Nowadays human activity continues to increase, this means energy needs community

electricity has increased. But humans must maximize utilization renewable energy as an
alternative because of the depletion of petroleum supplies at Indonesia. In order to support
the Green Building Program in the Electric Workshop Building
Semarang State Polytechnic then designed and realized in the Project
The Final Project is a Solar Power Plant. This generator uses
solar energy as a source of power which is then absorbed by solar panels.
This tool can also be used as a technology for PLTH (Power Plant)
Hybrid) that is by combining 2 generator sources, including electricity from
PLN and power backup or PLTS (Solar Power Plant). This matter
aims to save electricity usage and costs incurred from
PLN, so it uses hybrid or merging systems. This PLTH is made for
supply loads to the Polines electrical workshop laboratory. In planning
It is planned that for Energy worth 3400 Wh,% Supply will be valued at 20%
or 688 Wh. and the energy value generated by 900Wp from an efficiency of 15.4%
is 693 Wh. While for Backup, it can supply 4800wh. On
Backup Testing, using DOD Settings or Depth of Discharge on value
25% so that the maximum capacity of the 4800 Wh battery can only be used
worth 3600Wh. In addition, the results of measurements of electrical quantities can also be
seen and
monitored via PC display and inverter. PLTS is equipped with 4 batteries
which will be used as a backup power if the PLTS source or PLN source
die. This system will be used as a saving tool from power usage
PLN source. The Semarang State Polytechnic Electric Workshop Building will be later
all loads will be automated and controlled and monitored via PLC and programs
SCADA