You are on page 1of 1

Project Management

Assignment -I

Submission Deadline : 4:00 p.m. 2nd Nov., 2020


This Assignment is to be attempted independently and submitted
individually

1. The following project network is associated costs are given ( T in days, C in


Rs.1,000s )

Activity Immediate Cost Slope


Predecessors Tn Cn Tc Cc
A -- 4 210 3 280 70
B -- 9 400 6 640 80
C A 6 500 4 600 50
D A 9 540 7 600 30
E B, C 4 500 1 1100 200
F B, C 5 150 4 240 90
G E 3 150 3 150 --
H D, F 7 600 6 750 150

1. Verify that the Normal Duration for this Project is 22 days and the direct cost is Rs.
3,050,000.

2. What is the Least Cost Schedule to reduce the Project Completion time to 21 days ?
What is the revised Project Cost ?

3. What is the Least schedule to reduce the Project Completion time to 20 days ? What
is the revised Project Cost ?

4. What is the earliest time in which the project can be completed and what is the Least
Cost Schedule for this ? What is the Project cost for this Schedule ?

You might also like