You are on page 1of 10

ISRM: SURFACEMONITORING OF DISCONTINUITY MOVEMENTS 267

Suggested Methods for Surface Monitoring of


Movements Across Discontinuities

TECHNICAL INTRODUCTION AND SUMMARY (c) Epoxy resin, polyurethane resin or cyanoacrylate
OF METHODS AVAILABLE adhesive.
1.(a) Monitoring of rock movements provides input to (d) Waterproof felt marking pens.
understanding the behaviour of a rock mass and to an (e) Ruler.
assessment of its stability. Observations of fracturing on
Procedure
a rock surface can provide useful information concern-
ing behaviour at depth, and surficial monitoring is Installation
usually far less expensive than borehole instrumentation 3.(a) The area to be monitored for crack movements
or other techniques for subsurface monitoring. is thoroughly inspected, and all existing cracks marked
(b) The use of wooden wedges driven into open with paint along their full length.
fractures and observing when wedges loosen has been a (b) The surfaces to which the glass plates are
traditional method used by mining personnel, but more cemented must be hard, for example hard rock, or
sophisticated techniques are often required. Table 2 concrete, in order to ensure reliable adhesion. When
indicates some of the available methods, with major necessary the surfaces should be cleaned and roughened
advantages and limitations and approximate accuracies. to provide a key for the adhesive.
The following four suggested methods are a sampling of (c) Glass plates are then cemented across each crack
available techniques. These suggested methods are not at several locations using epoxy resin adhesive or similar
intended to be recommended methods: they are merely material of strength greater than the glass plate.
samples to be used as a guide when adopting the method (d) Having installed all plates, their positions are
most applicable to a particular project. Simple optical and marked on plans and cross sections. A number designa-
mechanical methods should be used, wherever possible, tion is marked clearly and permanently adjacent to each
in preference to electrical methods, as electrical methods plate and the corresponding designation is also marked
tend to be less reliable for long-term monitoring unless on the plans and sections.
the physical environment (moisture, dust, temperature, (e) During installation, installation record sheets
vibration) is suitably controlled. should be completed, t*
(c) Typical applications include monitoring tension
cracks behind slopes, and monitoring cracks in concrete Inspection and reading
structures, pavements or tunnel linings, or discontinuties 4.(a) Inspection entails observation of breakages.
in rock. Reading entails use of a ruler to measure crack sepa-
ration and direction of relative movement. Reading
accuracy should be approximately __+1 mm.
METHOD 1: SUGGESTED METHOD FOR
(b) The frequency of inspection and/or readings
MONITORING MOVEMENT ACROSS
DISCONTINUITIES USING GLASS should be related to site activity and to the rate at which
PLATES deformation is occurring.2
(c) Data should be recorded on specially prepared
Scope field data sheets)
1. This method provides a simple and direct means of (d) Where a glass plate has been broken by move-
monitoring movement across discontinuities. It consists ment, it is often helpful to cement a new plate alongside
essentially of cementing glass plates across dis- the broken one, to check whether movement is con-
continuities and observing breakages, supplemented as tinuing.
necessary by measurement and recording of crack
separation and direction of relative movement. Calculations 4
5. If readings have been taken, they should be con-
Apparatus verted into movements in a timely manner, using spe-
2.(a) Spray paint, brightly coloured to contrast with cially prepared calculation sheets:
the surface to which it will be applied.
(b) Glass plates, approximately 80 x 20 x 2 mm. Reporting of Results
6. An "installation report" should be prepared on
* Superscript numbers refer to Notes at the end of the text. completion of plate installation:
268 ISRM: SURFACE MONITORING OF DISCONTINUITY MOVEMENTS

Table 2. Methods for surface monitoring of crack and fault movements


Approximate
Method Advantages Limitations accuracy
Optical methods
Surveying and Monitoring can cover Limited accuracy. Depends on
EDM a a wide area Monitoring is method
"people intensive"
Photogrammetry Monitoring gives Limited. accuracy. Depends on
comprehensive data Monitoring is method
over a wide area "people intensive"

Monitoring and
interpretation
require specialist skill

Mechanical methodsb
Wooden wedges Simple and inexpensive Qualitative only. Crude
Can be used by all Interpretation
personnel unreliable
Glass platesc Simple and inexpensive + 1 mm
Plaster patchesd Simple and inexpensive + 1 mm
Pins and tape c Simple and inexpensive + 2 mm
Pins and tensioned Simple and inexpensive + 2 mm
wire, using weightc Can be adapted to
trigger alarm
Pins and mechanical Simple + 0.1 mm
extensometerf
Grid tell-taleB Simple and inexpensive + 1 mm
Pins and steel rule Simple and inexpensive Span limited +0.5 mm
Pins and calipers Simple and inexpensive Span limited + 0.2 mm
Tape extensometerh Simple +0.2 mm
Portable mechanical Simple Span limited + 0.01 mm
gauge~
Dial indicatorJ Simple and inexpensive Span limited _+O.Oi mm

Electrical methods
Electrical Allows readings to Expensive. ___0.1-0.002 mm
jointmeter~'~ be made at a Range limited, but Depends on
remote location can be extended transducer
by resetting.
Reading often affected
by lead wire
changes, temperature
and other
environmental
conditions
iISRM Suggested Methods are in preparation for survey triangulation, levelling, offset and electronic distance
measurement (EDM).
bAll require access by monitoring technician to the reading location.
cSuggested Method is included in this text. These four suggested methods are not intended to be recommended
methods: they are merely samples to be used as a guide when adopting the method most applicable to a particular
project. Simple optical or mechanical methods should be used wherever possible.
dMethod is similar to glass plate method, but using gypsum plaster instead of glass plates and adhesive. The plaster
is applied with a flat trowel.
eA wire is stretched across the discontinuity between a pin on one side and a pulley mounted to a measurement
station on the other side. A weight on the wire below the pulley maintains tension. A scale is attached to the
measurement station behind the wire, and a reference mark made on the wire. Observation of the reference mark
position with respect to the scale provides movement data. A trip block can be added to the wire, arranged to contact
a trip switch on the scale when a predetermined movement occurs. This can be connected to an alarm if required.
rA portable steel tape with punched holes, or a stainless steel wire, is attached to a pin on one side of a
discontinuity, and passed through a measurement station on the other side. A mechanical indicator ("Potts
extensometer") is mounted on the measurement station, and the tape or wire attached to the indicator. The indicator
is adjusted to apply a constant tension, and mechanical scales on the indicator provide movement data.
q'he grid tell-tale consists of two overlapping transparent plastic plates, one mounted on each side of the
discontinuity. Crossed cursor lines on the upper plate overlay a graduated grid on the lower plate. Movement is
determined by observing the position of the upper plate cross with respect to the grid.
h Tape extensometers are available from many suppliers of geotechnical instrumentation. They consist essentially
of a tape in series with an adjustable spring for tension control, and a dial indicator for measurement of movement.
Reference points attached to pins on each side of the discontinuity mate with attachments on the tape extensometer.
An ISRM Suggested Method is in preparation for convergence measurements, including use of tape extensometers.
JA dial indicator can be attached to a bracket on one side of the discontinuity and arranged to bear against a
machined reference surface on the other side. Tri-directional dial indicator systems are also available.
kAn electrical linear displacement transducer can be attached to a bracket on one side of the discontinuity and
arranged to bear against a machined reference surface on the other side. Alternatively, anchor points can be located
on either side of a discontinuity and the transducer attached to the anchor points via ball joints. Available
transducers include linear potentiometers, linear variable differential transformers (LVDTs), direct current
differential transformers (DCDTs), vibrating wire transducers, bonded and unbonded resistance strain gauge
transducers, and inductance transducers that form an oscillating circuit with frequency output.
ISRM: SURFACE MONITORING OF DISCONTINUITY MOVEMENTS 269

7. A "monitoring report" should be prepared follow- approximately, in general equidistant from and perpen-
ing each set of readings. 7 If glass plates are being used dicular to the discontinuity. The surface between the
merely for observation of breakages, clearly the mon- pins may require flattening, to remove any irregularities
itoring report will not include graphs. which would otherwise interfere with the correct posi-
tioning and operation of the tape. The pins are then
METHOD 2: SUGGESTED METHOD FOR cemented to the surface using a strong, fast-setting epoxy
MONITORING MOVEMENT ACROSS resin adhesive.
DISCONTINUITIES USING PINS (c) In soft ground or broken surfaces, pins can be
AND A TAPE driven to depths of about 10 cm or such that the pins are
Scope rigidly positioned. Alternatively, pins may be positioned
in boreholes and grouted in.
1.(a) This method is intended as a simple technique (d) Having installed all pins, their positions are
for monitoring movements using pins set on either side
marked on plans and cross sections. A number designa-
of the discontinuity. Measurements are taken using a tion is marked clearly and permanently adjacent to each
steel tape spanning the pins.
pair of pins (measuring span) and the corresponding
(b) Pins are typically set at 1-3 m apart but may
designation is also marked on the plans and sections. It
extend to 20 m across a single discontinuity or series of
also may be useful to use brightly coloured paint to mark
discontinuities. the structure in the vicinity of the pins so that they can
(c) The accuracy required will depend on the applica-
be found without difficulty when taking readings.
tion but will typically be approximately +_2 mm. With
(e) During installation, installation record sheets
care, _+0.5 mm accuracy is possible.
should be completed. 1
Apparatus
Reading
Pins and fixing materials 5.(a) Several sets of initial readings are required to
2.(a) The type and dimensions of the pins and the establish a reliable base, ideally unaffected by site activ-
fixing system to be used should be appropriate to the ity. The frequency of subsequent readings should be
condition of the ground or structure to be monitored, to related to site activity and to the rate at which the
ensure the pins are rigidly attached to the surface and readings are changing. 2
will remain attached throughout the monitoring pro- (b) Where the pin separation is less than about 2 m,
gramme. measurements can be made to an accuracy of _+2 mm
(b) When the surface is strong rock or concrete using a steel tape, e.g. standard construction quality
unaffected by local cracking, pins are typically 2cm product. Temperature and sag corrections are not nor-
long, 5 mm dia with a tapered point at one end and a mally required over this measurement distance. Where
welded base at the other. Epoxy resin is used to fix the the pin separation exceeds 2 m, a survey chain should be
base to the surface, or a concrete rivet gun may be used used. The end of this chain should be attached to one of
to embed pins. the pins to minimize referencing errors and a standard
(c) For soils or soft rocks, pins of 50 crn in length and pull should be applied to eliminate the need to apply sag
1.5 cm dia are typically used where they are to be driven corrections. If the pins are not rigid or are not securely
into the formation. Alternatively, pins may be grouted attached to the ground so it is not possible to attach the
in. chain to one pin, then two people will be required to
(d) Pins should have pointed tips or alternatively have make the measurements, one to hold each end of the
filed cross-lines on the tip of a flat head. chain. A standard pull should be used and temperature
3. A steel tape graduated in millimetres is typically corrections applied as required. In all cases, three mea-
used to measure displacements. surements of pin separation should be made each time
sets of readings are carried out, and the average sepa-
Procedure ration calculated. Individual readings should not differ
Pin installation by more than _+2 mm.
4.(a) The area to be monitored is first inspected to (c) Adequate lighting must be provided to ensure
determine critical discontinuities and the most appropri- satisfactory reading conditions.
ate number and location of measuring spans. Both shear (d) The position of pins relative to a fixed reference
and normal displacement of a discontinuity can be made point should be checked where possible to ensure that
by installing a pair of pins on either side of the discon- the true measurement is being measured.
tinuity and taking diagonal and normal measurements. (e) Readings should be recorded on specially pre-
The discontinuities may first be monitored visually or pared field data sheets, and immediately compared with
with glass plates (Method 1) for sufficient time to previous readings to examine for reading errors or
establish the genreral pattern of movements. instrument malfunction?
(b) Where pins are to be fixed directly to a firm
surface, the surface is first cleaned of loose material and Calculations 4
dust which might otherwise interfere with adequate 6. Readings should be converted into movements in a
bonding of the adhesive. The pin locations are marked timely manner, using specially prepared calculation
270 ISRM: SURFACE MONITORING OF DISCONTINUITY MOVEMENTS

sheets) For each pair of pins, the reading change is Apparatus


calculated by subtracting the initial reading from the 2. A portable displacement gauge with the following
subsequent reading, taking note of the positive or nega- characteristics (e.g. Fig. 1).
tive sign. A positive sign indicates opening, a negative (a) The gauge typically has a fixed gauge length,
sign indicates closing. requiring that targets are mounted at a predetermined
separation distance) Typical gauge lengths are in the
Reporting of Results range 50-250 mm. A suitable gauge length should be
7. An "installation report" should be prepared on selected for the application; for example when moni-
completion of the installation of pins and after taking toring cracks there is usually a minimum separation of
the initial readings. 6 targets that will ensure that the targets do not become
8. A "monitoring report" should be prepared follow- loose or damaged in service.
ing each set of readings. 7 (b) The portable instrument usually employs a
mechanical displacement sensor such as a dial gauge
with a lever system to amplify the movements between
METHOD 3: SUGGESTED METHOD FOR targets. Typically the instrument has a reading resolu-
MONITORING MOVEMENT ACROSS tion in the order of 0.003 mm.
DISCONTINUITIES USING A (c) The accuracy and repeatability of readings de-
PORTABLE MECHANICAL pends on a robust design of instrument and on the
GAUGE avoidance of errors that result from friction or wear in
the mechanical amplification system. Repeatability
Scope should be on the order of +0.005 mm for successive
1.(a) This method is intended for the measurement of readings.
variation in distance between two targets, one located on (d) In general the more accurate the instrument the
each side of the discontinuity to be monitored. The smaller is its measuring range. Typical ranges are from
method requires manual access to the targets. + 2 to + 5 mm. The instrument should only be employed
(b) The targets are typically separated by a distance if the anticipated displacement is consistent with this
of between 50 and 250mm. A portable mechanical measuring range. 9
displacement gauge is used to take measurements be- (e) The instrument makes contact with the targets
tween any pair of targets. through one fixed arm and one pivoted arm connected
(c) The method is generally employed for accurate with the displacement sensor. The contact between
determinations of small movements, usually not exceed- points and targets must be precisely reproducible. For
ing + 5 mm. example, the points may be conical, locating in conical

Fig. 1. Exampleof portable displacementgauge. (Photo: W. H. Mayes& Son, Windsor Ltd, England).
ISRM: SURFACE MONITORING OF DISCONTINUITY MOVEMENTS 271

depressions in the targets; spherical, locating in spherical surface, the surface is first cleaned of loose material and
depressions; or the targets may themselves be spherical, dust which might otherwise interfere with adequate
locating in conical depressions in the points. bonding of the adhesive. The target locations are marked
approximately, in general equidistant from, and perpen-
Targets and fixing materials dicular to, the discontinuity. The surface between the
3.(a) A design of target should be employed to suit the targets may require flattening, to remove any irregu-
selected gauge. The target fixing system should be appro- larities which would otherwise interfere with the correct
priate to the condition of the ground or structure at the positioning and operation of the gauge. The setting tool
measuring location to ensure that the target will remain is usually needed to ensure correct target separation to
fixed in place and immovable throughout the pro- suit the make of gauge, adjusting this distance if neces-
gramme of measurements. sary just before the adhesive sets. l° The targets are then
(b) A setting tool is usually required to ensure that the cemented to the surface using a strong, fast-setting epoxy
separation of targets is within the prescribed gauge resin adhesive.
length of the instrument. (c) When targets are to be fixed in shallow drilled
(c) When the surface on which the targets are to be holes, the locations are first marked approximately, the
located consists of strong rock or concrete unaffected by first hole is drilled, and the hole separation is checked
local cracking, the targets may be fixed to this surface before drilling the second location. Dust is removed by
using a strong adhesive such as epoxy resin. blowing through a tube, the holes and target pins are
(d) When the surface is weak or friable or when there coated with adhesive, and the target pins are installed.
is risk of mechanical damage to the targets, the targets The target separation is checked and if necessary ad-
should take the form of steel pins, typically 2-5 mm dia justed before the adhesive has set? ° When targets are to
and 50--100 mm long, installed in drilled holes using a be fixed to deeper anchors a similar procedure is fol-
strong adhesive such as epoxy resin. lowed except that anchor posts are installed first, and
(e) In situations such as the monitoring of tension checked for rigidity. They should not flex or displace and
cracks in soil where the material on either side of the should be located so that they are protected from
crack is weak or friable, the targets should be fixed to mechanical damage due to site traffic. The targets may
deeper anchors, e.g. 20-30 mm dia and 0.5-1.5 m long then be fixed to the upper surface of the anchor posts
bars into the ground or installed in drillholes by grouting with strong adhesive. If the posts need to be separated
over their full length. by a distance greater than the gauge length, they may be
(f) The targets and adhesives and the anchoring sys- supplied fitted with crossbeams allowing the targets
tems where employed should be of strong and corrosion themselves to be at the correct separation.
resistant materials to ensure that readings are unaffected (d) Check readings are taken between each pair of
by distortion, damage, loosening or dimensional changes targets, ensuring that the locating points are free from
during their operating life. adhesive and paint and that the targets themselves are
securely anchored and at the correct separation distance.
Calibration equipment (e) Having installed all targets, their positions are
4.(a) The displacement gauge should be supplied with marked on plans and cross sections. A number designa-
a calibration bar to permit frequent checks on its tion is marked clearly and permanently adjacent to each
calibration, adjustment and correct functioning. pair of targets (measuring span) and the corresponding
(b) The calibration bar should be robust and corro- designation is also marked on the plans and sections. It
sion resistant and should incorporate targets of identical also may be useful to use brightly coloured paint to mark
design and separation to those to be employed for the structure in the vicinity of the targets so that they can
displacement measurements. Readings on the calibration be found without difficulty when taking readings.
bar should be reproducible within the specified re- (f) During installation, installation record sheets
producibility of the instrument. The bar should be kept should be completed, l
clean and protected against mechanical damage.
Reading
Procedure 6.(a) Several sets of initial readings are required to
establish a reliable base, ideally unaffected by site activ-
Target installation ity. The frequency of subsequent readings should be
5.(a) The area to be monitored is first inspected to related to site activity and to the rate at which the
determine critical discontinuities and the most appropri- readings are changing. 2
ate number and location of measuring spans. Both shear (b) Adequate lighting must be provided to ensure
and normal displacement of a discontinuity can be made satisfactory reading conditions.
by installing a pair of targets on either side of the (c) Readings should be recorded on specially pre-
discontinuity and taking diagonal and normal meas- pared field data sheets, and immediately compared with
urements. The discontinuities may first be monitored previous readings to examine for reading errors or
visually or with glass plates (Method 1) for sufficient instrument malfunction. 3
time to establish the general pattern of movements. (d) If at all possible, the same instrument should be
(b) Where targets are to be fixed directly to a firm used to take readings throughout a project. If it becomes
272 ISRM: SURFACE MONITORING OF DISCONTINUITY MOVEMENTS

necessary to change instruments it is advisable to take a should be recorded in millimetres of convergence or


duplicate set of readings on the day of change, one set divergence, generally to three decimal places.
with each instrument, to facilitate determination of a
correction factor to be applied to all subsequent read-
Reporting of Results
ings.
(e) Before each day of readings the instrument should 8. An "installation report" should be prepared on
be checked and calibrated using the calibration bar and completion of the installation of targets and after taking
if possible by also taking readings on calibration spans the initial readings. 6 It should include the model and
installed for this purpose at stable locations on the serial number of the portable reading instrument, and a
structure to be monitored. The procedure for taking complete set of calibration readings, together with
calibration readings is identical to that for other read- specifications for the calibration constant of the instru-
ings. The ambient temperature should be recorded, to ment (ram/division).
the nearest I°C, at the time of each calibration. 9. A "monitoring report" should be prepared follow-
(f) The recorded distances between pairs of targets ing each set of readings. 7 It should include reading values
should be the average value calculated from not less than and computed values for corrected reading change and
three individual readings. H When possible these readings movement. Graphs should be annotated to show any
should be taken interspersed with readings between adjustments or repairs to the portable reading instru-
other pairs of targets rather than consecutively, in order ment, and the report should draw attention to any
to reduce the possibility of a repetition of the same instrument malfunctions, repairs or adjustments since
reading error each time; for example, read Spans 1-2; the previous readings were taken.
2-3; 3-4; 1-2; 2-3; 3-4 rather than 1-2; 1-2 etc.
(g) The manner in which the instrument is held will
usually affect the readings. Variations are due to changes METHOD 4: SUGGESTED METHOD FOR
in magnitude and direction of the applied pressure and MONITORING MOVEMENT ACROSS
in some cases to heat transferred to the metal instrument DISCONTINUITIES USING
from the hands of the operator. The instrument should A REMOTE READING
be held in the same way each time and the same pressure ELECTRICAL JOINTMETER
used. When possible, the same operator should take
readings throughout the project. The instrument oper- Scope
ator should have thoroughly practiced taking readings 1.(a) This method is intended for the measurement of
on the calibration bar before taking them in the field. variation in distance between two anchor points, one
(h) The instrument calibration should again be located on each side of this discontinuity to be mon-
checked on completion of each day of readings. itored. Readings are made from a remote location, hence
overcoming the need for manual access to the anchor
Calculations 4 points.
(b) Two basic arrangements are possible. First, an
7.(a) Readings should be converted into movements
electrical linear displacement transducer can be attached
in a timely manner, using specially prepared calculation
to a bracket on one side of the discontinuity and
sheets, s
arranged to bear against a machined reference surface on
(b) The average or median t~ of each set of target
the other side. Second, anchor points can be located on
readings is calculated and recorded.
either side of a discontinuity and the transducer attached
(c) The average or median ~' of each set of calibration
to the anchor points via ball joints. This Suggested
readings is calculated and recorded.
Method describes use of the second arrangement.
(d) For each pair of targets (span) the reading change
(c) In this text the electrical device itself is referred to
is calculated by subtracting the initial reading from the
as a transducer, and the transducer, anchor points and
subsequent reading, taking note of the positive or nega-
attachments are referred to as a jointmeter.
tive sign. Depending on the design of the instrument the
(d) The anchor points are typically located between
sign will indicate either convergence or divergence of the
10 and 50cm apart along a line perpendicular to the
targets.
discontinuity to be monitored.
(e) The calibration change is calculated by subtracting
(e) Depending on the type of transducer, the displace-
the initial calibration reading from subsequent cali-
ment measurement capacity of the jointmeter ranges
bration readings.
from 10 to 100mm, and can usually be extended by
(f) The corrected reading change (dial gauge divisions)
resetting, using extension rods. If the expected direction
is calculated by subtracting the calibration change from
of movement is unknown, the transducer can be set
the reading change, again taking note of the positive or
initially in mid-range.
negative sign.
(f) The jointmeter is intended for precise remote
(g) The displacernentfrom initial readings is calculated
displacement measurements, requiring cable connection
by multiplying the corrected reading change by a cali-
of the instrument to an electronic readout unit. For most
bration constant (mm/division) for the instrument, again
types of transducer, automatic data logging capability is
taking note of the positive or negative sign. This value
available, often allowing reading in engineering units.
ISRM: SURFACE MONITORING OF DISCONTINUITY MOVEMENTS 273

EXTENSION
ROD
CABLE #)) SLIDING
TRANSDUCER BAR BALL
JOINT

ANCHOR ~BALL JOINT BA


Nz/,#'xx~

r::l ~ DISCONTINUITY I,I

!F;: %
Fig. 2. Example of jointmeter. (Photo: Irad Gage Inc., U.S.A.).

Apparatus should be supplied with the transducer, and the trans-


2. Typical apparatus is shown in Fig. 2. ducer should include a temperature sensor.
3. A remote reading electrical linear displacement (f) Insensitivity to temperature variation along the
transducer. Available transducers include linear potenti- lead wires.
ometers, linear variable differential transformers (g) Ball joints at each end of the transducer, to allow
(LVDTs), direct current differential transformers for lateral and rotational movement of the discontinuity
(DCDTs), vibrating wire transducers, bonded and un- without damage to the transducer. The ball joints should
bonded resistance strain gauge transducers, and in- be arranged for attachment to the anchor points.
ductance transducers that form an oscillating circuit (h) An over-range protection, typically by allowing
with frequency output. The transducer should, unless the the sliding bar to move beyond the specified range, by
particular application requires other characteristics, shearing a pin inside the housing without destroying the
have the following features: transducer.

(a) O-ring or other seals betwen the sliding bar and


transducer housing to protect the transducer from mois- Anchors and fixing materials
ture and dirt. 4.(a) Selection of an anchor should be made to match
(b) Facility for increasing the length of the sliding bar, the ball joint fixtures provided with the transducer. The
by screwing together lengths of extension rods to match anchor fixing system should be appropriate to the condi-
the separation distance between anchor points, or to tion of the ground or structure at the measuring location
increase the range of the jointmeter after initial displace- to ensure that the anchor will remain fixed in place and
ments have taken place. immovable throughout the programme of mea-
(c) An accuracy consistent with specific monitoring surements.
needs. Available transducers have accuracies ranging (b) Some form of setting tool is usually required to
from _+0.1 mm to _+0.002 ram. ensure that the separation of anchors is within the
(d) If lead wire length is likely to be changed during prescribed gauge length of the instrument. A ruler may
the monitoring programme, the transducer reading be suitable or, if transducer range is small, a location jig
should be insensitive to change in lead wire length. may be needed.
(e) Insensitivity to temperature variation at the trans- (c) When the surface on which the anchors are to be
ducer. Alternatively a temperature correction factor located consists of strong rock or concrete unaffected by
274 ISRM: SURFACE MONITORING OF DISCONTINUITY MOVEMENTS

local cracking, the anchors may be fixed to this surface before drilling the second location. Dust is removed by
using a strong adhesive such as epoxy resin. blowing through a tube, the holes and anchors are
(d) When the surface is weak or friable, or when there coated with adhesive, and the anchors are installed. The
is risk of mechanical damage to the anchors, the anchors anchor separation is checked and if necessary adjusted
should take the form of rebar anchors suitably grouted before the adhesive has set. 1° Anchors should not flex or
into drill holes or the form of steel pins, typically displace and should be located so that they are protected
50-100 mm long installed in drilled holes using a strong from mechanical damage due to site traffic.
adhesive such as epoxy resin. The rebar anchors or pins (d) Full advantage of the transducer range can be
should be machined to accept a threaded member of the utilized if the direction of movement is known before-
ball joint fixture provided with the transducer. hand. A suitable separation distance for the anchor
(e) In situations such as the monitoring of tension points should then be selected for the application. For
cracks in soil where the material on either side of the example, if only extension is expected, the sliding bar can
crack is weak and friable, the anchors should be set in be fully pushed in and anchor positions can be selected
deep holes, for example, 20-30 mm dia and 0.5-1.5 m for extension only.
long bars driven into the ground or installed in drilled
holes by grouting over their full length. Again, the bars Transducer installation
should be adapted to accept the threaded ball joint 7.(a) After the anchor points have been fixed in
attachment fixtures. position, the ball joints, sliding bar, transducer, and any
(f) The anchors and adhesives, where employed, necessary extension rods are fixed in position, following
should be of strong and corrosion resistant materials to the general scheme shown in Fig. 2. Details will depend
ensure that readings are unaffected by distortion, dam- on the type of transducer and will generally be described
age, loosening or dimensional changes during their in the manufacturer's instruction manual.
operating life. (b) It is generally necessary to protect the jointmeter
from vandalism and damage, and to protect the cable by
Calibration equipment burial or by use of conduit.
5.(a) Each jointmeter should be supplied with a cali- (c) When a number of jointmeters are to be read at
bration factor and temperature correction factor for one location, the cables can be connected to a switch
calculation of the actual displacement from the readout box, which in turn is connected to the readout unit. In
unit change. standard data-logging systems, the cables are terminated
(b) A hand-held calibration unit should be provided to a number of switch modules which are automatically
for on-site calibration of the jointmeter prior to installa- scanned by the data-logger.
tion. Readings made with the calibration unit should be
reproducible within the specified reproducibility of the Installation records
jointmeter. The calibration unit should be kept clean and 8.(a) Having installed the jointmeters, their positions
protected against mechanical damage. are marked on plans and cross sections. A number
designation is marked clearly and permanently adjacent
Procedure to each jointmeter, and the corresponding designation is
also marked on the plans and sections.
Anchor point installation (b) During installation, installation record sheets
6.(a) The area to be monitored is first inspected to should be completed. ~
determine critical discontinuities and the most appropri-
ate number and location of measuring spans. The dis- Reading
continuities may first be monitored visually or with glass 9.(a) Several sets of initial readings are required to
plates (Method 1) for sufficient time to establish the establish a reliable base, ideally unaffected by site activ-
general pattern of movements. ity. The frequency of subsequent readings should be
(b) Where anchor points are to be fixed directly to a related to site activity and to the rate at which the
firm surface, the surface is first cleaned of loose material readings are changing.2
and dust which might otherwise interfere with adequate (b) Readings should be recorded on specially pre-
bonding of the adhesive. The anchor locations are pared field data sheets, and immediately compared with
marked approximately, in general equidistant from, and previous readings to examine for reading errors or
perpendicular to, the discontinuity. The surface between instrument malfunction2
the anchors may require flattening, to remove any (c) If at all possible, the same readout instrument
irregularities which would otherwise interfere with the should be used to take readings throughout a project. If
correct positioning and operation of the jointmeter. The it becomes necessary to change instruments it is advis-
setting tool is usually needed to ensure correct anchor able to take a duplicate set of readings on the day of
point separation. The anchors are then cemented to the change, one set with each instrument, to facilitate deter-
surface using a strong, fast-setting epoxy resin adhesive. mination of a correction factor to be applied to all
(c) When anchors are to be fixed in shallow drilled subsequent readings.
holes, the locations are first marked approximately, the (d) The calibration of the readout unit should be
first hole is drilled, and the hole separation is checked checked on a regular schedule, at a maximum internal of
ISRM: SURFACE MONITORING OF DISCONTINUITY MOVEMENTS 275

6 months. This can be achieved by calibration at the point number, readings, remarks, weather, temperature,
manufacturer's facility or at a commercial calibration construction activity, and any other factors that might
house, using equipment traceable to a fixed standard. A possibly influence the readings. One or more sheets will
sticker on the readout unit should indicate the last and be used for each date, with later transcription of data to
next calibration date. one calculation sheet for each measurement point.
4. The aims of calculations should be to provide a
Calculations 4 rapid assessment of the data in order to detect sudden
10.(a) Readings should be converted into movements changes requiring immediate action, and to summarize
in a timely manner, using specially prepared calculation and present the data in order to show trends and
sheets. 5 compare observed with predicted behaviour for deter-
(b) If the transducer is sensitive to temperature, the mination of the appropriate action to be taken.
raw data should be corrected for any temperature vari- 5. The raw field data are first transcribed from the
ation, using the correction factor supplied by the manu- field data sheets onto calculation sheets for conversion
facturer. into movements. Usually this task should be accom-
plished within 24 hr of taking the readings. Calculation
Reporting of Results sheets should be prepared specially for each project and
11. An "installation report" should be prepared on instrument to record project name, instrument type and
completion of the jointmeter installation and after number, date and time of readings, initials of person
taking initial readings. It should include the model and making and checking calculations, readings transcribed
serial numbers of the jointmeters and the readout device, from field data sheets, and any remarks.
and a complete set of calibration readings, together with 6. The installation report should contain at least the
specifications of the calibration gauge factor and tem- following information:
perature correction factor of the jointmeters. (a) Plans, sections, drawings, photographs, etc.
12. A "monitoring report" should be prepared fol- sufficient to show the positions of measurement points
lowing each set of readings] It should include reading and their number designations, together with the posi-
values and calculated values of corrected readings for tions, orientations, and other characteristics of discon-
temperature change and movement. Graphs should be tinuities to be monitored, and to show sufficient detail of
annotated to show any adjustment or repairs to the geology, structural design, etc. as necessary for purposes
readout device, and the report should draw attention to of interpreting the monitoring results.
any instrument malfunctions, repairs or adjustments (b) Details of the measurement point design, mate-
since the previous readings were taken. rials and installation procedures employed.
(c) Details and manufacturer of any reading appa-
NOTES ratus used.
(d) Initial readings (not applicable for Method 1).
1. During installation a record should be made of all (e) A copy of each field installation record form, as
factors that may be relevant to subsequent data inter- described in Note 1.
pretation on forms specially prepared for each project.
Items to be recorded should include project name, 7. The monitoring report should contain at least the
instrument type and number, location in plan and following information:
elevation, personnel responsible for installation, installa- (a) An updated tabulation of readings to show the
tion date, and actual and unusual features of the instal- measurement point designation, date, time, temperature
lation. and reading change.
2. Too many readings overload the processing and (b) Updated graphs of movement vs time, an-
interpretation capacity, whereas too few may cause notated to show the scale of the graph, the sign con-
important events to be missed and prevent timely action vention for convergence and divergence, also showing
from being taken. If construction is in progress, readings the nature, date and time of any activities which might
should be taken frequently when construction ap- have contributed to the recorded movements (e.g. exca-
proaches a measurement point, e.g. once a week, once a vation, blasting, measurement point repairs).
day, once a shift, or even more frequently in relation to (c) The monitoring report should identify the tech-
construction activity. It is often wise to increase the nicians taking the readings and should be independently
frequency of readings during heavy rainfalls. As con- checked and signed by the engineer responsible for the
struction activity moves away from the measurement monitoring programme.
point or ceases altogether and when readings have (d) The report should be accompanied by a brief
stabilized and remained constant, the frequency may written account drawing attention to any significant
then be decreased. movements or changes since the previous readings, and
3. It is important that the latest readings be compared to their possible cause.
immediately with previous readings so that changes can (e) The principal conclusions of the monitoring
be verified as real or as errors caused by misreading. report should be communicated verbally where urgency
Space on the sheets should be provided for project name, of information transfer is essential. This communication
instrument type, date, time, observer, measurement should be followed by a written report within a specified
276 ISRM: SURFACE MONITORING OF DISCONTINUITY MOVEMENTS

time period (generally not greater than 1-2 days from the outside the measuring range of the instrument after the
time the readings were taken). adhesive has set, one of the pair must be replaced.
8. Some instruments are designed to allow the possi- 11. Where the number of replicated readings for any
bility of several alternative gauge lengths. The gauge one span is five or more, it is generally preferable to use
length is, however, not generally adjustable since this the median value rather than the average value to
would tend to reduce the accuracy of the instrument. represent the span distance. The median value is ob-
9. If the measuring range is exceeded during the tained by deleting highest and lowest values until only
monitoring programme, replacements targets may be one central reading remains, this being the median. If
installed alongside the intial targets to allow readings to two readings remaifl (as is the case for an even number
be continued. of readings), the average of these two is taken as the
10. In some cases it may be easier to fix one target or median value.
anchor point in place, then to mark out and fix the
second of the pair. If the separation is found to be Received 16 April 1984.

You might also like