______________________ (Compulsory)

3. The size of the pay-off matrix of a game can be reduced by using the
principle of
a. Dominance
b. Rotation
c. Game inversion
d. Game transpose

4. For a two person Game with A and B ,the minimising and maximising
players, the optimum strategies are:
a.Minimax for A and Maximin for B
b.Maximax for A and Minimax for B
c.Minimin for A and Maximin for B
d.Maximin for A and Minimax for B

5. Find the Economic Order Quantity if annual demand is 7000 units,


carrying cost is Rs.10 per unit per year and ordering cost is Rs. 350 per
order.
a. 495
b. 700
c. 300
d. 100
6. In Inventory model, the Cost of damage in stoarage and quality losses
are components of _________
a. ordering cost
b. unit cost
c. carrying cost
d. shortage cost
7. If Annual demand = 3900 units, ordering cost = Rs. 26 per order ,
Carrying cost = Rs 3 per unit per year, find the inventory variable cost.
a. Rs.780
b. Rs. 552
c. Rs 260
d. Rs.900
8. If Annual demand = 1000 units, ordering cost = Rs. 25per order , shortage
cost is Rs. 30 per unit per year, holding cost = Rs 5 per unit per year. find
the economic order quantity when shortages are allowed.
a. 76
b. 108
c. 150
d. 158
9. If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7
respectively, then its expected time and variance are respectively
a. 3.5 and 5/6
b. 5 and 25/36
c. 3.5 and 25/36
d. 4 and 5/6
10. The particular task performance in CPM is known as
a. Event
b. Activity
c. Dummy
d. Contract
11.PERT technique of network analysis is mainly useful for
a. Small projects
b. Deterministic activities
c. Large and complex projects
d. Research and development projects
12.If a11 = 5, a12=4, a21=8, a22=9 then value of the game is
a. 6
b. 6.5
c. 7
d. 8