Professional Documents
Culture Documents
1 SCOPE OF WORK................................................................................................................................. 1
2 OBJECT AND LIMIT OF SUPPLY........................................................................................................ 1
3 SERVICE GATE..................................................................................................................................... 4
3.1 GENERAL......................................................................................................................................................4
3.2 DESIGN DATA........................................................................................................................................... 4
3.3 DESIGN CRITERIA......................................................................................................................................7
3.4 STRUCTURAL DETAILS..............................................................................................................................8
3.4.1 Gate Leaf............................................................................................................................................8
3.4.2 Gate Seals...........................................................................................................................................8
3.4.3 Sealing Surfaces.................................................................................................................................9
3.5 ANCHOR RODS AND PLATE.......................................................................................................................9
3.6 GATES POSITION INDICATORS...................................................................................................................9
3.7 LADDERS, PLATFORMS, HANDRAILS.........................................................................................................9
3.8 OPERATING SYSTEM................................................................................................................................10
3.9 DOGGING DEVICE....................................................................................................................................11
3.10 FASTENERS..............................................................................................................................................11
3.11 STAINLESS STEEL PLATES.......................................................................................................................11
3.12 CONTROL.................................................................................................................................................11
3.13 ELECTRICAL EQUIPMENT.........................................................................................................................12
3.14 MAINTENANCE........................................................................................................................................12
3.15 TOLERANCES...........................................................................................................................................12
3.16 TESTS......................................................................................................................................................12
3.16.1 Shop Tests.........................................................................................................................................12
3.16.2 Site Tests...........................................................................................................................................13
3.17 PROTECTIVE COATINGS...........................................................................................................................13
3.18 SPARE PARTS AND SPECIAL TOOLS.........................................................................................................13
3.18.1 Spare Parts.......................................................................................................................................13
3.18.2 Special Tools....................................................................................................................................14
4 MAINTENANCE GATES (STOPLOGS).............................................................................................. 15
4.1 GENERAL.................................................................................................................................................15
4.2 DESIGN DATA......................................................................................................................................... 15
4.3 DESIGN CRITERIA....................................................................................................................................16
4.4 STRUCTURAL DETAILS............................................................................................................................17
4.4.1 Gate Leaf..........................................................................................................................................17
4.4.2 Gate Seals.........................................................................................................................................17
4.4.3 Sealing Surfaces...............................................................................................................................18
4.5 ANCHOR RODS AND PLATE.....................................................................................................................18
4.6 GATES POSITION INDICATORS.................................................................................................................18
4.7 LADDERS, PLATFORMS, HANDRAILS.......................................................................................................18
4.8 OPERATING SYSTEM................................................................................................................................19
4.9 DOGGING DEVICE....................................................................................................................................20
4.10 FASTENERS..............................................................................................................................................20
4.11 STAINLESS STEEL PLATES.......................................................................................................................20
4.12 CONTROL.................................................................................................................................................20
4.13 ELECTRICAL EQUIPMENT.........................................................................................................................21
4.14 MAINTENANCE........................................................................................................................................21
4.15 TOLERANCES...........................................................................................................................................21
4.16 TESTS......................................................................................................................................................21
4.16.1 Shop Tests.........................................................................................................................................21
4.16.2 Site Tests...........................................................................................................................................22
4.17 PROTECTIVE COATINGS...........................................................................................................................22
i
4.18 SPARE PARTS AND SPECIAL TOOLS...........................................................................................................22
4.18.1 Spare Parts.......................................................................................................................................22
4.18.2 Special Tools....................................................................................................................................22
5 TRASHRACKS..................................................................................................................................... 24
5.1 GENERAL.................................................................................................................................................24
5.2 DESIGN DATA......................................................................................................................................... 24
5.3 DESIGN CRITERIA....................................................................................................................................24
5.4 STRUCTURAL DETAILS............................................................................................................................25
5.4.1 Trashrack Bars.................................................................................................................................25
5.4.2 Panels and Frames...........................................................................................................................25
5.4.3 Manual Racker.................................................................................................................................26
5.4.4 Embedded Parts...............................................................................................................................26
5.5 WORKSHOP AND SITE TESTS...................................................................................................................26
5.6 PROTECTIVE COATINGS...........................................................................................................................26
5.7 SPARE PARTS AND SPECIAL TOOLS.........................................................................................................26
5.7.1 Spare Parts.......................................................................................................................................26
5.7.2 Special Tools....................................................................................................................................26
6 HEADRACE PIPE & PENSTOCK....................................................................................................... 27
6.1 GENERAL.................................................................................................................................................27
6.1.1 Scope and Limits of Supply..............................................................................................................27
6.1.2 General Arrangement.......................................................................................................................28
6.1.3 Main Dimensions..............................................................................................................................28
6.1.4 Operating Conditions.......................................................................................................................28
6.1.5 Design Criteria.................................................................................................................................29
6.1.6 Materials..........................................................................................................................................30
6.1.7 Testing of Materials.........................................................................................................................31
6.1.8 Manufacturing..................................................................................................................................32
6.1.9 Tolerances........................................................................................................................................34
6.1.10 Installation.......................................................................................................................................34
6.1.11 Submittals.........................................................................................................................................36
6.2 HEADRACE PIPE AND PENSTOCK.............................................................................................................37
6.3 BIFURCATION..........................................................................................................................................37
6.4 BENDS.....................................................................................................................................................38
6.5 BUTT STRAPS..........................................................................................................................................38
6.6 STIFFENER RINGS....................................................................................................................................38
6.7 THRUST RINGS........................................................................................................................................38
6.8 SEEPAGE RINGS.......................................................................................................................................38
6.9 MANHOLE AND FLANGES........................................................................................................................38
6.10 TRANSITION PIECE..................................................................................................................................39
6.11 SADDLE AND WEAR PLATES...................................................................................................................39
6.12 EXPANSION JOINTS..................................................................................................................................39
6.13 AIR RELEASE AND ANTI-VACUUM VALVE................................................................................................39
6.14 SHUT-OFF VALVE.....................................................................................................................................39
6.15 FLUSHING VALVE AND PIPES...................................................................................................................39
6.16 PROTECTION AGAINST CORROSION..........................................................................................................40
6.17 SPARE PARTS.......................................................................................................................................... 40
6.18 SHOP ASSEMBLY AND TESTS...................................................................................................................40
6.18.1 Shop Assembly..................................................................................................................................40
6.18.2 Records.............................................................................................................................................40
6.18.3 Shop Tests.........................................................................................................................................40
6.19 SITE TESTS..............................................................................................................................................41
6.19.1 Inspection after Installation.............................................................................................................41
6.19.2 Painting Inspection..........................................................................................................................41
6.19.3 Pressure Test....................................................................................................................................41
6.19.4 Handling and Placing......................................................................................................................41
6.19.5 Field Welding...................................................................................................................................42
ii
iii
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
1 SCOPE OF WORK
The present Specifications cover the minimum technical requirements and limits for the design, supply,
manufacture, shop testing, painting, shipping, storage at site, installation and site testing of
Hydromechanical and Electrical Equipment to be installed in the 6.2 MW Lower Jogmai Khola
Hydropower Project.
The supply shall include the design, material supply, manufacture, shop testing, painting, delivery to the
site, installation, field testing, commissioning, acceptance testing and placing into successful operation
of all structure and equipment hereinafter outlined.
The Employer's personnel training and spare parts supply are also included.
The supply shall conform to the General Technical Specifications, unless otherwise specified.
The description of the items of the supply in the following paragraphs does not limit the responsibility
of the Contractor to perform all works and to supply all accessories, within the contractual limits, in
order for the same to be complete and ready for operation.
b) One (1) set of maintenance stoplog complete with seals, fittings, hoist, all necessary
appurtenances for the operation of the gates and related fixed parts, all as detailed in Chapter 4.
a) Two (2) sets of vertical fixed wheel gates for intake (Inlet), comprising of structural steel
complete sections with guide rollers, seals, hoists (Screw spindle), related fixed parts including
seal paths and embedded parts, as detailed in Chapter 3.
b) One (1) set of vertical fixed wheel gates for intake (Outlet), comprising of structural steel
complete sections with guide rollers, seals, hoists (Screw spindle), related fixed parts including
seal paths and embedded parts, as detailed in Chapter 3.
c) One (1) set of trash passage gate comprising of gate leaf, seals, guide rollers, gate embedded
parts, manual screw spindle hoist, fittings and connections necessary for operation of the gate
and stems and supports, all as detailed in Chapter 3.
d) One (1) set of steel Trashrack for Intake, complete with frames and bars, related fixed parts and
embedded parts, connections; all as detailed in Chapter 5.
e) Two (2) sets of gravel trap flushing gates (one flushing and one stoplog) comprising of gate
leaf, seals, guide rollers, gate embedded parts, hoists (screw spindle), fittings and connections
necessary for operation of the gate and stems and supports, all as detailed in Chapter 3.
f) Two (2) sets of settling basin inlet gates comprising of gate leaf, seals, guide rollers, gate
embedded parts, hoists (screw spindle), fittings and connections necessary for operation of the
gate and stems and supports, all as detailed in Chapter 3.
Page 1 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
g) Four (4) set of settling basin outlet gates comprising of gate leaf, seals, guide rollers, gate
embedded parts, manual screw spindle hoists (screw spindle), fittings and connections
necessary for operation of the gate and stems and supports, all as detailed in Chapter 3.
h) Two (2) sets of vertical lift gates for settling basin flushing structure comprising of structural
steel complete sections with guide rollers, seals, hoists (screw spindle), related fixed parts
including seal paths and embedded parts, as detailed in Chapter 3.
i) One (1) set of vertical lift gates for headrace pipe inlet structure comprising of structural steel
complete sections with guide rollers, seals, hoists (screw spindle), related fixed parts including
seal paths and embedded parts, as detailed in Chapter 3.
j) Two (2) sets of maintenance stoplogs for settling basin flushing gates complete with seals,
hoists (screw spindle), guide rollers, two (2) sets of fixed parts including seal paths and sill
beam, as detailed in Chapter 4.
k) Two (2) set of steel Trashrack before Canal, complete with frames and bars, related fixed parts
and embedded parts, connections; all as detailed in Chapter 5.
l) One (1) set of steel Trashrack before Headrace pipe, complete with frames and bars, related
fixed parts and embedded parts, connections; all as detailed in Chapter 5.
a) One (1) lot of headrace pipes complete with straight pipe, bends, stiffeners, anchor bars flanges
with manholes, air-relief valves with pipe, flushing valve with pipe, expansion joints and
necessary accessories all as detailed in Chapter 6.
b) One (1) lot of surge tank/pipe complete with all the necessary accessories all as detailed in
Chapter 6.
c) One (1) lot of penstock complete with straight pipe, bends, expansion joint, manholes,
stiffeners, anchor bars and necessary accessories all as detailed in Chapter 6.
Tailrace Equipment
a) Two (2) sets of vertical lift gates comprising of structural steel complete sections with guide
rollers, seals, hoists (Screw spindle), manual control system, related fixed parts including seal
paths and embedded parts, as detailed in Chapter 3.
Page 2 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
3 SERVICE GATE
3.1 General
This section covers the Special Technical Specifications for the following equipment and its
accessories, spare parts and special tools.
The gate shall be of vertical lift type, complete with seals, guide rollers, fixed parts, fittings and
connections necessary for operation as well as electrical power-driven screws and manual drive wheel.
The gates shall be completely assembled in the shop and inspected by the Employer/Employer’s
Representative prior to shipment.
Intake Gate
- Type Vertical lift
- Opening dimensioning (w x h) 2.4 m x 2.0 m (Inlet)
2.0 m x 2.11 m (outlet)
- Number of
Gates (set) Three (3) (Two Inlet and One Outlet)
Fixed parts (set) Three (3)
- Elevation of
Sill beam (m.a.s.l) 646.0/646.72 (Inlet/Outlet)
Design Water Level (m.a.s.l.) 652/651
Design Head (m) 6/4.3
Operating platform (m.a.s.l) 653.3
- Operating system Manual screw spindle hoist
Page 3 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
Page 4 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
Tailrace Gate
- Type Vertical lift
- Opening dimensioning (w x h) 1.5 m x 2.15 m
- Number of
Gates (set) Two (2)
Fixed parts (set) Two (2)
- Elevation of
Sill beam (m.a.s.l) 514.2
Page 5 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
The structures shall be designed in accordance with relevant IS standard or equivalent. All gates shall
be considered to be fully opened or fully closed or partially opened and capable of passing partial
operation without undue vibration or cavitation. They should be designed to operate against the
maximum flow under the design head. The opening and closing forces shall prevail against the resisting
forces with a safety factor of 1.5.
In general, the loading shall be divided into 3 different classes according to the following typical
examples.
- Normal loading;
Loading due to dead loads
Hydrostatic loads, from vacuum to maximum
External pressure
Hydrodynamic loads, guaranteed pressure rise
Environmental loads with a return period of 50 years
Dynamic loads due to normal operation
Vibrational loads caused by flowing water or by ordinary operation
- Unusual loading;
Sediment loading
Unsymmetrical loading due to uneven frictional forces
- Extreme loading;
Earthquake loading
Loading due to maximum floods
Vacuum in steel linings
Loading due to transportation and erection
Emergency situations
The various loads shall for normal loading be combined if physically possible, and the most severe shall
determine the design conditions. At unusual and extreme loading, each unusual or extreme load case
shall be combined with the most severe normal loading. Unusual or extreme load cases need not be
combined.
Regarding power screws, the rods and nuts shall be made of high strength alloyed steel with minimum
possibility of corrosion and bronze respectively as well as the rods shall be checked against buckling
forces.
An impact factor 2 shall be applied to all connecting parts on the gate bodies and power drivers,
connections between segments (if any) as well as dogging devices. Moreover, the case of the design
shall be considered as normal case.
In the normal case, intake gate and maintenance gates/stoplogs for under sluice shall be kept in the
gates' parking (above the opening) by related which and power screw without the use of any mechanical
devices whereas the service gate for settling basin shall be closed.
Page 6 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
The gates shall be manufactured of welded steel sections consisting of horizontal beams and vertical
stiffeners that shall support a continuous watertight surface (skin plate). The thickness shall be
increased by 2 mm to allow for corrosion. The minimum skin plate thickness shall not be less than 12
mm.
The maximum admissible deflection of main girders shall not exceed 1/800 of the maximum distance
between supports. Butt weld joints shall be designed for a weld efficiency of 0.9.
The gates shall be sealed along the sill by a square edge knife edge natural rubber elastomeric seal and
UHMW seals at the sides. Special precautions shall be taken to ensure the seals are adequately
restrained to prevent excessive displacement due to the water pressure. The seals shall also not-unduly
interfere with the operation of the gates. The bottom edge of the skin plate shall be machined to make a
near watertight contact with the sill beam.
Seals shall be in continuous lengths and all corners shall be separate moldings. Where joints are
necessary, these shall be oblique, rather than perpendicular, to the line of contact and a minimum of 300
mm from a corner. All joints shall be hot vulcanized or joined by an appropriate compound such that
these have a tensile strength of not less than 80% of the tensile strength of un-spliced material.
All seals shall be secured to the gate with stainless steel bolts, nuts and washer to facilitate their
replacement. Bolt spacing shall not exceed 100 mm. The seals shall be guarded so as to protect them
from possible damage due to timber of other objects becoming jammed between the seals and the fixed
parts.
When the gate is in the position, the seals compressing shall be at least 3 mm for side and top seals and
5 mm for bottom seal.
Holes for seal bolts in the gate leaf and seal clamp bars shall be drilled in the workshop.
After inspection, the seals shall be match-marked with the gate element and when the gate is prepared
for shipment, the seals shall be removed and packed separately.
Contractor shall not apply rubber cement to the joint in the shop but shall provide sufficient cement in
suitable airtight containers for application by others during Site assembly.
The gate shall be guided by the channels extending from the sill beam up to the gates parking position
in order to prevent the gate from vibrating during operation.
The rails/channels and sealing surface shall be supplied complete with anchor plates and bolts and other
accessories including the welding plates to be embedded in the first stage concrete. Stud bolts to be
welded to the welding pads during erection shall be provided with double nuts and washers for precise
Page 7 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
alignment of the rails. The welding plates shall be provided with two drilled holes to facilitate nailing to
formworks.
The supply shall include all distribution plates having a thickness of not less than 15 mm.
The dimensions of the plates shall be such that stresses in the concrete will be less than 60 kg/cm 2.
- handgrips and steps of both sides of the gate body over its whole height for inspection
and adjustment of the seals and guide rollers.
To protect the gates’ hoisting system from rains, direct heat from sun etc., the structural steel sheds with
colour CGI roofing shall be designed, fabricated, supply and erection as necessary or as proposed by the
bidder or as directed by the Employer/Employer’s Representative. The shed shall be made from steel
pipe trusses and posts. The main pipe post of the truss shall not be less than 60 mm in diameter and
properly anchor in concrete slab of hoisting deck. The other members of steel pipe truss also shall not
be less than 40 mm in diameter. The colour CGI sheet for roofing shall be of 22 gauge thick. The design
of the steel structural shed shall be subjected to be approved by the Employer/Employer’s
Representative.
The forces resulting from the gate or stoplog being jammed against the guides, on a single side or on
both sides simultaneously, and the maximum hoist motor torque transferred to both lifting points or
entirely to one lifting point, as appropriate.
Effects of hoist brake shall be taken as 150% full operating motor torque.
If an accurate estimate of stalled motor torque is not available, take its value to be 275% rated motor
torque.
Design shall be based on the most adverse possible combination of forces acting on gates and stoplogs.
Page 8 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
The diameter of the handle shall be approximate 600 millimeters and manual handling force shall be
less than 10-kilogram force per operator.
The handle shall be so installed that the handle center is located at the range of 600 to 800-millimeter-
high on the concrete deck. The handle shall be furnished with suitable locking device for locking the
handle while the handle is out of work
In the power-driven screws, the power of an electrical motor shall be transferred to main gearbox.
Main screw and nut located in the gearbox shall be made of alloy steel and bronze respectively. The
buckling of the screws shall be checked, and buckling safety 5 in the elastic range and 3 in the inelastic
range shall be considered.
Considering power screw middle supports (not more than 3 meter in distance), is mandatory.
The screw shall be connected to the gates by means of stainless-steel pin and nut. The gate shall be
operated separately through related screw.
An emergency hand wheel shall be designed for operating the gate in emergency condition.
3.10 Fasteners
All bolts for field assembly of structural joints and assemblies shall be ASTM A325M, and all other
bolts and studs shall be ASTM E449 except as otherwise specified herein.
All fasteners for field jointing shall be supplied 10 % in excess of actual requirements. Stainless steel
bolting shall have suitable anti-galling compound applied to the threads at times of installation.
Page 9 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
3.12 Control
All gates (except under sluice) are operated manually from hoist deck.
The under sluice gates operation shall be local from the relevant local control panels installed adjacent
the gates.
The gate shall be equipped with open/closed limit and torque switches with contacts to send remote
signals to the Control Board.
The control of each gate shall be done by means of push buttons. The local control panels shall be
provided with the following controls:
In addition to one mechanical position indicator on the gate body, the gate shall also be equipped with
an opening degree indicator on the local control panel with transducer to send a remote signal to the
Control Board; the signal shall be continuous (4-20 mA) type.
For the motors and all other devices, required AC supply shall be provided through local control panels
which shall be fed from the sub-distribution board installed in the gates platform.
The power and control panels shall comply with the requirements given in the General Technical
Specifications.
3.14 Maintenance
Design of the gates and operating systems shall make easy operation and maintenance.
The Contractor shall also provide all required accessories for gate disassembling and maintenance in the
site without using any devices supplied by others.
3.15 Tolerances
The dimensions’ tolerances of the gate shall be according to DIN EN 13920 and IS Code 4622:2003
ANNEX H. The possible parallelism error between lower and upper sides, as well as between side
edges, shall be fully compensated by the deformation of the rubber sealing. The sealing surfaces of the
side and top seals, when assembled on the finished gate element shall not depart from a true plane
surface by more than ±1 mm.
All points on the sill sealing face shall lie between two planes parallel to the horizontal plane at the
theoretical sill elevation with ±1 mm.
Page 10 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
3.16 Tests
3.16.1 Shop Tests
a) Mechanical Tests
Gate shall be shop assembled for inspection and test.
The assembly shall be checked and tested for dimensional accuracy, tolerance, operation and to control
that the requirements of these Specifications are met. Any error or omission discovered shall be
corrected.
Moveable elements shall be stroked through several operating cycles to assure smooth, non-binding
operation.
b) Tests on Welding
All main welds shall be ultrasonically tested. At least 20% of welds shall be radio graphically examined
according to the procedures indicated in the General Technical Specifications. In any case, all butt
welds of skin plates and T- Joints shall be 100% radio graphed.
Dye penetration tests on the sliding surfaces shall be carried out in workshop. No cross-joint welds shall
be allowed at all cases.
After being installed and completely wired, the gates shall be inspected and operated to check
clearances and accuracy of alignment and smoothness of operation.
All motions of the completely assembled gates shall be thoroughly observed for smooth and free
operation and from any mechanical interference, proper alignment of all running parts and freedom
from vibration. Electrical continuity of all circuits and servicing of all points requiring lubrication shall
be completely inspected.
The Contractor shall take care of the spare parts for all of the Gates during the entire Defect Liability
Period of the Project. Then-after, upon mutual understanding with the Employer, the Contractor will
provide the minimum amount of basic spares that will be required for a year period based on the
experience during the operation & maintenance period. All spare parts shall be interchangeable and of
Page 11 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
the same material and workmanship and shall meet the same requirements as of the corresponding
original parts.
Eyebolts, lifting lugs, shackles, slings and any other special equipment required for handling during
shipment to site or during erection of the gate shall be furnished.
Page 12 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
4.1 General
This Section covers the Special Technical Specifications for the following Equipment and its
accessories, spare parts and special tools.
- One (1) set of stoplog complete with one (1) set of fixed part for the Under sluice
- One (1) set of stoplog complete with one (1) set of fixed part for the gravel flushing
- Two (2) sets of maintenance gate (stoplogs) complete with two (2) sets of fixed parts for the
settling basin flushing structure
Each gate shall be complete with seals, guide rollers, embedded parts, fittings, operation wheel etc.
Page 13 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
In general, the loading shall be divided into 3 different classes according to the following typical
examples.
- Normal loading;
Loading due to dead loads
Hydrostatic loads, from vacuum to maximum
External pressure
Hydrodynamic loads, guaranteed pressure rise
Environmental loads with a return period of 50 years
Dynamic loads due to normal operation
Vibrational loads caused by flowing water or by ordinary operation
- Unusual loading;
Sediment loading
Unsymmetrical loading due to uneven frictional forces
- Extreme loading;
Earthquake loading
Loading due to maximum floods
Vacuum in steel linings
Loading due to transportation and erection
Emergency situations
The various loads shall for normal loading be combined if physically possible, and the most severe shall
determine the design conditions. At unusual and extreme loading, each unusual or extreme load case
shall be combined with the most severe normal loading. Unusual or extreme load cases need not be
combined.
Regarding power screws, the rods and nuts shall be made of high strength alloyed steel with minimum
possibility of corrosion and bronze respectively as well as the rods shall be checked against buckling
forces.
An impact factor 2 shall be applied to all connecting parts on the gate bodies and power drivers,
connections between segments (if any) as well as dogging devices. Moreover, the case of the design
shall be considered as normal case.
In the normal case, intake gate and maintenance gates/stoplogs for under sluice shall be kept in the
gates' parking (above the opening) by related which and power screw without the use of any mechanical
devices whereas the service gate for settling basin shall be closed.
Page 14 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
The gates shall be manufactured of welded steel sections consisting of horizontal beams and vertical
stiffeners that shall support a continuous watertight surface (skin plate). The thickness shall be
increased by 2 mm to allow for corrosion. The minimum skin plate thickness shall not be less than 12
mm.
The maximum admissible deflection of main girders shall not exceed 1/800 of the maximum distance
between supports. Butt weld joints shall be designed for a weld efficiency of 0.9.
The gates shall be sealed along the sill by a square edge knife edge natural rubber elastomeric seal and
UHMW seals at the sides. Special precautions shall be taken to ensure the seals are adequately
restrained to prevent excessive displacement due to the water pressure. The seals shall also not-unduly
interfere with the operation of the gates. The bottom edge of the skin plate shall be machined to make a
near watertight contact with the sill beam.
Seals shall be in continuous lengths and all corners shall be separate moldings. Where joints are
necessary, these shall be oblique, rather than perpendicular, to the line of contact and a minimum of 300
mm from a corner. All joints shall be hot vulcanized or joined by an appropriate compound such that
these have a tensile strength of not less than 80% of the tensile strength of un-spliced material.
All seals shall be secured to the gate with stainless steel bolts, nuts and washer to facilitate their
replacement. Bolt spacing shall not exceed 100 mm. The seals shall be guarded so as to protect them
from possible damage due to timber of other objects becoming jammed between the seals and the fixed
parts.
When the gate is in the position, the seals compressing shall be at least 3 mm for side and top seals and
5 mm for bottom seal.
Holes for seal bolts in the gate leaf and seal clamp bars shall be drilled in the workshop.
After inspection, the seals shall be match-marked with the gate element and when the gate is prepared
for shipment, the seals shall be removed and packed separately.
Contractor shall not apply rubber cement to the joint in the shop but shall provide sufficient cement in
suitable airtight containers for application by others during Site assembly.
The gate shall be guided by the channels extending from the sill beam up to the gates parking position
in order to prevent the gate from vibrating during operation.
The rails/channels and sealing surface shall be supplied complete with anchor plates and bolts and other
accessories including the welding plates to be embedded in the first stage concrete. Stud bolts to be
welded to the welding pads during erection shall be provided with double nuts and washers for precise
alignment of the rails. The welding plates shall be provided with two drilled holes to facilitate nailing to
formworks.
Page 15 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
The supply shall include all distribution plates having a thickness of not less than 15 mm.
The dimensions of the plates shall be such that stresses in the concrete will be less than 60 kg/cm 2.
- handgrips and steps of both sides of the gate body over its whole height for inspection
and adjustment of the seals and guide rollers.
To protect the gates’ hoisting system from rains, direct heat from sun etc., the structural steel sheds with
colour CGI roofing shall be designed, fabricated, supply and erection as necessary or as proposed by the
bidder or as directed by the Employer/Employer’s Representative. The shed shall be made from steel
pipe trusses and posts. The main pipe post of the truss shall not be less than 60 mm in diameter and
properly anchor in concrete slab of hoisting deck. The other members of steel pipe truss also shall not
be less than 40 mm in diameter. The colour CGI sheet for roofing shall be of 18 gauge thick. The design
of the steel structural shed shall be subjected to be approved by the Employer/Employer’s
Representative.
The forces resulting from the gate or stoplog being jammed against the guides, on a single side or on
both sides simultaneously, and the maximum hoist motor torque transferred to both lifting points or
entirely to one lifting point, as appropriate.
Effects of hoist brake shall be taken as 150% full operating motor torque.
If an accurate estimate of stalled motor torque is not available, take its value to be 275% rated motor
torque.
Design shall be based on the most adverse possible combination of forces acting on gates and stoplogs.
(i) Overload conditions
All loads imposed during raising the gate due to the overload hoist or gate jammed condition.
Page 16 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
The diameter of the handle shall be approximate 600 millimeters and manual handling force shall be
less than 10 kilograms force per operator.
The handle shall be so installed that the handle center is located at the range of 600 to 800 millimeters
high on the concrete deck. The handle shall be furnished with suitable locking device for locking the
handle while the handle is out of work
In the power-driven screws, the power of an electrical motor shall be transferred to main gearbox.
Main screw and nut located in the gearbox shall be made of alloy steel and bronze respectively. The
buckling of the screws shall be checked, and buckling safety 5 in the elastic range and 3 in the inelastic
range shall be considered.
Considering power screw middle supports (not more than 3 meter in distance), is mandatory.
The screw shall be connected to the gates by means of stainless-steel pin and nut. The gate shall be
operated separately through related screw.
An emergency hand wheel shall be designed for operating the gate in emergency condition.
4.10 Fasteners
All bolts for field assembly of structural joints and assemblies shall be ASTM A325M, and all other
bolts and studs shall be ASTM E449 except as otherwise specified herein.
All fasteners for field jointing shall be supplied 10 % in excess of actual requirements. Stainless steel
bolting shall have suitable anti-galling compound applied to the threads at times of installation.
4.12 Control
Page 17 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
All gates (except under sluice) are operated manually from hoist deck.
The under-sluice gates operation shall be local from the relevant local control panels installed adjacent
the gates.
The gate shall be equipped with open/closed limit and torque switches with contacts to send remote
signals to the Control Board.
The control of each gate shall be done by means of push buttons. The local control panels shall be
provided with the following controls:
In addition to one mechanical position indicator on the gate body, the gate shall also be equipped with
an opening degree indicator on the local control panel with transducer to send a remote signal to the
Control Board; the signal shall be continuous (4-20 mA) type.
For the motors and all other devices, required AC supply shall be provided through local control panels
which shall be fed from the sub-distribution board installed in the gates platform.
The power and control panels shall comply with the requirements given in the General Technical
Specifications.
4.14 Maintenance
Design of the gates and operating systems shall make easy operation and maintenance.
The Contractor shall also provide all required accessories for gate disassembling and maintenance in the
site without using any devices supplied by others.
4.15 Tolerances
The dimensions’ tolerances of the gate shall be according to DIN EN 13920 and IS Code 4622:2003
ANNEX H. The possible parallelism error between lower and upper sides, as well as between side
edges, shall be fully compensated by the deformation of the rubber sealing. The sealing surfaces of the
side and top seals, when assembled on the finished gate element shall not depart from a true plane
surface by more than ±1 mm.
All points on the sill sealing face shall lie between two planes parallel to the horizontal plane at the
theoretical sill elevation with ±1 mm.
Page 18 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
4.16 Tests
4.16.1 Shop Tests
a) Mechanical Tests
The assembly shall be checked and tested for dimensional accuracy, tolerance, operation and to control
that the requirements of these Specifications are met. Any error or omission discovered shall be
corrected.
Moveable elements shall be stroked through several operating cycles to assure smooth, non-binding
operation.
b) Tests on Welding
All main welds shall be ultrasonically tested. At least 20% of welds shall be radio graphically examined
according to the procedures indicated in the General Technical Specifications. In any case, all butt
welds of skin plates and T- Joints shall be 100% radio graphed.
Dye penetration tests on the sliding surfaces shall be carried out in workshop. No cross-joint welds shall
be allowed at all cases.
After being installed and completely wired, the gates shall be inspected and operated to check
clearances and accuracy of alignment and smoothness of operation.
All motions of the completely assembled gates shall be thoroughly observed for smooth and free
operation and from any mechanical interference, proper alignment of all running parts and freedom
from vibration. Electrical continuity of all circuits and servicing of all points requiring lubrication shall
be completely inspected.
Page 19 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
the same material and workmanship and shall meet the same requirements as of the corresponding
original parts.
Eyebolts, lifting lugs, shackles, slings and any other special equipment required for handling during
shipment to site or during erection of the gate shall be furnished.
Page 20 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
5 TRASHRACKS
5.1 General
This Section covers the Special Technical Specifications for the supply trashracks and related
accessories for the intake, approach culvert inlet and Headrace pipe inlet.
The trashracks will be installed to prevent debris, which could damage the downstream equipment.
The trashrack structures and bars shall be calculated in accordance with relevant IS standards and
Erbisti recommendations. The resulting thickness for bars shall be increased by 2 mm to allow for
corrosion. Minimum thickness of bar shall not be less than 12 mm including 2 mm for corrosion. The
trashracks shall be including equally spaced bars which installed parallel to the stream lines. The
Page 21 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
Trashrack shall be exempt from vibration during all operating conditions and shall be sufficiently sturdy
to limit as much as possible any deformation.
Each trashrack shall be completely fabricated and shipped ready for erection.
The structural designs of the trashracks shall be done for a 6 m head differential as a normal loading
case or as specified in the design data. The design of the trashracks shall take into account the
uniformly distributed load under which the max admissible deflection shall not exceed 1/600 of the max
distance between supports.
The trashracks vibrations shall be limited by adequate device of connections made of stainless steel and
checked in both directions, parallel with flow and perpendicular to flow. For each bar, the ratio of
inherent frequency to frequency of exciting force by Karman's vortex shall be at least 2.5.
The trashrack shall be of welded structure consisting of a series of equally spaced vertical bars, top and
sill beams, fastening bolts, spacer pipes. All bar elements shall be rigidly fixed on the supporting beams
to prevent vibration.
The allowable stress of the bars shall be determined from the following formula for the lateral buckling
check:
Page 22 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
Each panel shall be shop assembled and its dimensions checked at workshop and after the erection at
Site.
The Contractor shall take care of the spare parts for all of the Gates during the entire Defect Liability
Period of the Project. Then-after, upon mutual understanding with the Employer, the Contractor will
provide the minimum amount of basic spares that will be required for a year period based on the
experience during the operation & maintenance period. All spare parts shall be interchangeable and of
the same material and workmanship and shall meet the same requirements as of the corresponding
original parts.
Eyebolts, lifting lugs, shackles, slings and any other special equipment required for handling during
shipment to Site or during erection of the trashrack shall be furnished.
Page 23 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
6.1 General
The headrace and penstock pipe according to its hydraulic function and definition includes the whole
water conduit from head pond to the turbine inlet valves at various locations as described in Ch 6.1.3.
The penstock may mean headrace (low pressure pipe as shown in the drawings) and penstock pipes
(high pressure pipe as shown in the drawings) wherever applicable.
- The low pressure steel headrace pipes with accessories as shown in the drawings.
- The steel penstock pipes up to extension piece of turbine inlet valves including bifurcation and both
branch pipes.
The low pressure headrace pipe shall be complete with straight pipes, bent or curved pipes, anchor
rings, thrust rings, stiffeners, anchor bars, wear plate, saddle plate, dismantling flanges with manholes,
air-relief valve with pipe, flushing valve with pipe, expansion joints and all other necessary
components. The penstock shall be complete with straight pipes, bell-mouth, bent or curved pipes,
reducing pipes, bifurcation, anchor rings, thrust rings, stiffeners, anchor bars, expansion joint, manhole,
wear plate, saddle plate and all other necessary components including connection to the adjacent
components. The scope of supply shall also include all fastenings, fixtures, holding-down arrangements,
support structures, construction of steel foundations for all erection and welding equipment, injection
facilities and stiffeners, required for transport and erection.
The Contractor shall also provide the lifting tackles, cranes, and winches required for transport and
offloading, as well as all transport vehicles for transportation from fabricating plant to the place of
installation.
The Contractor's services shall also include all controls and material tests with supply of the respective
certificates, ultrasonic and radiographic tests of the welds, including the provision of all equipment
required for these tests.
- All excavation works, anchor and saddle support civil works, backfilling, concrete work including
contact grouting (if required) is included in Civil Lot but alignment, anchoring, welding and
anticorrosive protection is part of Hydro-mechanical (HM) Contractor.
- All equipment necessary for transport, fabrication and erection of the penstock and steel headrace
pipe components has to be provided and maintained by the HM Contractor.
To Lot 4 - EM Contractor
- At both branches of the bifurcated penstock, the finished and drilled connection flanges on the
penstock for the turbine inlet valves (of diameter 1.0 m) and for each individual bypass and drain pipe
(internal diameter 100 mm) have to be provided by the HM Contractor according to the dimensions
given by and agreed with the EM Contractor. After the connection flanges in the penstock branches,
all other connection pipes, valves, bolts and seals are included and to be provided by the EM
Contractor.
Page 24 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
Headrace Pipe
- Inside diameter of headrace pipe 1.8 m
- Length of headrace pipe 2900.5 m
Surge Pipe
-Inside diameter of surge pipe 3.0 m
-Length of surge pipe 55.2 m
Penstock
- Inside diameter of penstock up to bifurcation 1.65 m
- Inside diameter of branch pipe up to turbine inlet valves 1.0 m
- Length of penstock up to bifurcation approximately 443 m
*Note: Length of penstock pipe and the Headrace Pipe may be extended/reduced upon finalization of
location of surge shaft/pipe. This length of pipe will be subject to changes. Likewise, sand/rocktrap
will also be located and length of pipe from the sand/rock trap will be varied accordingly.
6.1.4.1 Pressure
Depending on the different headwater levels in the head pond, the pressure losses in the waterways, the
internal pressure acting in the headrace pipe at different locations will vary.
Depending on the different headwater levels in the head pond, the pressure losses in the waterways, and
load variations of the generating units, the internal pressure acting in the penstock at different locations
will vary.
Upsurge and downsurge level in the surge tank/pipe subject to vary according to final location of the
surge tank/pipe.
Discharge
- Rated discharge of the power plant : 5.78 m³/s
- All static and dynamic hydraulic loads due to design water head.
- All loads due to dead weight and friction forces.
- Seismic, temperature, wind loads, and
- Other loads
Page 25 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
The Contractor shall design the headrace, penstock and bifurcation to resist both internal and external
pressures as defined below.
Unless otherwise specified, designs and calculations shall be carried out in accordance with the
"Recommendations for the Design, Manufacture and Erection of Steel Penstocks of welded
Construction for Hydro-Electric installations" issued by the European Committee for Boiler making and
kindred steel structures (CECT - Recommendations), and this Specification which shall prevail in case
of discrepancies unless otherwise directed by the Employer’s Representative.
The mechanical properties of the weld material and the welded joint shall be equal or better than those
of the base material in order to achieve better weld efficiency.
The low pressure headrace pipe and high pressure penstocks shall be designed, taking no account of any
rock support, for the following cases:
The penstock shall be capable of resisting the external pressure of 0.5 bar at the time of dewatering.
Moreover, vertical and horizontal acceleration shall be combined in the most unfavorable position.
Design accelerations of 0.23 g horizontal and 0.115 g vertical for solid structures on rock.
Axial Forces
The headrace and penstock pipe shall be capable to resist the axial forces as follows.
- All forces resulting from the unbalanced water-loads.
- Bending stress due to continuous beam of the headrace/penstock.
- Bending stress due to restraining the pipe shell expansion by ring girder supports.
- Stress due to axial component by internal pressure at the reducing pipes, and the main inlet valves.
- Stress due to the thrust rings.
- Stress due to centrifugal force and unbalanced force at the bend pipes.
- Stress due to temperature variation of the headrace pipe and penstock.
- Stress due to Poisson's effect.
- Stress caused during hydrostatic test at Site.
Page 26 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
When erection, welding and other inspections of the headrace pipe and penstock pipes have been
completed in accordance with these specifications, the required sections of headrace pipe and penstock
pipes will be encased by concrete by the Lot Civil Contractor.
The Contractor of Hydro-mechanical Works shall supply and install sufficient interior bracings in
addition to that required for welding to maintain the roundness within the specified tolerances until the
encasement is completed in the required section. The Contractor shall supply and install sufficient
exterior bracings and anchor bands and bars to resist the loading due to the placing of concrete and or
backfilling by excavated materials. Particular care shall be given.
6.1.6 Materials
All steel for headrace, penstock and surge pipe shall be fine grained, fully normalized and stress
relieved, not subject to brittle fracture, non-ageing, and highly wieldable. The steel properties shall be
equivalent to or better than IS2062 E250 Br.
For subordinate structures and for small quantities, steels shall be ST-37-2 according to DIN 17100 or
Equivalent.
Steel material of other standards than those specified above shall be equivalent. However, prior
approval of the Employer/Employer’s Representative shall be obtained.
Allowable stresses in the steel shall be one third of minimum tensile stress or half of yield stress
whichever is less.
Each plate shall have the respective marks of Customer Name, Grade, Heat/ Plate No., Size in mm,
Quality, etc. Every certificates will have the similar information of plates such as Heat/ Plate No., Size
in mm, steel quality, rolling mill and signature of quality control expert.
Automatic welding processes in the shop will be permitted provided they produce a weld of the
specified quality. In addition to the above-specified tests, the quality of electrodes shall be tested
periodically during welding operations.
Page 27 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
Ten (10) % of all circumferential butt welds shall be x-ray tested. Should any defect be found, the
welding seam shall be one hundred (100) % x-ray tested. The quality of radiographic pictures shall
comply with DIN 54 109 and DIN 54 111.
Objectionable defects discovered in welds shall be prepared in accordance with the following
procedures:
(a) A weld line length in 30 cm to both sides from the defect portion shall be radio graphed to
examine whether there are objectionable defects therein or not.
(b) If there is any defect found therein, all weld lines of the concerned joint shall be radiographed
and defective welds discovered shall be repaired accordingly.
(c) If there is no defect found therein, the defective portion only shall be repaired.
(d) Objectionable defects in welds shall be chipped or flame or arc-gouged to show sound metal
and the defects re-welded. Welds that have been repaired shall be 100% radiographed again.
The Contractor shall furnish all equipment, films and labor necessary to perform the radiographic tests.
All original films of the radiographs shall become the property of the Employer. The Contractor shall
provide proper storage for its radiographs and shall store and preserve all radiographs of welding,
whether the welding is accepted or rejected.
6.1.8 Manufacturing
6.1.8.1 General
The steel materials to be used for the steel conduits, pipes, penstocks, bifurcations, linings and other
components of this contract shall be clearly marked for easy identification.
If the Contractor proposes to deliver any material to the Site and partly or fully fabricate components in
a site fabrication shop before moving into final position, such site fabrication shop complete with all
equipment, lighting, heating, power, staffing, etc., shall be provided by the Contractor. Approval by the
Employer’s Representative for these proposals shall be provided before the work is commenced. The
Contractor shall be solely responsible for the whole of the temporary work, machinery and appliances,
even though these may have been approved by the Employer’s Representative.
All weld joints shall be dressed smooth and the maximum reinforcement shall be limited to the required
tolerances on the inside of the headrace pipe and penstock pipes. On the outside of the headrace pipe,
bifurcation and penstock, welds shall be (where possible) dressed free of all fluxes and scale and
smooth finished to the extent necessary to allow radiographic and/or ultrasonic examination.
The orientation of the place for fabrication shall be such that the final direction of rolling is placed
circumferentially. No stamping or groove marking on the steel "T" other than indications for cutting
lines for fabrication purpose shall be allowed.
Page 28 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
Bending of plates shall be performed by cold working as a rule. If bending is to be made by hot
working, the Contractor shall obtain the prior approval of the Employer’s Representative of the
temperature control procedures.
(e) Preheating
When preheating is part of an approved welding procedure, weld joints shall be preheated in accordance
with the kind of steel material and plate thickness. Maximum inter-pass temperature of preheating shall
be 200°C and preheating area shall be over a distance of more than four times of plate thickness for
each side from the welding joints. If welding work is made under the condition of ambient temperature
less than 5°C, steel materials on weld joints shall also be preheated even though application of
preheating is not required due to the kind and thickness of the steel materials under normal welding
condition. The relations between the carbon equivalent and the preheating temperature in cases of
manual welding shall be as follows:
Pre-Heating Temperature for Low Hydrogen
Carbon Equivalent (Ceq) % Plate Thickness(mm)
Welding Rods (°C)
0 - 0.28 0- 100
0.28 - 0.38 0- 25
0.28 - 0.38 25-100 40-60
0.38 - 0.48 0- 25 40-60
0.38 -0.48 25-100 80-100
more than 0.48 0- 100 100-150
Page 29 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
Note: Ceq (%) = C+1/6 Mn + 1/24 Si + 1/40 Ni + 1/5 Cr + 1/4 Mo + 1/14 V and Cu, P, etc., could be
added as necessary.
6.1.9 Tolerances
All tolerances shall be indicated on the Contractor's drawings.
The dimensions, especially clearances and fits, (ISO-Recommendation R 286) which are essential for
proper function of work shall be carefully checked in an approved manner.
The Contractor shall be responsible for ensuring that all equipment complies with the specified
tolerance requirements on completion of installation and under the full range of design operating
conditions.
Allowable tolerances which differ in part from CECT recommendations are listed below:
- External circumference deviation from the theoretical 0.1%.
- Deviation "c" from the circular form measured with a circular gauge having a length of r/2.c
= (r/1000) + (20/s) + 0.5
- Ovality: d/2d = 0.0025 * (dmax – dmin)/(dmax + dmin)
(dmax and dmin shall be measured at the same cross section)
- Lengths of the steel pipe 5 mm
- Deviation (U) from a straight line over length of tube "e"U< 2e/1000
- Displacement (Vz) of plates at longitudinal seams
Vz< (s/50) + 1
- Displacement (Vr) of plates at circular seams
Vr< (s/50) + 2 + s/2
Page 30 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
6.1.10 Installation
The installation work shall include the erection, field welding, painting and inspection of the penstock
and headrace pipe sections in accordance with the final approved drawings and erection manual. The
Contractor shall carefully proceed with the installation in accordance with the schedule and instructions
from the Employer’s Representative, since the installation of the penstock/headrace pipe is required to
keep pace with the progress of other related works. Prior to installation, the Contractor shall prepare a
work plan for the order, method and schedule of installation with careful coordination with the other
Contractors, and shall obtain the approval of the Employer’s Representative for the work plan.
6.1.10.1Erection Equipment
The equipment required for installation shall include, but not be limited to the following:
- Suitable lifting and handling equipment provided in the site storage areas and at the point of
installation of the equipment,
- A winch or winches complete with controls, cable and guide pulleys etc., for lowering and
positioning of equipment,
- Electrical connectors and cables for connection to the temporary power supply,
- Welding equipment, including transformers and other accessories such as dark glasses,
gloves, etc.
- Furnaces and drying ovens for drying the electrodes,
- Grinding and cutting tools.
- X-ray and ultrasonic testing equipment,
- Field telephone if required,
- Temporary lighting where necessary,
- Vehicles for personnel.
In order to maintain the accuracy of roundness of the conduit sections within the tolerance specified,
internal spiders or other suitable devices shall be provided in the sections immediately upon completion
of fabrication to prevent any deformation that may take place during transportation, installation,
concrete placing and contact grouting, etc.
6.1.10.3Field Welding
Welding at the installation site shall be performed manually, in accordance with the requirements of
Clause 4.1.8.3 and according to the method as specified herein. All site joints shall be inspected and
approved by the Employer’s Representative before the joint is made. If a gap is found to exist which
would prejudice the effectiveness of the weld, the edges of the plate shall be corrected before the joint is
made. Each joint shall be completed as soon as possible after the Employer’s Representative has given
his approval.
Matching of field welding girth joints shall be carried out with spiders and pad plates or tack weld jigs.
In no case, steel conduit sections shall be forcibly jointed. During the welding operations, the centers
and distances between edge preparations shall be maintained at their proper positions.
All weld joints shall be dressed smooth and the inside surface welds shall be dressed flush. On the
outside of the steel conduits welds shall be dressed free of all flux and scale and smooth to the extent
necessary to allow radiographic examination.
After field welding, ultrasonic or radiographic examination of all in situ welds shall be carried out as
specified and any defects found repaired as outlined in Clause 6.1.7.
Page 31 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
6.1.10.5Painting
The headrace pipe, surge pipe, penstock and bifurcation shall be painted after erection and testing of the
welding seams. Those surfaces against which concrete will be placed shall be thoroughly clean and free
of all rust, mill-scale, oil, paint or other loose or deleterious matter. The Contractor shall take any steps
necessary to ensure that no significant rusting or pitting of these surfaces occurs during transport,
storage and erection.
At the transition zone between concrete and steel linings all steel surfaces in contact with concrete shall
be carefully sandblasted and coated with two layers of zinc-rich primer at least up to 20 cm distance
from the borderline concrete-steel-air.
6.1.11 Submittals
The Contractor shall submit manufacturing and fabrication materials’ list, product data and shop
drawings, and installation procedures for the following:
- Structural and pressure vessel steel, each type.
- High-strength bolts, each type, including nuts and washers.
- Temporary supports and concrete embedment.
- Protective Coatings, including primers for factory and field application, surface preparation
materials and methods, and coating procedures.
- Manufacturing and erection procedures including weld joint locations and field make-up joint
locations. Fabrication drawings not showing all weld joint locations; longitudinal and
circumferential, joints on bends, grouting plugs etc. will be rejected.
- Applicable non-destructive testing procedures proposed.
- Welding Procedure Specifications (WPS), Procedure Qualification Records (PQR), Record of
Welding Operator Qualification Tests, and material control program, including electrode
control.
For each steel tube and for the bifurcation the Contractor shall provide the following information:
- Number of plates used for the tube.
- Records relating to tests performed on plates and on the completed tube.
- Theoretical weight of the complete tube or bifurcation in total.
- Measured dimensions including plate thickness, tube length and circumference.
- Four perpendicular diameters, one of which is measured through the longitudinal weld,
deviations from roundness template.
- Radiographs.
- Results of ultrasonic tests.
- Results of water pressure tests, if any.
- Thermal treatments.
- Special remarks.
- Number and dates of the relevant reports.
Each certificate shall show in sketch form the sequence of the welds, the position of the radiographs,
repair locations, etc.
Page 32 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
The dimensions of the anchor blocks of reinforced concrete shown in the drawings for the horizontal
and vertical bends and support piers shall be understood as reference only and shall be determined by
the Contractor for the definite design.
An inclined pressure pipe has been provided at the end of headrace pipe to accommodate the surge
within the pipe. Extreme values of surge level have been calculated by running hytran transient analysis
software. Time of valve closure and opening has been taken as 10sec. Similarly, the time of valve
opening has also been taken as 10sec. Diameter of pipe has been taken as 3m.
Penstock pipe is used to convey the water from headrace pipe to the turbines. It is a surface steel
structure just after the headrace pipe. Considering same assumptions as in the headrace pipe, the
optimised diameter of penstock pipe is 1.8m but the thickness varies from 8mm to 16mm. Total length
of the penstock pipe is 430m.
6.3 Bifurcation
Both bifurcation branches 1.0 m diameter shall be provided by the Contractor at the ends with:
- Finished connection flanges according to the dimensions required for connection of the turbine inlet
valves. From the flange on the bifurcation branches, the E/M Contractor will supply the connection
bolts and seals.
- Two flanged connections with an inside diameter of 100 mm for connecting the bypass and drain
pipe. The adjoining flanges, pipe work, connection valves, bolts and seals from these flanges will be
supplied by the EM Contractor.
The design of the bifurcation shall ensure minimum hydraulic losses and exclude any oscillation of
pressure or flow downstream of the bifurcation, which may have an incidence on the operation of the
turbines. The Contractor shall submit drawings showing the proposed design of the bifurcation in detail.
The reinforcement rib of the bifurcation shall be arranged internally. No external reinforcement of the
bifurcation will be permitted.
Information about the results of hydraulic tests, head loss coefficient, etc. shall be attached.
6.4 Bends
Bends are fabricated from mitered sections of pipe. The mitered pipe sections must be joined by full
penetration, single or double welded butt joints.
The radius of bends must be between 3-5 times pipe diameters. The maximum deflection angle of the
mitered segment must be between 5-10 degrees.
Page 33 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
The axial thrust forces due to the unbalanced water-loads and due to closure of main valves shall be
transmitted to the penstock, for which the thrust rings shall be provided. The exact location and design
of thrust rings shall be coordinated with the design of the civil works.
Saddle Plate and Wear Plate at saddle supports and penstock holding down rings at saddle shall be
provided as per the instruction of the Engineer. Also, HDPE sheet shall be inserted in between saddle
and wear plate. The steel rod support shall be provided at bends to anchor the penstock against thrust.
Such supports shall be placed by the contractor and confirm line and level as provided in alignment
sheet before installation of the plates. The materials for the base plates shall be IS 2062 E250 BR or
equivalent national & international standards.
The suitable expansion joints shall be designed and fabricated to absorb the thermal stresses due to
temperature difference in penstock. The expansion joints shall be designed to withstand the pressure as
described in Clause 6.1.4. The expansion joints shall be designed to 100% water tight.
Air release valve shall be, having intake cross sectional area not less than 300 mm, PN 6 double acting
type with epoxy coated ductile cast iron (or similar) body and stainless steel internal parts with
protected cage.
Page 34 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
Flushing pipe for sand/rocktrap shall be mild steel of grade similar to the penstock pipe. Flushing Valve
house, trench excavation and backfilling shall be designed and constructed by the Contractor, the price
of which is included in the cost.
In total four coats shall be applied with a total dry film thickness of not less than 290 µm.
Surfaces to be covered by compressible wrapping shall be treated for application of the compressible
wrapping as required by the manufacturer of the wrapping material.
All major parts shall be inspected by the Employer’s Representative for welding and surface
imperfections such as undercut welds, stamps, clamp or chisel marks, surface pitting in the plate and
other similar surface irregularities. Faulty material and workmanship shall be made good by the
Contractor to the Employer’s entire satisfaction. Material which shows defects subsequent to erection
will be rejected and the Contractor notified.
6.18.2 Records
The Contractor shall submit full information about the quality control system for fabrication including
data report forms and records of welders, welding tests and radiographic and other non-destructive
examination of welded joints, all to be accessible for inspection by the Employer’s Representative.
Page 35 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
A record shall be maintained of the location of all imperfections and the corrective measures taken to
effect repairs.
Pinhole Inspection
The dried films on the pipe shells shall be checked by holiday detector for pinholes at any time after
painting work is finished.
Thickness Inspection
The thickness of dried films shall be measured by elco-meter after painting work is finished, to a check
point in every one square meter, or the area where the Employer’s Representative so requests.
Objectionable defects in the welds found during the test shall be chipped or flame or arc-gouged to
show sound metal and the defects re-welded. Welds have been repaired shall be pressure tested again
until the Engineer's satisfaction. A record of the actual result of test shall be submitted to the Engineer.
External structural steel supports and facilities for anchorage shall be supplied and installed to prevent
displacement or uplift of the penstock sections due to buoyancy or external forces that may occur
during placing of concrete. The supports will be concreted into place with the penstocks. Inserted bars
for supports where required in the primary concrete by the Contractor will be supplied and embedded
by the other Contractor in locations as shown on the approved drawings prepared by the Contractor.
Page 36 of 41
Asian Hydropower Ltd. Contract Document for Lot 3 : Hydromechanical Works
Lower Jogmai Khola Hydropower Project (6.2 MW) Volume 2, Section II : Special Technical Specifications
In no case, penstock sections shall be forcibly jointed. During the welding operations, the centers and
distances between edge preparations shall be maintained at their proper positions.
Field welded joints shall be preheated in accordance with kind of steel materials and plate thickness.
However, maximum Inter pass temperature shall be 200 degrees C and preheated area shall be a
distance of more than four times as plate thickness from the welding edges. Suitable cover shall be
provided over the pipe shells to protect the water fallen on the welded joints for all working times for
welding. Equipment for drying the welding rods shall be provided to ensure that the welders used dry
welding rods at all times.
After field welding, girth welds in length including T joint shall be RT/UT or 100% test by ultrasound
method or as instructed by the Engineer and the welding defects repaired.
Page 37 of 41