Professional Documents
Culture Documents
The Arbitration and conciliation Act, 1996 or the Contract Act, 1872 does not
define the expression “Public Policy” or “opposed to public policy.” “Public
Policy” is not the policy of an executive authority. It connotes some matter
which concerns the public good or the public interest. ‘Public Policy’ is
equivalent to the “Policy of Indian Law.” Therefore any acts that have a
mischievous tendency so as to be injurious to the interest of the state or the
public or against justice and morality is stated to be against “Public Policy” or
against the ‘Policy of Indian Law.”
Doctrine of ‘Public Policy’ is somewhat open ended and flexible, and this
flexibility has been the cause of judicial subjectivity and misinterpretation of
the doctrine. There is a general agreement that the courts may extend existing
concept of ‘Public Policy’ to new situations and the difference between
extending on existing principle as opposed to creating a new one will often be
wafer thin like a butterfly wing. ‘Public Policy’ is not absolute. In the broader
view, the doctrine of “Public Policy” is equivalent to the “Policy of Law,”
whatever leads to obstruction of justice or violation of a statute or is against
the good morals when made the object of contract would be against ‘Public
Policy of India” and being void, would not be susceptible to enforcement.
After that we move to the judgement given in ONGC v. Saw pipes Limited [2]
which widened the horizons of public policy .The facts of the said case – Oil
and Natural Gas Commission had placed an order on Saw Pipes for supply of
equipment for off shore exploration, to be procured from approved European
manufacturers. The delivery was delayed due to general strike of steel mill
workers in Europe. Timely delivery was the essence of the contract. ONGC
granted extension of time, but it invoked the clause for recovery of Liquidated
Damages by withholding the amount from the payment to the supplier. ONGC
deducted from the payment $3,04,970.20 and Rs 15,75,557 towards customs
duty, sales tax and freight charges. Saw pipes disputed the deduction and
matter was referred to arbitration. While the arbitral tribunal rejected Saw
Pipe’s defence of force majeure, it required ONGC to lead evidence to
establish the loss suffered by breach and proceed to hold, in absence of
evidence of financial losses, that the deduction of Liquidated damages was
wrongful. The award was challenged by ONGC; inter alia as being opposed to
public policy. ONGC’s case was that the arbitral tribunal failed to decide the
dispute by not applying the prevailing substantive law, ignoring the terms of
the contract and customary practices of usage of trade in such transactions.
ONGC challenged the award as being patently illegal. The single judge and
division bench of Bombay High Court dismissed the challenge. The Supreme
Court set aside an arbitration award directing ONGC to refund $3,04,970.20
and Rs 15.76 Lakhs towards liquidated damages retained by it while making
payment to the company.
The Court held that in case of an application u/s 34 to set an award aside, the
role of the Court was similar to an appellate/revision court, therefore, it had
wide powers. Further, the Court also added a new ground – patent illegality to
the grounds enumerated in Renusagar Power Co. Ltd; under which the arbitral
award could be set aside.
“Therefore, in our view, the phrase ‘Public Policy of India’ used in Section
34 in context is required to be given a wider meaning. It can be stated that
the concept of public policy connotes some matter which concerns public
good and the public interest. What is for public good or in public interest or
what would be injurious or harmful to the public good or public interest has
varied from time to time. However, the award which is, on the face of it,
patently in violation of statutory provisions cannot be said to be in public
interest. Such award/judgment/decision is likely to adversely affect the
administration of justice. Hence, in our view in addition to narrower
meaning given to the term 'public policy' in Renusagar's case (supra) it is
required to be held that the award could be set aside if it is patently illegal.
Result would be--award could be set aside if it is contrary to: -
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality,
or (d) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if the illegality is of trivial
nature it cannot be held that award is against the public policy. Award
could also be set aside if it is so unfair and unreasonable that it shocks
the conscience of the Court. Such award is opposed to public policy and
is required to be adjudged void.”
The judgment debtor contented before the Delhi High Court that the impugned
award was against public policy as (i) the award was against the express
terms of the contract which rendered it patently illegal and (ii) the arbitral
tribunal refused to entertain the counter claim of the judgment debtor, denying
it an opportunity to present its case. The judgment debtor relied on Venture
Global Engineering v. Satyam Computer Services Limited (AIR 2008 SC
1061) to contend that the foreign award is subject to challenge u/s 34 of the
Act, and then relied on Saw Pipes [2] to contend that since the award was
patently illegal it could not be enforced. Contrarily, the decree holder
contented that while enforcing an award u/s 47-49 of the Act, the court is not
mandated to adjudicate on the merits of the dispute. The decree holder further
contended that the law laid down in Saw Pipes [2] is only applicable to
domestic awards and that the term “Public Policy” has a different connotation
u/s 48(2)(b) to that in S. 34(2)(b)(ii) of the Act.
The Delhi High Court upholding the contention(s) of the decree holder, held
that the term “public policy” in S. 48(2)(b) of the Act carries a narrower
meaning when compared to the meaning assigned to the same term u/s 34(2)
(b)(ii) of the Act. The court relied on the Supreme Court decision in Furest
Day Lawson v. Jindal Exports (AIR 2001 SC 2293) and its own decision
in Jindal Exports v. Furest Day Lawson to hold that a narrow meaning must
be given to the term “public policy” u/s 48(2)(b) and only when the most “basic
notions of morality and justice” are violated should the court refuse the
enforcement of the foreign award. Having drawn a distinction between s. 48(2)
(b) and s. 34(2)(b)(ii), as far the tem “public policy” is concerned, the court
further seems to have agreed that the ratio of Venture Global was not
applicable to the present case as the substantive law governing the contract
was not Indian Law (arguably suggesting an implied exclusion of Part I of the
Act).
In 2011, the Supreme Court in Phulchand [4] while deciding the meaning of
‘public policy’ under Section 48 of the 1996 Act held that the test laid down in
ONGC v. Saw Pipes case must be followed in case of foreign awards as well,
thereby allowing Indian Courts to deny enforcement of a foreign award on
additional grounds of “patent illegality”. Notably however, the Supreme Court
expounded no reasons for ignoring the distinction drawn between foreign
awards and domestic awards in Saw Pipes itself or for departing from
Renusagar [3] which although dealt with a separate statute, had in fact
interpreted a provision identical in text and intention to that of Section 48.
The appellant then brought its appeal before the Supreme Court. The
appellant argued that the wider meaning attributed by the Supreme Court
in Saw Pipes [2] to the definition of 'public policy' (under Section 34 of the act)
in the context of setting aside a domestic award should also be applied to the
definition of the same expression under Section 48(2)(b) of the act. While
accepting the wider definition of 'public policy' in Saw Pipes over the narrow
scope ascribed in Renusagar Power, the Supreme Court held that a foreign
award can be set aside under Section 48(2)(b) of the act "if it is patently
illegal". The court therefore decided to consider the arbitral award based on
patent illegality. However, on the merits, the court did not find the impugned
arbitral award to be patently illegal and consequently dismissed the
appellant's civil appeal.
The buyer sought to enforce the award before the Delhi High Court. The seller
opposed enforcement, contending that the arbitral tribunal had placed greater
reliance on quality certificates prepared by non-contractual agencies than on
the quality certificate prepared by the agency nominated under the contract.
The seller argued that the arbitral award delivered on this basis was contrary
to the express provision in the contract and enforcing such an award would be
contrary to the public policy of India. The High Court refused to interfere with
the award on the basis that it was not expected to re-determine questions of
fact in enforcement proceedings. The seller appealed against this decision to
the Supreme Court of India. The seller relied on Phulchand and argued that
the court had the power to consider the merits of a case where there was a
patent illegality in the award, even in enforcement proceedings. On the other
hand, the buyer relied on the decision of the Supreme Court in Renusagar
Power Co Ltd. v General Electric Company – which predated the decision
in Phulchand but was delivered by a larger bench than Phulchand – and
argued that patent illegality cannot be a ground to challenge an award in
enforcement proceedings especially in the context of foreign awards where,
as laid down in Renusagar, the relevance of Indian law is more limited.
A three-judge bench of the Supreme Court speaking through Justice RM
Lodha (who was interestingly also the author of the decision in Phulchand),
overruled Phulchand and accepted the contentions of the buyer. The court
held that during setting aside proceedings, the arbitral award is not yet final
and executable, and this is in contradistinction to a challenge during
enforcement where the award is final and binding. On this basis the court
refused to apply the definition of the term ‘public policy’ as applied in the
context of setting aside proceedings and as laid down in ONGC v Saw
Pipes in the context of a challenge during an enforcement action. The court
followed the decision in Renusagar and held that enforcement can only be
opposed on grounds of public policy where it is contrary to:
Fundamental policy of Indian law;
The interests of India; or
Justice and morality.
In particular, the court expressly declined to allow a challenge on the grounds
of ‘patent illegality’. Since the challenge raised by the seller required
reconsideration of the merits of the case and re-looking at the facts, the court
declined to entertain the challenge and allowed enforcement.
In 2014, the two Supreme Court decisions, Associate Builders and Western
Geco, once again tangled the interpretation with respect to the meaning and
scope of the term ‘public policy’ under Section 34 of the Act.
The arbitrator inter alia held that deductions made by the Appellant for delay
after the intimation that Respondent was not seeking to pursue the request for
licence before the U.S. authorities was unjustified. Aggrieved by the award,
the Appellant challenged the award under section 34 of the 1996 Act before
the Bombay High Court, which was rejected. The Appellant then preferred an
appeal before the Supreme Court.
The Apex Court was required to decide whether the award violated the public
policy of India. The Court while agreeing with ratio of Saw Pipes, went a step
further to elaborate the meaning of ‘fundamental policy of Indian law’. It
determined that three ‘distinct and fundamental juristic principles’ form a part
and parcel of fundamental policy of Indian law: first, the court or adjudicating
authority must adopt a ‘judicial approach’ when determining the rights of a
citizen. This implies that it cannot act in an ‘arbitrary, capricious or whimsical
manner’; second, the court or quasi-judicial authority must determine rights
and obligations of parties in accordance with principles of natural justice which
encompasses that the authority deciding the matter must apply its mind to the
attendant facts; and third, a decision which is perverse or so irrational that a
reasonable person could not have reached such a conclusion may not be
sustained in a court of law.
In this case, the Appellant entered into a works contract with the Respondent
for construction of a residential colony. There was a delay in the completion of
the project which the Appellant attributed to the Respondent. The arbitrator
held that the entire delay of 25 months was attributable to the Respondent.
Aggrieved by the decision, the Respondent challenged the award before a
Single Judge of the High Court of Delhi where the application was dismissed.
An appeal was preferred to the Division Bench where the judgment of the
Single Bench was set aside. The Appellants then came before the Supreme
Court in appeal against the order of the Division Bench.
The Court in Associate Builders not only referred to Saw Pipes and
Renusagar, but also relied on the Western Geco decision. It further elaborated
on the concept of fundamental policy of Indian law, interest of India, justice,
morality and patent illegality as held in several prior decisions and in particular
further expounded the position of law laid down in Western Geco. As a result,
Associate Builder accelerated the expansion of challenge jurisdiction, despite
having upheld the award on facts.
The Court however, also stated that “while applying the public policy test to an
arbitration award, it [the court] does not act as a court of appeal and
consequently errors of fact cannot be corrected” and that “the arbitrator is the
ultimate master of the quantity and quality of evidence relied upon when he
delivers the arbitral award.” Whilst on one hand, the Apex Court held that the
Division Bench had exceeded its jurisdiction by interfering with a possible view
of the Arbitrator; on facts the Apex Court upheld the award based on its own
assessment that the arbitrator’s views were indeed correct.
Although Western Geco and Associate Builders were decisions under Section
34 of the 1996 Act , it became apprehensive that they would apply with equal
force to cases under Section 48 of the 1996 Act (enforcement of foreign
award) which were then governed by the Renusagar case test which inter alia
includes ‘fundamental policy of India’.
Western Geco case opened the floodgates for further scrutiny and review of
domestic arbitral awards on merits by introducing well-established judicial
principles having a long line of precedents in common law, into the concept of
‘fundamental policy of Indian law’.
Thus, Courts can no longer reappraise evidence or set aside awards merely
because the Arbitral Tribunal has made errors when dealing with the same. It
is interesting to note that the amendment did not make any changes to the
interpretation of “justice and morality” as explained in Associate Builders.
Since the amendment, Courts have refrained from giving a wider interpretation
to “public policy” or interfering with the merits of the case. In the November
2017 Supreme Court Judgment of Venture Global Engineering LLC and Ors v
Tech Mahindra Ltd. and Ors [9] the Court observed –
“The Award of an arbitral Tribunal can be set aside only on the grounds
specified in Section 34 of the AAC Act and on no other ground. The Court
cannot act as an Appellate Court to examine the legality of Award, nor it can
examine the merits of claim by entering in factual arena like an Appellate
Court.”
An arbitral award dated 3 April 2006 (the Award) was passed against Venture
in an arbitration initiated by Satyam directing Venture to transfer its interest,
i.e., 50% of the shares in a Joint Venture Company (JVC) to Satyam (the
other shareholder holding 50%). Thereafter, Venture filed a civil suit before the
City Civil Court, Secunderabad which was transferred to the City Civil Court
Hyderabad (Trial Court). Venture sought a declaration that the Award was
illegal and without jurisdiction, and requested an injunction restraining Satyam
from enforcing the Award.
HELD:
As the Bench hearing the matter had differing views, the matter was referred
to a larger Bench. A brief discussion on each of their rulings is set out below:
Justice Sapre's view: Justice Sapre listed the following three questions for
consideration:
Whether the acts of Mr. Raju in the affairs of Satyam, as admitted by
him in his confessional statement, amounted to misrepresentation/
suppression of material facts and, if so, whether they could be made the
basis of seeking quashing of the Award on the ground that it is against
the public policy of India under Section 34(2)(b)(ii) read with Explanation
(1)(i)(ii) and (iii) of the Act?
Whether Mr. Raju's acts had any causative link with the facts pertaining
to the arbitration at hand?
If the above questions are answered in the affirmative, whether it would
constitute a ground for setting aside the Award?
Justice Sapre set aside the Award on the following grounds:
Citing the definition of "fraud" as enumerated in Kerr on Fraud and
Mistake, 7th Edn., suppression of Mr. Raju's acts amounted to a fraud
played in the arbitration. Relying on SC's Judgement in Onkar Nath &
Ors. v Delhi Administration1, the judicial notice of the confessional
statement of Mr. Raju could be taken without any more formal proof
since neither the letter nor the signature on it had been disputed in any
proceeding.
In addition, since both Satyam and Venture were 50% shareholders in
the JVC, any unlawful act by Mr. Raju vis-à-vis Satyam's affairs would
also have a direct impact on the JVC. By this, there was indeed a
causative link between Mr. Raju's acts and the present matter. Further,
the suppression of facts by Mr. Raju and ergo, Satyam, deprived
Venture of their right to terminate the Contract earlier, as well as plead
the same grounds before the arbitration.
The above points vitiated the entire arbitral proceedings, rendering the
Award illegal and against the public policy of India.
Justice Sapre also accepted the Trial Court's finding that Satyam had
violated the provisions of FEMA, using the finding to bolster the
argument that the Award was against the public policy of India.
On the question of whether Venture's challenge to the Award was
barred by issue estoppel, Justice Sapre relied on Masud Khan v State
of Uttar Pradesh to hold that the principle of "issue estoppel" only
applied in the context of criminal proceedings. Since arbitral
proceedings are in the nature of civil proceedings, it was held that the
HC had erred in applying the same to dismiss Venture's Application
under Section 34 of the Act.
Justice Chelameshwar's view:
In his order, Justice Chelameshwar listed the following two questions for
consideration:
Whether the Award was against the public policy of India on the ground
of violation of the FEMA, etc?
Whether the Award was vitiated by fraud / suppression of material facts
by Satyam?
Justice Chelameshwar upheld the Award on the following grounds:
Justice Chelameshwar noted that Venture had pleaded that the Award,
insofar as it directed Venture to transfer shares to Satyam at book value
(rather than fair value) was in violation of the Foreign Exchange
Management (Transfer or Issue of Security by a Person Resident
outside India) Regulations, 2000. He noted that this contention was
merely accepted at face value by the Trial Court, without mention of the
relevant regulation or the scheme of FEMA or any other reasoning.
Further, the Trial Court had erroneously set aside the Award because
there was lack of discussions on the fair value of the shares, how that
fair value was to be determined or any similar relevant question, as well
as lack of reasoning relating to the public policy ground.
Even if Mr. Raju's acts were relevant to the arbitration proceedings,
whether the same were "material facts", the non-disclosure of which
could be said to have "affected the Award by fraud", was required to
have been dealt with by the Trial Court. The lack of any discussion
regarding this aspect in the Trial Court's order rendered the same
erroneous.
As far as the appeal filed by Satyam was concerned, since the same
was re-agitating the question of the applicability of Part- I of the Act to
an international commercial arbitration, it was an indirect challenge to
the decision of the constitutional bench of the SC in Bharat Aluminium
Company v Kaiser Aluminium Technical Services Inc3, which could not
be allowed.
Comment
Despite being inconclusive, the Judgement is a welcome addition to the Indian
jurisprudence on fraud and its role in judicial proceedings. We await the larger
bench's Judgement in this matter as it would shed further light on SC's view
on fraud vitiating an arbitration award.
A similar view was also taken in the judgment of Sutlej Construction v. The
Union Territory of Chandigarh [10]
It has been opined by Supreme Court that when it comes to setting aside of
an award under the public policy ground, it would mean that the award should
shock the conscience of the court and would not include what the court thinks
is unjust on the facts of the case seeking to substitute its view for that of the
arbitrator to do what it considers to be "justice." (Associate Builders v. Delhi
Development Authority MANU/SC/1076/2014 : (2015) 3 SCC 49).
It was also opined by Supreme Court that the approach adopted by the
learned Additional District Judge, Chandigarh was, thus, correct in not getting
into the act of re-appreciating the evidence as the first appellate court from a
trial court decree. An arbitrator is a chosen Judge by the parties and it is on
limited parameters can the award be interfered with. (Sudarsan Trading Co. v.
The Government of Kerala MANU/SC/0361/1989 : (1989)1 SCR 665; Harish
Chander & Co. v. State of U.P. MANU/SC/0985/2016 : AIR 2016 SC 4257 and
Swan Gold Mining v. Hindustan Copper Limited MANU/SC/0849/2014 :
2014(4)Arb LR 1(SC)).
It also opined that the learned single Judge ought to have restrained himself
from getting into the meanderings of evidence appreciation and acting like a
second appellate court. In fact, even in second appeals, only questions of law
are to be determined while the first appellate court is the final court on facts. In
the present case the learned single Judge has, thus, acted in the first appeal
against objections dismissed as if it was the first appellate court against a
decree passed by the trial court.
These judgments show that the recent trend of interpretation of “public policy”
has been one where the Courts have refused to examine the arbitral awards
on merits, thereby upholding the legislative mandate of “minimal intervention
of the Courts in the arbitral process” as reflected by the changes brought by
the Arbitration and Conciliation (Amendment) Act, 2015.
Conclusions
The interpretation of ‘public policy’ has shuttled across various interpretations
and in absence of proper laid down definition, the subordinate courts have
given arbitrary and whimsical decisions in past as to its definitive meaning.
There have been reported instances where mere violation of an Indian Law
has been labelled to be against Public Policy. The ‘patent illegality’ test
opened a Pandora’s Box for litigants as in multiple adjudications, after
thorough examination and proper application of rule of law by the arbitral
tribunals, the courts again started sitting on the merits of the case which
delayed justice and vitiated the whole purpose of arbitration.
While there is a need for a developed and broad version of the concept of
public policy in the realm of contractual relationships, the same may not be
extended to the laws governing arbitrations. The process of arbitration is a
method of alternate dispute resolution that has become increasingly popular in
the settlement of commercial disputes on account of speed and efficiency.
The process of arbitration centres on the guarantee of minimal interference by
the judiciary. Thus, to further the object of arbitration and to increase its utility
in expediting the dispute settlement in the country, it is essential that not only
is the concept of public policy interpreted in a restrictive sense, but that it has
clearly and distinctly defined parameters, whose ambiguities do not lend them
to conflicting interpretations in dispute resolutions. The recent amendments to
the Arbitration and Conciliation Act 1996, are clearly positive and pragmatic in
furtherance of this pro-arbitration stance and it is hoped that they will advance
the dispute resolution in speedier and efficient manner in the years to come.
[9] 473 U.S. 614; 105 S.Ct.3346; 87 L.Ed.2d. 444 (1985); 24 ILM 1064 (1985)
[10] Parsons & Whittemore Overseas Co, Inc v Societe Generale de l’Industrie
de Papier, and Bank of America, 508 F.2d` + 969 (2d. Cir. 1974)