Professional Documents
Culture Documents
Abstract—Special system studies are needed to assess the that, most consulting companies recommend performing a
different preliminary designs of solar photovoltaic (PV) projects. snubber circuit study as well as a ferroresonance study prior
One of these is a ferroresonance study. The main purpose of a to project energization. This paper deals exclusively with the
ferroresonance study is to investigate whether the voltage within
the project can reach damaging levels under steady state opera- ferroresonance study. In solar PV projects, the distributed
tion. Ferroresonance can become a concern for solar PV project nature of cable capacitance across a large georgraphical area
owners due to the distributed nature of shunt cable capacitance may raise a concern for ferroresonance due to the possibility
in the collector system. This distributed shunt capacitance can of interaction between those distributed capacitance and the
interact with the inductance of the main power transformers iron core of the MPTs, ISUs and instrument transformers.
and the instrument transformers causing the voltage within the
project to reach dangerous levels. To perform a ferroresonance The paper is organized as follows: the EMT system model
study for a large 240 MW solar PV farm, a detailed electro- is developed in section §II. The scenarios studied are present
magnetic transient (EMT) model of the project has to be built. in section §III. Simulation results are offered in section §IV.
A detailed EMT model will have a large number of inverters Conclusions are provided at the end of the paper.
and thus the run time of the model becomes prohibitive even
for a single scenario. In this paper, we simplify the EMT model II. S YSTEM M ODEL
focusing only on the components that need to be modeled for the
purpose of the ferroresonance study thus reducing the run time A simplified schematic of one-line diagram of the project
of the EMT model. Various scenarios corresponding to different is shown in figure 1 below. A detailed PSCADTM model
operation modes of the project have been simulated. Simulation has been built and used for producing the results on this
results shows that the project is not susceptible to ferroresonance report. The inverter is represented as a voltage source behind
except for unusual operating modes during energization and at
night when the inverters are not producing any power output. the LCL filter. The voltage source magnitude and angle are
adjusted such that they produce the correct power flow under
I. I NTRODUCTION the various scenarios studied. This simplified inverter model
Increased penetration of renewable energy resources into the should not affect the results as it is not known that the inverter
grid has resulted in higher demand for special system studies controls bear a relation to the ferroresonance phenomenon.
[1] to assess their impact on various aspects of the power This inverter model simplification results in a drastic reduction
system. One of these studies is ferroresonance study. of runtime of the EMT model.
Ferroresonance is sustained overvoltages at the secondary The project is divided into two phases and each phase is
sides of the main power transformers (MPT), inverter step-up connected to a different MPT. The low voltage sides of the
(ISU) transformers and instrument transformers under certain MPTs are connected to each other using a normally open tie
system configurations [2]. The cause of all known ferroreso- breaker that is closed in case one MPT fails. Due to grid
nance overvoltages is the interaction between the capacitance requirements, the project has 28 MVArs of capacitor banks
of the system (including stray, transmission line and cable distributed across four capacitor banks. The capacitor banks
charging capacitances) and the nonlinear inductance of the are attached to phase II of the project. Phase I is double the
transformers. size of phase II in terms of gross name plate, i.e., phase I is
The point of operation on the magnetization curve of the 160 MW while phase II is 80 MW. Each feeder has different
transformer is greatly affected by the capacitance of the system number of inverters connected to it.
[3]. For very small capacitance and/or light loading conditions, The configuration of each feeder has been removed from
the operating point could lie on the saturation part of the mag- the paper for confidentiality reasons. Phase I has a sizable
netization curve of the MPTs, ISUs or instrument transformers fault current limiter on of the feeders to limit the short circuit
causing very high sustained overvoltages. Ferroresonance is contribution of the project. The project is constructed over a
generally excited at low power output or unbalanced switching relatively large geographical areas and due to that the collector
of feeders. This can be understood by referring to [4], [5], [6]. system has overhead lines connecting the underground cable
Recently, solar PV project owners are concerned of trans- to the project substation. The length of some of the overhead
former failure due to switching transients [7], [8]. Due to lines are more than five miles.
Authorized licensed use limited to: Cornell University Library. Downloaded on September 04,2020 at 14:44:28 UTC from IEEE Xplore. Restrictions apply.
2018-PSEC-0683 Page 2 of 4
Authorized licensed use limited to: Cornell University Library. Downloaded on September 04,2020 at 14:44:28 UTC from IEEE Xplore. Restrictions apply.
Page 3 of 4 2018-PSEC-0683
TABLE I
F ERRORESONANCE STUDY SCENARIOS
Fig. 3. Secondary three phase voltages of CCVT for scenario A1 Fig. 4. Secondary three phase voltages of CCVT for scenario B2
Authorized licensed use limited to: Cornell University Library. Downloaded on September 04,2020 at 14:44:28 UTC from IEEE Xplore. Restrictions apply.
2018-PSEC-0683 Page 4 of 4
Fig. 6. Secondary three phase voltages of MV PTs for scenario C1 Fig. 8. Secondary three phase voltages of MV PTs for scenario D3
is re-energized in scenarios D1 to D4, it was found that the detail. Each inverter was modeled as a voltage source behind
project is in risk for ferroresonance unless all poles of the HV its LCL filter. The feeders of the collector system has been
breaker is closed. The three phase voltages at the secondaries modeled using pi-sections. The inverter LCL filter has been
of the medium voltage transformers are shown in figure 7. retained in the EMT model due to the important role the filter
It was found that CCVT is not at risk of ferroresonance and plays in the ferroresonance phenomenon. Various study scenar-
ferroresonance only occurs at the MV potential transformers ios have been designed to simulate the operating conditions of
secondaries. the solar project. These scenarios simulate project energization
and steady state at 0%, 10% or 100% project output. It
was revealed that under unusual system configuration, mainly
during energization and at night, the project is susceptible to
ferroresonance.
R EFERENCES
[1] A. Abdullah and B. Yancey, “A reduced order model for a tov study in
a solar pv project,” in 2017 IEEE/IAS Industrial & Commercial Power
Systems Technical Conference (I&CPS), 2017.
[2] D. A. Jacobson, “Examples of ferroresonance in a high voltage power
system,” in Power Engineering Society General Meeting, vol. 2, 2003.
[3] E. Dolan, D. Gillies, and E. Kimbark, “Ferroresonance in a transformer
switched with an ehv line,” IEEE Transactions on Power Apparatus and
Systems, no. 3, pp. 1273–1280, 1972.
[4] U. Karaagac, J. Mahseredjian, and L. Cai, “Ferroresonance conditions
in wind parks,” Electric Power Systems Research, vol. 138, pp. 41–49,
2016.
[5] R. Karlicek and E. Taylor, “Ferroresonance of grounded potential trans-
Fig. 7. Secondary three phase voltages of MV PTs for scenario D2 formers on ungrounded power systems,” Transactions of the American
Institute of Electrical Engineers. Part III: Power Apparatus and Systems,
Lastly, scenarios E1 to E3 simulate the cases in which one vol. 78, no. 3, pp. 607–614, 1959.
[6] G. Swift, “An analytical approach to ferroresonance,” IEEE Transactions
of the MPTs fails, the tie breaker is closed and the project on Power Apparatus and Systems, vol. 1, no. PAS-88, pp. 42–46, 1969.
is online at night with no power output. In these cases, it [7] P. E. Sutherland, M. E. Valdes, and G. H. Fox, “Snubber design for
was found, similar to scenarios D1 to D4, that the project is transformer protection,” IEEE Transactions on Industry Applications,
vol. 52, no. 1, pp. 692–700, 2016.
is susceptible to ferroresonance unless all poles of the HV [8] D. D. Shipp, T. J. Dionise, V. Lorch, and B. G. MacFarlane, “Trans-
breaker is closed. It was also found that CCVT is not at risk former failure due to circuit breaker induced switching transients,”
of ferroresonance and ferroresonance only occurs at the MV in 2011 IEEE Industrial and Commercial Power Systems Technical
Conference. IEEE, 2011, pp. 1–10.
potential transformers secondaries.The three phase voltages at [9] EMA Electromechanics, “Combined vacuum substation circuit breaker
the secondaries of the MV potential transformer is shown in and high-speed mechanically interlocked grounding switch.” [Online].
figure 8. Available: http://emaelectromechanics.com/vdhgsmi/
[10] J. Woodworth, “Arrester selection guide.” 2011, available on-
All scenarios that were found to be in risk for ferroresonance line at http://www.arresterworks.com/arresterfacts/pdf_files/Arrester_
are pointed out in table I in the red color. Characteristics_for_ATPDraw_Users.xls.
V. C ONCLUSIONS
A ferroresonance study of a relatively large solar farm has
been presented. The study modeled the project in PSCADTM in
Authorized licensed use limited to: Cornell University Library. Downloaded on September 04,2020 at 14:44:28 UTC from IEEE Xplore. Restrictions apply.