Professional Documents
Culture Documents
Progress Keuangan Trafo PS PDF
Progress Keuangan Trafo PS PDF
NO NO
harga satuan Progress harga satuan Progress
Sipil Volume Jumlah Sipil Volume Jumlah
material jasa material jasa
1 D 30 2.05 mtr 3,750,000 3,750,000 1.442 1 D 30 8.5 mtr 3,750,000 3,750,000 1.44
0.27 m3 0.27 m3
0.5535 m3 2.295 m3
semen 2.7675 sak 70,000 193,725.00 0.074 semen 11.475 sak 70,000 803,250.00 0.31
pasir 1 pickup 1,250,000 1,250,000.00 0.481 pasir 1 pickup 1,250,000 1,250,000.00 0.48
kerikil 1 pickup 1,250,000 1,250,000.00 0.481 kerikil 1 pickup 1,250,000 1,250,000.00 0.48
besi 10 3 btg 81,378 244,134.00 0.094 besi 10 3 btg 81,378 244,134.00 0.09
3 btg 81,378 244,134.00 0.094 3 btg 81,378 244,134.00 0.09
Triplek 9 mm 2 lbr 165,000 330,000.00 0.127 Triplek 9 mm 1 lbr 165,000 165,000.00 0.06
Alat kecil 1 lot 650,000 650,000.00 0.250 Alat kecil 1 lot 650,000 650,000.00 0.25
2 D100 5.75 mtr 6,000,000 6,000,000 2.307 2 D100 2.6 mtr 6,000,000 6,000,000 2.31
0.48 m3 0.48 m3
2.76 m3 1.248 m3
semen 13.8 sak 70,000 966,000.00 0.371 semen 6.24 sak 70,000 436,800.00 0.17
pasir 1 pickup 1,250,000 1,250,000.00 0.481 pasir 1 pickup 1,250,000 1,250,000.00 0.48
kerikil 2 pickup 1,250,000 2,500,000.00 0.961 kerikil 2 pickup 1,250,000 2,500,000.00 0.96
besi 10 12 btg 81,378 976,536.00 0.376 besi 10 12 btg 81,378 976,536.00 0.38
12 btg 81,378 976,536.00 0.376 12 btg 81,378 976,536.00 0.38
Triplek 9 mm 2 lbr 165,000 330,000.00 0.127 Triplek 9 mm 2 lbr 165,000 330,000.00 0.13
Alat kecil 1 lot 650,000 650,000.00 0.250 Alat kecil 1 lot 650,000 650,000.00 0.25
Sarana Drainase 1 Lot 3,000,000 3,000,000 1.154
3 Rumah Trafo 1 2,000,000 2,000,000 0.769 3 Rumah Trafo 1 2,000,000 2,000,000 0.77
Beton 0.72 m3 Beton 0.72 m3
semen 3.6 sak 70,000 252,000.00 0.097 semen 3.6 sak 70,000 252,000.00 0.10
pasir 1 pickup 1,250,000 1,250,000.00 0.481 pasir 1 pickup 1,250,000 1,250,000.00 0.48
kerikil 1 pickup 1,250,000 1,250,000.00 0.481 kerikil 1 pickup 1,250,000 1,250,000.00 0.48
besi 10 37.4 btg 81,378 3,043,537.20 1.170 besi 10 37.4 btg 81,378 3,043,537.20 1.17
24.93333333 btg 81,378 2,029,024.80 0.780 24.9 btg 81,378 2,029,024.80 0.78
Triplek 9 mm 2 lbr 165,000 330,000.00 0.127 Triplek 9 mm 2 lbr 165,000 330,000.00 0.13
Alat kecil 1 lot 650,000 650,000.00 0.250 Alat kecil 1 lot 650,000 650,000.00 0.25
Pagar BRC 1 lot 1,000,000 1,000,000.00 0.385 Pagar BRC 1 lot 1,000,000 1,000,000.00 0.38
5 Relokasi Cubicle
Sewa Crane 2 hari 4,000,000 8,000,000
Mob-Demob 1 lot -
8,000,000 -
6 Elektrikal 5 Elektrikal
Instalasi Trafo 1 unit 2,500,000 2,500,000 Instalasi Trafo 1 unit 2,500,000 2,500,000
Penarikan Kabel 99 mtr 34,000 3,366,000 Penarikan Kabel 101 mtr 34,000 3,434,000
Terminating 2 set 750,000 1,500,000 Terminating 2 set 750,000 1,500,000
Panel COS 1 unit 500,000 500,000 Panel COS 1 unit 500,000 500,000
Support 1 lot 500,000 500,000 Support 1 lot 500,000 500,000
8,366,000 - 8,434,000 -
218,331,627.00 13.98 41,714,952.00 12.80
NO Deskripsi Progress Keuangan
1 Progress Saat ini 26.78 69,646,579
2 Progress Sisa 73.22 190,400,000
3 Kas Gantung 100,000,000
4 Sisa Kebutuhan 160,046,579.00 ======> Pengaspalan dan Pemasangan Trafo, Kabel dan Panel COS