Project Management Assignment-I PGPM-2019-2021
Project Management Assignment-I PGPM-2019-2021
Assignment -I
1. Verify that the Normal Duration for this Project is 22 days and the direct cost is Rs.
3,050,000.
2. What is the Least Cost Schedule to reduce the Project Completion time to 21 days ?
What is the revised Project Cost ?
3. What is the Least schedule to reduce the Project Completion time to 20 days ? What
is the revised Project Cost ?
4. What is the earliest time in which the project can be completed and what is the Least
Cost Schedule for this ? What is the Project cost for this Schedule ?