No. Doc.

:
KLARIFIKASI TEKNIK Tgl. Terbit :
Revisi :
UBJOM Indramayu REHABILITASI MECHANICAL SAMPLER TT2 Halaman :

SPESIFIKASI PEKERJAAN YANG DIMINTA PENAWARAN

RINCIAN PEKERJAAN PT MAHARDHIKA RAYA HASIL


NO NILAI
YANG DIMINTAKAN PENAWARANNYA SEBELUM KLARIFIKASI SESUDAH KLARIFIKASI (M/TM)

MATERIAL

- Sampling Methodology : ASTM D7430 or ISO - spesifikasi motor tidak mencantumkan dust proof/ IP 65 sesuai
- Electric Motor with brake system kesepakatan pada saat anwizing lelang.
- Power : 15 Kw 380V 50Hz 1450rpm
- IP 65 dust proof insulation for motor
Coal Automatic Primary Sampler - Gear Box : Ratio Gear Box
1 Type Primary Sampler : Cross Belt - Heavy – Duty Construction
- Cover Thickness plate : 5.0 mm ( Mild Steel )
- Scoop Taker : 5.0 mm Thickness ( SS 304 )
- Structural frame : UNP 120 mm
- Rotating Scoop and Flexible wiper
- Peep hole with fiber glass/acrylic 50cmX50cmX0,5cm

- automatic operation Mode : Forward to Crusher and to Original sample for sizing measurement - IP 55 tidak sesuai permintaan BA anwizing dan spesifikasi kabel
- Controlled by PLC & HMI Touchscreen kontrol standar hazardous environment tidak tercantum sesuai
- Belt Width : 500 mm kesepakatan pada saat anwizing lelang.
- Length : 4 meters ( 4000 mm )
- Power : 3 KW
- IP 65 dust proof insulation for motor
2 Feeder Conveyor with Cover
- Belt Capacity : 5 T/H
- included with original sample box and damper
- 2 way Hydroulic/motorize damper
- Chute thicness : 5 mm (mild steel)
- Sampling box : 1m X 1m X 1m
- Box thicness : 5mm (mild steel)
- Type : Hammer Crusher - spesifikasi motor tidak mencantumkan dust proof/ IP 65 sesuai
- Power source : Electromotor, 3 phase 15 Kw, 220 – 380 V, 50 Hz. kesepakatan pada saat anwizing lelang.
- IP 65 dust proof insulation for motor
3 Crusher - Hammer Crusher : Two pieces, made of hardened Special Steel
- Input Size : 0 - 200mm
- Output : 10.0 mm ASTM or adjustable base on screen
- Capacity : up to 5000 kg/h
- Type sampler: cross belt - spesifikasi motor tidak mencantumkan dust proof/ IP 65 sesuai
- Power : 3 Kw 380V 50Hz 1450rpm kesepakatan pada saat anwizing lelang.
- IP 65 dust proof insulation for motor
- Cover Thickness plate : 3.0 mm ( Mild Steel )
- Scoop Taker : 3.0 mm Thickness ( SS 304 )
- Structural frame : UNP 120 mm
- Rotating Scoop and Flexible wiper
4 Secondary Sampler system with sampler, feeder and crusher - Peep hole with fiber glass/acrylic 25cmX25cmX0,5cm
- Feeder power : 3 kw
- Feeder with cover thicness 3mm
- Belt Width : 500 mm
- Belt Capacity : 3 T/H
- Power source crusher: Electromotor, 3 phase 11 Kw 220 – 380 V, 50 Hz
- Capacity: up to 3000Kg/H
- Output size 4,75 mm
- Diameter Input rotary tube divider : 200 mm - spesifikasi motor tidak mencantumkan dust proof/ IP 65 sesuai
- Diameter rotary tube divider : 650 mm kesepakatan pada saat anwizing lelang.
- Diameter output sample : 150 mm x 150mm
5 Type : Rotary Tube Divider (RTD) - Diameter reject sample : 200 mm
- Plate : Stainless Steel 304
- Height : 810 mm
- Length : 925 mm
-- Power : 2 KW 220 – 380 50Hz - spesifikasi motot tidak mencantumkan dust proof/ IP 65 sesuai
- Canister Sample Qty : 6 pcs kesepakatan pada saat anwizing lelang.
- Capacity Canister : 20 – 30 kg
6 Automatic Canister Sampler Collector - Material Canister : Stainless steel 304
- Automatic filling container canister each lot sample
- Omron limit switch
- Controlled by PLC
- Height : 12 meters (as height transfer tower 2 elevation 3) - spesifikasi motor tidak mencantumkan dust proof/ IP 65 sesuai
- Center to Center Capacity : up to 5 Ton kesepakatan pada saat anwizing lelang.
7 Reject Bucket Elevator - Motor Capacity : 5 KW
- Elevator belt 140 mm, 3.6 Bucket/meter
- Mild Steel Bucket type. Speed 2 - 3.5 m/s Material : Coal
- Motor type : screw 3 phase, 50Hz, 380 VAC, IP65 dust proof - spesifikasi motor tidak mencantumkan dust proof/ IP 65 sesuai
- 2 way hydroulic/motorize damper kesepakatan pada saat anwizing lelang.
- Power motor : 8 Kw
8 Reject screw Feeder
- Coal canal and chute: width and lenght same as existing.
- Chute and material thicness: 5mm
- Control automatic from control panel
- Omron CP - Series Programmable Logic -IP 55 tidak sesuai permintaan BA anwizing
- Controller
- Omron Digital Timer
- Touch Screen Operation 7 inch
- CONTROLLER FEATURE :Capable controlled for control 2 Cross belt Primary Sample,
Secondary Sampler, feeder conveyor, reject conveyor/Bucket Elevator, crusher & Canister.
- Operating Mode : Automatic Increment or
- Manual operation, Stand By position
- Automatic Increment & Timer Calculation
- Upgradable with standard Methodology
- Diagnostic system, Interlock for fail / error equipment or fail operation
- Emergency Stop
- Indicator : Motor ON/OF, Scoop Running
- Manual Check (standalone operation) primary sampler, crusher, feeder & reject conveyor,
9 Electrical Controller & Operation Panel canister Powerful for maintenance equipment
- Primary Cutter Parking Position
- Calibration
- Canister position calibration
- Automatic increment counter
- Sample Canister adjust setting
- Error Alarm
- Belt conveyor C2 speed indicator
- Belt conveyor C2 running indicator
- Analog Indicator : Pilot Lamp for Power
- Pole, Automatic On, Automatic Off
- Analog Ampere Meter
- Plugging alarm
- kabel standar harsh environment (kabel kontrol dan kabel power)
- panel IP 65 branded non lokal (ex: weidmuller, rittal, hanger, etc)
- tidak mencantumkan spesifikasi panel dust proof dan spesifikasi
- Dreddger on primary crusher and scondary crusher
kabel kontrol standar hazardous environment sesuai kesepakatan
10 Anti plugging sistem - Dredger with electrical device system
pada saat anwizing lelang.
- Sensor anti plugging with contact system.
- tidak tersedia engineering tool (laptop dan program PLC)
SESUAI
Deck, structural support and grating on mechanical sampler TT 2 - All structural included suporrting material, grating and deck size and material is same as existing.
11
and name tag equipment - tagging ring dan name tag menggunakan stainless steel
- tidak tersedia didalam dokumen penawaran
Computer set industrial standar for HMI on control building and - Status operasi mechanical sampler dibuatkan ke dalam interface operasi CCR CHCB
12
Engineering tools set for programming logic control PLC - Laptop set included OS full license, Toolkit PLC full licence and office full licence

- Peralatan angkat angkut - tidak tersedia didalam dokumen penawaran


- Direksi kit
- Air dan udara servis
- Panel box
- Material consumable
- Scafolding
13 Tool And Consumable
- Mesin las
- kawat las *sesuai WPS yang disahkan
- Forklift
- Special tools dan tools set
- Chain block & sling
- Scafolding
JASA

1. Collect data mechanical sampler (manual instruction, as built drawing, parameter operasi)

2. Approval drawing meliputi dan tidak terbatas pada :


- Assembly drawing
- Spare part drawing
1 Tahap Engineering - Maintenance access drawing
- Logic drawing
- Schematic drawing
- Fire protection drawing (piping dan wiring)

3. Approval prosedur assembly dan diassembly on site

1. Tahap fabrikasi dilaksanakan di workshop manufacture pihak pelaksana


2 Tahap Fabrikasi
2. Pembuatan part mechanical coal sampler sesuai approval drawing

1. Pembongkaran primary cutter beserta pondasi yang terpasang pada belt conveyor.
2. Pembongkaran mechanical coal sampler total.
3 Pembongkaran mechanical sampler
3. Pembongkaran panel kontrol dan panel listrik mechanical coal sampler.
4. Pembongkaran pondasi struktur supporting pada mechanical coal sampler.

1. Repair pondasi meliputi proses chipping dan rekondisi pada permukaan yang sudah rusak
2. Injection grouting untuk memperbaiki pondasi yang retak dan untuk menyatukan beton lama
4 Tahap Repair Pondasi mechanical coal sampler
dengan beton baru
3. Jarak pedestal harus sesuai eksisting
1. Instalasi first flatform dan feeder flatform mechanical coal sampler.
2. Instalasi pondasi primary cutter C2A dan C2B dan pemasangan primary cutter.
3. Instalasi mechanical coal sampler total.
4. Pemasangan lubang intip pada primary cutter, crusher, scondary crusher dan canister.
5 Instalasi mechanical coal sampler baru 5. Instalasi power dan wiring mechanical coal sampler
6. Instalasi local control panel mechanical coal sampler.
7. Integrasi mechanical sampler TT2 dengan HMI CHCB.
8. Integrasi keseluruhan sistem mechanical coal sampler.
9. Pelaksanaan reliability run selama 14 (empat belas) hari.
1. pihak pelaksanan wajib melakuka Bias Test peralatan oleh pihak yang berkompetensi melakukan
biast test
6 Pelaksanaan Bias Test
2. wajib menyerahkan sertifikat Bias Test dengan standar acuan ASTM D7430-16b Part D atau
setara atas nama PT. PJB UBJOM PLTU Indramayu
1. Pemasangan connection wiring electrical dan control equipment sampai ke power room dan
local control station.
2. Bila kapasitas breaker existing di PT PJB UBJO&M Indramayu tidak mampu memikul beban
Pemasangan dan pengetesan electrical dan instrumentation
7 motor listrik pada mechanical coal sampler, maka pihak pelaksana pekerjaan harus menyediakan
wiring
breaker sendiri
3. Logic program tidak boleh di password/ dikunci tanpa sepengetahuan pihak PT. PJB UBJOM
PLTU Indramayu
1. Diikuti oleh personil Pemeliharaan Mesin 2 (2 orang), Elektrik (2 orang), Instrumentasi dan
Kontrol (2 orang), Bahan Bakar (2 orang), Operator CHCB semua shift (8 orang), Engineering (2
orang), Rendal Operasi (1 orang), Rendal Pemeliharaan (1 orang).
2. Materi yang disajikan berkenaan dengan Standar Operational Procedure (SOP), troubleshoting,
First Line Maintenance (FLM), Preventive Maintenance (PM) serta materi tentang operasi dan
8 Training Operasi dan Pemeliharaan
pemeliharaan yang berkaitan lainnya sebagai panduan penyusunan Instruksi Kerja (IK) dan
Standar Job PM.
3. Dilaksanakan di site selama 2 (dua) hari dan di perwakilan atau workshop (Class session) di luar
kota Indramayu selama 2 (dua) hari, setiap biaya yang dtimbul menjadi tanggung jawab
pelaksana pekerjaan.
1. Standar operasional prosedur
2. Fungsi dan prinsip kerja setiap peralatan
3. Spesifikasi peralatan
9 Pembuatan Instruction Manual Book Operasi dan Pemeliharaan
4. Logic control diagram
5. Wiring diagram
6. As built drawing modifikasi beserta keterangan jenis material dan dimensi secara umum
1. Mandatory dan recomended spare part serta special tools harus dibukukan dan menjadi
10 Katalog spare part dan special tools
tanggung jawab pelaksana pekerjaan.
1. Membuat dan menyampaikan form check list Commissioning untuk scope Pekerjaan Rehabilitasi
11 Pengujian & Commisioning Sistem Mechanical Sampler TT2 kepada PT. PJB dan hasilnya akan dipakai sebagai acuan
commissioning sesudah pelaksanaan pekerjaan.

1. Melakukan pendampingan pengoperasian selama 1 bulan pertama terhitung dari tanggal Berita
12 Pendampingan Pengoperasian
Acara Penyelesaian Pekerjaan (BAPP) dikeluarkan dari pihak PT PJB UBJOM PLTU Indramayu.

1. melakukan kedatangan material paling lambat 90 hari kalender


13 Waktu penyelesaian Pekerjaan
2. penyelesaian pekerjaan jasa paling lambat 70 hari kalender

ADMINISTRASI

SESUAI
Merupakan perusahaan yang mempunyai pengalaman melakukan pekerjaan instalasi mechanical
coal sampler dengan menunjukkan surat pengalaman kerja perusahaan yang disertai diskripsi
1 Pengalaman Kerja
pekerjaan diutamakan di unit pembangkit listrik (minimal pernah melakukan 2 pekerjaan dalam 5
tahun terakhir) dibuktikan oleh Berita Acara Serah Terima Pekerjaan (BASTP).

2 Sertifikat ISO dan OHSAS Memiliki sertifikat ISO 9001 dan OHSAS 18001. SESUAI

SESUAI
Mempunyai personil yang mempunyai keahlian dalam melakukan pekerjaan instalasi mechanical
3 Personil Kerja
coal sampler dengan menunjukan surat pengalaman kerja yang disertai deskripsi pekerjaan.
1. Supervisor : minimal 1 orang
Tanggung jawab : koordinasi eksternal dan internal seluruh pekerjaan, mulai dari perencanaan SESUAI
pekerjaan, perijinan (working permit), teknik, administrasi, pelaporan sampai penanggung jawab
pekerjaan.

2. Teknisi : minimal 3 orang


Tanggung jawab : eksekusi pelaksanaan pekerjaan instalasi mechanical coal sampler dan termasuk
integrasi control antara HMI, local control panel dan mechanical coal sampler.
4 Persyaratan Personil Kerja
3. Welder : minimal 1 orang (memiliki sertifikat dari Depnaker atau Migas kelas 6G yang masih
berlaku)
Tanggung jawab : eksekusi pekerjaan pengelasan.

4. Helper : minimal 4 orang


Tanggung jawab : membantu eksekusi pekerjaan lapangan.
SESUAI
5 Perijinan Perusahaan pelaksana pekerjaan memiliki SIUJK dan SBUJK
KESIMPULAN Nilai :

Non Negotiable Technical Aspec


Memenuhi :
Tidak Memenuhi : -