0% found this document useful (0 votes)
225 views11 pages

Cable Laying and Testing Costs

This document provides cost estimates for different methods of laying 33KV underground cables, including laying cable in an open trench, in HDPE pipes, in cable ducts, and using horizontal directional drilling. The costs include expenses for materials, labor, overhead, and supervision. Horizontal directional drilling is noted to be the most expensive option due to its technical complexity, with estimated total costs over half a million rupees per kilometer laid.

Uploaded by

Suryamsh Vikrama
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
225 views11 pages

Cable Laying and Testing Costs

This document provides cost estimates for different methods of laying 33KV underground cables, including laying cable in an open trench, in HDPE pipes, in cable ducts, and using horizontal directional drilling. The costs include expenses for materials, labor, overhead, and supervision. Horizontal directional drilling is noted to be the most expensive option due to its technical complexity, with estimated total costs over half a million rupees per kilometer laid.

Uploaded by

Suryamsh Vikrama
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
  • Task 1: Laying and Testing of 3.8 kV Cable: Details the financial breakdown for the task of laying and testing specific cable types, including costs and margins for the supply used.
  • Task 2: Installation of DWC HDPE Pipes: Provides details for the installation of DWC HDPE pipes including labor, overhead, and supervision costs.
  • Task 3: Laying of 8.3 kV Cable Using HDD: Outlines the costs and processes for laying high voltage cables using horizontal directional drilling (HDD) methods.
  • Task 4: Installation of Cable Duct: Covers the details and associated costs for installing cable ducts, including civil works and supervision.
  • Task 5: Laying of 11 kV Cable Using DWC HDPE Pipes: Describes the laying procedures and financial plan for using DWC HDPE pipes for 11 kV cables.
  • Task 6: Laying and DWC HDPE Piping for 3 Core Cable: Details the costs and logistical plan for piping and cable laying including necessary civil work.
  • Task 7: Brick Laying and Cover for Cable Route: Lists the steps and financial estimations for brick laying along cable routes for protection.
  • Task 8: Duct laying and Minor Civil Work: Provides financial outlines for duct laying combined with minor civil construction tasks.
  • Task 9: Execution Details for Cable Trench: Lists the detailed execution plan and costs for constructing cable trenches including manpower and materials used.
  • Summary and Totals: Compiles the overall financial details and summaries for daily and monthly expenses for the tasks documented in previous sections.

    Qty Man- Man- Day Rate Total Billing/ Profit Comments Billing per Billing per

hours days Cost/Km KM Margin month for 10 month for 5


KM KM

        10hr/day including            
food&camp
I Laying and testing of 33KV, 3 core, 400       Rs Rs          
sqmm UG cable
1 Laying of 33 KV ,3 core, 400sqmm, cable                    
in open trench
  0.5 hour per meter including laying of                    
warning tapes
  cable cover tiles, supply and laying of               Supply of    
bricks every 3 meters bricks to be
discussed
with L&T
a Per Kilometer=0.5X1000   500 50 400.00 20,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter
c Bricks Approx cost Rs.15,000   1 1 15,000.00 15,000.00          
            40,000.00 100,050 60,050.00 This 1,000,500.00 500,250.00
.00 activity can
be speed-
up and
even up to
2 Km per
day also
can be
done.
                       

2 Laying of 11 KV ,3 core, 400sqmm in                    


1 of 12
DWC HDPE pipes
  1.5 hour per meter including laying of                    
warning tapes
  cable cover tiles                    
a Per Kilometer=1.5X1000   1500 150 400.00 60,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter
                     

Cable to be
pulled in
between
the route
in HDPE
pipes and
will take
time.
            65,000.00 108,483 43,483.00 Prior 1,084,830.00 542,415.00
.00 planning
required.
3 Laying of 33 KV, 3 cores, 400sqmm in                    
cable duct including civil works
  1.5 hour per meter including laying of                    
warning tapes
  cable cover tiles                    
a Per Kilometer=1.5X1000   1500 150 400.00 60,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter

c Civil works approx/KM Rs.10,000   1 1 10,000.00 10,000.00     Cable to be    


pulled in
between
the route
in HDPE
pipes and
will take
time.
2 of 12
            75,000.00 129,567 54,567.00 Prior 1,295,670.00 647,835.00
.00 lanning
required.
                  Civil works    
are
involved.

4 Laying of 33 KV ,3 core, 400sqmm in                    


DWC HDPE pipes by HDD
  Lumpsum   1 1 550,000.00 550,000.00 606,817 56,817.00 HDD is 6,068,170.00 3,034,085.00
.00 normally a
costly
activity and
a minimum
margin
only can be
expected.
However,
depends on
skill and
machine
we can
reduce cost
and get
maximum
results.
                       
5 Laying of cable up to ground level from                    
33kv feeder outgoing isolator
  Laying of 33 KV ,3 core, 400sqmm in DWC                    
HDPE pipes
  1.5 hour per meter including laying of                    
warning tapes
  cable cover tiles, clamping and   1500 150 400.00 60,000.00          
connection
3 of 12
  over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00     Cable to be    
meter pulled in
between
the route
in HDPE
pipes and
will take
time.
  Consumables approx Rs.8,000         8,000.00     Prior    
planning
required.
            73,000.00 123,817 50,817.00 Electrical joint 1,238,170.00 619,085.00
works are
.00
involved.

To be
discussed with
Company

II Laying and testing of 11KV, 3 core, 300                    


sqmm UG cable
1 Laying of 11 KV ,3 core, 300sqmm, cable                    
in open trench
  cable cover tiles, supply and laying of                    
bricks every 3 meters
a Per Kilometer=0.3 hrX1000   300 30 400.00 12,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter
c Bricks Approx cost Rs.15,000   1 1 15,000.00 15,000.00          

4 of 12
            32,000.00 87,783. 55,783.00 This 877,830.00 438,915.00
00 activity can
be speed-
up and
even up to
2 Km per
day also
can be
done.

2 Laying of 11 KV ,3 core, 300sqmm in                    


DWC HDPE pipes by HDD
  Lumpsum   1 1 500,000.00 500,000.00 549,397 49,397.00 HDD is 5,493,970.00 2,746,985.00
normally a
.00
costly activity
and a
minimum
margin only
can be
expected.How
ever, depends
on skill and
machine we
can reduce
cost and get
maximum
results.
                       
                       
3 Laying of 11 KV ,3 core, 300sqmm in                    
DWC HDPE pipes
  1.0 hour per meter including laying of                    
warning tapes
  cable cover tiles                    
a Per Kilometer=1.0X1000   1000 100 400.00 40,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter
                  Cable to be    
pulled in
between
5 of 12
the route
in HDPE
pipes and
will take
time.
            45,000.00 93,150. 48,150.00 Prior 931,500.00 465,750.00
00 planning
required.

4 Laying of 11 KV, 3 core, 300sqmm in                    


cable duct including civil works
  1.0 hour per meter including laying of                    
warning tapes
  cable cover tiles                    
a Per Kilometer=1.0X1000   1000 100 400.00 40,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter
c Civil works approx/KM Rs.10,000   1 1 10,000.00 10,000.00     Cable to be    
pulled in
between
the route
in HDPE
pipes and
will take
time.
            55,000.00 124,583 69,583.00 Prior 1,245,830.00 622,915.00
.00 planning
required.
                  Civil works    
are
involved.

III Laying and testing from RMU outgoing to                    


DTR HV bushings
1 Laying of 3 core, 185sqmm, 11 kv cable in                    
open trench

6 of 12
  cable cover tiles, supply and laying of                    
bricks every 3 meters
a Per Kilometer=0.2 hrX1000   200 20 400.00 8,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter
c Bricks Approx cost Rs.15,000   1 1 15,000.00 15,000.00          
            28,000.00 72,833. 44,833.00 This 728,330.00 364,165.00
00 activity can
be speed-
up and
even up to
2 Km per
day also
can be
done.
2 Laying of 3 core, 185sqmm 11 kv in DWC                    
HDPE pipes
  0.2 hour per meter including laying of                    
warning tapes
  cable cover tiles                    
a Per Kilometer=1.0X1000   1000 100 400.00 40,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter
                  Cable to be    
pulled in
between the
route in
HDPE pipes
and will take
time.
            45,000.00 76,667. 31,667.00 Prior 766,670.00 383,335.00
00 planning
required.
3 Laying of 33 KV, 3 core, 300sqmm in cable                    
duct including civil works
  1.0 hour per meter including laying of                    
warning tapes
  cable cover tiles                    

7 of 12
a Per Kilometer=1.0X1000   1000 100 400.00 40,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter
c Civil works approx/KM Rs.10,000   1 1 10,000.00 10,000.00     Cable to be    
pulled in
between
the route
in HDPE
pipes and
will take
time.
            55,000.00 97,750. 42,750.00 Prior 977,500.00 488,750.00
00 planning
required.
                  Civil works    
are
involved.
IV Laying and testing from RMU outgoing to                    
HT service metering cubical point
1 Laying of 3 core, 185sqmm, 11 kv cable in                    
open trench
  cable cover tiles, supply and laying of                    
bricks every 3 meters
a Per Kilometer=0.2 hrX1000   200 20 400.00 8,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter
c Bricks Approx cost Rs.15,000   1 1 15,000.00 15,000.00          
            28,000.00 72,833. 44,833.00 This activity 728,330.00 364,165.00
can be speed-
00
up and even
up to 2 Km
per day also
can be done.
                       
2 Laying of 3 core, 185sqmm 11 kv in DWC                    
HDPE pipes
  0.2 hour per meter including laying of                    
warning tapes
  cable cover tiles                    

8 of 12
a Per Kilometer=1.0X1000   1000 100 400.00 40,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter
                  Cable to be    
pulled in
between
the route
in HDPE
pipes and
will take
time.
            45,000.00 76,667. 31,667.00 Prior 766,670.00 383,335.00
00 planning
required.
3 Laying of 33 KV, 3 core, 300sqmm in cable                    
duct including civil works
  1.0 hour per meter including laying of                    
warning tapes
  cable cover tiles                    
a Per Kilometer=1.0X1000   1000 100 400.00 40,000.00          
b over heads and Supervision @ .05 hr per   50 5 1,000.00 5,000.00          
meter
c Civil works approx/KM Rs.10,000   1 1 10,000.00 10,000.00     Cable to be    
pulled in
between the
route in HDPE
pipes and will
take time.
V RCC Cable trench                    
1 Supply and erection of cable trench of Rmtr     6,000.00 6,000.00 8,302.0 2,302.00   83,020.00 41,510.00
size 1M Wx 1.2M D x 1M L 0

                     
Excavation
2.1 Excavation of all soils by Machine except Cu.m       100.00 150 50.00   1,500,000.00 750,000.00
haard rock and morrum
2.2 Excavation of all soils by Manpower Cu.m                  
except haard rock and morrum

9 of 12
  1 person per day=5 running meter cum 4 0.4 400.00 160.00 307 147.00   3,070,000.00 1,535,000.00
2 persons per day= 5 cubic meter
one digging, one banking & clearing soil
20 manhours per day for 5 cum
4 hours per cum

2.3 Excavation in soft rock , BT roads and Cu.m 4 0.4 400.00 160.00 230 70.00   2,300,000.00 1,150,000.00
Maccadam surfaces,PCC and hard
murrum

3.3 Excavation by using manpower hard Cu.m 6 0.8 400.00 320.00 438 118.00      
morrum and soft rock
4.3 In hard rock excavation shall be done by Cu.m 20 2 400.00 800.00 1246 446      
chiseling and by pneumatic drilling
  In concrete roads excavation shall be Cu.m 12 1.2 400.00 480.00 636 156      
done by chiseling and by pneumatic
drilling
3 Filling with clean sand in excavated trench Cu.m 2 0.2 400.00 80.00 150 70      
in layers
3 Back filling the cable trench and restoring Cu.m 1 0.2 400.00 80.00 123 43      
up to thre ground level with avilable earth
                       
  Total Manpower required=200 minimum     200 400.00 80,000.00          
per day
  Foremen/Mastry one for 20 people=10     10 500.00 5,000.00          
per day
  Supervisor one for work location=5 per     5 1,000.00 5,000.00          
day
  Vehicles and Overheads and water and     200 50.00 10,000.00          
safety per day
  Materials and consumables Lumpsum per     1 20,000.00 20,000.00          
day

  Equipment Lumpsum (compressor     10 4,000.00 40,000.00     Not    


+tractor) @ 4,000/- per day required
every day,
should be
10 of 12
subcontrac
t on target
basis.
  TOTAL per day         160,000.00          
  Per month     30   4,800,000.00       30,156,990.00 15,078,495.00

11 of 12

You might also like