Professional Documents
Culture Documents
Methodology
– Assessment of Cracking Morphology
– Assessment of corrosion along edges of
cracking
– Optical and SEM evaluation
– Material testing to confirm impact properties
– Approximate correlation to Fracture Toughness
Benefits
– Support determining course of action (repair/monitoring)
during outage
Environmental Cracking Assessment
Cracking identified during inspection
Objective
– Assess continued use prior to replacement vessel
Methodology
– Finite element analysis used to confirm local stresses
(head to vessel and nozzle locations)
– Residual stresses estimated from API 579 & BS 7910
– Cracking not found acceptable
Remediation
– Post weld heat treat to lower residual stresses
– Internally coat to prevent further damage
– Fatigue assessment completed
Enabled the operator to use damaged vessel prior to
replacement being installed
Thick Wall Ammonia Reactor
Evaluation of defects found, cause & remaining life
Damage mechanisms evaluated
– Temper Embrittlement, Nitriding, Thermo-mechanical Fatigue
Assess increasing internal radius full circumferential
– Removes all cracking and notches
– Stresses reduced close to original defect free vessel
– Access difficult to complete in practice
Assess local grinding to remove defects
– Notch base radius shown more critical than the depth
– Fatigue life still reduced from original design
Remediation to reduce thermal driving forces
– Installation of internal thermal liner
– Reduced crack driving force & improved fatigue life
– Consider critical defect if thermal liner failed
Probabilistic Life Assessment
Probabilistic Modelling of Radiant Tubes
– Bespoke approach for
• Furnace Tubes
• Steam Reformers
Methodology
– Review of operating data since
commissioning
– Inspection history
– Modelling of damage mechanisms
Benefits
– Refined prediction of remaining life, less
conservative than deterministic assessment
– Aids
• Inspection planning and operating optimisation
• Reduction in CAPEX
Outlet Manifold Failure Investigation
Failure Analysis & Root Cause Analysis
Background
– High Temperature Outlet System Failure
– Failed after 2 Years of Operation
Methodology
– Site Inspection & Document Review
– Independent Stress Analysis
– Piping Support Failures
– Root Cause Analysis
Benefits
– Independent Expert Witness Report
– Support for Insurance Claim
Reformer Outlet Failure Analysis
On-Site Field Metallography Detects Cracking (RINA)
Main causes of the cracking
– Hanger settings contributed to the stress relief
damage
– Cracking allowed the formation of more brittle
phases, leading to further cracking
Lessons Learnt
– Root cause analysis of stress relief damage should
have been completed
– Dye preventive surface crack detection had poor
surface preparation and showed no surface cracking
Fire Damage Evaluation
Evaluation of severity of damage to nearby furnace
Background
– Chemical plant had suffered a failure in a fired heater
– Two parallel units
Scope of inspection
– Visual, Wall thickness, Internal coking
– Metallography & Hardness
– Operational Temperature / Pressure review
Benefits
– One unit confirmed as requiring complete
replacement
– One unit suitable for minor repairs and return to
service
– Enabled partial operation of the site
Reciprocating Gas Compressor
Investigation into repeat failures of a reciprocating
compressor
The areas for investigation were
• Manufacture
• Assembly
• Design
• Operation
Assessment
– Evaluation of residual weld stress
– Transient thermal fatigue analysis
– Creep assessment
– Fracture mechanics assessment of tolerable
defect sizes
Benefits delivered
– Risk assessment for inspection frequency
– Advice on the number of spare sets to stock
RCA of ID Fan Dorsal Fin Failure
Detailed analysis to prevent future failures
Background
– Following a number of failures and previous
redesign attempt, evaluate the root cause
Assessment
– Baseline simulation to verify against
manufacture performance data
– Demonstration of the cause of high cycle fatigue
failures by transient CFD and harmonic FEA
simulations
Benefits delivered
– Critical opening angles of the fan operation
highlighted
– Evaluation of revised redesigns
– Understanding and evidence to provide in-
service reliability of a new modified design
Power Transformer Failure
Failure Analysis & Root Cause Analysis
Background
– Both main and backup 33kV transformers failed in a
matter of seconds
– Prolonged and unplanned site outage
– Units were 20 years old
Failure Analysis
– Failure was caused by arcing of the tap changer
– Root cause was a poor maintenance regime
– Proactive maintenance review would have prevented
the failure
Reformer Radiant Tube Failures (1)
Reformer Radiant Tube Failure (2)
Other Reformer Issues
Possible lower creep rupture properties of
outlet system tube material
• Ex-service (less than 2 years) shown
lower than expected creep rupture
properties on short term testing.
• Further longer term testing required to
confirm
Cracking of 347H inlet branch piping
• Cracking experienced within 2 years of
operation
• Possible thermal fatigue issues
associated with transient conditions
• Recommendations for further
assessment of transients and local
conditions
• Possible external lagging issue
Power Sector
Project Examples
Boiler Inspection Prioritisation
Assessments completed for cyclic operation of a power
boiler
– Conservative estimate of stress based on original
boiler design code
– Evaluation of critical damage mechanisms to assess
– In-house spreadsheets & MathCAD worksheets used
for assessment
Initial fatigue lives estimated for prioritisation of
detailed assessment and inspection
Project Outputs
– Financial planning
– Targeting of critical components
• Considering FAC, Fatigue, Corrosion, Erosion
– Safety case justification to operator and regulator
Inspection & review of HRSGs
Visual & Operational Health Check of HRSGs
On site visual examination
– Gas side, Crawl spaces, Steam Drum internals
• Off line corrosion, fouling, oxide condition, pitting,
casing, alignment
– Recommendations for future inspection
Operational Reviews
– Water Chemistry
– DCS & Thermocouple data
Benefits
– Early indications of issues highlighted
– Optimisation of process
– Prioritising actions
– Future inspection optimised
Rapid Response Inspection & FFS
Assessment of Crack Life Flaw in HP Downcomer
Services Performed
– Immediate mobilisation for field replication
– On-site metallurgical characterisation of defects
– Assessment of critical defect size & potential fatigue
crack growth
Assessment Included
– Identification of Damage Mode (From metallography)
– Confirmation of Material grade (Metallography &
Hardness)
– Design, Manufacture & Process Operation to date
– Abnormal loads (Vibration, Environmental, System loads)
Benefit to the client
– Technical safety case for 12 months operation provided
Rotor Life Assessment