Professional Documents
Culture Documents
(For 1 Unit) Z-16-319 R4 - Access. Supply For CB 20 - Estimate - Discounted
(For 1 Unit) Z-16-319 R4 - Access. Supply For CB 20 - Estimate - Discounted
Discount
Sr No DESCRIPTION Type Make Size Unit Qty Unit M rate VAT ED FREIGHT LBT %
LIST OF VALVES
Isolation valve at inlet of
Softener Ball Unison 50 mm 1 no 5410 676.25 676.25 54.10 - 20%
Isolation valve at outlet of doser Gate Expert 25 mm 1 no 8208 1026.00 1,026.00 82.08 - 20%
NRV at outlet of doser Disc check 25 mm 1 no 1000 125.00 125.00 10.00 - 20%
Valve at the inlet of soft water t Ball Unison 50 mm 1 no 5589 698.63 698.63 55.89 - 20%
Isolation valve at outlet of mm no 5410 676.25 54.10 -
soft water service tank Ball Unison 50 1 676.25 20%
Isolation valve at drain of soft mm no 417.50
water service tank Ball Unison 40 1 3340 417.50 33.40 - 20%
Isolation valve at inlet of feed Ball Unison 50 mm 4 no 5410 676.25 54.10 -
pumps 676.25 20%
Strainer at inlet of feed pumps Y type Procedyne 50 mm 4 no 9001 1125.13 1,125.13 90.01 - 20%
Valve for sampling at inlet of mm no 125.00
feed pumps Needle 15 4 1000 125.00 10.00 - 20%
WATER SYSTEM
TOTAL M Rate (w/o
VAT) M cost
45,490.80 45,490.80
11,384.05 11,384.05
38.38 53,732.00
18.00 25,200.00
5.00 7,000.00
- 2,000.00
4,596.75 4,596.75
10,215.00 10,215.00
209.98 209.98
209.98 209.98
209.98 209.98
153.23 153.23
324.61 324.61
324.61 324.61
153.23 306.45
787.69 787.69
1,021.50 1,021.50
194.93 2,339.16
66.66 399.96
271.69 4,890.42
271.69 1,630.14
222.20 888.80
90.90 181.80
277.75 1,666.50
277.75 555.50
101.00 404.00
50.50 202.00
121.20 484.80
121.20 484.80
- -
21.21 84.84
9.09 36.36
43.43 434.30
43.43 173.72
- -
28.28 1,583.68
- -
- -
- -
4,912.28 4,912.28
7,452.86 7,452.86
908.00 908.00
5,074.81 5,074.81
4,912.28 4,912.28
3,032.72 3,032.72
4,912.28 19,649.12
8,172.91 32,691.63
908.00 3,632.00
261,873.10
COST ESTIMATION FOR PROJECT
A. DIRECT COSTS:
A.1 Material Costs:
Item Basic Cost ED* ST CIF
1.00 Water System 261873.10
2.00 Drain & Safety System 29952.56
3.00 Flue gas system 762121.62
4.00 Insulation 72804.74
5.00 Electricals 41955.84
6.00 Structurals 18414.00
7.00 STEAM SYSTEM 624939.30
8.00
9.00
10.00 0
Sub-total 1812061
7.00 Contingency 3.00% On Basic Cost
8.00 Escalation's 0.00% On Basic Cost
9.00 FOAK 0.00% On Basic Cost
Total
(a) Basic costs includes landed cost (transport + LBT + Taxes)
C. PROFIT + MARGIN :
Re Item Parameter
1.00 Profit before tax (%: of sales) 10.00%
2.00 Negotiation margin (%: of sales) 5.00%
Total
E. OFFER ANALYSIS:
PREPARED B PS
DATE 2-Feb
REVISION 4
our case
Unit Cost Cost Remarks
0
0
0
0
0
A2 0.00
Supervision of
E and C
A.6 0.00
p/security,etc.
Lumpsum
0.00% 0
0
A.8 135248
A 2001671.04 2001671.04
0
D 0.00 0.00
2,299,216.73
2,299,216.73
2,704,960.86
2,704,960.86
33.0%
Rates (Rs./Day)
2000.00
2500.00
5000.00
COST ESTIMATION FOR ERECTION
C BOARDING CHARGES
C.1 Sub Contractor
1 Labourers 1 Room
C.2 Veda Crew - For Outstation Sites
2 Site Engg. - VEDA 1 Hotel Room
3 Inspection Engg. - VEDA 0 Hotel Room
4 Commissioning Engg. - VEDA 1 Hotel Room
D TRANSPORTATION
1 Labour - Site Moblization & Demobilization Lumpsum
2 Site Engg. - VEDA 1 No
3 Inspection Engg. - VEDA 0 No
4 Commissioning Engg. - VEDA 0 No
5 Transpotation of Tools & Tackle Lumpsum
E MISCELLANEOUS
1 Hydra Charges Lumpsum
2 Crane Charges Lumpsum
3 Consumables Lumpsum 1 Nos
4 IBR Approval - Boiler
TOTAL
MARGIN FACTOR 30%
QUOTED
ECTION
b PREPARED BY PS
ccessories DATE 30-Dec
uette REVISION 0
10,000.00
500.00 Rs/Trip 2 Trips 1,000.00
1,500.00 Rs/Trip 2 Trips -
1,500.00 Rs/Trip 2 Trips -
5,000.00 Rs. 1 Nos 8,000.00
TOTAL 2,576,030.00
WATER 411,000.00
DRAIN 80,000.00
FLUE GAS 1,505,000.00
INSULA 33,000.00
ELECT 215,000.00
STR 150,000.00
P&F ### 35,910.00
STEAM SYSTEM
TOTAL 2,429,910.00
ENC 580,000.00
IBTR 60,000.00
VAM 3,800,000.00
P&F 3% 114,000.00
GRAND TOTAL 9,559,940.00
CTV MARGIN
1,856,000.00 0% 1,856,000.00
0% -
1,856,000.00 1,856,000.00
3,668,061.16 4,039,206.22
316,216.55 432,690.31
FINAL
3,984,277.71 4,471,896.52 ###
LAST QUOTED
2,630,000.00 7.50% 2,827,250.00 2,889,000.00
7,299,146.52
0.89
141,896.52
8 STEAM SYSTEM
Size Unit Qty Unit M. Rate
1 Steam Header 100 NB 3 mtr 1623
Fabrication Steam header 1.00 set
3 Steam piping before PRS1 inlet to PRS 2 inlet for VAM m/c
Pipe 40 NB 24 mtr 411
Bends 40 NB 6 No 245
Flanges 40 NB 8 No 342
TOTAL SUPPLY
TOTAL
Margin
M. Cost Labour Rate Labour cost
4869 1,200.00 3600
10000 10000
30000 30000
10000 20000
50000 50000
5000 5000
268542
20% 322250.4