 2,100.00 2,300.00
L.02 0.063 OH Tukang Cat 135,000.00 145,000.00 8,505.00 9,135.00
L.03 0.0063 OH Kepala Tukang 140,000.00 150,000.00 882.00 945.00
L.04 0.0030 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 9,680.00 12,084.00
0.1 Kg Plamir 25,000.00 32,000.00 2,500.00 3,200.00
0.1 Kg Cat Dasar 12,000.00 15,000.00 1,200.00 1,500.00
0.26 Kg Cat Penutup 2 kali 23,000.00 28,400.00 5,980.00 7,384.00
C PERALATAN
D Jumlah A + B + C 21,557.00 24,899.00
E Overhead & Profit (contoh 10%) 10% 2,155.70 2,489.90
F Harga Satuan Pekerjaan (D+E) 23,712.70 27,388.90

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 1 m2 16,684.80 19,015.70
Penutup)
A Tenaga 9,588.00 10,375.00
L.01 0.028 OH Pekerja 105,000.00 115,000.00 2,940.00 3,220.00
L.02 0.042 OH Tukang Cat 135,000.00 145,000.00 5,670.00 6,090.00
L.03 0.0042 OH Kepala Tukang 140,000.00 150,000.00 588.00 630.00
L.04 0.0030 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 5,580.00 6,912.00
0.12 Kg Cat Dasar 12,000.00 15,000.00 1,440.00 1,800.00
0.18 Kg Cat Penutup 2 kali 23,000.00 28,400.00 4,140.00 5,112.00
C PERALATAN
D Jumlah A + B + C 15,168.00 17,287.00
E Overhead & Profit (contoh 10%) 10% 1,516.80 1,728.70
F Harga Satuan Pekerjaan (D+E) 16,684.80 19,015.70

12 A.4.7.1.12 1 m2 Pengecatan Tembok dengan Kalkarium 11,041.80 11,962.50


A Tenaga 9,588.00 10,375.00
L.01 0.028 OH Pekerja 105,000.00 115,000.00 2,940.00 3,220.00
L.02 0.042 OH Tukang Cat 135,000.00 145,000.00 5,670.00 6,090.00
L.03 0.0042 OH Kepala Tukang 140,000.00 150,000.00 588.00 630.00
L.04 0.0030 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 450.00 500.00
0.1 Kg Kalkarium 4,500.00 5,000.00 450.00 500.00
- -
C PERALATAN
D Jumlah A + B + C 10,038.00 10,875.00
E Overhead & Profit (contoh 10%) 10% 1,003.80 1,087.50
F Harga Satuan Pekerjaan (D+E) 11,041.80 11,962.50

13 A.4.7.1.13 1 m2 Pelaburan Tembok dengan Kapur Sirih 20,222.40 22,244.75


A Tenaga 16,224.00 17,772.50
L.01 0.150 OH Pekerja 105,000.00 115,000.00 15,750.00 17,250.00
L.02 0.001 OH Tukang Cat 135,000.00 145,000.00 135.00 145.00
L.03 0.0001 OH Kepala Tukang 140,000.00 150,000.00 14.00 15.00
L.04 0.0025 OH Mandor 130,000.00 145,000.00 325.00 362.50
B Bahan 2,160.00 2,450.00
0.15 Kg Kapur Sirih 7,500.00 8,000.00 1,125.00 1,200.00
0.1 lbr Amplas 4,100.00 5,000.00 410.00 500.00
0.25 ikat Alang-alang 2,500.00 3,000.00 625.00 750.00
C PERALATAN
D Jumlah A + B + C 18,384.00 20,222.50
E Overhead & Profit (contoh 10%) 10% 1,838.40 2,022.25
F Harga Satuan Pekerjaan (D+E) 20,222.40 22,244.75

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 1 m2 8,789.00 9,831.25
(pemeliharaan)
A Tenaga 5,270.00 5,762.50
L.01 0.040 OH Pekerja 105,000.00 115,000.00 4,200.00 4,600.00
L.02 0.005 OH Tukang Cat 135,000.00 145,000.00 675.00 725.00
L.03 0.0005 OH Kepala Tukang 140,000.00 150,000.00 70.00 75.00
L.04 0.0025 OH Mandor 130,000.00 145,000.00 325.00 362.50

file:///conversion/tmp/scratch/500669137.xls 125/116 13-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 2,720.00 3,175.00
0.30 Kg Kapur Sirih 4,250.00 4,750.00 1,275.00 1,425.00
0.2 lbr Amplas 4,100.00 5,000.00 820.00 1,000.00
0.25 ikat Alang-alang 2,500.00 3,000.00 625.00 750.00
C PERALATAN
D Jumlah A + B + C 7,990.00 8,937.50
E Overhead & Profit (contoh 10%) 10% 799.00 893.75
F Harga Satuan Pekerjaan (D+E) 8,789.00 9,831.25

15 A.4.7.1.15 1 m2 Pemasangan Wallpaper 93,747.50 105,228.75


A Tenaga 32,225.00 34,662.50
L.01 0.020 OH Pekerja 105,000.00 115,000.00 2,100.00 2,300.00
L.02 0.200 OH Tukang Cat 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.0200 OH Kepala Tukang 140,000.00 150,000.00 2,800.00 3,000.00
L.04 0.0025 OH Mandor 130,000.00 145,000.00 325.00 362.50
B Bahan 53,000.00 61,000.00
1.20 lbr Wall Paper 35,000.00 40,000.00 42,000.00 48,000.00
0.2 kg Lem 55,000.00 65,000.00 11,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 85,225.00 95,662.50
E Overhead & Profit (contoh 10%) 10% 8,522.50 9,566.25
F Harga Satuan Pekerjaan (D+E) 93,747.50 105,228.75

16 A.4.7.1.16 1 m2 Pengecatan Permukaan Baja dg Meni Besi 36,030.50 39,833.75


A Tenaga 29,705.00 31,962.50
L.01 0.02 OH Pekerja 105,000.00 115,000.00 2,100.00 2,300.00
L.02 0.2 OH Tukang Cat 135,000.00 145,000.00 27,000.00 29,000.00
L.03 0.002 OH Kepala Tukang 140,000.00 150,000.00 280.00 300.00
L.04 0.0025 OH Mandor 130,000.00 145,000.00 325.00 362.50
B Bahan 3,050.00 4,250.00
0.1 Kg Meni Besi 25,000.00 36,000.00 2,500.00 3,600.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 32,755.00 36,212.50
E Overhead & Profit (contoh 10%) 10% 3,275.50 3,621.25
F Harga Satuan Pekerjaan (D+E) 36,030.50 39,833.75

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 1 m2 71,115.00 78,223.75
Perancah
A Tenaga 57,600.00 62,462.50
L.01 0.25 OH Pekerja 105,000.00 115,000.00 26,250.00 28,750.00
L.02 0.225 OH Tukang Cat 135,000.00 145,000.00 30,375.00 32,625.00
L.04 0.0075 OH Mandor 130,000.00 145,000.00 975.00 1,087.50
B Bahan 7,050.00 8,650.00
0.1 Kg Meni Besi 25,000.00 36,000.00 2,500.00 3,600.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
0.002 m3 Perancah Kayu 2,000,000.00 2,200,000.00 4,000.00 4,400.00
C PERALATAN
D Jumlah A + B + C 64,650.00 71,112.50
E Overhead & Profit (contoh 10%) 10% 6,465.00 7,111.25
F Harga Satuan Pekerjaan (D+E) 71,115.00 78,223.75

file:///conversion/tmp/scratch/500669137.xls 125/117 13-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
HARGA SATUAN PEKERJAAN SANITASI DALAM
XIV A.5.1.1
GEDUNG
1 A.5.1.1.1 1 Unit Pemasangan Closet Duduk / Mono Blok 2,433,134.00 2,775,685.00
A Tenaga 515,940.00 562,350.00
L.01 3.3 OH Pekerja 105,000.00 115,000.00 346,500.00 379,500.00
L.02 1.1 OH Tukang Batu 135,000.00 145,000.00 148,500.00 159,500.00
L.03 0.001 OH Kepala Tukang 140,000.00 150,000.00 140.00 150.00
L.04 0.16 OH Mandor 130,000.00 145,000.00 20,800.00 23,200.00
Buah Bahan 1,696,000.00 1,961,000.00
1 Buah Kloset Duduk / Monoblok 1,600,000.00 1,850,000.00 1,600,000.00 1,850,000.00
0.06 Kelengkapan 6% dari harga Kloset 1,600,000.00 1,850,000.00 96,000.00 111,000.00
C PERALATAN
D Jumlah A + B + C 2,211,940.00 2,523,350.00
E Overhead & Profit (contoh 10%) 10% 221,194.00 252,335.00
F Harga Satuan Pekerjaan (D+E) 2,433,134.00 2,775,685.00
Overhead & Profit (contoh 10%)
2 A.5.1.1.2 1 Unit Pemasangan Closet Jongkok Porselen 762,630.00 826,760.00
A Tenaga 538,300.00 580,700.00
L.01 1 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00
L.02 1.5 OH Tukang Batu 135,000.00 145,000.00 202,500.00 217,500.00
L.03 1.5 OH Kepala Tukang 140,000.00 150,000.00 210,000.00 225,000.00
L.04 0.16 OH Mandor 130,000.00 145,000.00 20,800.00 23,200.00
B Bahan 155,000.00 170,900.00
1 Buah Kloset Jongkok 145,000.00 160,000.00 145,000.00 160,000.00
6 Kg Portland Semen 1,150.00 1,200.00 6,900.00 7,200.00
0.01 m3 Pasir Pasang 310,000.00 370,000.00 3,100.00 3,700.00
C PERALATAN
D Jumlah A + B + C 693,300.00 751,600.00
E Overhead & Profit (contoh 10%) 10% 69,330.00 75,160.00
F Harga Satuan Pekerjaan (D+E) 762,630.00 826,760.00

3 A.5.1.1.4 1 Unit Pemasangan Urinoir 805,200.00 866,690.00


A Tenaga 267,000.00 289,500.00
L.01 1 OH Pekerja 105,000.00 115,000.00 105,000.00 115,000.00
L.02 1 OH Tukang Batu 135,000.00 145,000.00 135,000.00 145,000.00
L.03 0.1 OH Kepala Tukang 140,000.00 150,000.00 14,000.00 15,000.00
L.04 0.1 OH Mandor 130,000.00 145,000.00 13,000.00 14,500.00
B Bahan 465,000.00 498,400.00
1 Buah Urinoir 350,000.00 375,000.00 350,000.00 375,000.00
0.3 - Perlengkapan 30% Harga Urinoir 350,000.00 375,000.00 105,000.00 112,500.00
6 Kg Portland Semen 1,150.00 1,200.00 6,900.00 7,200.00
0.01 m3 Pasir Pasang 310,000.00 370,000.00 3,100.00 3,700.00
C PERALATAN
D Jumlah A + B + C 732,000.00 787,900.00
E Overhead & Profit (contoh 10%) 10% 73,200.00 78,790.00
F Harga Satuan Pekerjaan (D+E) 805,200.00 866,690.00

4 A.5.1.1.5 1 Unit Pemasangan Wastafel 637,532.50 692,367.50


A Tenaga 179,575.00 196,025.00
L.01 1.2 OH Pekerja 105,000.00 115,000.00 126,000.00 138,000.00
L.02 0.145 OH Tukang Batu 135,000.00 145,000.00 19,575.00 21,025.00
L.03 0.15 OH Kepala Tukang 140,000.00 150,000.00 21,000.00 22,500.00
L.04 0.1 OH Mandor 130,000.00 145,000.00 13,000.00 14,500.00
B Bahan 400,000.00 433,400.00
1 Buah Wastafel 300,000.00 325,000.00 300,000.00 325,000.00
0.3 - Perlengkapan 30% Harga Wastafel 300,000.00 325,000.00 90,000.00 97,500.00
6 Kg Portland Semen 1,150.00 1,200.00 6,900.00 7,200.00
0.01 m3 Pasir Pasang 310,000.00 370,000.00 3,100.00 3,700.00
C PERALATAN
D Jumlah A + B + C 579,575.00 629,425.00
E Overhead & Profit (contoh 10%) 10% 57,957.50 62,942.50
F Harga Satuan Pekerjaan (D+E) 637,532.50 692,367.50

5 A.5.1.1.6 1 Unit Pemasangan Bathcuip porselen 1,122,016.50 1,197,966.00


A Tenaga 120,015.00 129,060.00
L.01 0.075 OH Pekerja 105,000.00 115,000.00 7,875.00 8,625.00
L.02 0.75 OH Tukang Batu 135,000.00 145,000.00 101,250.00 108,750.00
L.03 0.075 OH Kepala Tukang 140,000.00 150,000.00 10,500.00 11,250.00
L.04 0.003 OH Mandor 130,000.00 145,000.00 390.00 435.00

file:///conversion/tmp/scratch/500669137.xls 125/118 14-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 900,000.00 960,000.00
1 Buah Batchuip 750,000.00 800,000.00 750,000.00 800,000.00
0.2 - Perlengkapan 20% Harga Bathcuip 750,000.00 800,000.00 150,000.00 160,000.00
C PERALATAN
D Jumlah A + B + C 1,020,015.00 1,089,060.00
E Overhead & Profit (contoh 10%) 10% 102,001.50 108,906.00
F Harga Satuan Pekerjaan (D+E) 1,122,016.50 1,197,966.00

6 A.5.1.1.7 1 Unit Pemasangan Bak Fibreglass vol.1 m3 1,489,950.00 1,618,650.00


A Tenaga 1,046,500.00 1,135,500.00

L.01 3 OH Pekerja 105,000.00 115,000.00 315,000.00 345,000.00


L.02 4.5 OH Tukang Batu 135,000.00 145,000.00 607,500.00 652,500.00
L.03 0.05 OH Kepala Tukang 140,000.00 150,000.00 7,000.00 7,500.00
L.04 0.9 OH Mandor 130,000.00 145,000.00 117,000.00 130,500.00
B Tukang Batu 308,000.00 336,000.00
1 Buah Bak Fibreglass 275,000.00 300,000.00 275,000.00 300,000.00
0.12 - Perlengkapan 12% Bak Fibreglass 275,000.00 300,000.00 33,000.00 36,000.00
C PERALATAN
D Jumlah A + B + C 1,354,500.00 1,471,500.00
E Overhead & Profit (contoh 10%) 10% 135,450.00 147,150.00
F Harga Satuan Pekerjaan (D+E) 1,489,950.00 1,618,650.00

7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,810,919.27 1,974,643.54
A Tenaga 1,080,900.00 1,174,350.00
L.01 6.00 OH Pekerja 105,000.00 115,000.00 630,000.00 690,000.00
L.02 3.00 OH Tukang Batu 135,000.00 145,000.00 405,000.00 435,000.00
L.03 0.30 OH Kepala Tukang 140,000.00 150,000.00 42,000.00 45,000.00
L.04 0.03 OH Mandor 130,000.00 145,000.00 3,900.00 4,350.00
B Bahan 565,390.24 620,780.49
150.0 bh Batu Bata 520.00 580.00 78,000.00 87,000.00
120 Kg Portland Semen 0.11 1,150.00 1,200.00 138,000.00 144,000.00
0.3 m3 Pasir Pasang 0.0121 310,000.00 370,000.00 93,000.00 111,000.00
360 buah Porselen 11 x 11 cm 82.6446 512.20 524.39 184,390.24 188,780.49
6 Kg Semen Nat 12,000.00 15,000.00 72,000.00 90,000.00
C PERALATAN
D Jumlah A + B + C 1,646,290.24 1,795,130.49
E Overhead & Profit (contoh 10%) 10% 164,629.02 179,513.05
F Harga Satuan Pekerjaan (D+E) 1,810,919.27 1,974,643.54

8 A.5.1.1.11 1 Unit Pemasangan Bak Beton Bertulang Vol. 1 m3 6,916,390.02 7,900,488.06


A Tenaga 984,340.00 1,065,110.00
L.01 3.50 OH Pekerja 105,000.00 115,000.00 367,500.00 402,500.00
L.02 4.50 OH Tukang Batu 135,000.00 145,000.00 607,500.00 652,500.00
L.03 0.05 OH Kepala Tukang 140,000.00 150,000.00 7,000.00 7,500.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00
B Bahan 1,234,810.87 1,374,430.09 5,303,287.29 6,117,151.87
0.9 m3 Beton K.150 1,109,178.98 1,221,351.48 998,261.08 1,099,216.33
180 Kg Baja Tulangan 0.11 14,107.50 16,371.30 2,539,350.00 2,946,834.00
8.0 m2 Kayu Bekisting 0.05 0.0121 110,000.00 135,000.00 880,000.00 1,080,000.00
500 buah Porselen 11 x 11 cm 20 82.6446 1,524.39 1,707.32 762,195.12 853,658.54
10 % Perlengkapan 1,234,810.87 1,374,430.09 123,481.09 137,443.01
C PERALATAN
D Jumlah A + B + C 6,287,627.29 7,182,261.87
E Overhead & Profit (contoh 10%) 10% 628,762.73 718,226.19
F Harga Satuan Pekerjaan (D+E) 6,916,390.02 7,900,488.06

9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 357,280.00 399,987.50
A Tenaga 49,800.00 53,625.00
L.01 0.030 OH Pekerja 105,000.00 115,000.00 3,150.00 3,450.00
L.02 0.300 OH Tukang Batu 135,000.00 145,000.00 40,500.00 43,500.00
L.03 0.030 OH Kepala Tukang 140,000.00 150,000.00 4,200.00 4,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 324,800.00 363,625.00
E Overhead & Profit (contoh 10%) 10% 32,480.00 36,362.50
F Harga Satuan Pekerjaan (D+E) 357,280.00 399,987.50

file:///conversion/tmp/scratch/500669137.xls 125/119 14-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
10 A.5.1.1.14 1 buah Pemasangan Floor Drain 56,760.00 66,412.50
A Tenaga 16,600.00 17,875.00
L.01 0.010 OH Pekerja 105,000.00 115,000.00 1,050.00 1,150.00
L.02 0.100 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.010 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 35,000.00 42,500.00
1 bh Floor Drain 35,000.00 42,500.00 35,000.00 42,500.00

C PERALATAN
D Jumlah A + B + C 51,600.00 60,375.00
E Overhead & Profit (contoh 10%) 10% 5,160.00 6,037.50
F Harga Satuan Pekerjaan (D+E) 56,760.00 66,412.50

Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi


11 A.5.1.1.15 1 bh 528,033.00 579,694.50
35 cm
A Tenaga 335,510.00 365,195.00
L.01 2.160 OH Pekerja 105,000.00 115,000.00 226,800.00 248,400.00
L.02 0.720 OH Tukang Batu 135,000.00 145,000.00 97,200.00 104,400.00
L.03 0.072 OH Kepala Tukang 140,000.00 150,000.00 10,080.00 10,800.00
L.04 0.011 OH Mandor 130,000.00 145,000.00 1,430.00 1,595.00
B Bahan 144,520.00 161,800.00
40.00 bh Batu Bata 520.00 580.00 20,800.00 23,200.00
44.00 kg Semen Portland 1,150.00 1,200.00 50,600.00 52,800.00
0.07 m3 Pasir Pasang 310,000.00 370,000.00 21,700.00 25,900.00
0.06 m3 Pasir Beton 340,000.00 375,000.00 20,400.00 22,500.00
0.07 m3 Kerikil 210,000.00 260,000.00 14,700.00 18,200.00
1.60 kg Baja Tulangan 10,200.00 12,000.00 16,320.00 19,200.00
C PERALATAN
D Jumlah A + B + C 480,030.00 526,995.00
E Overhead & Profit (contoh 10%) 10% 48,003.00 52,699.50
F Harga Satuan Pekerjaan (D+E) 528,033.00 579,694.50

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 1 bh 782,364.00 855,767.00
tinggi 50 cm
A Tenaga 494,870.00 538,720.00
L.01 3.200 OH Pekerja 105,000.00 115,000.00 336,000.00 368,000.00
L.02 1.150 OH Tukang Batu 135,000.00 145,000.00 155,250.00 166,750.00
L.03 0.011 OH Kepala Tukang 140,000.00 150,000.00 1,540.00 1,650.00
L.04 0.016 OH Mandor 130,000.00 145,000.00 2,080.00 2,320.00
B Bahan 216,370.00 239,250.00
70.00 bh Batu Bata 520.00 580.00 36,400.00 40,600.00
77.00 kg Semen Portland 1,150.00 1,200.00 88,550.00 92,400.00
0.13 m3 Pasir Pasang 310,000.00 370,000.00 40,300.00 48,100.00
0.09 m3 Pasir Beton 340,000.00 375,000.00 30,600.00 33,750.00
0.02 m3 Kerikil 210,000.00 260,000.00 4,200.00 5,200.00
1.60 kg Baja Tulangan 10,200.00 12,000.00 16,320.00 19,200.00
C PERALATAN
D Jumlah A + B + C 711,240.00 777,970.00
E Overhead & Profit (contoh 10%) 10% 71,124.00 77,797.00
F Harga Satuan Pekerjaan (D+E) 782,364.00 855,767.00

Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi


13 A.5.1.1.17 1 bh 903,804.00 994,774.00
60 cm
A Tenaga 494,870.00 538,720.00
L.01 3.200 OH Pekerja 105,000.00 115,000.00 336,000.00 368,000.00
L.02 1.150 OH Tukang Batu 135,000.00 145,000.00 155,250.00 166,750.00
L.03 0.011 OH Kepala Tukang 140,000.00 150,000.00 1,540.00 1,650.00
L.04 0.016 OH Mandor 130,000.00 145,000.00 2,080.00 2,320.00
B Bahan 326,770.00 365,620.00
123.00 bh Batu Bata 520.00 580.00 63,960.00 71,340.00
114.00 kg Semen Portland 1,150.00 1,200.00 131,100.00 136,800.00
0.18 m3 Pasir Pasang 310,000.00 370,000.00 57,040.00 68,080.00
0.12 m3 Pasir Beton 210,000.00 260,000.00 25,200.00 31,200.00
4.85 kg Baja Tulangan 10,200.00 12,000.00 49,470.00 58,200.00
C PERALATAN
D Jumlah A + B + C 821,640.00 904,340.00
E Overhead & Profit (contoh 10%) 10% 82,164.00 90,434.00
F Harga Satuan Pekerjaan (D+E) 903,804.00 994,774.00

file:///conversion/tmp/scratch/500669137.xls 125/120 14-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
14 A.5.1.1.18 1 m' Pemasangan Pipa Galvanis Ø ½" 68,894.83 72,444.17
A Tenaga 22,590.00 24,525.00
L.01 0.054 OH Pekerja 105,000.00 115,000.00 5,670.00 6,210.00
L.02 0.090 OH Tukang Batu 135,000.00 145,000.00 12,150.00 13,050.00
L.03 0.009 OH Kepala Tukang 140,000.00 150,000.00 1,260.00 1,350.00
L.04 0.027 OH Mandor 130,000.00 145,000.00 3,510.00 3,915.00
B Bahan 40,041.67 41,333.33
1.20 m' Pipa Galvanis Ø ½" 25,833.33 26,666.67 31,000.00 32,000.00
0.35 Ls Perlengkapan 35% x pipa 25,833.33 26,666.67 9,041.67 9,333.33
C PERALATAN
D Jumlah A + B + C 62,631.67 65,858.33
E Overhead & Profit (contoh 10%) 10% 6,263.17 6,585.83
F Harga Satuan Pekerjaan (D+E) 68,894.83 72,444.17

15 A.5.1.1.19 1 bh Pemasangan Kran Ø ½" atau Ø ¾" 97,691.00 121,974.88


A Tenaga 61,300.00 65,875.00
L.01 0.010 OH Pekerja 105,000.00 115,000.00 1,050.00 1,150.00
L.02 0.400 OH Tukang Batu 135,000.00 145,000.00 54,000.00 58,000.00
L.03 0.040 OH Kepala Tukang 140,000.00 150,000.00 5,600.00 6,000.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 27,510.00 45,011.25
1.00 bh Kran Air 27,500.00 45,000.00 27,500.00 45,000.00
0.0025 bh Sealtape 4,000.00 4,500.00 10.00 11.25
C PERALATAN
D Jumlah A + B + C 88,810.00 110,886.25
E Overhead & Profit (contoh 10%) 10% 8,881.00 11,088.63
F Harga Satuan Pekerjaan (D+E) 97,691.00 121,974.88

16 A.5.1.1.20 1 m' Pemasangan Pipa Galvanis Ø ¾" 80,261.50 83,810.83


A Tenaga 22,590.00 24,525.00
L.01 0.054 OH Pekerja 105,000.00 115,000.00 5,670.00 6,210.00
L.02 0.090 OH Tukang Batu 135,000.00 145,000.00 12,150.00 13,050.00
L.03 0.009 OH Kepala Tukang 140,000.00 150,000.00 1,260.00 1,350.00
L.04 0.027 OH Mandor 130,000.00 145,000.00 3,510.00 3,915.00
B Bahan 50,375.00 51,666.67
1.20 m' Pipa Galvanis Ø ¾" 32,500.00 33,333.33 39,000.00 40,000.00
0.35 Ls Perlengkapan 35% x pipa 32,500.00 33,333.33 11,375.00 11,666.67
C PERALATAN
D Jumlah A + B + C 72,965.00 76,191.67
E Overhead & Profit (contoh 10%) 10% 7,296.50 7,619.17
F Harga Satuan Pekerjaan (D+E) 80,261.50 83,810.83

17 A.5.1.1.21 1 m' Pemasangan Pipa Galvanis Ø 1" 111,519.83 116,490.00


A Tenaga 22,590.00 24,525.00
L.01 0.054 OH Pekerja 105,000.00 115,000.00 5,670.00 6,210.00
L.02 0.090 OH Tukang Batu 135,000.00 145,000.00 12,150.00 13,050.00
L.03 0.009 OH Kepala Tukang 140,000.00 150,000.00 1,260.00 1,350.00
L.04 0.027 OH Mandor 130,000.00 145,000.00 3,510.00 3,915.00
B Bahan 78,791.67 81,375.00
1.20 m' Pipa Galvanis Ø 1" 50,833.33 52,500.00 61,000.00 63,000.00
0.35 Ls Perlengkapan 35% x pipa 50,833.33 52,500.00 17,791.67 18,375.00
C PERALATAN
D Jumlah A + B + C 101,381.67 105,900.00
E Overhead & Profit (contoh 10%) 10% 10,138.17 10,590.00
F Harga Satuan Pekerjaan (D+E) 111,519.83 116,490.00

18 A.5.1.1.22 1 m' Pemasangan Pipa Galvanis Ø 1½ " 150,674.33 156,964.50


A Tenaga 38,810.00 41,945.00
L.01 0.108 OH Pekerja 105,000.00 115,000.00 11,340.00 12,420.00
L.02 0.180 OH Tukang Batu 135,000.00 145,000.00 24,300.00 26,100.00
L.03 0.018 OH Kepala Tukang 140,000.00 150,000.00 2,520.00 2,700.00
L.04 0.005 OH Mandor 130,000.00 145,000.00 650.00 725.00
B Bahan 98,166.67 100,750.00
1.20 m' Pipa Galvanis Ø 1½" 63,333.33 65,000.00 76,000.00 78,000.00
0.35 Ls Perlengkapan 35% x pipa 63,333.33 65,000.00 22,166.67 22,750.00
C PERALATAN
D Jumlah A + B + C 136,976.67 142,695.00
E Overhead & Profit (contoh 10%) 10% 13,697.67 14,269.50
F Harga Satuan Pekerjaan (D+E) 150,674.33 156,964.50

file:///conversion/tmp/scratch/500669137.xls 125/121 14-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
19 A.5.1.1.23 1 m' Pemasangan Pipa Galvanis Ø 3" 263,831.33 271,569.83
A Tenaga 48,680.00 52,615.00
L.01 0.135 OH Pekerja 105,000.00 115,000.00 14,175.00 15,525.00
L.02 0.225 OH Tukang Batu 135,000.00 145,000.00 30,375.00 32,625.00
L.03 0.023 OH Kepala Tukang 140,000.00 150,000.00 3,220.00 3,450.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 191,166.67 194,266.67
1.20 m' Pipa Galvanis Ø 3" 123,333.33 125,333.33 148,000.00 150,400.00
0.35 Ls Perlengkapan 35% x pipa 123,333.33 125,333.33 43,166.67 43,866.67
C PERALATAN
D Jumlah A + B + C 239,846.67 246,881.67
E Overhead & Profit (contoh 10%) 10% 23,984.67 24,688.17
F Harga Satuan Pekerjaan (D+E) 263,831.33 271,569.83

20 A.5.1.1.24 1 m' Pemasangan Pipa Galvanis Ø 4" 467,010.50 473,470.25


A Tenaga 48,680.00 52,615.00
L.01 0.135 OH Pekerja 105,000.00 115,000.00 14,175.00 15,525.00
L.02 0.225 OH Tukang Batu 135,000.00 145,000.00 30,375.00 32,625.00
L.03 0.023 OH Kepala Tukang 140,000.00 150,000.00 3,220.00 3,450.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 375,875.00 377,812.50
1.20 m' Pipa Galvanis Ø 4" 242,500.00 243,750.00 291,000.00 292,500.00
0.35 Ls Perlengkapan 35% x pipa 242,500.00 243,750.00 84,875.00 85,312.50
C PERALATAN
D Jumlah A + B + C 424,555.00 430,427.50
E Overhead & Profit (contoh 10%) 10% 42,455.50 43,042.75
F Harga Satuan Pekerjaan (D+E) 467,010.50 473,470.25

21 A.5.1.1.25 1 m' Pemasangan Pipa PVC tipe AW Ø ½" 26,213.00 28,646.75


A Tenaga 12,980.00 14,030.00
L.01 0.036 OH Pekerja 105,000.00 115,000.00 3,780.00 4,140.00
L.02 0.060 OH Tukang Batu 135,000.00 145,000.00 8,100.00 8,700.00
L.03 0.006 OH Kepala Tukang 140,000.00 150,000.00 840.00 900.00
L.04 0.002 OH Mandor 130,000.00 145,000.00 260.00 290.00
B Bahan 10,850.00 12,012.50
1.20 m' Pipa PVC Ø ½" 7,000.00 7,750.00 8,400.00 9,300.00
0.35 Ls Perlengkapan 35% x pipa 7,000.00 7,750.00 2,450.00 2,712.50
C PERALATAN
D Jumlah A + B + C 23,830.00 26,042.50
E Overhead & Profit (contoh 10%) 10% 2,383.00 2,604.25
F Harga Satuan Pekerjaan (D+E) 26,213.00 28,646.75

22 A.5.1.1.26 1 m' Pemasangan Pipa PVC tipe AW Ø ¾" 28,770.50 30,991.13


A Tenaga 12,980.00 14,030.00
L.01 0.036 OH Pekerja 105,000.00 115,000.00 3,780.00 4,140.00
L.02 0.060 OH Tukang Batu 135,000.00 145,000.00 8,100.00 8,700.00
L.03 0.006 OH Kepala Tukang 140,000.00 150,000.00 840.00 900.00
L.04 0.002 OH Mandor 130,000.00 145,000.00 260.00 290.00
B Bahan 13,175.00 14,143.75
1.20 m' Pipa PVC Ø ¾" 8,500.00 9,125.00 10,200.00 10,950.00
0.35 Ls Perlengkapan 35% x pipa 8,500.00 9,125.00 2,975.00 3,193.75
C PERALATAN
D Jumlah A + B + C 26,155.00 28,173.75
E Overhead & Profit (contoh 10%) 10% 2,615.50 2,817.38
F Harga Satuan Pekerjaan (D+E) 28,770.50 30,991.13

23 A.5.1.1.27 1 m' Pemasangan Pipa PVC tipe AW Ø 1" 35,164.25 38,876.75


A Tenaga 12,980.00 14,030.00
L.01 0.036 OH Pekerja 105,000.00 115,000.00 3,780.00 4,140.00
L.02 0.060 OH Tukang Batu 135,000.00 145,000.00 8,100.00 8,700.00
L.03 0.006 OH Kepala Tukang 140,000.00 150,000.00 840.00 900.00
L.04 0.002 OH Mandor 130,000.00 145,000.00 260.00 290.00
B Bahan 18,987.50 21,312.50
1.20 m' Pipa PVC Ø 1" 12,250.00 13,750.00 14,700.00 16,500.00
0.35 Ls Perlengkapan 35% x pipa 12,250.00 13,750.00 4,287.50 4,812.50
C PERALATAN
D Jumlah A + B + C 31,967.50 35,342.50
E Overhead & Profit (contoh 10%) 10% 3,196.75 3,534.25
F Harga Satuan Pekerjaan (D+E) 35,164.25 38,876.75

file:///conversion/tmp/scratch/500669137.xls 125/122 14-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
24 A.5.1.1.28 1 m' Pemasangan Pipa PVC tipe AW Ø 1½" 38,467.00 43,041.17
A Tenaga 19,470.00 21,045.00
L.01 0.054 OH Pekerja 105,000.00 115,000.00 5,670.00 6,210.00
L.02 0.090 OH Tukang Batu 135,000.00 145,000.00 12,150.00 13,050.00
L.03 0.009 OH Kepala Tukang 140,000.00 150,000.00 1,260.00 1,350.00
L.04 0.003 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 15,500.00 18,083.33
1.20 m' Pipa PVC Ø 1½" 10,000.00 11,666.67 12,000.00 14,000.00
0.35 Ls Perlengkapan 35% x pipa 10,000.00 11,666.67 3,500.00 4,083.33
C PERALATAN
D Jumlah A + B + C 34,970.00 39,128.33
E Overhead & Profit (contoh 10%) 10% 3,497.00 3,912.83
F Harga Satuan Pekerjaan (D+E) 38,467.00 43,041.17

25 A.5.1.1.29 1 m' Pemasangan Pipa PVC tipe AW Ø 2" 45,571.17 52,987.00


A Tenaga 19,470.00 21,045.00
L.01 0.054 OH Pekerja 105,000.00 115,000.00 5,670.00 6,210.00
L.02 0.090 OH Tukang Batu 135,000.00 145,000.00 12,150.00 13,050.00
L.03 0.009 OH Kepala Tukang 140,000.00 150,000.00 1,260.00 1,350.00
L.04 0.003 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 21,958.33 27,125.00
1.20 m' Pipa PVC Ø 2" 14,166.67 17,500.00 17,000.00 21,000.00
0.35 Ls Perlengkapan 35% x pipa 14,166.67 17,500.00 4,958.33 6,125.00
C PERALATAN
D Jumlah A + B + C 41,428.33 48,170.00
E Overhead & Profit (contoh 10%) 10% 4,142.83 4,817.00
F Harga Satuan Pekerjaan (D+E) 45,571.17 52,987.00

26 A.5.1.1.31 1 m' Pemasangan Pipa PVC tipe AW Ø 3" 78,941.50 87,215.33


A Tenaga 29,140.00 31,495.00
L.01 0.081 OH Pekerja 105,000.00 115,000.00 8,505.00 9,315.00
L.02 0.135 OH Tukang Batu 135,000.00 145,000.00 18,225.00 19,575.00
L.03 0.0135 OH Kepala Tukang 140,000.00 150,000.00 1,890.00 2,025.00
L.04 0.004 OH Mandor 130,000.00 145,000.00 520.00 580.00
B Bahan 42,625.00 47,791.67
1.20 m' Pipa PVC Ø 3" 27,500.00 30,833.33 33,000.00 37,000.00
0.35 Ls Perlengkapan 35% x pipa 27,500.00 30,833.33 9,625.00 10,791.67
C PERALATAN
D Jumlah A + B + C 71,765.00 79,286.67
E Overhead & Profit (contoh 10%) 10% 7,176.50 7,928.67
F Harga Satuan Pekerjaan (D+E) 78,941.50 87,215.33

27 A.5.1.1.32 1 m' Pemasangan Pipa PVC tipe AW Ø 4" 91,003.00 94,999.67


A Tenaga 12,980.00 14,030.00
L.01 0.036 OH Pekerja 105,000.00 115,000.00 3,780.00 4,140.00
L.02 0.060 OH Tukang Batu 135,000.00 145,000.00 8,100.00 8,700.00
L.03 0.006 OH Kepala Tukang 140,000.00 150,000.00 840.00 900.00
L.04 0.002 OH Mandor 130,000.00 145,000.00 260.00 290.00
B Bahan 69,750.00 72,333.33
1.20 m' Pipa PVC Ø 4" 45,000.00 46,666.67 54,000.00 56,000.00
0.35 Ls Perlengkapan 35% x pipa 45,000.00 46,666.67 15,750.00 16,333.33
C PERALATAN
D Jumlah A + B + C 82,730.00 86,363.33
E Overhead & Profit (contoh 10%) 10% 8,273.00 8,636.33
F Harga Satuan Pekerjaan (D+E) 91,003.00 94,999.67

28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 85,481.00 94,204.00
cm
A Tenaga 14,880.00 16,180.00
L.01 0.080 OH Pekerja 105,000.00 115,000.00 8,400.00 9,200.00
L.02 0.040 OH Tukang Batu 135,000.00 145,000.00 5,400.00 5,800.00
L.03 0.004 OH Kepala Tukang 140,000.00 150,000.00 560.00 600.00
L.04 0.004 OH Mandor 130,000.00 145,000.00 520.00 580.00
B Bahan 62,830.00 69,460.00
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,150.00 1,200.00 40,250.00 42,000.00
0.014 m3 Pasir Pasang 310,000.00 370,000.00 4,340.00 5,180.00
0.014 m3 Pasir Urug 160,000.00 220,000.00 2,240.00 3,080.00
- -

file:///conversion/tmp/scratch/500669137.xls 125/123 14-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 77,710.00 85,640.00
E Overhead & Profit (contoh 10%) 10% 7,771.00 8,564.00
F Harga Satuan Pekerjaan (D+E) 85,481.00 94,204.00

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15


29 A.5.1.1.34 1 m' 41,327.00 46,997.50
cm
A Tenaga 11,160.00 12,135.00
L.01 0.060 OH Pekerja 105,000.00 115,000.00 6,300.00 6,900.00
L.02 0.030 OH Tukang Batu 135,000.00 145,000.00 4,050.00 4,350.00
L.03 0.003 OH Kepala Tukang 140,000.00 150,000.00 420.00 450.00
L.04 0.003 OH Mandor 130,000.00 145,000.00 390.00 435.00
B Bahan 26,410.00 30,590.00
1.60 bh pipa tanah 8,000.00 9,500.00 12,800.00 15,200.00
6.80 kg Semen Portlan 1,150.00 1,200.00 7,820.00 8,160.00
0.013 m3 Pasir Pasang 310,000.00 370,000.00 4,030.00 4,810.00
0.011 m3 Pasir Urug 160,000.00 220,000.00 1,760.00 2,420.00
,
C PERALATAN
D Jumlah A + B + C 37,570.00 42,725.00
E Overhead & Profit (contoh 10%) 10% 3,757.00 4,272.50
F Harga Satuan Pekerjaan (D+E) 41,327.00 46,997.50

30 A.5.1.1.35 1 m' Pemasangan Pipa Beton Ø 15 - 20 cm 122,955.80 138,340.40


A Tenaga 26,040.00 28,315.00
L.01 0.140 OH Pekerja 105,000.00 115,000.00 14,700.00 16,100.00
L.02 0.070 OH Tukang Batu 135,000.00 145,000.00 9,450.00 10,150.00
L.03 0.007 OH Kepala Tukang 140,000.00 150,000.00 980.00 1,050.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan 85,738.00 97,449.00
1.10 bh pipa beton 45,000.00 50,000.00 49,500.00 55,000.00
0.027 m3 Batu Bata 390,000.00 435,000.00 10,530.00 11,745.00
3.920 kg Semen Portlan 1,150.00 1,200.00 4,508.00 4,704.00
0.056 m3 Pasir Pasang 310,000.00 370,000.00 17,360.00 20,720.00
0.024 m3 Pasir Urug 160,000.00 220,000.00 3,840.00 5,280.00
C PERALATAN
D Jumlah A + B + C 111,778.00 125,764.00
E Overhead & Profit (contoh 10%) 10% 11,177.80 12,576.40
F Harga Satuan Pekerjaan (D+E) 122,955.80 138,340.40

31 A.5.1.1.36 1 m' Pemasangan Pipa Beton Ø 30 - 100 cm 565,328.50 616,038.50


A Tenaga 70,680.00 76,855.00
L.01 0.380 OH Pekerja 105,000.00 115,000.00 39,900.00 43,700.00
L.02 0.190 OH Tukang Batu 135,000.00 145,000.00 25,650.00 27,550.00
L.03 0.019 OH Kepala Tukang 140,000.00 150,000.00 2,660.00 2,850.00
L.04 0.019 OH Mandor 130,000.00 145,000.00 2,470.00 2,755.00
B Bahan 443,255.00 483,180.00
1.10 bh pipa beton 180,000.00 190,000.00 198,000.00 209,000.00
0.55 m3 Batu Bata 390,000.00 435,000.00 214,500.00 239,250.00
10.300 kg Semen Portlan 1,150.00 1,200.00 11,845.00 12,360.00
0.061 m3 Pasir Pasang 310,000.00 370,000.00 18,910.00 22,570.00
0.069 m3 Pasir Urug 160,000.00 220,000.00 11,040.00 15,180.00
C PERALATAN
D Jumlah A + B + C 513,935.00 560,035.00
E Overhead & Profit (contoh 10%) 10% 51,393.50 56,003.50
F Harga Satuan Pekerjaan (D+E) 565,328.50 616,038.50

file:///conversion/tmp/scratch/500669137.xls 125/124 14-15


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 1 Titik Pemasangan Lampu 412,280.00 431,508.00


A Tenaga 187,400.00 196,140.00
100 % Pekerja 187,400.00 196,140.00 187,400.00 196,140.00

Bahan 187,400.00 196,140.00


3.00 btg Pipa Listrik 5/8" **) 4,000.00 4,200.00 12,000.00 12,600.00
24.00 m Kabel **) 6,000.00 6,200.00 144,000.00 148,800.00
3.00 buah T.Dus 500.00 600.00 1,500.00 1,800.00
4.00 buah L.Bow 500.00 600.00 2,000.00 2,400.00
3.00 buah Las Dop 500.00 600.00 1,500.00 1,800.00
24.00 buah Klem 50.00 60.00 1,200.00 1,440.00
1.00 buah Mongkok 1,200.00 1,300.00 1,200.00 1,300.00
1.00 buah Saklar 12,000.00 13,000.00 12,000.00 13,000.00

1.00 buah Pitting 12,000.00 13,000.00 12,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 374,800.00 392,280.00
E Overhead & Profit (contoh 10%) 10% 37,480.00 39,228.00
F Harga Satuan Pekerjaan (D+E) 412,280.00 431,508.00
Overhead & Profit (contoh 10%)
2 A.8.4.6.2 1 buah Pemasangan MCB 505,340.00 536,448.00
A Tenaga 229,700.00 243,840.00
L.01 100 % Pekerja 229,700.00 243,840.00 229,700.00 243,840.00

B Bahan 229,700.00 243,840.00


3 Btg Pipa Listrik 5/8" **) 4,000.00 4,200.00 12,000.00 12,600.00
15 m Kabel **) 6,000.00 6,200.00 90,000.00 93,000.00
1 buah T.Dus 500.00 600.00 500.00 600.00
2 buah L.Bow 500.00 600.00 1,000.00 1,200.00
24 buah Klem 50.00 60.00 1,200.00 1,440.00
1 buah MCB 125,000.00 135,000.00 125,000.00 135,000.00
C PERALATAN
D Jumlah A + B + C 459,400.00 487,680.00
E Overhead & Profit (contoh 10%) 10% 45,940.00 48,768.00
F Harga Satuan Pekerjaan (D+E) 505,340.00 536,448.00

file:///conversion/tmp/scratch/500669137.xls 125/125 15-15

You might also like