Professional Documents
Culture Documents
CIVWARE Supplementary Design Exercise On Urban - Water - Distribution (Reference IHE Delft) PDF
CIVWARE Supplementary Design Exercise On Urban - Water - Distribution (Reference IHE Delft) PDF
Design Exercise
case),
● x 6 or 30, which are respectively the years of the beginning and the
assignment,
● z the serial number of the particular network layout explored within
the alternative.
table/figure,
● Conclusions that suggest further steps based on the calculation
results,
● Comments that elaborate points in a wider context of the problem,
● Reading that refers to the chapters of the main text that are related to
the problem.
A2.1.1 Topography
Safi is a secondary town located in a hilly area with ground elevations
ranging between 8 and 28 msl. Figure A2.2 shows the configuration of
the terrain together with the layout of the main streets in the urban area
(dotted lines).
C4
C3
A
C1
C2
E3
B D1
F
E2
E1 D3 D2
Table A2.1. The town of Safi: surface area of the districts and sub-districts.
A 225 1.0
B 248 1.2
C1,2,3,4 186 2.0
D1,2,3,4 202 2.7
E1,2,3 144 2.9
F 115 3.3
10
Source 1
12 Factory
14
16
18
8
20
10
22
12
14
Source 2
24 16
26 28 26 24 22 20 18
200 600 1000
Figure A2.2. Topography and (m)
location of supply sources. 0 400 800
01
350
15 750 16
07 800 800
24
650
500
1050
850
800
300 60
14 0
350
03
1050 02
13 17 800 23
450
70
04 0
600
500
500
06
00
15
70
10 22
12 18
00
500
0
20 05
10
1250
1050
1100
08 21
1450
600
09
650 600
200 600 1000
11 19 20
(m)
0 400 800
1.6
1.4
1.2
1.0
pf
0.8
0.6
0.4
0.2
0.0
2 4 6 8 10 12 14 16 18 20 22 24
Figure A2.4. Consumption 1 3 5 7 9 11 13 15 17 19 21 23
pattern. Hours
Design Exercise 309
A2.2 QUESTIONS
Nodal consumptions
1.4 Calculate the average consumption for nodes 01–24
● at the beginning of the design period,
Network layout
1.5 Size the pipe diameters in the system at the beginning and the end
of the design period.
Pumping stations
1.6 For the source pumping stations, determine:
● the required duty head and duty flow,
Storage
1.8 Determine the volume of the clear water reservoir at the suction
side of the source pumping stations, at the beginning and the end of
the design period (assume ground level tanks with a bypass for
maintenance purposes).
1.9 For Alternative B only: determine the provisional location, volume
and dimensions of the balancing storage in the network at both the
beginning and the end of the design period.
Summary
1.10 Draw conclusions based on the hydraulic performance of the
system throughout the entire design period. Explain the phased
development of the system, if applied. Suggest a preference for the
A- or B-layout.
Regular operation
2.1 Propose a plan of operation for both pumping stations during regu-
lar supply conditions. Compare the manual pump operation with an
automatic operation based on the pressure in selected critical node
(or tank) in the network.
Factory supply under irregular conditions
2.2 A reliable supply and fire protection have to be provided for the
factory. Analyse the preliminary layout under the maximum con-
sumption hour conditions, if:
● a single pipe, either 15–16, 16–24 or 16–17, bursts,
3
● a requirement for fire fighting of 180 m /h at a pressure of
Cost comparisons
2.7 Calculate the investment costs of the network.
2.8 Calculate the operation and maintenance (O and M) costs of the
network.
2.9 Determine the average increase in cost per cubic meter of water, due
to the loan repayment and O and M of the system.
Summary
2.10 Summarise all the conclusions and select the final design.
Clarification:
● An exponential growth model is assumed in the demand calculations.
Conclusions:
● The population i.e. the demand will nearly double in the next 30 years.
Population (inhabitants)
Comments:
● The exponential growth model simulates a faster growth of
from the peak factors displayed in Figure A2.4. The factory demand is
added based on a 12-hour operation (1300/12 108.3 m3/h) if the
factory was in operation during the maximum/minimum consumption
hour.
Conclusions:
● From the domestic diurnal diagram, the maximum hourly peak factor
Max Min 12 4
Factory: 1300 m3/d Factors: 1.265 0.855 1.45 0.5
hour occurs at 12:00 hours due to the factory demand (combined with
the peak factor of the domestic demand of 1.45). The minimum con-
sumption hour is at 04:00 hours (peak factor 0.50 and the factory is
closed).
● By applying the direct pumping scheme (Alternative A), the maxi-
mum capacity of the first source is going to be reached in Year 7
i.e. already by the second year after being commissioned. The addi-
tional peak capacity needed from the second source is therefore:
4697.3 2506.5 2200 m3/h (see Table A2.6, column Qmax,hour).
● By applying the combined system (Alternative B), the capacity of
the first source is going to be reached in Year 21. If this capacity is
Design Exercise 315
minimum)?
● A distinction should be made between the UFW percentage and the
leakage percentage (i.e. physical loss). Part of the UFW is water that
is in the system but is not paid for, e.g. due to illegal connections or
water meter under reading. Consequently, including the entire UFW
level instead of the leakage level alone reduces the calculated pres-
sures, which eventually works as a kind of safety factor for the design.
Moreover, the UFW is often much easier to assess than its isolated
components, as this figure is reflected in the loss of revenue.
Reading:
● Chapter 2, Paragraphs 2.3 and 2.4: ‘Water demand patterns’ and
‘Water Demand calculation’.
Scenarios
The following scenarios are going to be tested while developing the
system:
Alternative A:
● Both sources 1 and 2 will be connected to the system at the beginning
of the design period because the first source alone will become
exhausted soon after the system is commissioned. By connecting the
second source immediately, the whole construction can be carried out
at once.
● The sources should have a similar capacity during regular operation of
the system. They are located on the opposite sides of the system that
allows for a network of similar pipe diameters, which is in principle a
more convenient layout for operation (in irregular situations) and for
future extensions.
● Source 1 will not exceed its maximum capacity during regular opera-
tion. Some 10–20% of the capacity will be kept as a stand-by for irreg-
ular supply (fire fighting, pipe bursts, etc.).
316 Introduction to Urban Water Distribution
Alternative B:
● Source 1 has to supply the average flow on the maximum consump-
tion day. The diurnal demand variation will therefore be satisfied from
the balancing tank.
● The balancing tank should also have provision for irregular supply
conditions.
● From the year in which it reaches its maximum capacity, the first source
will continue to operate at this capacity until the end of the design period.
● The second source should become operational in Year 21, at the latest.
If required, this source should also assist with supply during irregular
situations.
● It is assumed that the volume of the balancing tank can only be recov-
ered from the two sources (no other source in the vicinity of the tank
is available).
principles’.
● The increase factor shown in the table indicates the ratio between the
demands at the end and the beginning of the design period.
Conclusions:
● Due to different growth percentages in the various town districts, the
pattern of population (demand) distribution will change throughout
the design period. It can be observed from the table that the demands
in Nodes 02, 04–06, 08–12 and 18–23 grow faster than in the rest of
the network, shifting the demand concentration towards the south of
the town. This fact should also be taken into consideration while
deciding on the network layout.
Comments:
● Analysis of the demand distribution is an important element of the
network design. Larger pipe diameters are normally laid in, or on the
route to, the areas of higher demand.
● Phased development of the system should follow the demand
● location and capacity of the supply points and their connection to the
system,
● pipe diameters,
of the system (Year 6). The given EPANET filename is S6A1.NET and
its contents can be studied from the enclosed CD. The main components
of the system have been modelled as follows:
● [JUNCTIONS]: An average nodal consumption as shown in
supply points have been assumed to equal the ground elevations taken
from Figure A2.2.
● [DEMANDS]: The multiplier of the nodal demand has been set for the
in the southern part of the town, the connection of the first source has
been tested in Nodes 06 and 02. The pipe lengths are estimated based
on the scale of Figure A2.2: for Pipe 102–06 at 1550 m and for 102–02
at 1700 m.
● [PIPES]: The factory is connected at Node 16 (pipe length
01–16 350 m). To provide good connectivity with Source 2, via the
shortest path along route 16–17–18, this source will be connected in
Node 18 (pipe length 202–18 750 m).
● [PUMPS]: Equal-size pumping stations have been assumed at the
sources, with the following duty head and flow: Hd 50 mwc; this is
an estimate to satisfy the design pressure criteria, and Qd 230 l/s
is an estimate based on the information from Table A2.6 (at Year 6:
Qmax,day 40,106 m3/d 460 l/s). For the duty head and flow speci-
fied as a single pair of Q/H points, EPANET generates a synthetic
pump curve based on the principle: Qp (at Hp 0) equals 2 Qd,
and Hp (at Qp 0) equal to 1.33 Hd. As a result, the following
three Q/H points define the curve: 0–66.5, 230–50 and
460–0 (in l/s-mwc).
Clarification:
● The graphs show the snapshot at 12:00 hours (the maximum con-
sumption hour).
● The pipe head-loss is displayed in m/km.
● With regard to the pumping stations, the negative figures indicate the
stations.
320 Introduction to Urban Water Distribution
101 102
-42.88
15 16 3.55
2.11
07 0.01
0.67 24
281.95
3.08
8.47 5.71
03 14
5.02
02
0.72 3.47
39.14
04 23
4.10
13 3.40 17
51.04
06 0.05
0.02
49.58
11.33
3.28
10 1.76
9.09 12 18 22
73.50
30.85 30.05
05 202 616.40
08 1.54
12.33 1.09 21
8.05 18.28
09 0.20 -14.54
201
D = 222 mm 0.13
0.59
11 19 20
8.11 0.06
101 102
-43.28
Lateral pipes
Factory
01
277.18 15 16 3.55
1.75
07 0.16
1.32 24
D = 222
2.96
10.48 4.96
03 14
4.45
02
8.77 5.46
115.88
04 23
2.30
13 3.96 17
25.55
06 0.04
1.07
49.03
Main loop 10.62
1.33
10 2.49
0.16 12 18 22
15.37
32.04 30.29
05 202 623.50
08 1.87
2.09 0.16 21
Extra loop 0.59 18.74
09 0.02 -13.93
201
1.13
0.81
11 19 20
9.19 0.14
Conclusions:
● The source connection to different nodes influences the head-loss
(flow) distribution.
● The pipes with a large head-loss (greater than 5–10 m/km) imply the
should pass through the peripheral area of the town; a possible main
loop is indicated in Figure A2.5. The logic behind it is to connect both
sources and the factory with pipes that can carry additional capacity
in case of accidents in the system.
● An alternative connection of Source 1 to Node 02 shifts the resistance
towards the central part of the system; the main loop is shown in
Figure A2.6. This loop is shorter ( cheaper) but may not provide a
satisfactory distribution of water throughout the network. An extra
loop or larger lateral pipes should therefore be considered.
● Out of the two equal pumping curves selected for the pumping sta-
tions, the one at Source 2 shows a lower head (i.e. higher supply),
which is in contradiction to the initial requirement that both sources
should supply a similar capacity. The likely cause is in the higher
elevation of this pumping station compared to that in Source 1.
Consequently, the pumping station at Source 2 can be smaller than the
one at Source 1 (to be tested later).
In order to proceed, the layout from Figure A2.5 has been further
developed:
● [PIPES]: The main loop from the figure has been formed from pipes
D 400 mm,
● [PIPES]: The source connections to the system were provided with
The input file has been named S6A2.NET, with simulation results shown
in Figure A2.7.
Conclusions:
● The head-losses in most of the secondary pipes are low, suggesting
required.
● to choose a smaller loop of secondary pipes.
101 102
-37.78
D = 400 mm
Factory
01
15 16 6.10
0.16
07 0.13
0.15 24
1.91
1.45
0.70 1.53
03 14
0.51
02
3.62 1.77
3.39
04 23
0.12
13 5.74 17
4.12
06 1.64
0.32
5.68
1.49
0.00
10 0.25
3.03 12 18 22
2.96
6.78 5.43
05 202 2.97
08 0.02
1.00 3.65 21
0.73 1.56
09 3.17 -21.47
201
0.01
0.59
Loop length = 10.25 km
11 19 20
0.45 2.09
the head-loss. However, some pipes are still too large (e.g. 04–10 or
13–17).
● The lateral pipes at the northern side of the town (03–07, 14–15,
The smaller loop of the secondary pipes combined with laterals stretched
towards the ends of the system appears to be a promising concept. To
explore in addition the effects of the connection between Source 1 and
Node 02, file S6A4.NET has been created from S6A3.NET:
● by introducing connection 102–02 instead of 102–06,
101 102
-37.85
Factory
01
15 16 6.10
07 2.53
0.86 24
0.84
1.90
D = 400 mm
10.44
13.48 7.10
03 14
6.89
02
0.79
2.96 2.51
04 23
0.01
13 0.03 17
3.65
06 0.54
0.06
7.78
2.05
3.23
0.99 10 0.27 12 18 22
3.37
2.86 3.72
05 2022.97
08 3.70
6.17 2.88 21
2.54 5.09
09 3.04 -21.39
201
Loop length = 9.5 km 0.21
1.70
11 19 20
0.44 0.39
101 102
-38.17
Factory
01
1.88 15 16 6.10
07 0.68
1.88 24
1.26
12.07
14.99 8.91
03 14
3.46
02
0.82
10.72 1.66
04 23
0.02
13 0.19 17
06
8.80
D = 400 mm 7.34
0.21
3.67
0.87
0.10
4.64 10 0.22 12 18 22
2.16
2.33 11.96
05 2023.00
08 1.82
0.63 6.90 21
0.03 8.01
09 6.21 -20.98
201
Loop length = 5.1 km
0.14
0.53
11 19 20
0.45 0.00
Conclusions:
● Connection 102–02 allows further reduction of the main loop. As a
The results of calculation with these values are shown in Figures A2.11
and A2.12.
101 102
#N/A
600
15 16 300
07 100
100 24
100
300 300
300
03 14
150
02 400 400
500
04 23
400 13
300 17
06 200
400 400
400
150
200
10 400
200 12 18 22
300
400 200
05 202
600
08 150
200 200 21
150 300
09 #N/A
200
201
100
Qd = 250 l/s 100
11 Hd = 40 mwc 19 20
200 150
101 102
-47.20
Factory
01
2.48 15 16 0.75
07 2.92
3.28 24
1.99
1.32
1.11 3.11
03 14
2.93
02
1.61
4.00 1.86
04 23
0.09
13 0.01 17
2.71
06 3.89
0.49
2.75
1.72
0.71
1.26 10 0.02 12 18 22
1.28
1.27 5.75
05 2022.34
08 1.48
2.37 4.28 21
1.80 2.28
09 2.45 -29.28
201
1.10
0.27
11 19 20
2.02 2.73
101 102
0.00 0.00 43.90 Pipes: v – m/s
Nodes: p – mwc
Q1 = 346 l/s Factory
01
26.62
1.22 15 16 0.43
07 0.41
23.94 0.44 23.59 24
0.34
30.73
31.45
0.57
0.52 0.88
03 14
0.54
02
0.76 26.51
1.3932.99
0.82
35.89 23
04 0.17
13 0.04 17
0.82 32.04 38.84
06 0.76
23.95 29.75
0.41
30.84 1.00
0.41
0.32
0.43 10 0.07 12 18 22
0.56 28.30
24.51 0.67 30.73 0.93 37.27
05 2021.19
08 27.54 29.28 0.38
0.59 0.80 21
26.57 0.42 0.75
09 pmin 0.60 0.00
201
33.13
22.52
0.25
0.00 0.12
11 Q 2 = 336 l/s 19 20
22.22 0.54 0.52
27.53 30.19
Conclusions:
● As preferred, the pumping stations now work at an even capacity. The
total supply (346 336 682 l/s 2455 m3/h) equals approxi-
mately the maximum hour on the maximum consumption day at the
beginning of the design period (in Table A2.6, Qmax,hour 2452.9 m3/h
at Year 6).
● The system has been deliberately left with extra capacity at this stage
Figures A2.15 and A2.16.The total cost of the pipes in this case is
US$4,484,500.
In both cases the same pump characteristics were used as in the S6A5
layout.
Conclusions:
● All three configurations, A5, A6 and A7, provide similar hydraulic
performances during the maximum hour on the maximum consump-
tion day. However, given the pattern of the population growth and reli-
ability requirements, the S6A5 layout is anticipated to be the most
attractive one. Further development of the direct pumping alternative
is going to be based on this layout.
● The S6A6 layout is more expensive than the other two. Nevertheless,
101 102
#N/A
15 16 300
150
07 400 24
400
600
300 400
400
03 14
100
02
100 100
400
04 23
100
13 200 17
06 400
200
100
400
100
100
10 100
300 12 18 22
400
Pipes: v – m/s 200 200
05 Nodes: p – mwc 202
600
08 100
300 21
400 400 400
09 #N/A
300
Q1=346 l/s 201
400
Qd = 250 l/s 100
11Hd = 40 mwc 19 20
400 150
101 102
0.00 0.00 44.90
Pipes: v – m/s
Q1 = 340.48 l/s
Nodes: p – mwc Factory
01
26.97
15 16 0.43
0.58
07 21.83 0.04 23.94
0.52 24
1.20 27.66
31.44
0.44
0.80 0.62
03 14
0.32
02
0.10
30.24 0.38 23.02
1.12
32.98 23
04 0.04
13 0.73 17
06 1.23 30.02 37.89
0.65
35.17
0.23 pmin 20.54 27.96
1.31
0.48
0.41
10 0.06
0.57 12 18 22
1.33 25.93
22.19 0.68 29.91 0.75 37.62
05 202 1.21
08 29.39 28.52 0.60
0.73 0.47 21
28.59 0.64 0.70
09 0.00 31.21
0.41
201
25.33
0.11
0.00 0.37
Q
11 1
= 341.06 l/s
19 20
23.37 0.40 0.64
27.67 29.56
101 102
#N/A
Qd = 270 l/s
Hd = 60 mwc Factory
01
600 15 16 300
07 100 200
200 24
200
300 400
03 14 100
02
400 300
500
04 100 23
13 100 17
300
06 200
400
400
100
300
200 10 400
12 18 22
200
400 200
05 202 600
08 100
150 300 21
80 300
09 200 #N/A
201
80
Qd = 250 l/s 100
11 Hd = 40
150mwc 19 20
200
101 102
0.00 0.00 44.41 Pipes: v – m/s
Q1 = 343.08 l/s Nodes: p – mwc
Factory
01
28.17
1.21 15 16 0.43
07 0.02 0.40
0.66 23.04 25.13 24
30.57
34.43
0.61
0.78 0.60
03 14 0.03
02 0.77
1.4433.47
1.07 26.37
36.46 23
04 0.16
0.65 13 0.18 17
06 32.06 0.60 39.34
23.56 29.09
32.45 0.64
1.08
0.38
0.37
0.54 10
0.06 12 18 0.71 22
0.87
27.86 0.69
24.05 30.31 38.25
05 2021.20
08 26.49 28.90 0.55
0.56 0.52
21
25.37 0.23 0.70
09 0.69 0.00 32.35
pmin 201
25.23
0.26 0.00 0.43
Q
11 1
= 338.45 l/s
0.62 19 0.37 20
20.93 27.42 31.13
● The S6A7 layout is the cheapest but probably the least reliable. The
cost saving compared to the S6A5 alternative does not itself make this
layout more attractive. Its weak points will be illustrated during the
reliability assessment of the network.
Comments:
● While sizing pipes:
● A pipe with extremely low velocity/head-loss is a potential source
(Table A2.7).
● [DEMANDS]: The multiplier of the nodal consumption represents the
The simulation has been run with the same pump characteristics as at the
beginning of the design period. The results are shown in Figure A2.17.
330 Introduction to Urban Water Distribution
101 102
0.00 25.27 -28.57 Pipes: DH – m/km
Q1 = 619 l/s Nodes: p – mwc
Factory
01
-61.07
7.84 15 16 0.75
14.87
07 -62.53 4.89 -64.10
3.91 24
-54.21
-65.80
3.52
3.43 5.74
03 14
7.67
02
6.25
-50.79 3.19 -58.55
11.32
-45.70 23
04 0.03
13 0.18 17
06 12.66 -53.28 -54.37
-61.06 14.24
1.04 -55.18
-61.18 9.59
4.03
0.02
7.75 10 0.56 12 18 22
5.60 -57.41
-60.87 6.10 -50.7922.95 -54.56
05 202 9.57
08 -67.50 -46.81 7.30
10.46 21.59 21
-70.09 6.88 10.26
09 46.81 -61.61
11.15
201
-80.50
6.67
0.00 0.29
DH > 8 m/km 11 Q2 = 685 l/s 19 20
-72.73 9.81 -62.36
10.80 -64.53
Conclusions:
● The nodal pressures become negative at a minimum of 80.54 mwc
101 102
0.00 -18.25 14.95
Q1 = 474 l/s Pipes: DH – m/km
Nodes: p – mwc Factory
01
-8.00
4.62 15 16 0.75
07 7.68
-10.29 3.78 -11.03 24
2.47
-3.12
-6.98
2.01
1.94 3.94
03 14
4.49
02
2.05 -7.29
3.75
6.79-0.45
3.29 23
04 0.05
13 0.04 17
7.14 -2.06 1.74
06 8.08
-9.82 -4.00
0.70
-6.41 5.23
2.29
0.02
4.25 10 0.24 12 18 22
3.18 -5.95
-9.61 3.28 -1.79 12.84 0.51
05 2025.23
08 -11.04 -1.06 4.10
5.92 12.04 21
-12.72 3.97 5.72
09 1.06 -4.94
6.29
201
-19.49
3.63
0.00 0.17
DH > 8 m/km Q 2 = 505 l/s
11 19 20
-16.13 5.44 6.08
-8.59 -7.94
in parallel.
During the second phase, the pipes already laid will be approxi-
mately10–15 years old. These should normally still be in good condition
and their replacement with a larger diameter pipe may not be economi-
cally justified. If reliability is an issue, parallel pipes could be considered
instead but the trench widening is required in this case. In this stage, the
332 Introduction to Urban Water Distribution
taken in around Year 15. Parallel pipes D 500 mm are planned along
routes 102–02, 02–03 and 202–18, while all other indicated pipes will
be replaced with the next larger diameter from Table A2.3.
● At the beginning of the design period, the diameters of Pipes 102–02
101 102
#N/A
Qd = 280 l/s
Hd = 60 mwc Factory
01
500 15 16 300
07 100 100
100 24
300
300 300
03 14 150
02
400 400
500
04 23
400
300 13 400 17
06 200
400
400
150
200
200 10 400 12 18 200 22
300
400
05 202500
08 150
200 200
21
150 300
09 200 #N/A
201
100 Qd = 280 l/s 100
Hd = 60 mwc
11 200 19 150 20
Figure A2.19. Alternative A: pipe diameters at the beginning of the design period.
Design Exercise 333
101 102
#N/A Replaced pipes
500 Factory
Qd = 560 l/s 01
Hd = 60 mwc
500 15 16 300
07 100 100
100 24
300
300 300
03 14 200
02 400
500500 400
04 400 23
400 13 400 17
06 300
400
500
150
200
200 10
400 12 18 300 22
300
400
05 202500
500
08 200
200 300
21
150 400
09 200 #N/A
201
100
Qd = 520 l/s 100
Hd =1140 mwc300 19 150 20
Figure A2.20. Alternative A: pipe diameters at the end of the design period.
101 102
0.00 0.00 47.58 Pipes: v – m/s
Q1 = 338 l/s Nodes: p – mwc
Factory
01
24.33
1.72 15 16 0.43
07 0.44 0.41
0.33 21.63 21.29 24
28.33
29.17
0.57
0.52 0.88
03 14 0.54
02 0.73
1.3530.58
0.79 24.19
33.42 23
04 0.14
0.82 13 0.01 17
06 29.68 0.76 36.57
21.65 27.45
28.40 0.38
1.03
0.42
0.31
0.43 10
0.10 12 18 0.93 22
0.56
25.98 0.70
22.20 28.51 35.03
05 2021.75
08 25.12 30.04 0.38
0.59 0.80
21
24.15 0.42 0.76
09 0.59 0.00 30.89
11
Q2 = 344 l/s 19
0.55 0.52 20
19.95 25.30 27.96
Figure A2.21. Alternative A: operation at 12:00 at the beginning of the design period.
334 Introduction to Urban Water Distribution
101 102
Pipes: v – m/s
0.00 0.00 50.14
Nodes: p – mwc
Q1 = 645 l/s
1.64
Factory
01
24.58
1.64 15 16 0.43
07 0.47 0.01
0.50 22.24 21.54 24
30.80
31.74
0.93
0.93 1.11
03 14 0.74
02 1.14
1.2334.23
1.23 1.63 26.18
36.88 23
04 0.16
1.04 13 0.29 17
06 31.39 0.79 39.76
23.63 29.54
31.55 0.84
1.24
0.54
0.49
0.62 10
0.32 12 18 0.88 22
1.24
26.62 1.08
23.00 30.75 38.88
05 2021.68
1.68
08 24.93 31.90 0.66
0.89 1.01
21
23.37 0.19 1.03
09 0.56 0.00 34.01
pmin 201
21.05
0.27 0.00 0.56
Q
11 2
= 659 l/s
0.83 19 0.76 20
21.06 26.86 27.79
Figure A2.22. Alternative A: operation at 12:00 at the end of the design period.
● an elevated tank
20 m high including
2 m water depth (the
set as follows:
● beginning of the design period: H
d,1 60 mwc, Qd,1 460 l/s
Qmaxd at Year 6,
101 102
#N/A
Qd = 460 l/s
H d = 60 mwc Factory
01
600 15 16 300
07 150
400 24
400
200
400 400
03 14 301
150
02
400 400
600
04 23
400 500
13 400 17
300
06 200
400
300
100
400
200 10 400 12 18 200 22
300
200
05
08 150
200 200
21
100 200
09 300
100 100
11 200 19 150 20
Figure A2.23. Alternative B: pipe diameters at the beginning of the design period.
336 Introduction to Urban Water Distribution
101 102
#N/A
Added pipes
Replaced pipes
Qd = 650 l/s Factory
H d = 60 mwc 01
600 15 16 300
07 400 150
400 24
200
400 400
03 14 301
150
02 400
600 400
04 400 500 23
400 13 400 17
06 300
400
300
100
400
200 10
400 12 18 300 22
300
400
05 600 202
08 200
200 300
21
100 300
09 300 #N/A
201
100 100
11 200 19 150 20
Figure A2.24. Alternative B: pipe diameters at the end of the design period.
101 102
0.00-43.50 40.20
Pipes: DH – m/km
Q1 = 622 l/s Nodes: p – mwc Factory
01
11.98
7.89 15 16 0.75
07 4.21
8.15 1.74 8.94 24
2.76
15.55
15.77
1.24
4.43 Qt = 60 l/s 0.12
03 14 301
0.07
02
5.93
19.47 4.52 10.65 0.00
6.07
22.99 23
04 2.28 0.21
13 1.93 17
3.10 17.09 20.72
06 3.98
6.78 11.71
3.48
17.53 3.05
0.54
0.35
0.30 10 1.09 12 18 22
1.55 11.26
6.80 2.77 9.79 3.31 17.80
05
pmin 2.15
08 14.04
1.69 5.24 21
13.21 5.51 1.85
09 13.32
2.39
4.52
1.35
0.10
11 19 20
DH > 5 m/km 2.35
4.57 1.97
7.04 10.16
Figure A2.25. Alternative B: ground tank, operation at 12:00 at the beginning of the design period.
Design Exercise 337
101 102
Pipes: DH – m/km
0.00-53.17 49.87
Nodes: p – mwc
Q1 = 533 l/s
Factory
01
27.40
5.82 15 16 0.75
07 4.11
23.10 1.12 24.36 24
1.90
29.82
31.28
1.53
3.32 Qt = 149 l/s 0.01
03 14 301
0.08
02
2.73 25.80 0.00
4.35
4.3433.18
36.19 23
04 1.03 1.22
13 2.72 17
2.75 31.36 36.24
06 4.01
22.68 27.25
2.18
31.09 3.04
0.50
0.99
0.66 10 0.42 12 18 22
1.31 26.44
22.38 2.81 25.34 3.32 33.34
05
pmin
08 27.78 2.15
1.59 5.32 21
26.96 4.44 1.85
09 28.87
2.42
19.62
1.66
0.10
DH > 5 m/km
11 19 20
20.13 2.35 1.98
22.60 25.71
Figure A2.26. Alternative B: elevated tank, operation at 12:00 at the beginning of the design period.
101 102
0.00-50.89 47.59
Pipes: DH – m/km
Nodes: p – mwc
Q1 = 784 l/s
Factory
01
10.21
12.51 15 16
Qmax = 695 l/s 0.75
5.54
07 6.05 1.30 7.17
2.94 24
13.60
12.94
3.30
6.33 Qt = 83 l/s 0.02
03 14 301
3.12
02
7.12
18.47 4.22 9.90 0.00
7.89
22.53 23
04 1.06 0.39
13 5.49 17
3.07 15.68 20.49
06 2.25
6.76 10.09
2.01
17.11 1.39
0.35
0.65
1.85 10 0.35 12 18 22
6.30 10.87
7.28 4.36 9.00 2.19 17.68
05 202
3.95
08 10.29 pmin 12.44 3.01
4.60 21
5.00
8.79 1.78 2.89
09 -12.44 12.78
5.46
201
4.77
0.82
DH > 5 m/km 0.00 5.77
11 Q2 = 438 l/s 19 20
1.68 0.80 5.17
5.42 6.21
Figure A2.27. Alternative B: ground tank, operation at 12:00 at the end of the design period.
338 Introduction to Urban Water Distribution
101 102
0.00-58.17 54.87
Pipes: DH – m/km
Nodes: p – mwc
Q1 = 679 l/s Factory
01
25.16
9.40 15 16 0.75
5.45
07 20.63 0.81 22.12
2.08 24
27.50
27.97
4.06Qt = 270 l/s
5.04 0.15
03 14 301
3.19
02
5.21
31.72 1.94 24.97 0.00
5.54
35.08 23
04 0.11 3.92
13 6.72 17
2.92 29.60 35.58
06 2.26
22.41 25.18
1.00
29.82 1.44
0.38
0.56
2.44 10 1.05 12 18 22
5.83 25.50
22.33 4.33 24.06 2.19 32.75
05 pmin 2.61
202
08 23.34 26.42 3.01
4.63 4.68 21
21.92 0.64 2.91
09 -26.42 27.85
5.48
201
19.32
0.49
0.00 5.80
DH > 5 m/km 11 Q2 = 355 l/s 19 20
16.70 0.76 20.21
5.41 21.26
Figure A2.28. Alternative B: elevated tank, operation at 12:00 at the end of the design period.
● end of the design period: Hd,1 60 mwc, Qd,1 650 l/s ( Qmax of
Source 1), and Hd,2 40 mwc, Qd,2 250 l/s (Qd,1 Qd,2 900 l/s ≈
Qmaxd at Year 30).
● To provide a link with the main loop, the second source has been
connected at Node 12.
Conclusions:
● Pipe investment for the network at the beginning of the design period is
US$4,927,500. The additional cost for the pipes to be laid in approxi-
mately Year 20 is US$1,455,000. Compared to Alternative A, the saving
is mainly obtained by avoiding parallel pipes from the sources.
● There is a difference in the head-loss distribution, depending on the
than it should supply to the system and therefore will soon become
empty. To prevent this, the pumping head at the source should be
increased.
● The amount of water entering and leaving the tank are known in
advance, if the supply source has been tuned to provide the average
flow throughout the day. A sophisticated way to quickly evaluate the
tank position is to model it as an ordinary node with the balancing
flows as its consumption. Such consumption would fluctuate between
the maximum or minimum hour consumption reduced by the average
flow supplied by the pump. It becomes negative when the tank is sup-
plying the system and positive when its volume is being recovered.
The pressure in the node, resulting from the simulations for two
extreme consumptions, can give an impression about the range of
water depths in the tank; it should therefore be reasonably high and
within a range of a few metres.
101 102
0.00-47.91 44.61 Pipes: DH – m/km
Q1 = 583 l/s Nodes: p – mwc
Factory
01
25.57
6.94 15 16 0.75
07 1.56
18.97 1.95 22.53 24
0.14
24.06
31.48
9.94
0.01 Qt = 99 l/s 5.28
03 14 301
1.16
02
7.95 14.21 0.00
9.95
5.1525.76 Qbs = 397 l/s
29.01 23
04 8.27 0.55
13 -18.4317
3.59 21.98 37.37
06 7.25
6.75
23.04
6.95 pmin 30.97
16.45
7.66
1.92
0.05 10 3.35 12 18 22
1.90 13.72
7.91 11.55 22.34 3.62 30.17
05
08 19.31 5.46
1.85 4.92 21
18.44 7.48 9.26
09 24.04
0.69
7.30
1.48
8.31
11 19 20
7.55 0.42 0.28
11.82 15.95
Figure A2.29. S6B2: ground tank and booster 13–17, operation at 12:00.
101 102
Pipes: DH – m/km
0.00-51.00 47.70
Nodes: p – mwc
Q1 = 554 l/s
Factory
01
29.54
6.28 15 16 0.75
07 1.59
23.18 1.63 26.51 24
0.03
28.36
35.43
13.28 Qt = 128 l/s
0.10 4.76
03 14 301
1.13
02
10.82
4.89
4.7330.11
16.25 0.00
Qbs =363 l/s
33.22 23
04 11.74 0.90
13 -21.8917
2.85 28.09 41.29
06 6.64
6.71
28.04
2.60 pmin 34.40
11.72
4.34
0.54 10 0.63 12 18 22
1.37 22.87
18.69 5.32 28.15 3.44 36.08
05
08 24.68 3.99
1.61 5.13 21
23.85 4.65 5.47
09 30.69
1.31
16.25
2.28
3.58
11 19 20
17.65 0.09 0.76
21.60 25.44
101 102
0.00-51.05 47.75 Pipes: DH – m/km
Q1 = 553 l/s Nodes: p – mwc
Factory
01
14.38
6.27 15 16 0.75
07 4.85
12.90 4.87 11.34 24
6.98
23.68
17.66
0.27
9.52 Qt = 128 l/s 1.52
03 14 301
0.01
02
12.71 14.77 0.00
4.8430.14
0.66
33.29 23
04
pmin 9.27 0.91
13 0.31 17
2.29 30.07 22.56
06 2.85
6.71 12.65
2.18
28.69 Qbs = 375 l/s 0.13
0.76
-20.72
1.25 10 5.38 12 18 22
0.99 28.20
27.63 25.65 12.31 3.16 20.42
05
08 25.59 0.75
1.30 5.93 21
24.83 1.81 1.51
09 16.64
6.27
20.77
1.56
2.41
11 19 20
21.13 18.52 4.01
13.10 14.99
101 102
0.00-47.76 44.46
Pipes: DH – m/km
Q1 = 584 l/s Nodes: p –mwc
Factory
01
13.52
6.98 15 16 0.75
07 3.20
10.91 3.37 10.48 24
5.03
20.13
18.12
7.21
0.48 Qt = 97 l/s 0.79
03 14 301
0.28
02
9.14 12.92 0.00
5.5425.44
0.40
28.80 23
04 6.13 0.53
13 0.01 17
06
1.99 25.00 pmin 1.86
23.26
6.75 12.55
24.51
Qbs = 266 l/s 16.93
-30.29
0.57 10 0.95 12 18 22
0.80 40.47
37.24 23.19 23.89 5.11 30.82
05
08 21.54 0.64
0.23 9.29 21
21.00 8.39 0.98
09 27.10
5.99
29.68
2.25
3.08
11 19 20
31.05 16.81 4.29
24.12 25.85
Figure A2.32. S6B2: booster 13–12, pipes 04–10 and 17–18 removed.
Design Exercise 343
101 102
Pipes: DH – m/km
0.00-51.48 48.18
Nodes: p – mwc
Q1 = 549 l/s
Factory
01
26.97
6.18 15 16 0.75
07 3.28
21.84 0.00 23.94 24
1.12
27.93
31.51
Qinflow=264 l/s
10.89
2.25 0.97
03 14 301
0.26
0.00 Qbs=396 l/s
02
11.38 16.4611.93
4.7230.76
0.89
33.88 23
04
pmin -18.49
13 7.17 17
2.44 30.15 36.63
06 4.28
25.29 27.86
29.11
0.09 0.23
4.79 3.02
1.07 10 0.35 12 18 22
1.10 26.69
23.09 2.93 25.95 3.42 33.90
05
08 25.95 2.09
1.44 5.50 21
25.16 2.94 1.83
09 29.45
2.46
19.68
2.07
DH > 8 m/km 0.06
11 19 20
20.79 2.40 2.03
23.23 26.31
becomes obvious if one pipe is removed from the loop(s); the pressure
downstream of the booster station will increase (Figures A2.30 and
A2.32).
● The pipe resistance increases in the vicinity of the booster station.
Contrary to expectations, enlarging the diameter of these pipes
makes no sense as it creates negative effects on the pressure in the
system. The fact is that, with larger pipes, even more water will be
pushed towards the booster station, which reduces the pumping
head.
To analyse the relation between the booster pumping capacity and the
pipe resistance, the pipes indicated in Figure 33 have been replaced with
the next larger diameter from Table A2.3 (file S6B3.NET). As a result
(shown in Figure A2.34), the booster station increases the flow on
account of the head (pressure). Installing much stronger pumps will rein-
state the pressure, but will also initiate the old problem of water re-
circulation and large pressure drops in some of the pipes. Operation of
the system with doubled duty flow (Hd,bs 30 mwc, Qd,bs 540 l/s) of
the booster station has been shown in Figure A2.35.
344 Introduction to Urban Water Distribution
101 102
0.00-46.27 42.97
Pipes: DH – m/km
Nodes: p – mwc
Q1 = 597 l/s
Replaced pipes Factory
01
19.48
7.30 15 16 0.75
07 0.12 2.76
1.23 14.26 16.45 24
20.44
24.44
3.74
2.42 Qinflow = 363 l/s
1.66
03 14 301
0.44
02
5.7023.35
0.34
5.79 13.537.04 0.00
26.76
04
Qbs = 448 l/s 23
-12.52
2.46 13 8.95 17
06 22.94 4.47 29.71
19.32 21.09
21.98 0.01
3.06
0.10
6.47
1.02 10
0.90 12 18 3.50 22
1.11
19.54 2.90
16.28 19.16 27.05
05 pmin
08 18.80 2.07
1.43 5.46
21
18.02 2.91 1.85
09 2.47 22.62
12.58
2.27 0.05
11 2.39 19 2.05 20
13.97 16.42 19.49
101 102
0.00-50.68 47.38 Pipes: DH – m/km
Q1 = 557 l/s Nodes: p – mwc
Factory
01
27.84
6.35 15 16 0.75
07 1.08
21.53 1.56 24.80 24
0.57
27.19
34.14
9.54 Qinflow = 493 l/s
1.44 4.57
03 14 301
1.65
02
9.23 17.0212.87 0.00
0.57
4.9129.61
32.78 Qbs = 618 l/s 23
04 -26.92
13 15.59 17
2.29 29.51 40.44
06 5.33
33.72 32.50
2.01
28.18 3.67
0.14
14.36
1.22 10 5.04 12 18 22
0.99 27.52
26.74 2.09 30.27 3.91 37.92
05
08 25.08 pmin 5.44
2.15
1.26 21
24.33 1.56 2.18
09 33.45
2.41
20.58
4.00
0.10
11 19 20
24.48 2.01 1.98
27.18 30.29
Comments:
● Booster stations are useful if pressure has to be provided for higher
in EPANET are:
● Compared to the modelling of a source pumping station, the suction
node of a booster station can be any node within the network. The
flow direction in the pump will be from the first to the second node
selected on the map after clicking the pump button. The reversed
flow is prevented by the programme (it shows Qbs 0).
● A pipe replaced by a booster station has to be deleted first; other-
wise the programme assumes two pipes in parallel where in fact one
is with the booster pump.
Due to all the listed deficiencies, Alternative B with a ground tank and
booster station is therefore discounted with regard to the Safi network.
volume equals 2200 2500 600 5300 m3. For example, for a
height of 5.5 m, Vtot 5290 m3. Two equal tanks yield the total
storage volume in the system of approximately 10,600 m3.
● In the case of Alternative B, the balancing volume is located within the
network. If the source pumping station works at constant average
capacity, the volume of the clear water reservoir in Source 1 will con-
sist mainly of the emergency provision. Thus, at the beginning of the
design period:
tot 2500 600 3100 m (for D 30 m and
● at Source 1, V
3
Such a large volume of the elevated balancing tank changes the earlier
conclusion about its better hydraulic performance compared to the
ground tank; to construct a volume of
10,000 m3 at a height of
20 m
might be a relatively expensive solution, not to mention the aesthetic
aspects if the structure is to be located in an urban area.
Preliminary dimensions of all tanks are summarised in Tables A2.12
and A2.13. The dimensions at the end of the design period indicate the
total required volumes. Depending on the selected form of the tanks (not
necessarily circular cross-section) these dimensions should match the
already existing design as much as possible in order to make the volume
extension easier (i.e. by adding of the second compartment).
Comments:
● The balancing volume is exclusively dependent from the demand and
Reading:
● Chapter 4, Section 4.2.3: ‘Storage design’.
Year 15. Laying of new pipes in the system will take place at the same
time.
● For practical reasons, the clear water tanks will be immediately con-
structed with the volumes required at the end of the design period,
which also adds to the reliability of supply.
water tank at Source 1 at the beginning with the volume that will be
required at the end of the design period.
Design Exercise 349
● The option with the ground level balancing tank has been abandoned
due to the pressure problems that cannot be solved by installing a
booster station. It is not yet clear either the option with the elevated
balancing tank should be accepted due to its excessively large volume
and consequently expensive construction.
It appears at this stage that the present topography does not offer an
effective way of using the balancing tank in the system, unless its (large)
volume is elevated. Initially, this makes Alternative A appear simpler and
more straightforward from the hydraulic point of view. Nevertheless,
this conclusion is yet to be verified by further analyses of the system
operation and a cost calculation.
The third possibility could be to keep the balancing volume at
the sources, combined by the water tower with its volume of
500–1000 m3. The main task of the water tower would be to stabilise
the operation of the pumps that in this case do not operate at a con-
stant capacity any more. Such alternative is in essence a combination
of A and B.
The simulation starts with three units, 1001, 1002 and 1003, in operation
at the first source and two units, 2001 and 2002, at the second source; for
all other units, the Initial Status in the pump property editor is set as
CLOSED. By checking the pressures in the system, hour-by-hour, each
pump is further switched on or off when the pressure in any node drops
outside the range of 20–60 mwc; this operation can be done manually or
automatically. It is necessary to keep the pressure as close to 20 mwc for
as long as possible.
Both the manual and automatic mode of pump operation are
modelled in EPANET in the browser option Data Controls (double-
click on Simple). For the above-selected pump units, the optimal
350 Introduction to Urban Water Distribution
Summarised per pump unit, the same schedule is shown in Table A2.14
(1 is On, 0 is Off ). Pumps 1007 and 2007 have been left out of the oper-
ation, serving as stand-by units.
50.0
40.0
Pressure (mwc)
30.0
20.0
10.0
0.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
1.5
1.2
Velocity (m/s)
0.9
0.6
0.3
0.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
300.0
250.0
Flow (l/s)
200.0
150.0
100.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
Conclusions:
● A fairly balanced supply with stable pressures is provided by the
Comments:
● Scheduling of pumps results in a minimum pressure that does not nec-
essarily occur during the maximum consumption hour.
● The minimum pressure criterion should be maintained throughout the
entire day. Much higher pressures during the low demand hours are
not justified; they cause increased waste of pumping energy and water.
● Choosing the same model of pump for all the installed units has the
advantage that the various units can implement the same pumping
schedule on different days, which loads them more evenly. The stand-
by unit can then also be employed. One possible adaptation of the
regime is shown in Table A2.15.
Design Exercise 353
Table A2.15. Alternative A: pumping schedule for adapted manual operation (S30A3).
Pumps 1001 and 1002 and 2001 and 2002 are assumed to be constantly
in operation. The simulation starts with three pumps switched at each
source. This control regime will result in the pump operation as shown
in Table A2.16.
For this schedule, the pressure and velocity range in the system are
shown in Figures A2.39 and A2.40, and the supply ratio in Figure A2.41.
Clarification:
● The same control node (11) has been selected for both pumping sta-
tions for reasons of simplification, which yields the same schedule for
both of them.
354 Introduction to Urban Water Distribution
60.0
50.0
Pressure (mwc)
40.0
30.0
20.0
10.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
1.5
1.2
Velocity (m/s)
0.9
0.6
0.3
0.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
300.0
250.0
Flow (l/s)
200.0
150.0
100.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
Conclusions:
● For specified controls, the model reacts by maintaining units
Comments:
● Modelling of the automatic pump operation yields the schedule as a
result (as in Table A2.16), while the modelling of the manual pump
operation requires such a schedule as an input (Tables A2.14 and
A2.15).
demand level is the same. The reason is the operation at 0 hours that
is defined through the initial status of the pumps, while the operation
at 24 hours depends on the specified control of pumps.
Conclusions:
● Unlike in S30A4, there is no overlap of the On and Off settings in the
[CONTROLS] section of S30A5. This is the likely cause of the unsta-
ble operation and the low pressure in the system.
50.0
40.0
Pressure (mwc)
30.0
20.0
10.0
0.0
-10.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
50.0
40.0
Pressure (mwc)
30.0
20.0
10.0
0.0
-10.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
Figure A2.43. S30A6: automatic pump operation with time steps of 1/2 hour.
same controls as in S30A5, the hydraulic time step and the demand
pattern step have been reduced from 1 hour to 30 minutes (the browser
option Data Options Times (click on Hydraulic/Pattern
Time Step). Linear interpolation of the hourly peak factors has been
applied resulting in 48 values, each for every 30 minutes. The pressure
in the system is indicated in Figure A2.43.
Alternative B – Pumping and balancing storage
The simulation starts with the same system components as listed in
Section A2.3.6 (input file S30B2.NET). As in the case of Alternative A,
the pump duty head of 50 mwc has been adopted in Source 1. After a
number of trial simulations, the tank D 50 m with a depth of 6.5 m,
slightly above the original estimate, has been elevated to 22 m (50 msl).
Furthermore:
● The pump suction water levels in 101 and 201 have been set at ground
level (modelled as reservoirs with a Total Head of 10.7 and 25.0 msl,
respectively).
● The minimum depth of the elevated tank in 301 is 2.5 m and at the
[PUMPS]
All pumps in both sources, except the stand-by pumps, are switched on
and operate for 24 hours at a more or less constant regime i.e. average
flow; the demand variation is balanced from the tank. Consequently, no
control commands are required for the pumps in this mode of operation.
The pressure range in the system is shown in Figure A2.44 and the tank
water depth variation in Figure A2.45.
Conclusions:
● The system operation is stable. The minimum pressure of 20.80 mwc
60.0
50.0
Pressure (mwc)
40.0
30.0
20.0
10.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
6.0
5.5
5.0
Depth (m)
4.5
4.0
3.5
3.0
2.5
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
A further test has been made with smaller pumps and an elevated tank of
20 m (S30B3.NET):
[PUMPS]
60.0
50.0
Pressure (mwc)
40.0
30.0
20.0
10.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
6.0
5.5
5.0
Depth (m)
4.5
4.0
3.5
3.0
2.5
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
tank elevation and its size. While doing this, the following three cases
are possible:
CASE 1 – The tank receives too much water: This situation is simulated
in the file S30B3-1.NET by putting the balancing volume 10 m lower,
i.e. from 20 to 10 m height. The water depth variation of the tank is
shown in Figure A2.48. It is clear from the figure that the tank will over-
flow by the next day already if the same operation is maintained. The
Design Exercise 361
6.0
5.5
5.0
Depth (m)
4.5
4.0
3.5
3.0
2.5
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
CASE 2 – The tank loses too much water: This is simulated in S30B3-
2.NET by setting the balancing volume 30 m high, instead of 20 m. The
water depth variation in the tank resulting from this action is shown in
Figure A2.49. This case contrasts with the above.
CASE 3 – The tank is balancing too quickly: To demonstrate this, the
volume of the tank has been reduced from D 50 m to D 25 m, keep-
ing the elevation at H 20 m. The results are shown in Figure A2.50
(S30B3-3.NET). The remedies are:
● to increase the tank volume i.e. the cross-section area (diameter)
When the elevated tank is reduced in volume, it loses the demand bal-
ancing function and becomes in fact a water tower.
Water towers provide stable pressures in the system and at the same
time prevent too frequent switching of the pumps. The pumping sched-
ule in this case becomes similar to those for the direct supply conditions.
To satisfy the pumping flow that exceeds Qavg in some periods of the day,
362 Introduction to Urban Water Distribution
6.0
5.5
5.0
Depth (m)
4.5
4.0
3.5
3.0
2.5
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
6.0
5.5
5.0
Depth (m)
4.5
4.0
3.5
3.0
2.5
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
depth at the beginning of the simulation was set at 1.0 m and the
following pump control is suggested by taking the same pumps from file
S30B2.NET:
[CONTROLS]
Two pumps at Source 1 and one pump at Source 2 are switched on at the
beginning of the simulation. Based on the above controls, the pumps will
operate further according to the schedule shown in Table A2.17. As a
consequence of the control regime, two additional units at Source 2 will
be needed.
The pressure range in the system is shown in Figure A2.51, while the
volume variation in the water tower is shown in Figure A2.52.
Conclusions:
● More sudden changes of the water tower depth are caused by the pump
the beginning of the day. This is not a problem because the tank does
Table A2.17. Alternative B: pumping schedule for automatic operation controlled from the water tower (S30B4).
60.0
50.0
Pressure (mwc)
40.0
30.0
20.0
10.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
6.0
5.5
5.0
4.5
4.0
Depth (m)
3.5
3.0
2.5
2.0
1.5
1.0
0.5
0.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
is
27 mwc, in both alternatives. Obviously, the most critical situation
will be caused by the pipe burst 01–16, which is rather easy to solve
because another pipe in parallel could be added to it. More difficult to
predict are the consequences of the failure of other pipes connecting
Node 16. Furthermore, the supply requirement during fire fighting in the
factory has been examined in this section.
In all cases it is assumed that the disaster takes place during the max-
imum consumption hour. As a remedy, both pumping stations are set at
full capacity, including the stand-by units.
Alternative A – Direct pumping
The regular operation of the S30A3 layout is shown in Figure A2.53. The
failure of pipes 15–16, 16–24 and 16–17 respectively are shown in
Figures A2.54–A2.56.
Clarification:
● While simulating a pipe failure, it is assumed that the line is closed
i.e. being repaired. This is an acceptable approach bearing in mind that
the real quantities of water lost from the system are difficult to predict.
Hence, the pipe should be simply disconnected from the rest of the
101 102
0.00 0.00 50.29
101 102
0.00 0.00 50.30
Pipes: v – m/s
0.00
1.55
Nodes: p – mwc Factory
0.00 01
26.57
0.00 1.55 15 16 0.43
0.00 07 0.00 0.10
0.42 24.61 23.54 24
0.00 32.21
33.88
0.00 0.89
0.92 1.15
Q1= 607 l/s 03 14 0.77
02 0.96
1.1435.60
1.52 28.35
38.11 23
04 0.01
1.02 13 0.45 17
06 33.08 0.79 42.12
25.85 31.91
32.87 0.73
1.36
0.58
0.51
0.63 10
0.44 12 18 0.89 22
1.21
pmin 28.63
25.16 1.18 33.43 41.51
05 2021.78
1.78
08 26.43 35.09 0.66
0.85 1.03
21
24.96 0.12 1.05
09 0.00
0.52 0.00
0.00
0.00
0.00
0.00
0.00 36.64
201
22.96
0.31
Q2= 697 l/s
0.00 0.56
11 0.86 19 0.76 20
23.56 29.46 30.40
101 102
0.00 0.00 50.29
0.00
Pipes: v – m/s
1.55 Nodes: p – mwc Factory
0.00 01
26.95
0.00 1.55 15 16 0.43
0.00 07 0.45 0.00
0.44 24.37 23.91 24
0.00 32.19
34.14
0.00 0.94
0.92 1.11
Q1= 607 l/s 03 14 0.74
02 0.96
1.1435.58
1.52 28.34
38.10 23
04 0.02
1.02 13 0.47 17
06 33.07 0.78 42.18
25.84 31.93
32.86 0.73
1.36
0.57
0.50
0.63 10
0.44 12 18 0.89 22
1.21
28.63 1.18
25.16 33.44 41.53
05 pmin 2021.78
1.78
08 26.42 35.10 0.66
0.85 1.03
21
24.95 0.12 1.05
09 0.00
0.51 0.00
0.00
0.00
0.00
0.00
0.00 36.66
201
22.95
0.31 0.00 0.56
11Q2= 697 l/s
0.86 19 0.76 20
23.56 29.47 30.41
101 102
0.00 0.00 50.19
0.00
1.55 Pipes: v – m/s Factory
0.00 Nodes: p – mwc 01
-314.42
0.00 1.55 15 16 0.43
0.00 07 5.39 5.05
0.66 20.96 -317.46 24
0.00 31.94
12.32
0.00 1.46
0.95
pmin 0.00
Q1= 609 l/s 03 14 2.00
02 0.98
1.1535.43
1.50 28.08
37.95 23
04 0.29
1.02 13 0.73 17
06 32.97 1.26 39.40
25.73 32.22
32.72 0.71
1.30
0.88
0.47
0.63 10
0.46 12 18 0.97 22
1.21
28.59 1.21
25.16 33.57 41.34
05 2021.77
1.77
08 26.31 35.21 0.65
0.84 1.03
21
24.86 0.10 1.05
09 0.00
0.50 0.00
0.00
0.00
0.00
0.00
0.00 36.48
201
22.90
0.32 0.00 0.54
Q=
11 2
695 l/s
0.86 19 0.77 20
23.65 29.58 30.44
the main path from Source 2 and if closed, the water will move to the
alternative routes towards the factory. In this case, pipes 15-16-24
become much too small and a severe pressure drop (velocities above
4 m/s!) will be caused. Increasing the pumping head at the
sources does not help and enlarging of at least one of the pipes will be
necessary.
Figure A2.57 shows the solution by replacing the diameter of 15-16 with
D 300 mm. In both pumping stations, the stand-by units are switched on.
368 Introduction to Urban Water Distribution
101 102
Pipes: v – m/s
0.00 0.00 54.93
Nodes: p – mwc
0.00
Factory
1.54
0.00 01
0.00 23.62
1.54 15 D=300 mm 16 0.43
0.00 07 1.08 0.76
0.86 21.91 20.58 24
0.00 36.73
37.89
0.00 1.91
Q1= 605 l/s
0.97
pmin 0.00
03 14 0.93
02 1.00
1.1440.29
1.45 32.89
42.80 23
04 0.53
1.02 13 0.97 17
06 37.99 0.85 47.68
30.86 37.82
37.61 0.65
1.30
0.60
0.43
0.64 10
0.52 12 18 0.90 22
1.19
33.76 1.27
30.42 39.18 47.24
05 2021.78
1.78
08 31.27 40.88 0.66
0.82 1.04
21
29.87 0.06 1.06
09 0.00
0.47 0.00
0.00
0.00
0.00
0.00
0.00 42.36
201
28.01
0.35 0.00 0.56
11
Q2= 700 l/s 19
0.88 0.76 20
29.13 35.14 36.09
Conclusions:
● The pressure in critical points has been restored at a somewhat
101 102
0.00 0.00 49.05 Pipes: v – m/s
Nodes: p – mwc
0.00 1.60
Factory
0.00 01
16.03
0.00 1.60 15 16 1.13
0.00 07 0.62
21.68 0.87 14.50 24
0.50
0.00 30.24 pmin
29.83
0.00 0.98
Q1= 629 l/s 0.93 1.70
03 14
0.90
02
1.09 25.84
1.2033.66
1.56
36.25 23
04 0.09
13 0.34 17
1.03 31.04 39.28
06 0.83
23.32 29.27
0.76
30.98 1.50
0.66
0.39
0.62 10 0.40 12 18 22
1.22 26.50
22.98 1.17 31.20 0.91 39.21
05 2021.85
1.85
08 24.47 33.26 0.66
0.87 1.02 21
22.97 0.14 1.04
09 0.00
0.00
0.00
0.00
0.00
0.00
0.00 34.34
0.52
201
20.87
0.31
0.00 0.55
11 Q2 = 726 l/s 19 20
21.35 0.85 0.76
27.24 28.16
101 102
Pipes: v – m/s
0.00 0.00 54.03
Nodes: p – mwc
1.59
0.00 Factory
0.00 01
28.90
0.00 1.59 15 16 1.13
0.00 07 0.07
26.86 0.73 27.37 24
0.55
0.00 33.05
37.66
0.00 1.11
1.42 1.13
Q1= 626 l/s 14
03 0.76
02
0.90 31.74
1.46
1.1938.73
41.32 23
04 0.18
13 0.62 17
1.02 36.39 45.85
06 0.78
29.30 35.59
0.66
36.11 1.46
0.61
0.46
0.63 10 0.51 12 18 22
1.20 32.12
pmin 28.76 1.25 37.40 0.90 45.46
05 2021.85
1.85
08 29.73 39.51 0.66
0.83 1.03 21
28.30 0.08 1.05
09 0.00
0.00
0.00
0.00
0.00
0.00
0.00 40.58
0.48
201
26.40
0.34
0.00 0.56
11 Q2= 728 l/s 19 20
27.40 0.87 0.76
33.38 34.32
Conclusions:
● The pressure in the factory is slightly below the required 30 mwc
(28.90 mwc). Further computer runs would show that reaching the
minimum of 30 mwc requires an additional pumping unit in both
pumping stations. This is considered to be rather an expensive option
in relation to the gain in the pressure.
Comments:
● It can be assumed that the fire is limited to a certain number of hours.
The fire demand specified in this exercise is slightly exaggerated for
educational purpose i.e. to realise the impact on the rest of the net-
work. Pressure problems during fire fighting can also be solved by
local measures, such as the operation of district valves, booster instal-
lation at the factory, etc. It is normal to assume that consumers in the
vicinity of the object will be temporarily affected during fire fighting.
Nonetheless, the inconvenience caused during a few hours is usually
acceptable compared to a large investment in pipes and pumps that
would rarely function.
[CONTROLS]
Clarification:
● Figures A2.61, A2.63 and A2.65 show the effect of the burst that
happened at 12:00, while Figures A2.62, A2.64 and A2.66 show the
situation after switching on the stand-by pump at the second source,
also at 12:00 hours.
Design Exercise 371
101 102
0.00 0.00 52.94 Pipes: v – m/s
Nodes: p – mwc
0.00 Factory
0.00 01
0.00 27.02
2.18 15 16 0.43
0.00 07 0.74
22.37 0.47 23.99 24
0.79
0.00 28.96
29.87
0.00 0.84
1.28 Qres= 357 l/s 0.28
301
Q1= 617 l/s 03 14
0.57
02
0.51 27.11
1.29
1.6232.92 4.54
35.92 23
04 0.15 1.82
13 1.65 17
1.02 31.01 37.52
06 0.75
24.66 27.14
0.50
30.73 0.62
0.15
0.71
0.63 10 0.70 12 18 22
1.19 27.11
24.14 1.24 25.95 0.74 34.64
05 1.17 202
08 24.39 27.96 0.67
0.81 1.09 21
23.00 0.11 0.86
29.74
09 pmin 1.18 0.000.000.00
201
20.89
0.13
0.00 0.59
Q=
11 2
331 l/s 19 20
18.53 0.32 0.74
22.07 23.13
Conclusions:
● In none of the cases did the burst cause severe pressure problems.
Pipes 15-16-17 already belong to the secondary mains loop and fur-
ther enlargement is therefore not required. Due to sufficient reserve
capacity in the system, the stand-by pump at Source 2 is able to easily
restore the minor drop of pressure.
Fire demand at the factory is analysed in a similar way as the pipe burst,
assuming that the fire breaks out exactly during the maximum con-
sumption hour. To achieve this condition in the model, the demand pat-
tern of the factory has been adjusted to simulate the disaster at 12:00 (the
peak factor has been changed from 1.0 to 2.66, which increases the reg-
ular factory demand from approximately 30 to 80 l/s). The simulation
results are shown in Figure A2.67.
Conclusions:
● No serious loss of pressure will be observed in the system. However,
the pressure in the factory itself drops significantly below the required
30–23.98 mwc; thus some remedying is necessary. In the first place
372 Introduction to Urban Water Distribution
101 102
Pipes: v – m/s
0.00 0.00 53.17
Nodes: p – mwc
0.00 Factory
0.00 01
0.00 24.23
2.16 15 16 0.43
0.00 07 0.68
24.95 0.00 21.20 24
0.44
0.00 30.59
Qres= 363 l/s 27.85
0.00 0.35
0.93 0.75
301
Q1= 610 l/s 02
03 14
0.64
0.70 27.18
1.6033.49
1.40 4.54
36.45 23
04 0.16 1.85
13 1.96 17
1.02 31.33 36.18
06 0.74
24.63 25.74
0.60
31.23 0.37
0.12
0.76
0.62 10 0.60 12 18 22
1.20 27.21
24.02 1.38 25.05 0.76 33.64
05 1.17 202
08 24.83 27.85 0.66
0.83 1.09 21
23.41 0.16 pmin 0.82
09 28.76
1.21 0.000.000.00
201
20.98
0.19
0.00 0.57
11 Q2= 332 l/s 19 20
18.12 0.40 0.75
21.40 22.38
101 102
0.00 0.00 53.41 Pipes: v – m/s
Nodes: p – mwc
0.00 Factory
0.00 01
0.00 24.96
2.13 15 16 0.43
0.00 07 0.67
25.47 0.00 21.92 24
0.45
0.00 31.13
28.57
0.00
0.94
0.31
Qres= 234 l/s0.75
Q1= 603 l/s 03 14 301
0.64
02
0.74 27.62
1.5834.05
1.30 4.54
36.98 23
04 0.21 1.19
13 1.89 17
1.01 32.14 36.91
06 0.74
25.04 26.47
0.50
31.79 0.25
0.13
0.14
0.63 10 0.71 12 18 22
1.19 28.23
25.27 1.44 25.93 0.77 34.52
05 1.65 202
08 25.47 30.86 0.66
0.81 1.10 21
24.08 0.11 0.81
09 29.64
1.22 0.000.000.00
pmin 201
21.97
0.18
0.00 0.57
11
Q2= 467 l/s 19 20
19.20 0.43 0.76
22.37 23.33
101 102
0.00 0.00 52.94 Pipes: v – m/s
Nodes: p – mwc
0.00 Factory
0.00 01
0.00 27.14
2.18 15 16 0.43
0.00 07 0.00
22.46 0.46 24.11 24
0.78
0.00 29.02
17.86
0.00 0.82
1.27 Qres= 357 l/s0.19
Q1= 617 l/s 03 14 301
1.32
02
0.52 27.12
1.30
1.6232.93 4.54
35.93 23
04 0.14 1.82
13 1.65 17
1.02 31.01 36.77
06 0.90
24.66 27.13
0.50
30.74 0.64
0.23
0.72
0.63 10 0.70 12 18 22
1.19 27.10
24.13 1.25 25.88 0.78 34.43
05 1.17 202
08 24.40 27.95 0.67
0.81 1.09 21
23.01 0.11 0.86
09 29.53
pmin 1.18 0.000.000.00
201
20.88
0.13
0.00 0.58
11
Q2= 331 l/s 19 20
18.49 0.32 0.75
22.01 23.04
101 102
0.00 0.00 53.17 Pipes: v – m/s
Nodes: p – mwc
0.00 Factory
0.00 01
0.00 27.74
2.16 15 16 0.43
0.00 07 0.00
23.04 0.45 24.70 24
0.77
0.00 29.58
18.46
0.80
0.00
1.27 Qres= 228 l/s 0.20
301
Q1= 610 l/s 02
03 14
1.32
0.57 27.54
1.20
1.6033.48 4.54
36.45 23
04 0.08 1.16
13 1.60 17
1.01 31.78 37.37
06 0.90
25.06 27.73
0.41
31.29 0.53
0.22
0.20
0.64 10 0.80 12 18 22
1.18 28.05
25.32 1.31 26.76 0.78 35.31
05 1.65 202
08 25.03 30.90 0.66
0.80 1.10 21
23.67 0.05 0.84
09 pmin 1.19 0.000.000.00
30.42
201
21.79
0.11
0.00 0.58
11 Q2= 461 l/s 19 20
19.53 0.35 0.75
22.97 23.97
101 102
0.00 0.00 52.79
Pipes: v – m/s
Nodes: p – mwc
0.00 Factory
0.00 01
0.00 24.45
2.20 15 16 0.43
0.00 07 0.60
20.45 0.74 21.41 24
1.00
0.00 27.84
28.82
1.06
0.00
1.49 Qres= 353 l/s 0.00
Q1= 621 l/s 03 14 301
0.72
02
0.40 26.99
1.6432.57
1.24 4.54
35.60 23
04 0.32 1.80
13 1.46 17
1.01 30.80 38.04
06 0.79
24.67 27.86
0.44
30.42 0.75
0.19
0.70
0.63 10 0.76 12 18 22
1.19 27.00
24.18 1.18 26.33 0.73 35.03
05 1.17 202
08 24.12 28.00 0.67
0.81 1.09 21
22.75 0.08 0.87
09 pmin 1.16 0.000.000.00
30.11
201
20.80
0.08
0.00 0.60
11 Q2= 331 l/s 19 20
18.69 0.28 0.74
22.33 23.42
101 102
0.00 0.00 53.02 Pipes: v – m/s
Nodes: p – mwc
0.00 Factory
0.00 01
0.00 24.97
2.17 15 16 0.43
0.00 07 0.59
20.97 0.74 21.93 24
1.00
0.00 28.37
29.39
1.05
0.00
1.49 Qres= 223 l/s 0.00
Q1= 615 l/s 03 14 301
0.73
02
0.45 27.44
1.14
1.6233.10 4.54
36.10 23
04 0.27 1.14
13 1.40 17
1.00 31.54 38.67
06 0.79
25.07 28.46
0.34
30.97 0.65
0.13
0.22
0.64 10 0.86 12 18 22
1.17 27.90
25.34 1.23 27.20 0.74 35.88
05 1.65 202
08 24.76 30.92 0.67
0.78 1.10 21
23.44 0.01 0.86
09 pmin 1.18 0.000.000.00
30.97
201
21.65
0.04
0.00 0.59
11 Q2= 467 l/s 19 20
19.70 0.30 0.74
23.27 24.34
101 102
0.00 0.00 52.78 Pipes: v – m/s
Nodes: p – mwc
0.00 Factory
0.00 01
0.00 23.98
2.20 15 16 1.13
0.00 07 0.72
21.17 0.62 22.46 24
0.90
0.00 28.18
28.67
0.00 0.96
1.39 0.53
Qres=301400 l/s
Q1= 622 l/s 03 14
0.60
02
0.45 26.87
1.28
1.6432.54 4.54
35.56 23
04 0.25 2.04
13 1.83 17
1.02 30.65 36.60
06 0.75
24.48 26.21
0.49
30.37 0.50
0.06
0.78
0.63 10 0.71 12 18 22
1.19 26.77
23.83 1.31 25.29 0.75 33.95
05 1.18 202
08 24.03 27.67 0.67
0.81 1.09 21
22.65 0.11 0.84
09 29.05
1.19 0.000.000.00
pmin 201
20.54
0.14
0.00 0.58
11 19
Q2= 333 l/s 20
18.07 0.35 0.75
21.51 22.54
the pipes 01-16 and 13-17 should be enlarged from 300 to 400 and
400 to 500 mm, respectively. In particular, the second pipe was gener-
ating a large velocity (head-loss) and this measure was meant to
reduce its resistance. In addition, two extra pumps should be added to
the pumping station in Source 2 (total 4 1). This remedy, shown in
Figure A2.68, brings the pressure in the factory close to 30 mwc, but
is altogether complex and rather expensive.
A better solution would have been reached if, instead of two extra units
in Source 2, a parallel pipe of 600 mm had been laid next to 102-02, and
the stand-by pump in Source 1 switched on. The pressure would
have grown substantially but the maximum supply capacity of Source 1
would have been exceeded in this situation. This solution, shown in
Figure A2.69, is therefore unacceptable.
101 102
0.00 0.00 54.01
Pipes: v – m/s
Nodes: p – mwc
0.00 Factory
0.00 01
0.00 29.64
2.07 15 16 0.64
0.00 07 0.68
25.06 0.44 26.74 24
0.77
0.00 31.60
33.28
0.00 0.76
1.27 Qres= 125 l/s 0.71
Q1= 584 l/s 03 14 301
0.63
02
0.67 29.28
0.92
1.5235.50 6.07
38.35 23
04 0.03 0.64
13 1.25 17
0.99 34.39 41.52
06 0.75
26.78 31.11
0.11
33.30 0.43
0.03
1.26
0.67 10 1.09 12 18 22
1.15 30.96
29.15 1.35 30.33 0.76 38.95
05 2.28 202
08 27.26 37.93 0.67
0.75 1.10 21
26.01 0.15 0.84
09 pmin 1.22 0.00
0.00
0.000.00
0.00 34.06
201
24.72
0.10
0.00 0.58
11 Q2= 645 l/s 19 20
23.11 0.35 0.75
26.55 27.57
0.00 29.84
15 16 0.64
0.00 1.38 0.72
07 25.74 0.65 26.94
1.01 24
0.00 33.20
33.07
0.00 Q res= 124 l/s
0.66
Q1= 779 l/s 1.50 0.50
03 14 301
0.59
02
1.25 29.38
1.59
2.1837.99 5.50
42.02 23
04
Qmax= 695 l/s 1.05
0.63 0.63
13 1.23 17
06 35.28 40.91
0.76
26.22 30.59
0.82
36.61 0.73
0.21
0.64
0.53 10 0.37 12 18 22
1.26 30.56
27.00 1.18 29.12 0.73 37.83
05 1.60 202
08 29.83 32.35 0.67
1.08
0.86
28.33 0.31 pmin 0.87
21
09 32.91
1.16 0.000.000.00
201
24.46
0.19
Q2= 452 l/s
0.00 0.60
11 19 20
21.56 0.29 0.74
25.16 26.24
on the maximum consumption day except for the factory where the
demand of 30.09 l/s has remained constant.
Effects of the failure have been analysed for each pipe in the system.
The nodes where the pressure drops below 20 mwc during the maximum
consumption hour, as a result of the failure, have been identified.
The direct pumping layout from the S30A3 file has been tested,
while in the case of Alternative B this was the layout from the S30B3
file. In both cases, the new input files have been created, by dropping
the demand (through the demand multiplier) to 75% and switching
Pipe burst Nodes with pmin (mwc) pfact (mwc) Q1 (l/s) Q2 (l/s)
p 20 mwc in node (x)
the stand-by pumps on. The new file names are S30A7.NET and
S30B5.NET, respectively. The calculation results are shown in
Tables A2.18 and A2.19.
Clarification:
● The tables indicate the nodes with pressure below 20 mwc, the
Pipe burst Nodes with pmin (mwc) pfact (mwc) Q1 (l/s) Q2 (l/s) Qr (l/s)
p 20 mwc in node (x)
Conclusions:
● Both layouts show fairly good reliability level. The effects of the pipe
bursts are for majority of the nodes minimal. In few cases the pressure
will be affected in the vicinity of the burst location. The most critical
pipes appear to be 02-06, 18-19 and 16-17 in case of the A layout and
02-06, 18-19, 17-23 and 102-02 in case of the B layout.
● The direct pumping alternative shows higher pressures in general,
which gives impression that this network has more reserve capacity
i.e. more room for reduction of the pipe diameters than the other one.
02-03 01, 03, 04, 07, 09-20 2.95 (15) 15.81 106 413
02-06 None 22.59 (08) 41.61 274 245
03-04 None 26.57 (11) 33.87 211 308
04-05 None 35.88 (11) 41.93 277 242
05-06 None 32.09 (08) 41.72 275 244
05-08 08 32.16 (08) 41.81 276 243
08-09 None 35.82 (11) 41.88 277 242
09-10 09 154.27 (09) 41.94 277 242
04-10 None 28.00 (11) 35.08 220 299
10-12 None 34.12 (11) 40.28 262 257
09-11 None 35.66 (11) 41.87 277 242
11-12 None 25.99 (11) 41.83 276 243
12-18 None 31.92 (13) 43.78 299 220
11-19 None 33.59 (11) 41.90 277 242
18-19 19 19.11 (19) 41.95 278 241
19-20 20 19.22 (20) 41.82 277 242
20-21 None 35.87 (11) 41.87 277 242
21-22 None 35.74 (11) 41.88 277 242
18-22 None 35.66 (11) 41.63 277 242
22-23 None 35.82 (11) 41.82 277 242
17-18 01, 16, 17, 23, 24 172.42 (16) 172.39 284 235
12-13 None 24.08 (08) 41.67 277 242
03-14 None 29.21 (15) 41.29 274 245
03-07 None 26.72 (15) 41.31 275 244
07-15 None 34.88 (15) 41.60 276 243
14-15 None 34.85 (15) 41.62 276 243
13-14 None 35.79 (11) 41.86 276 243
13-17 None 35.82 (11) 41.83 277 242
17-23 None 35.80 (11) 41.81 277 242
15-16 None 35.80 (11) 41.77 276 243
16-17 01, 16, 24 176.49 (16) 173.46 280 239
16-24 None 26.42 (24) 42.08 277 242
23-24 None 35.81 (11) 41.86 277 242
102-02 01-24 32.25 (15) 6.89 0 519
202-18 01-24 49.86 (11) 45.29 519 0
380 Introduction to Urban Water Distribution
This conclusion will be taken into account while deciding the final
layout of this alternative.
102-02 and 202-18 burst. The critical pipe is also 16-17. In case the
branched layout of the secondary pipes would have to be maintained,
laying of the parallels is inevitable in case of the listed pipes.
● parallel pipes, D 300 mm, have been laid along route 01–16.
station in Source 1.
The main characteristics of the pumping stations and the storage volume
are given in Table A2.21.
Qp Hp No. of D H Vtot
(l/s) (mwc) units (m) (m) (m3)
101 102
#N/A
#N/A
Factory
#N/A 500 01
#N/A 300
15 16 300
07 100
300 24
100
300
200 300
03 14
150
02
400 400
500
04 23
400 13
300 17
06 200
400 400
400
150
200
10 400
200 12 18 22
300
400 200
05 202
500
500
08 150
200 200 21
80 300
09 #N/A #N/A
#N/A #N/A
200
201
80
100
11 19 20
200 150
Figure A2.70. Alternative A: pipe diameters at the beginning of the design period.
The final layout of the system at the beginning of the design period
is shown in Figure A2.70 (file S6A9.NET). For the manual operation as
shown in Table A2.22, the range of pressures in the system on the maxi-
mum consumption day is shown in Figure A2.71.
The registered pressure in the factory during the maximum con-
sumption hour is 30.38 mwc. The following pressures are observed in
382 Introduction to Urban Water Distribution
60.0
50.0
Pressure (mwc)
40.0
30.0
20.0
10.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
the case of the pipe burst (the stand-by pumps are Off ):
15-16 28.79
16-17 24.73
16-24 30.53
01-16 (single) 30.18
The pressure during the fire fighting in the factory is 34.12 mwc (the
stand-by pumps On).
The reliability assessment for the 75% demand conditions shows
insufficient pressure during the following pipe bursts (the stand-by
pumps are On):
Except for Node 13, all indicated are peripheral nodes. The table shows
that the effects of the listed pipe bursts are localised to very small parts
of the system and the situation can therefore be considered as satisfac-
tory. The pressure in the factory will also not be affected.
Design Exercise 383
Three additional pump units of the same size as the existing ones, are
planned in each pumping station. For the manual operation as shown in
Table A2.23, the range of pressures in the system during the maximum
consumption day is shown in Figure A2.72.
60.0
50.0
Pressure (mwc)
40.0
30.0
20.0
10.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
101 102
#N/A
#N/A
#N/A Factory
#N/A 01
#N/A 300
600 15 16 300
07 150
400 24
400
200
400 400
03 14 301
150
02
400 400
600
04 23
400 500
13 400 17
300
06 200
400
300
100
400
200 10 400 12 18 22
300
200 200
05
08 150
200 200 21
80 200
09 300
80 100
11 19 150 20
200
Figure A2.73. Alternative B: pipe diameters at the beginning of the design period (S6B4).
Qp Hp No. of D H Vtot
(l/s) (mwc) units (m) (m) (m3)
60.0
50.0
Pressure (mwc)
40.0
30.0
20.0
10.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
6.0
5.5
5.0
Depth (m)
4.5
4.0
3.5
3.0
2.5
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
15-16 27.17
16-17 29.34
16-24 29.72
01-16 (single) 29.50
The pressure during the fire fighting in the factory is pfact 28.59 mwc
(the stand-by pumps are On).
The reliability assessment for the 75% demand conditions shows
insufficient pressure during the following pipe bursts (the stand-by
pumps are turned on):
● two additional pump units of the same type as the existing ones are
going to be installed in the pumping station of Source 1,
● the pumping station in Source 2 is going to be built with three units
of the following duty flow and head: Qd 120 l/s, Hd 40 mwc,
● the clear water reservoir, V 4600 m3 is going to be constructed in
Source 2,
● the diameter of the balancing tank is to be increased from D 40 to
50 m, which effectively means the construction of additional com-
partment, D 30 m, besides the existing one. The total additional
388 Introduction to Urban Water Distribution
For the average flow supply from the pumping stations, the system oper-
ation on the maximum consumption day is shown in Figures A2.76 and
A2.77.
60.0
50.0
Pressure (mwc)
40.0
30.0
20.0
10.0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
6.0
5.5
5.0
Depth (m)
4.5
4.0
3.5
3.0
2.5
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time (hours)
15-16 24.43
16-17 24.01
16-24 27.49
01-16 (single) 27.09
During the fire fighting in the factory, the pressure on the maximum con-
sumption hour is pfact 26.28 mwc (stand-by pumps are On). This pres-
sure is below the required minimum of 30 mwc and local pressure
boosting is advised.
The reliability assessment for the 75% demand conditions (stand-by
pumps are On) shows insufficient pressure during the following pipe bursts:
pressure until the extension will take place. The two remaining units
are left for the second phase.
Alternative B:
● In the case of layout S6B4, the pressure problems start for the
demands around
950 l/s (3420 m3/h), which is the maximum
consumption hour demand around Year 19–20. The reason for this
is the reservoir itself; it facilitates the pressure as long as it is
not empty. To prevent this, the final decision has been made to
build the pumping station with the full number of seven units
already at the beginning of the design period. This should help main-
taining the balancing role of the reservoir in the years before the
extension will take place. The proposed year of the system extension
is Year 19.
The Tables A2.25 and A2.26 show the summary of the phased develop-
ment of the system for the two alternatives.
D 80 2700 — 2700
D 100 2200 — 2200
D 150 2550 — 2550
D 200 6850 — 6850
D 300 5950 1650 7600
D 400 4800 2100 6900
D 500 3500 2000 5500
D 600 — — —
Total pipes (m) 28,550 5750 34,300
D 80 2700 — 2700
D 100 1200 — 1200
D 150 2750 — 2750
D 200 7250 — 7250
D 300 4050 2050 6100
D 400 7100 2950 10,050
D 500 100 — 100
D 600 2000 — 2000
Total pipes (m) 27,150 5000 32,150
Pumping stations Number of units / Qp (l/s) / Hp (mwc)
Investment costs
The investment costs of the final layouts are summarised in Table A2.27
for Alternative A and Table A2.28 for Alternative B.
Clarification:
● The installed capacity of the pumping stations has been assumed as
structure.
Pipe diameter (mm) Total length (m) Total price (US$) Total length (m) Total price (US$)
D 80 2700 162,000.– — —
D 100 2200 154,000.– — —
D 150 2550 229,500.– — —
D 200 6850 890,500.– — —
D 300 5950 1,071,000.– 1650 297,000.–
D 400 4800 1,248,000.– 2100 546,000.–
D 500 3500 1,085,000.– 2000 620,000.–
D 600 — — — —
Total pipes 28,550 4,840,000.– 5750 1,463,000.–
Pumping stations Installed Total price (US$) Installed Total price (US$)
capacity (m3/h) capacity (m3/h)
Alternative B:
Conclusions:
● Alternative B is cheaper than A. The reason is the lower initial invest-
Pipe diameter (mm) Total length (m) Total price (US$) Total length (m) Total price (US$)
D 80 2700 162,000.– — —
D 100 1200 84,000.– — —
D 150 2750 247,500.– — —
D 200 7250 942,500.– — —
D 300 4050 729,000.– 2050 369,000.–
D 400 7100 1,846,000.– 2950 767,000.–
D 500 100 31,000.– — —
D 600 2000 720,000.– — —
Total pipes 27,150 4,762,000.– 5000 1,136,000.–
Pumping stations Installed Total price (US$) Installed Total price (US$)
capacity (m3/h) capacity (m3/h)
Reservoirs Total volume (m3) Total price (US$) Total volume (m3) Total price (US$)
● The cost of the elevated balancing tank appears not to be the predom-
inant factor. Alternative A has lower investment costs for the storage
but more expensive pumping stations.
Reading:
● See notes, Chapter 4, Section 4.1.2: ‘Economic aspects’.
Alternative B:
Distribution system: 0 . 0 0 5 ( 4 , 7 6 2 , 0 0 0 1 , 1 3 6 , 0 0 0 )
US$29,490.–
Pumping stations: 0.020 (4,488,675 2,137,603) US$132,526.–
Reservoirs: 0.008 (2,475,700 1,726,000) US$33,614.–
TOTAL: US$195,630.– per year.
Water price increase
From Table A2.6, the average water demand/production at Year 6 is
31,977 m3/d 11,671,605 m3/y.
At the end of the design period, the annual production equals
61,344 365 22,390,560 m3/y.
The total quantity of water supplied during the design period equals
406,381,510 m3 or on average 16,255,260 m3 per year.
Due to the loan repayment and the O&M costs, the average water
price increase is going to be:
Alternative A:
Alternative B:
Supply factory
Here as well, Alternative B shows better performance than A. The layout
provides good pressures in the factory regardless of calamities in the
system. The small deficit of pressure during the fire fighting should be
overcome by local measures.
Reliability
Both A- and B-layouts are fairly reliable in case of failure in the system.
Overall conclusion
Given all the facts, the final choice in this exercise is Alternative B.