Energy-Power SystemConcrete Floor (With Base) NewScene20170618221141
Energy-Power SystemConcrete Floor (With Base) NewScene20170618221141
Trademark Notice
is trademarks or registered trademarks of Huawei Technologies Co.,Ltd.
Other trademarks,product,service and company names mentioned are the property of their respective owners.
Preconditon:
Remark : Operartions mark in yellow are forbidden in case of thunder storm day
0:22 0:37 0:37 0:52 0:52 1:22 1:22 1:32 1:32 1:42
30Person*Minute 30Person*Minute 30Person*Minute 20Person*Minute 20Person*Minute
Person CD Person BC Person B Person BC Person BC
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
1
Make preparations
4 0
before site visit
Procedure
1.1. Before visiting a site, check site preparations based on
Site Preparation Checklist. For example, check whether
materials arrive at the site, whether site access is
permitted, and whether transmission information, design
files, and tools are ready.
Notes
1. If onsite conditions are inconsistent with the conditions
described in the design file, contact Huawei site engineers
for confirmation.
2. If you encounter site access problems, contact Huawei
site engineers.
Tools
1 2 3
4 5 6
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
1 2 Prepare the utes/Unit
installation for new
network 4 60
deployment
scenarios
Procedure
1. After you arrive at a site, check and confirm related
information based on Site Preparation Checklist Onsite. For
example, check whether the site information and
installation environment are consistent with the design,
whether the materials are a whole set, and whether the
tools are a whole set, and check the responsibility scope.
2. Move installation auxiliaries and tools to the site, and
Material and tool transportation neatly arrange them by type.
to the site 3. Assign tasks based on actual situations.
4. Wear protective cloths and gloves, and set warning
signs.
Notes
1. If onsite conditions are inconsistent with the conditions
described in the design file, contact Huawei site engineers
Responsibility division
3 4 for confirmation.
2. Gently move the materials and protect the product
components from colliding with the door, wall, or goods
EHS protection shelf.
Tools
Helmet&Safet Paper and
1 Compass 2 y Shoes 3 pencil
Long
4 Seat belts 5 measuring 6
tape
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
Material packaging check Unpacking inspection
Check the
materials for 4 30
1 2 Energy
Procedure
1. Check whether the model and number of onsite main
equipment, such as the cabinet, antennas, RRUs, BBU,
and DCDU, are consistent with that specified in the
engineering design file and material checklist (there is a
packing list attached to the equipment packaging), and
whether the appearance of packaging is intact.
2. If the inspection passes, unpack the packaging, and
check whether the number of materials is correct and
whether they are intact. In addition, request the logistics
service provider and implementation team to sign the DN.
3. Provide the NMC with the BBU ESN, which can be
obtained from the left mounting ear of the BBU.
4. Sort the materials and classify them as main equipment
and materials for the antenna system.
Notes
1. Do not unpack the packaging, and report the problem to
the project team in either of the following scenarios:
The model and number of onsite equipment are
Material placement inconsistent with the design file.
3 The packaging is seriously damaged or soaked.
4
Tools
1 2 3
4 5 6
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Installed storage Personnel
utes/Unit
batteries 1 Install storage
batteries and
2 30
related cables in a
TP48200A
Procedure
1. Turn off the BAT power switch on the ETP to avoid large
current.
BAT 2. Install storage batteries into the battery compartment of
2 switch the cabinet in sequence.
3. Remove the protective cover from the storage batteries,
and install a copper bar on the poles of adjacent storage
batteries.
4. Connect the other end of the power cable of the storage
batteries to the positive and negative poles of the storage
batteries. After the exhaust pipe is installed, install the
removed protective cover and turn on the BAT power
switch.
3
Notes
1. During installation, prevent the exposed metal conductor
of the power cable from contacting the metal housing of the
cabinet.
2. Add an insulation cover when using a wrench and
screwdriver. Otherwise, the storage batteries may be
burned out and cause human injuries.
4 Tools
Phillips
screwdriver and
1 flat-head 2 Diagonal pliers 3 Socket wrench
screwdriver (6
mm)
4 5 6
Materials
1 Storage batteries 2 Copper bar/pole cable
3 Cable tie 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
Install alarm cable
2 30
for TP48200A
Procedure
1. Connect FE to BBU(UPEU) MON1,Route the FE to
TPA SMU02B board 10101(RS485) port.
2. Connect transmission FE to BBU LTE FE/GE0
1 port,Route to SLPU(UFLP) inside FE/GE0 port.
Notes
Tools
1 2 3
4 5 6
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
1 utes/Unit
Install a power
input cable for a 1 30
TP48200A
Procedure
1. Determine the length of the power cable based on the
designed circuit route and then prepare AC power cables.
2. Route the power cables into the cabinet from the cable
outlet at the left front part of the cabinet, install a terminal
on the power cable, and connect the power cables to the
AC wiring terminals on the PDU as follows: a. Three-phase
power: Connect the brown, black, gray, and blue power
cables to the L1, L2, L3, and N wiring terminals,
respectively. b.Single-phase power: Install the short-
circuiting bars and L and N wires before cable connection.
3. Route the power cables into the AC power cabinet (a
PVC pipe is recommended for the power cable outside the
cabinet), trim off the excess of the power cables, prepare
connectors, and connect the power cables to the specified
3 positions.
Notes
1. The color of the power cable differs in different countries.
The procurement of the power cable must comply with local
regulations.
2. The OT terminal must be coated by PVC insulation tape
during cable routing to avoid contacting with the electrode.
3. The electrode to be connected to the power cabinet must
be powered off (the circuit breaker is turned off or the fuse
is pulled out) before the power cabinet is powered on.
2 During the power-on operation, the operation personnel
must wear a pair of insulation gloves and use insulated
Tools
tools. If a voltage monitoring cable is installed, connect it
and Measuring
the powertape
cable
(5 to the Cable
circuitcutter
breaker. Hydraulic pliers
1 m) 2 and utility knife 3 and heat gun
4 5 6
Materials
1 PGND cable for cabinet 2 14-8 OT terminal
5 6
Duration
Installation
SN Task Description Person*min
Personnel
Installed TP48200A 1 utes/Unit
Install a TP48200A 2 30
Procedure
1. Determine the position for installing the cabinet,Use a
hammer drill to drill holes, and hammer expansion bolts into
the holes. Then, rotate the expansion bolts clockwise for
two or three circles and remove the bolts counterclockwise
from the holes. (If attachment plates for U steel or universal
bases are adopted onsite, skip this step.)
2. Move the cabinet onto the required installation
position,.Add spacers to ensure level.then use a torque
wrench to tighten the bolts.
4-M12x60 Notes
1. Newly installed cabinets must be level with existing ones.
2. Do not use a hammer drill to drill holes from the base.
3. After disassembling an expansion bolt, ensure that the
2 top of the expansion tube is level with the concrete floor. If
they are not level with each other, the cabinet cannot be
securely installed on the concrete floor.
Hammer drill,
1.Bolt 2.Spring washer vacuum
Tools
cleaner,
3.Flat washer 4.Expansion tube
Goggle,
Measuring tape (5
1 m) 2 Earplug, claw 3 Socket wrench
hammer, level
meter, marker
4 5 (marking-off 6
template)
Materials
1 TP48200A 2 Expansion bolt
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
Connection of a
1 PGND cable Install a PGND
cable for a 1 30
2 TP48200A
Procedure
1. Prepare a cable with a proper length based on the actual
route and install an OT terminal at both ends of the cable.
2. Connect one end of the PGND cable to the ground bar
on the inner side of the cabinet.
3. Route and connect the other end of the PGND cable to
the external cabinet copper bar for grounding.
Notes
1. Grounding principles: An equipotential cable is used to
3 connect the BTS3900AL AC cabinet and another cabinet,
and the PGND cable in the BTS3900AL AC cabinet is
connected to an outdoor ground bar.
2. When installing the PGND cable, tightly press the OT
terminal in the correct direction.
External Tools
ground bar Measuring tape (5 Cable cutter Hydraulic pliers
1 m) 2 and utility knife 3 and heat gun
4 5 6
Materials
1 PGND cable for cabinet 2 14-8 OT terminal
5 6
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
Install a TP48200A
monitoring signal 1 15
cable
Procedure
1. prepare signal cable, connect this cable from
RS485/RS232 port of SMU to MON1 port of BBU/UPEU
Notes
Tools
1 Diagonal pliers 2 3
4 5 6
Materials
1 Alarm signal cable 2 Cable tie
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
utes/Unit
1
Prepare labels 1 25
Procedure
1. Choose proper labels (labels are classified into labels of
signal cables and labels of power cables) based on
application scenarios.
2. Fill in/prepare labels following label content rules agreed
by the customer.
3. Attach/secure prepared labels. Fold labels of signal
cables in the way specified in the figure, and bind labels of
power cables using in the delivered cable ties.
4.Ensure that the label orientation and installation location
is easy for information query.
2 Labels of signal cables Labels of power cables
Notes
cable cable
Adhesive side 1. Labels are attached at the position 20 mm away from a
right folding connector by default.
right folding
3 4
Tools
cable
Three procedures 4 5 6
5 6
Duration
Installation
SN Task Description Person*min
Personnel
1 utes/Unit
Check the
hardware 2 20
installation
Procedure
1.Check the hardware installation based on the design
drawings and Hardware Installation Quality Checklist.
2. Check whether the equipment, cabinets, antennas, and
BBU are securely installed at specified positions and
whether their appearances are intact.
3. Check whether the cable routes are correct, whether the
feeder connectors are securely installed, and whether cable
labels are legible.
4. Check whether the downtilt angle and azimuth of the
antennas are correct.
5. Check whether the installation position and route of the
PGND cable are correct and whether the cable connectors
are securely installed.
6. Check whether connectors are reliably and securely
waterproofed.
2 3
Notes
1. The design drawings may be a TSSR for projects outside
China.
2. The project team needs to confirm and sign Hardware
Installation Quality Checklist with the customer and
subcontractors in advance.
4 5 6 Tools
4 5 6
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
1 Tool sorting 2 Material sorting utes/Unit
Clean the site
4 20
before leaving
Procedure
1. Sort onsite tools.
2. Remove the redundant materials.
3. Clean the equipment room and the area for installing the
antenna system. Then, pack onsite garbage and take it
when leaving the site.
4. Based on requirements in Project PAT Document, take
photos, which will be used for preparing acceptance
documents.
5. Fill in the registration form for equipment room visit.
6. Lock the door of the equipment room, and notify the
3 Cleaning
Photograph
NMC engineer of alarm information checking. If no alarm is
4 generated, leave the site.
Notes
1. Customize Project PAT Document based on project
requirements before using it.
2. Ensure that no sundries are reserved onsite after project
implementation.
3. Before leaving the equipment room, check whether the
Registration form for equipment room live network works properly with the OMC engineer.
5 visit 6 Door locking before leaving the site
Tools
Broom and
1 dustpan 2 Camera 3
4 5 6
Materials
1 2
3 4
5 6
Duration
Installation
SN Task Description Person*min
Personnel
1 utes/Unit
2
Conduct a power-
1 20
on check (energy)
Procedure
1. Use a multimeter to measure the voltage of the storage
battery group and record the value.
2. Turn off the circuit breaker for AC power and check
whether the voltage between the DC busbar and the
negative busbar is the same as that displayed on the
monitoring module. Decrease the float charging voltage on
the monitoring module to ensure that it is about 1 V higher
than the voltage of the storage battery group.
3. Use an insulated handle to install the fuse for storage
batteries and restore the float charging voltage on the
monitoring module. Then, check whether the indicators on
each module indicate an alarm.
Notes
3
1. The float charging voltage must be decreased on the
monitoring module. Otherwise, the sparking that may be
generated when the fuse is installed for storage batteries
will cause human injuries.
2. If an exception occurs, shut down the power switch,
rectify the fault, and power on the equipment.
Tools
1 Multimeter 2 3
4 5 6
Materials
1 2
3 4
5 6
Main Item NO 条目
first
Prepare the installation aid kit
for new network 1.1 and fire
deployment scenarios extingui
sher
Pre-
Prepare the installation climbing
for new network 1.1 tower
deployment scenarios EHS
checking
Check
whether
the
storage
Install storage
batteries and related 1.1 batterie
s are
cables in a TP48200A installe
d
correctl
y
Check
the
Install alarm cable for alarm
1.1
TP48200A cable
connecti
on
Check
the
Install alarm cable for alarm
TP48200A 1.1 cable
connecti
on
Check
the
power
cable
Install a power input connecti
cable for a TP48200A 1.1 on is
installe
d
properly
.
Check
the
power
cable
Install a power input 1.1 connecti
cable for a TP48200A on is
installe
d
properly
.
Check
whether
the
cabinet
is
installe
Install a TP48200A 1.1
d
accordin
g to the
construc
tion
drawing.
Check
whether
the
cabinet
is
installe
Install a TP48200A 1.1 d
accordin
g to the
construc
tion
drawing.
Check
whether
the
appearan
ce of
Install a TP48200A 1.1 the
cabinet
is in
good
conditio
n
Check
whether
the
appearan
ce of
Install a TP48200A 1.1 the
cabinet
is in
good
conditio
n
Check
whether
the
appearan
ce of
Install a TP48200A 1.1 the
cabinet
is in
good
conditio
n
Check
whether
the
appearan
ce of
Install a TP48200A 1.1 the
cabinet
is in
good
conditio
n
Check
whether
the
groundin
g cable
Install a PGND cable for
a TP48200A 1.1 route
is
installe
d
correctl
y
Check
whether
the
groundin
g cable
Install a PGND cable for 1.1 route
a TP48200A
is
installe
d
correctl
y
Check
whether
the
equipote
Install a PGND cable for ntial
1.1 cables
a TP48200A are
installe
d
correctl
y
Check
whether
the
equipote
ntial
Install a PGND cable for
a TP48200A 1.1 cables
are
installe
d
correctl
y
Check
the
Install a TP48200A monitori
monitoring signal cable 1.1 ng
signal
cable
Check
whether
the
environm
Clean the site before 1.1 ent of
leaving
site is
clean
before
leaving
Fire
Clean the site before extingui
leaving 1.1 sher in
Vehicle?
Oil/Fuel
Clean the site before
leaving 1.1 /Water
Levels?
Windshie
Clean the site before 1.1 ld
leaving
Wipers ?
Brakes
Clean the site before (Pedal
1.1
leaving Pressure
)?
Sides/Ce
ntral
Mirrors
Clean the site before
leaving 1.1 (adjust
before
driving)
?
Site
Clean the site before 1.1 Clockin
leaving or punch
in done?
Both
Clean the site before Headligh
1.1 ts (High
leaving & Low
Beam)
Installa
Clean the site before tion
leaving 1.1 tools
check
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
图片 原始图片 200 N N
是否是
条目类型 默认值 严重级别 样例图片
EHS
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Major
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Critical
N Major
N Critical
N Major
Installation Quick Guide
1.Make preparations before site visit:Before visiting a site, check site
preparations, especially site access, design files, and materials, based 5.Install alarm cable for TP48200A: 9.Install a TP48200A monitoring signal cable:
on Site Preparation Checklist Before Site Visit.
3.Check the materials for Energy:Unpack the packaging, check the 7.Install a TP48200A:Determine the position for installing the cabinet, 11.Check the hardware installation:Check hardware installation based
materials, and place them based on installation positions and drill holes, and install the base. Then, adjust the base and secure the
on the design drawings and quality requirements.
sequences. cabinet to the base.
4.Install storage batteries and related cables in a TP48200A:Install 8.Install a PGND cable for a TP48200A:Cut off a PGND cable based on 12.Clean the site before leaving:Clean the construction area, take
storage batteries and copper bars, and then connect the batteries to the actual cable route, prepare connectors for the cable, and use the
photos based on the requirements, and take records.
preconfigured charging cables for storage batteries. cable to connect the cabinet ground point and outdoor ground bar.
Installation Quick Guide
13.Conduct a power-on check (energy):Power on the equipment after
verifying that the equipment and cables are correctly installed.
Standard Inspect Procedure(SIP)
Site name: Date: Construction team: Supervisor: Overseer:
Cable Pole screw of battery line should be sure to tighten Visually Audit onsite 4
2 installatio Subcont
Signal Signal cable should not be damaged, fracture, tab, signal cable plug without
n ractor / Visually Audit onsite 4
cable damage, the plug connection are correct and reliable;
Huawei
Pigtail routed outside the cabinet, must take protective measures, such as adding
protection tube or channel.RRU equipment optical fiber (CPRI) into the window Visually Audit onsite 4
Subcont before have drip loop;
Without use of optical fiber head and single board interface should be protected by
ractor / Cable Visually Audit onsite 4
protective cap (plug);
Huawei
A tail fiber in the cabinet shall be neatly coiled fiber in disc box or wound into a
Visually Audit+Tape onsite 4
diameter greater than 8cm ring fixed;
Feeder, lightning arrester connection is reliable, outdoor do waterproof processing.
Feeder Subcont Visually Audit onsite 8
Should done drip loop before inter room.
3 installatio ractor / Feeder Feeder grounding in accordance with design, and waterproofing. Visually Audit onsite 4
n Huawei
Bending radius is not less than the diameter of the feeder 10 times. Visually Audit+Tape onsite 4
For 1.2m and above the microwave antenna must be installed reinforcing bar
Visually Audit onsite 4
Antenna Subcont correctly.
4 installatio ractor / Antenna Compare design
n Huawei Microwave /radio antenna model, caliber, hanging high file,visually audit or use onsite 8
telescope to check
Tag Subcont
Power line, ground line, signal cable , optical fiber sticking reliable and neat, label
5 specificat ractor / Tag Visually Audit onsite 4
filled out correctly, meet customer requirements.
ion Huawei
Check the site self-inspection
Hardware Subcont Self- After the subcontractor complete the site installation , according to installation reports,whether self-inspection onsite/
6 self- ractor / inspect standards on the site for the 100% self-inspect and output reports. results is the same whit onsite, remot 8
whether self-inspection
inspect Huawei report qualified to cutover network e
Subcont
Finished Site
7 ractor / The rack should be clean, no debris. Visually Audit onsite 4
cleaning cleaning
Huawei
Standard Tools
Antenna
install
ation
tool
Compass 1PCS
Auxilia
ry
Tools
Paper and Broom and
Scissor 1PCS Camera 1PCS
pencil 1PCS dustpan 1PCS
Cable
connect
or
process
ing and
Phillips
connect
ion Long measuring Cable cutter screwdriver and Diagonal pliers Hydraulic pliers
Tools and utility knife flat-head and heat gun
tape 1PCS 1PCS
1SET screwdriver (6 2SET
mm) 1SET
Cabinet
s &
Module Hammer drill,
Install vacuum cleaner,
ation Goggle,
Tools Inclinometer Multimeter Measuring tape Socket wrench Earplug, claw
1PCS 1PCS (5 m) 1PCS 1PCS hammer, level
meter, marker
(marking-off
template) 1SET
EHS
Tools
Helmet&Safety
Seat belts 2PCS
Shoes 4SET
Main Equipment List
Provide 220V AC to
DC -48V DC, the DC
3 TP48200A power supply PGND
4 cable for cabinet
equipment, outdoor
ac scene allotment
Store electrical
7Storage batteries energy, emergency 8 Cable tie
power during a power
outage
Copper
9 bar/pole cable 10
Alarm signal cable
Special Requirement
CraftName Custom Requirement