a. Indirect Material
b. Direct Material
c. Finished Material
d. Standard Parts
View Answer- b
_________ are the basic materials which have not undergone any conversion since their
receipt from suppliers.
a. WIP
b. Raw Material
c. Finished Parts
View Answer- b
a. Seasonal Buying
c. Scheduled Buying
d. Tender Buying
e. Speculative Buying
View Answer
a. Right Quality
b. Right Quantity
c. Right Source
d. Right Price
View Answer
a. Micro Factors
b. Macro Factors
c. Controllable Factors
View Answer
b. Macro Factors
__________ also called part lists or building lists is the document generated at the design
stage.
View Answer
Purchasing responsibilities can be divided into Buying, Clerical and ________ division.
a. Packing
b. Traffic
c. Record
d. Follow up
View Answer
b. Traffic
d. Inspection of goods
View Answer
________ is the time that elapses between issuing replenishment order and receiving the
material in stores.
a. Replenishment time
b. Lead time
c. Idle-time
View Answer
b. Lead time
_________ is the scientific technique for planning the ordering and usage of materials at
various levels of production and for monitoring the stocks during these transactions.
a. MPS
b. MRP
c. BOM
_________ is the task of buying goods of the right quality, in the right quantities, at the
right time and at the right price.
a. Supplying
b. Purchasing
c. Scrutinizing
View Answer
b. Purchasing
Procuring an item in staggering deliveries according to the delivery schedule finished to the
supplier by the buyer.
a. Seasonal Buying
c. Scheduled Buying
d. Tender Buying
e. Speculative Buying
View Answer
c. Scheduled Buying
Buying of the annual requirements of an item during its season is called _______
a. Seasonal Buying
c. Scheduled Buying
d. Tender Buying
e. Speculative Buying
View Answer
e. Speculative Buying