You are on page 1of 4

Page 1 of 4 2018-PSEC-0683

A Ferroresonance Study of a 240 MW Solar PV


Project
Ahmad Abdullah
Department of Electrical Power and Machines
Cairo University, Faculty of Engineering
Gizah, Egypt 12613
ahmad.abdullah@ieee.org

Abstract—Special system studies are needed to assess the that, most consulting companies recommend performing a
different preliminary designs of solar photovoltaic (PV) projects. snubber circuit study as well as a ferroresonance study prior
One of these is a ferroresonance study. The main purpose of a to project energization. This paper deals exclusively with the
ferroresonance study is to investigate whether the voltage within
the project can reach damaging levels under steady state opera- ferroresonance study. In solar PV projects, the distributed
tion. Ferroresonance can become a concern for solar PV project nature of cable capacitance across a large georgraphical area
owners due to the distributed nature of shunt cable capacitance may raise a concern for ferroresonance due to the possibility
in the collector system. This distributed shunt capacitance can of interaction between those distributed capacitance and the
interact with the inductance of the main power transformers iron core of the MPTs, ISUs and instrument transformers.
and the instrument transformers causing the voltage within the
project to reach dangerous levels. To perform a ferroresonance The paper is organized as follows: the EMT system model
study for a large 240 MW solar PV farm, a detailed electro- is developed in section §II. The scenarios studied are present
magnetic transient (EMT) model of the project has to be built. in section §III. Simulation results are offered in section §IV.
A detailed EMT model will have a large number of inverters Conclusions are provided at the end of the paper.
and thus the run time of the model becomes prohibitive even
for a single scenario. In this paper, we simplify the EMT model II. S YSTEM M ODEL
focusing only on the components that need to be modeled for the
purpose of the ferroresonance study thus reducing the run time A simplified schematic of one-line diagram of the project
of the EMT model. Various scenarios corresponding to different is shown in figure 1 below. A detailed PSCADTM model
operation modes of the project have been simulated. Simulation has been built and used for producing the results on this
results shows that the project is not susceptible to ferroresonance report. The inverter is represented as a voltage source behind
except for unusual operating modes during energization and at
night when the inverters are not producing any power output. the LCL filter. The voltage source magnitude and angle are
adjusted such that they produce the correct power flow under
I. I NTRODUCTION the various scenarios studied. This simplified inverter model
Increased penetration of renewable energy resources into the should not affect the results as it is not known that the inverter
grid has resulted in higher demand for special system studies controls bear a relation to the ferroresonance phenomenon.
[1] to assess their impact on various aspects of the power This inverter model simplification results in a drastic reduction
system. One of these studies is ferroresonance study. of runtime of the EMT model.
Ferroresonance is sustained overvoltages at the secondary The project is divided into two phases and each phase is
sides of the main power transformers (MPT), inverter step-up connected to a different MPT. The low voltage sides of the
(ISU) transformers and instrument transformers under certain MPTs are connected to each other using a normally open tie
system configurations [2]. The cause of all known ferroreso- breaker that is closed in case one MPT fails. Due to grid
nance overvoltages is the interaction between the capacitance requirements, the project has 28 MVArs of capacitor banks
of the system (including stray, transmission line and cable distributed across four capacitor banks. The capacitor banks
charging capacitances) and the nonlinear inductance of the are attached to phase II of the project. Phase I is double the
transformers. size of phase II in terms of gross name plate, i.e., phase I is
The point of operation on the magnetization curve of the 160 MW while phase II is 80 MW. Each feeder has different
transformer is greatly affected by the capacitance of the system number of inverters connected to it.
[3]. For very small capacitance and/or light loading conditions, The configuration of each feeder has been removed from
the operating point could lie on the saturation part of the mag- the paper for confidentiality reasons. Phase I has a sizable
netization curve of the MPTs, ISUs or instrument transformers fault current limiter on of the feeders to limit the short circuit
causing very high sustained overvoltages. Ferroresonance is contribution of the project. The project is constructed over a
generally excited at low power output or unbalanced switching relatively large geographical areas and due to that the collector
of feeders. This can be understood by referring to [4], [5], [6]. system has overhead lines connecting the underground cable
Recently, solar PV project owners are concerned of trans- to the project substation. The length of some of the overhead
former failure due to switching transients [7], [8]. Due to lines are more than five miles.

978-1-5386-4536-9/18/$31.00 © 2018 IEEE

Authorized licensed use limited to: Cornell University Library. Downloaded on September 04,2020 at 14:44:28 UTC from IEEE Xplore. Restrictions apply.
2018-PSEC-0683 Page 2 of 4

The 345 kV circuit breaker supports single pole operation


and is modeled as such. All MV circuit breakers are EMA
breakers [9] that has a grounding switch mechanically inter-
locked with the breaker’s main contacts. These circuit breakers
are equipped with a mechanically interlocked switch on the
load side that grounds the load side within 1 cycle of opening
the circuit breaker’s main contacts. . Finally, Surge Arrester
V-I characteristics have been modeled according to [10].
III. M ETHODOLOGY
The analysis targeted to determine if the solar PV project
can suffer from ferroresonance under various operating con-
ditions. The operating conditions are listed in table I. The
scenarios have been designed to correspond to operating
conditions that is anticipated during the life of the project.

The project is operated with the tie breaker in the open


position and scenarios from A1 to A3 and C1 to C3 are
designed to simulate normal operation in which the project
is operated at low output or with the inverter at the idle status
producing no power. Ferroresonace is not known to be excited
under full project output and as such no scenarios for full
output power has been investigated for ferroresonance. In case
one of the MPTs are out of service, the tie breaker is closed
and the project is operated using on MPT only. Scenarios D1
Fig. 1. Single Line Diagram of the project
to E3 simulate such conditions.
Scenarios B1 to B4 and D1 to D3 simulate the energization
of the project with the inverters disconnected. Scenarios C1 to
C3 and E1 to E3 simulate night conditions when the inverters
are online yet producing no power, i.e., “idle conditions”.
To run the scenario, the PSCADTM case has been set up
from the beginning with the correct power flow under three
phase balanced condition. After than, switching actions to
correspond for the scenarios was invoked during run-time.
For example, to set up the case for scenario B2, the HV CB
would be setup such that all of its poles are closed from the
beginning. After 1 seconds of simulations, two poles of it
are opened to simulated the scenario under study. The case
is then run for an additional10 seconds. This relatively long
simulation time is due to the fact that the for the effect of the
Fig. 2. MV potential transformers magnetization curve ferroresonance to appear, the hysteresis of the iron core has
to come into play and this is simulated within the solution
engine of PSCADTM as a integration. Thus, this relatively
The MPTs, ISUs and the instrument transformers are mod- long simulation time is done mainly for the integral to have
eled utilizing their magnetization curves. Both the MPTs and sufficient time to cause high voltages, if there any.
the ISUs have a knee voltage of 1.24 pu while the MV
potential transformers have a knee voltage of 1.16 pu. The IV. R ESULTS
POI has a voltage of 345 kV and the HV CCVT at the project For the scenarios A1 to A3 in which is operated at 10%
entrance has a knee voltage of 1.2 pu. The magnetization capability, it was found that the project is not at risk for
characteristics of the MV potential transformers are shown ferroresonance. The scenarios from A1 to A3 simulate the
in figure 2 which is the same for MPTs and ISUs but with the conditions that are encountered at early morning and in the
knee voltage points mentioned above. The projects has two late afternoon when the sun is either still rising or setting.
potential transformer only each of which is installed the MV The three phase voltages at the secondaries of the CCVT for
bus of each project phase. Voltage at the secondaries of the all scenarios are shown in figure 3.
ISUs and instrument transformers as well as at the MV and Scenarios B1 to B4 which were designed to simulate project
HV levels have been monitored. energization showed risk of ferroresonance. The risk only

978-1-5386-4536-9/18/$31.00 © 2018 IEEE

Authorized licensed use limited to: Cornell University Library. Downloaded on September 04,2020 at 14:44:28 UTC from IEEE Xplore. Restrictions apply.
Page 3 of 4 2018-PSEC-0683

TABLE I
F ERRORESONANCE STUDY SCENARIOS

Study Scenario Study Case Description


A1 MV CBs closed with all poles of HV CBs closed (normal operation)
Inverter at 10% Output
Tie Breaker Open A2 MV CBs closed with single pole of HV CBs open
A3 MV CBs closed with two poles of HV CBs open
B1 MV CBs open and MPTs energized
Inverter Disconnected B2 Two poles of HV CBs open with MV CBs closed
B3 Single pole of HV CBs open with MV CBs closed
B4 All HV CBs poles closed with MV CBs closed
C1 MV CBs closed with two poles of HV CBs open
Inverter Idle
C2 MV CBs closed with single pole of HV CBs open
C3 MV CBs closed with all HV CBs poles closed
Tie Breaker Closed

D1 MV CBs closed with all HV CBs poles closed


Inverter Disconnected
D2 MV CBs closed with single pole of HV CBs open
D3 MV CBs closed with two poles of HV CBs open
E1 MV CBs closed with HV poles closed
Inverter Idle
E2 MV CBs closed with single pole of HV CBs open
E3 MV CBs closed with two poles of HV CBs open

Fig. 3. Secondary three phase voltages of CCVT for scenario A1 Fig. 4. Secondary three phase voltages of CCVT for scenario B2

exists when the project is energized in an unbalanced manner


in which one or two phase of the HV circuit breaker is closed
while the others are open. It was found that ferroresonance are
at the secondaries of the potential transformers at the MV level
but not at the HV side altogether. The three phase voltages at
the secondaries of the CCVT and the potential transformers for
scenario B2 are shown in figure 4 and figure 5, respectively.
Scenarios C1 to C3 were simulated to see whether the
project is susceptible to ferroresonance at night when the
inverters are online yet producing no power. It was found that
only scenario C1 is susceptible to ferroresonance. Ferroreso-
nance were found to be at the secondaries of the MV potential
transformers and it was found that the ferroresonance is not Fig. 5. Secondary three phase voltages of MV PTs for scenario B2
severe as shown in figure 6.
In case one of the power transformers fails and the project

978-1-5386-4536-9/18/$31.00 © 2018 IEEE

Authorized licensed use limited to: Cornell University Library. Downloaded on September 04,2020 at 14:44:28 UTC from IEEE Xplore. Restrictions apply.
2018-PSEC-0683 Page 4 of 4

Fig. 6. Secondary three phase voltages of MV PTs for scenario C1 Fig. 8. Secondary three phase voltages of MV PTs for scenario D3

is re-energized in scenarios D1 to D4, it was found that the detail. Each inverter was modeled as a voltage source behind
project is in risk for ferroresonance unless all poles of the HV its LCL filter. The feeders of the collector system has been
breaker is closed. The three phase voltages at the secondaries modeled using pi-sections. The inverter LCL filter has been
of the medium voltage transformers are shown in figure 7. retained in the EMT model due to the important role the filter
It was found that CCVT is not at risk of ferroresonance and plays in the ferroresonance phenomenon. Various study scenar-
ferroresonance only occurs at the MV potential transformers ios have been designed to simulate the operating conditions of
secondaries. the solar project. These scenarios simulate project energization
and steady state at 0%, 10% or 100% project output. It
was revealed that under unusual system configuration, mainly
during energization and at night, the project is susceptible to
ferroresonance.
R EFERENCES
[1] A. Abdullah and B. Yancey, “A reduced order model for a tov study in
a solar pv project,” in 2017 IEEE/IAS Industrial & Commercial Power
Systems Technical Conference (I&CPS), 2017.
[2] D. A. Jacobson, “Examples of ferroresonance in a high voltage power
system,” in Power Engineering Society General Meeting, vol. 2, 2003.
[3] E. Dolan, D. Gillies, and E. Kimbark, “Ferroresonance in a transformer
switched with an ehv line,” IEEE Transactions on Power Apparatus and
Systems, no. 3, pp. 1273–1280, 1972.
[4] U. Karaagac, J. Mahseredjian, and L. Cai, “Ferroresonance conditions
in wind parks,” Electric Power Systems Research, vol. 138, pp. 41–49,
2016.
[5] R. Karlicek and E. Taylor, “Ferroresonance of grounded potential trans-
Fig. 7. Secondary three phase voltages of MV PTs for scenario D2 formers on ungrounded power systems,” Transactions of the American
Institute of Electrical Engineers. Part III: Power Apparatus and Systems,
Lastly, scenarios E1 to E3 simulate the cases in which one vol. 78, no. 3, pp. 607–614, 1959.
[6] G. Swift, “An analytical approach to ferroresonance,” IEEE Transactions
of the MPTs fails, the tie breaker is closed and the project on Power Apparatus and Systems, vol. 1, no. PAS-88, pp. 42–46, 1969.
is online at night with no power output. In these cases, it [7] P. E. Sutherland, M. E. Valdes, and G. H. Fox, “Snubber design for
was found, similar to scenarios D1 to D4, that the project is transformer protection,” IEEE Transactions on Industry Applications,
vol. 52, no. 1, pp. 692–700, 2016.
is susceptible to ferroresonance unless all poles of the HV [8] D. D. Shipp, T. J. Dionise, V. Lorch, and B. G. MacFarlane, “Trans-
breaker is closed. It was also found that CCVT is not at risk former failure due to circuit breaker induced switching transients,”
of ferroresonance and ferroresonance only occurs at the MV in 2011 IEEE Industrial and Commercial Power Systems Technical
Conference. IEEE, 2011, pp. 1–10.
potential transformers secondaries.The three phase voltages at [9] EMA Electromechanics, “Combined vacuum substation circuit breaker
the secondaries of the MV potential transformer is shown in and high-speed mechanically interlocked grounding switch.” [Online].
figure 8. Available: http://emaelectromechanics.com/vdhgsmi/
[10] J. Woodworth, “Arrester selection guide.” 2011, available on-
All scenarios that were found to be in risk for ferroresonance line at http://www.arresterworks.com/arresterfacts/pdf_files/Arrester_
are pointed out in table I in the red color. Characteristics_for_ATPDraw_Users.xls.

V. C ONCLUSIONS
A ferroresonance study of a relatively large solar farm has
been presented. The study modeled the project in PSCADTM in

978-1-5386-4536-9/18/$31.00 © 2018 IEEE

Authorized licensed use limited to: Cornell University Library. Downloaded on September 04,2020 at 14:44:28 UTC from IEEE Xplore. Restrictions apply.

You might also like