Professional Documents
Culture Documents
16 - Chapter 6 PDF
16 - Chapter 6 PDF
16 - Chapter 6 PDF
SIX
TRANSMISSION PRICING
6.1 Introduction
76
Chapter 6. Transmission pricing 77
Many methods have been proposed in the literature [83, 84, 87, 141] to
evaluate the costs of transmission transactions or wheeling transactions. These
methods are broadly classified as incremental or marginal cost method and
embedded cost method. Marginal cost methods involve short run marginal
cost (SRMC) and long run marginal cost (LRMC).
Postage stamp method [83] assumes that the entire transmission system is
used in the wheeling transaction irrespective of the actual transmission facilities
Chapter 6. Transmission pricing 78
which carry out the transaction i.e., the cost of wheeling is determined based
on the amount of transacted power independent of the distance or location.
This method is simple and straightforward but ignores actual system operation
thus masking the actual cost incurred by a transaction.
Contract path method [89] selects a specific continuous path between the
seller and buyer for wheeling transaction. All changes in the power flows
through the transmission facilities which are not along the contract path are
ignored. The path chosen must have “sufficient unused capacity” to carry the
amount of power to be transported. The selection of the contract is, however,
not usually based on the power flow study to identify the facilities actually
involved in the transaction. This method is simple and provides a distinct
way of settling financial liabilities to influenced parties along the contract
path. However, majority of the transacted power may actually flow through
transmission lines outside the contracted path and hence the actual operating
environment may be ignored. It overlooks the possibility of outages occurring
in the contract path, which would impose additional flows on neighboring
systems which are not parties of the contract path.
Flow based MW -mile method [88] allocates the charges of each transmission
facility to a wheeling transaction based on the extent of use of that facility
by the transaction. These allocated charges are then added up over all
Chapter 6. Transmission pricing 79
transmission facilities to evaluate the total price for using the transmission
system. The charges are determined as a function of magnitude, the path, and
the distance traveled by the transacted power. Two power flows are executed
successively, with and without wheeling, to get the changes in MW flows in
all transmission lines. This method emulates the actual system operating
conditions, insensitive to the order of wheeling transactions as each transaction
is treated separately, provides better cost signals for long and short distance
wheeling customers and encourages the economic use of the transmission
network capacity by giving a higher cost signal to transactions with several
delivery points.
In the flow based MW -mile method, the changes in power flow in each
facility, due to a transaction are multiplied by the length of each facility. This
implies that the transmission of same power over a transmission line with
long length will have more weightage over short length. But the transmission
lines may have different type of conductor with different thermal rating &
cost, leading to different weightages for the same length. This drawback can
be avoided by replacing the length of the line with the cost of the conductor.
Hence instead of multiplying the changes of power flow with length of the
line, the changes in power flow should be multiplied by its cost (i.e., average
revenue requirement per hour of the facility). With this idea, two methods
called MW -cost method and MVA-cost method have been proposed in this
chapter and applied on IEEE 30 bus system and Indian utility 62 bus system.
Pt
W Ct = T C × (6.1)
Ppeak
where
W Ct – transmission or wheeling charge for transaction ($/hr)
T C – total transmission charges ($/hr)
Pt – magnitude of transacted power (MW )
Ppeak – system peak demand (MW ).
In the contract path method, transmission service provider and the customer
agree on a fictitious path (contract path) for the transmission service. The
contract path interconnects the points of injection and receipt, although it
is defined “virtually” without power flow studies. Once the contract path
has been determined, all or a part of the transmission cost related to the
Chapter 6. Transmission pricing 81
specified path is assigned to the transaction and wheeling charges are calculated
according to the equation:
X Pt
W Ct = T Ck × (6.2)
k
Ppeak
where
W Ct – transmission or wheeling charge for transaction ($/hr)
T Ck – transmission charge of the contract path k ($/hr)
Pt – magnitude of transacted power (MW )
Ppeak – system peak demand (MW ).
The postage stamp and contract path methods are not considering the ac-
tual system operating condition for the estimation of transmission charges.
Hence the transmission charges determined using these methods provide an
incorrect economic signal to the transmission customers. Also in the power
flow based MW /MVA-mile methods, the charges for each transmission facility
to transmission transaction is allocated based on the extent of use of that
facility by these transactions. But in actual practice, the transmission lines of
same length may have different capacity & costs. Hence they have different
weightage for cost allocation. Moreover, modern power systems are facilitated
with FACTS devices to control the power flow in the system. In such cases,
the cost of these equipments cannot be so easily replaced by their equivalent
length. Most of the time, this involves some approximations which sacrifice
the accuracy of flow based mile methods. Hence it is proposed that instead of
multiplying the changes in the flow by length, it should be multiplied by its
cost i.e., the average revenue requirement per hour of the facility. This power
flow based embedded cost method may be called flow cost method with two
Chapter 6. Transmission pricing 82
sub categories:
1. MW -cost method
2. MVA-cost method.
In this method, two power flows are executed successively, with and without
the wheeling transaction T and the changes in MW flows in all transmission
line facilities are noted. The transaction cost in $/hr or |/hr for a transaction
T is given by the equation
P
C× (∆M Wf )T × Cf
f
W Ct = P P (6.3)
8760 × ( (∆M Wf )T × Cf
T f
where
W Ct – transmission or wheeling charge for transaction ($/hr or |/hr)
C – total transmission annual revenue requirement ($/yr or |/yr)
(4M Wf )T – change in real flow in facility f due to transaction T (MW )
4M Wf – real flow in facility f (MW )
Cf – Average revenue requirement per hour of the facility f ($/hr or |/hr).
It has been recognized that the use of transmission resources is best measured
by monitoring both real and reactive power. The proposed MVA-cost method
can consider both active and reactive power loading of the transmission network
during a transaction and allocate embedded cost of transmission accordingly.
In this method, two power flows are executed successively, with and without
the transaction T , & the changes in MVA flows in all transmission line facilities
are noted. The transaction cost W Ct in $/hr or |/hr for a transaction T is
given by the equation
Chapter 6. Transmission pricing 83
P
C× (∆M V Af )T × Cf
f
W Ct = P P (6.4)
8760 × ( (∆M V Af )T × Cf
T f
where
(4M V Af )T – change in MVA flow in facility f due to transaction T (MW )
4M V Af – MVA flow in facility f (MW ).
In this method, a transaction causing more reactive power loading will be
charged more than other transactions. This method is the most fair and
realistic among all the above methods including MW -cost method.
Table 6.2: Real power flows for various transactions – IEEE 30 bus system
Table 6.3: Apparent power flows for various transactions – IEEE 30 bus
system
The one line diagram of Indian utility 62 bus system is given in figure 6.1 and
G G
1 9
57 10
G 11 G
55 G
53 2
56 12
G 58 3 6
51 61 7
52 4
13 G
G 60 5
50 G
54 20 8
G G
59 14
62
15
49 48 44
G 19 18
42 43 G 16
47 46 17
G
28 23 21
G
37 39
41 25 22
G
38 45
26
24
34 35 27
40 30 29
G
33
31
G
32
36
G
the line data (Table C.1), bus data (Table C.2) and cost coefficients (Table C.3)
can be found in Appendix C. The proposed algorithm is applied on this test
system with three simultaneous bilateral (Table 6.5) and three multilateral
transactions (Table 6.6). The real and apparent power flows for the base case
and the corresponding wheeling transactions are given in Tables 6.7 and 6.8
Chapter 6. Transmission pricing 88
respectively. The wheeling costs are determined for these transactions using
the proposed methods and presented in Table 6.9. From the Table 6.9, it is
observed that the cost due to first multilateral transaction (TM 1 ) is negative
which reduces the system losses and hence favorable to the system.
Table 6.7: Real power flows for various transactions – Indian utility 62
bus system
Bus number Base
Line From To case TB1 TB2 TB3 TM 1 TM 2 TM 3
1 1 2 37.0687 63.9595 64.4487 50.1893 39.1288 43.636 47.6826
2 1 4 51.486 98.5449 99.5515 125.8505 59.3739 44.3368 55.0955
3 1 6 11.3091 10.0791 9.5946 8.1779 5.1035 21.7851 24.494
4 1 9 14.2323 17.207 17.9636 34.6257 8.1997 56.2834 18.4916
5 1 10 4.2856 14.8548 24.4393 21.8287 24.8089 17.2482 19.401
6 1 14 104.2786 74.6825 74.2683 71.6715 74.6312 117.0865 118.8432
7 2 3 369.8616 350.2154 370.2158 370.2146 345.6368 401.9628 370.2068
8 2 6 142.3408 129.5837 127.408 105.4201 142.408 158.2345 167.7058
9 3 4 440.01 440.01 440.01 440.01 415.01 454.01 440.01
10 4 5 111.2585 109.8517 109.3685 107.9327 104.9011 121.5786 24.1762
11 4 14 112.5137 109.697 109.1629 107.475 104.296 122.9178 125.3192
12 4 15 78.3005 78.3005 73.8488 91.8316 65.6285 33.4198 24.6169
13 5 6 36.2432 36.2432 32.0328 76.9296 37.7496 44.2597 58.5204
14 5 8 23.8601 23.8601 38.4868 47.1856 23.7231 19.3772 31.0821
15 6 7 103.6944 74.306 73.8939 71.3095 74.255 116.4228 108.2472
16 7 8 135.3359 136.0477 135.4083 140.2801 108.3683 110.4464 106.4975
17 11 10 23.2691 25.2026 24.4553 30.9399 14.791 9.4722 15.7156
18 11 16 21.23 20.1755 20.7957 16.0901 21.4492 25.6582 49.8932
19 12 11 23.1526 25.0586 44.3195 30.7258 14.7391 9.5299 15.9574
20 12 13 6.4277 8.2166 8.8638 14.4356 0.6986 26.1627 35.313
21 12 20 108.0546 111.7755 103.4367 110.3122 99.6976 99.2729 110.3233
22 13 14 6.4167 8.188 8.8318 14.3747 0.7666 26.4684 35.8445
23 13 17 67.7754 71.5942 64.1909 69.311 77.2569 39.2746 54.0419
24 14 15 46.2128 49.8833 42.5694 47.6416 30.4758 27.8296 32.6519
25 14 16 33.3843 31.7235 35.7383 32.3941 22.1961 11.7891 17.5429
26 14 18 21.8538 31.6014 22.9343 27.6345 27.7742 8.3207 11.8745
27 14 19 48.406 49.9756 45.9514 49.3023 59.5883 39.5207 54.0717
28 16 17 48.9258 50.4848 46.3828 49.798 60.3144 39.8368 54.6659
29 17 21 117.4578 118.7424 114.3347 118.0034 129.3558 107.2975 123.2379
30 20 23 14.83 14.83 14.83 14.83 49.83 14.83 14.83
31 21 22 118.4399 119.7619 122.3812 118.9089 86.7442 114.0443 110.5124
32 22 23 39.2409 37.3869 27.7368 38.6314 70.7848 39.766 37.1083
33 23 24 69.4892 70.0212 77.052 69.6298 69.6409 69.4892 29.5493
34 23 25 75.9831 76.3099 83.772 76.1132 80.411 75.9831 94.4214
35 24 41 11.9171 12.3328 19.5948 12.1411 16.3257 8.4415 29.9235
36 24 45 119.6669 124.3343 124.1685 114.9042 112.0177 125.1902 119.0289
37 25 26 137.4024 128.694 130.8722 152.8526 91.6192 31.304 9.861
38 25 27 252.8009 250.9469 241.2968 252.1914 284.3448 253.326 210.6683
39 25 28 51.0803 52.1308 35.2881 51.6802 67.6557 50.9269 44.1642
40 27 29 11.8575 12.277 10.5406 12.0865 16.2407 8.4022 29.6849
41 29 30 13.4565 13.6142 20.5794 13.5239 30.4525 19.5169 0.0951
42 30 31 84.4692 84.9196 91.1723 84.646 97.1149 87.7183 100.4335
43 32 31 5.5206 5.2272 5.8924 5.4103 9.7145 8.2823 23.9132
44 32 34 30.9379 28.0478 27.2211 40.1611 33.7399 4.1873 0.7871
45 32 36 4.1854 0.6704 0.5506 12.5345 5.8368 23.1312 27.6114
46 32 37 86.5403 84.9861 85.9917 85.7935 85.4244 87.2334 74.0428
47 32 46 20.9583 22.3206 21.3155 21.5194 21.8839 20.101 6.742
48 33 32 15.6077 18.3934 19.2177 6.4445 12.7485 8.9049 47.7065
49 34 33 7.3261 5.0258 6.0312 5.833 5.464 7.2729 37.9572
50 34 35 20.49 20.3557 11.0566 13.1267 16.3632 0.3657 35.1009
51 34 37 19.7714 5.1116 1.7877 39.0715 12.7052 19.7714 87.9507
52 35 32 13.4398 22.8397 21.513 4.883 13.7814 13.4398 42.6212
53 36 46 24.258 34.2689 32.967 7.4404 25.3897 27.1789 53.8372
54 37 46 187.6993 172.9184 145.9208 107.4435 180.6234 77.471 78.8233
55 38 34 43.809 53.4528 52.1067 25.7024 44.2739 57.6997 73.6161
Continued on next page
Chapter 6. Transmission pricing 90
Table 6.8: Apparent power flows for various transactions – Indian utility
62 bus system
Bus number Base
Line From To case TB1 TB2 TB3 TM 1 TM 2 TM 3
1 1 2 68.87 85.6188 86.0371 99.7378 65.3567 48.138 61.2791
2 1 4 123.5395 147.6499 148.4347 169.3182 119.4072 107.2808 117.2996
3 1 6 77.3747 94.2682 94.6917 108.5881 73.8511 54.9455 67.1961
4 1 9 88.8376 95.2839 95.6059 103.4936 88.4068 108.2538 127.8365
5 1 10 41.5067 52.0595 52.268 60.5804 39.0156 23.6566 33.7831
6 1 14 124.0184 124.6599 124.3198 129.46 117.6153 116.9524 147.417
7 2 3 128.6 127.8067 127.4373 126.5188 123.0749 135.7187 139.3455
8 2 6 37.8082 40.7656 40.6072 38.8655 41.4156 39.2968 73.6663
9 3 4 122.5043 121.4739 121.0437 119.5162 116.5227 131.8186 134.1176
10 4 5 114.9003 96.706 96.4419 94.8139 96.6732 127.359 119.6106
11 4 14 112.6255 94.4795 94.2153 92.5861 94.4467 125.0079 118.6225
12 4 15 405.1178 405.1168 405.0046 405.3271 385.8153 431.8156 407.2039
13 5 6 166.4658 168.4141 167.198 150.2358 179.1542 267.8344 287.1872
14 5 8 145.6251 143.4579 144.9945 165.8759 114.0329 76.5102 72.6001
15 6 7 440.6539 440.6535 440.6064 440.7423 416.5391 454.4854 441.5644
Continued on next page
Chapter 6. Transmission pricing 91
6.4 Conclusions
This chapter presents two new embedded cost methods for the computation of
wheeling charges. These methods are applied on IEEE 30 bus and Indian utility
62 bus systems. Simultaneous bilateral and multilateral wheeling transactions
are carried out in the test systems to compute the wheeling charges. The
obtained results of the proposed embedded methods are compared with other
embedded cost methods such as postage stamp method and contract path
method to prove their effectiveness. The proposed methods consider the actual
system operating condition and hence, are more efficient.