Professional Documents
Culture Documents
Span Length 50 M
Designing
Implementation
Planning
Execution
Monitoring
Organization Chart
Key persons
Chairman
Managing
Director
General Manager
Project Manager
Deputy project
Manager
Organization Chart
Site Key persons
PM
DPM
APM
Site engineer
Junior engineer
DTE GTE
Foremen, Foremen,
Supervisor Supervisor
Site engineer
Junior engineer
DTE GTE
Foremen, Foremen,
Supervisor Supervisor
Store,Material, D.A.M
Purchasing
A.M
A.M
Sr.Accountant
Store keeper
Accountant
Sr.Store Asst
Trainees,Helpers Trainees
HR Organization Chart
HR Manager
HR Executive
Asst.HR
Trainees
Project Site TechnicalDepartments
Highway Dept
Fabrication
QA/QC Dept yard
Survey Dept
Steel Yard
Project Site Non-TechnicalDepartments
HR Dept Foremen
Accounts Dept
Supervisors
Material Dept
Technical Ast
Store Dept
Operators
Safety Dept
Labour Dept
Piling Equipment&Labours
25 T Crane
Riggers
Excavator
Transit mixer
Trimi
Pipe,Hauper
Chain
Sub contractor
labour
Pilecap Equipment & Labours
excavator Compressor
12T Hydra
Breakers
Concrete pump
Labour
Transit mixer
Sub contractor
Vibrator Needle labour
Pier cap Equipment & Labours
12T Hydra
25T Crane
Concrete pump
Transit mixer
Vibrator Needle
Sub contractor
labour
Casting yard Equipment & Labours
Grouting Pipe
Sheathing,HDPE
Pipe
ZIG
Site office work
No of Abutments 2 Nos.
Width of Deck 12 M
Abutments A1,A2.
Pier,Piercap P1,P2,P3,P4
Excavation&PCC
Completed
MAJOR BRIDGE-174+025
MAJOR BRIDGE-174+025
MAJOR BRIDGE-174+025
MAJOR BRIDGE-174+025
MAJOR BRIDGE-174+025
MAJOR BRIDGE-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Major Bridge-174+025
Site office work