You are on page 1of 8

Detail scope of work Plan of approach, risks and costs of the project

Start: 2/16/19 ID: 1 Start: 2/19/19 ID: 2


Finish: 2/18/19 Dur: 2 days Finish: 2/20/19 Dur: 2 days
Res: Res:

Page 1
Preparation of internal and external layout of the building Operating excavation machinery,operating cranes and construction of the building
Start: 2/21/19 ID: 3 Start: 3/1/19 ID: 4
Finish: 2/28/19 Dur: 6 days Finish: 3/21/19 Dur: 15 days
Res: Res:

Preliminaries
Start: 2/21/19 ID: 5
Finish: 2/22/19 Dur: 2 days
Res:

Page 2
Wall,floor and ceiling installation Inspection
Start: 3/22/19 ID: 6 Start: 4/2/19 ID: 7
Finish: 4/1/19 Dur: 7 days Finish: 4/2/19 Dur: 1 day
Res: Res:

Page 3
Internal walls and particians Gym facilities
Start: 4/3/19 ID: 8 Start: 4/10/19 ID: 9
Finish: 4/9/19 Dur: 5 days Finish: 4/15/19 Dur: 4 days
Res: Res:

Electric Settings
Start: 4/10/19 ID: 20
Finish: 4/16/19 Dur: 5 days
Res:

Water pumps and pipes


Start: 5/8/19 ID: 16
Finish: 5/13/19 Dur: 4 days
Res:

Page 4
Swimming Pool Basketball, Badminton,Astroturf
Start: 4/16/19 ID: 10 Start: 4/19/19 ID: 11
Finish: 4/18/19 Dur: 3 days Finish: 4/22/19 Dur: 2 days
Res: Res:

Additional furniture fittings Internal doors and windows


Start: 5/14/19 ID: 17 Start: 5/16/19 ID: 18
Finish: 5/15/19 Dur: 2 days Finish: 5/17/19 Dur: 2 days
Res: Res:

Page 5
Parking Lot Spa Facilities
Start: 4/23/19 ID: 12 Start: 4/26/19 ID: 13
Finish: 4/25/19 Dur: 3 days Finish: 5/1/19 Dur: 4 days
Res: Res:

Aerobic centre Solar Panels


Start: 5/20/19 ID: 19 Start: 5/22/19 ID: 21
Finish: 5/21/19 Dur: 2 days Finish: 5/28/19 Dur: 5 days
Res: Res:

Page 6
Changing rooms and Lockers Rest room
Start: 5/2/19 ID: 14 Start: 5/6/19 ID: 15
Finish: 5/3/19 Dur: 2 days Finish: 5/7/19 Dur: 2 days
Res: Res:

Testing the facilities for any loop halls and areas of improvements
Start: 5/29/19 ID: 22
Finish: 5/30/19 Dur: 2 days
Res:

Page 7
Critical Summary Critical External

Noncritical Critical Inserted External

Project: Project1
Critical Milestone Inserted Project Summary
Date: Thu 4/18/19
Milestone Critical Marked Highlighted Critical

Critical Summary Marked Highlighted Noncritical

Page 8

You might also like