1. Commonly needed for collecting runoff from pavements to prevent erosion or to intercept water
upgrade or downgrade of bridges.

Answer: Embankment Inlets


2. It is often dictated by street –geometrical conditions rather than the spread-of-water
computations.
Answer: Inlet Locations
3 and 4 give atleast two major considerations in the selection of design frequency and design
spread of highway and pavement.
Answers :
 Classification of the highway
 Design speed of the highway
 Projected traffic volumes
 Rainfall intensities
 Capital costs
 Hazards and nuisances to pedestrian traffic