Professional Documents
Culture Documents
Functional related to
Operational
Specification Qualification
Design Installation
related to
Specification Qualification
System
Build
“Process validation is
Validation
establishing Protocol
documented evidence
Product
which provides a high Installation
Performance
Qualification
degree of assurance Qualification
– Quality should be built into the product, and testing alone cannot be
relied on to ensure product quality
– Integrated Lifecycle
– Integrated Team
– Integrated Design
– Integrated Procurement
– Integrated Scheduling
– Integrated Construction/ Fabrication
– Integrated Field Engineering
– Integrated Change Management
– Integrated Handover
Company
Quality Reqs.
Risk Management
Design Review
Change Management
interdiscipl.
R&D Subject Matter Expert (SME)
expert team
Construction
Construction
Commissioning
Commissioning
IQOQ
IQOQ
Construction
Construction
Commissioning
Commissioning
IQOQ
IQOQ
Construction
Construction
Verification
Verification
Design Lifecycle
Field
Team
Engineering
Integrated
C&Q
Change Schedule/
Management Program
Procurement Construction
BRINE
CLEAN STEAM
DISTRIBUTION
Forecast
0%
20%
40%
60%
80%
100%
120%
Plan Progress
Variance ( + ‐ )
1.
Actual Progress
Remaining No. of
1
Actual No. of Docs.
Complete per Week
No. of Docs. Plan to
Completed per Week
Documents to Complete
2
Week Ending
Cut‐off Date:
Week No.
3
0.00% 0.00% 0.00% 14/03/08
0
0
1
4
0.00% 2.97% 2.97% 21/03/08
9
9
2
5
0.00% 3.74% 3.74% 28/03/08
1
1
3
6
27‐Jun‐08
0
0
7
4
0.77% 20.77% 20.00% 11/04/08
41
40
5
9
0.31% 27.67% 27.36% 18/04/08
21
21
6
22
10
7
11.58% 42.84% 31.25% 02/05/08
8
17.71% 55.67% 37.96% 09/05/08
1 15
9
23.65% 62.90% 39.25% 16/05/08
10 23 13
10
No. of Docs. Plan to Complete per Week
6
4 21
11
16.70% 68.90% 52.20% 30/05/08
9
12
7.01% 70.44% 63.43% 06/06/08
2
1 17
13
8.90% 75.52% 66.62% 13/06/08
9
‐1.10% 76.44% 77.54% 20/06/08 14
3
7 22
15
7
16
0
0 16
17
127 117 94 81 75 66 64 55 52 45 45 45
0
18
0
3 13
19
0
0
20
Week No.
0
4
21
Actual No. of Docs. Completed per Week
0
1
22
0
4
23
0
1
24
0
1
25
0
0
26
Plan Progress
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
41
45 45 45 45 45 45 45 45 45 45 45
43
2. Best Practice Commissioning and Start-Up
Definition of GEP:
– “Established engineering methods and standards that are applied throughout
the project lifecycle to deliver appropriate cost-effective solutions.”
New Good Practice Guide from ISPE is approved on GEP outlining core
concepts and core practices- available from www.ispe.org
RISK COMMUNICATION
Science and
Risk- Based
Approach
– Some Pitfalls
• Bad Document Quality/ practices
• Poor Change Control
• Less control by Customer
• Training opportunity lost