You are on page 1of 8

SOCIETY OF PETROLEUMENGINEERS OF AIME PAPER

<man *,.-AL
OLUU l!ur bll
m-”. +... l
bcll L/l a-l. Expre s sway
NUMBER SPE 3470
Dallas~ Texas 75206

THIS IS A PREPRINT --- SUBJECT TO CORRECTION

Optimization of Sucker Rod Replacement

BY

Maston L. Powers, Member AIME, ContinentalOil Co.

@ Copyright 1971
American Institute of Mining, Metallurgical, and Petroleum Engineera, Inc.

This paper was prepared for the &th Annual Fall Meeting of the Society of Petroleum Engineers
of AIM33,to be held in New Orleans, La., od. 3-6, 1971. Permissionto copy is restrictedto an
abstractof not more than 300 words. Illustrationsmay not be copied. The abstract should contain
conspicuousacknowledgmentof where and by whom the paper is presented. Publicationelsewhereafter
publicationin the JOURNAL OF PETROLEUMTECHNOLOGYor the SOCIETY OF PETROLEUMENGINEERSJOURNAL is
usually granted upon request to the Editor of the appropriatejournalprovided agreementto give
proper credit is made.

Discussionof this paper is invited. Three copies of any discussionshould be sent to the
Society of Petroleum Engineersoffice. Such discussionmay be presented at the above meeting and,
with the paper, may be consideredfor publicationin one of the two SPE magazines.

ABSTRACT through Aug., 1970, it was found that fatigued


rod strings were being replaced after an average
A technique has been developed to optimize of 7.6 failures. Wells that exhibited symptoms
sucker-rod string replacementdecisions. The of specific mechanical problems were excluded
basis for this optimizationassumes that the from this analysis. For example, instances of
failure frequency expectation of sucker rods chronic joint failures were attributedto
increases with time at a variable rate improper makeup practices rather than fatigue.
approximatinga Gaussian curve throughout their
usable life. At some point in time the mainte- Ju4gment indicated that the observed
nance cost of continued operation of a fatigued replacementpractices needed improvement. An
rod string exceeds the capital cost and engineetig basis for economicallyoptimizing
associated maintenance cost of a replacement sucker-rodreplacementdecisions was therefore
string. A mathematical.expression representing pursued.
this optimum replacementpoint was developed and
solved for the time interval between sucker rod BASIS OF OPTIMIZATIONTECHNIQUE
failures. The resulting equation csn be appliec
to a partial replacement as well as a complete Performance of sucker reds is affected by
replacement rod string. A graphical solution numerous well conditions such as maximum rod
was deveioped to implement the Optfiiizaticm ~t~~~~, ~tre~~ ~aiiL~~, ...1-...4
pU1lyU.frj
m“ .PGU,
.r.a.4 -“.
enm’mm.iv+
. ““AV-.J
+77

technique for routine field use. of the environment,and a variety of mechanical


problems. Thus, each well can be expected to
INTRODUCTION exhibit unique behavior. However, by assuming
that individual well conditionsremain constant
A need for improved criteria for making during an snslysis period, sucker rod perfor-
sucker-rod string replacementdecisions became mance can be generalized.
evident while making a detailed study of operat-
ing costs and field practices in the midcontine~ For any combinationof constant well condi-
area. It was found that sucker rods were being tions a properly designed sucker rod string will
replaced on as many bases as there were initially have relativelyinfrequent failures.
individualsmaking replacementdecisions. As a result of cyclic loading in normal use, the
failure frequency expectationof the string
During the time interval for which sucker- should increase with time in a rough approxima-
rod replacementdata was compiled, Nov., 1969, tion to a Gaussian curve, as depicted in Fig. 1.
References and illustrationsat end of paper.
2 OPTIMIZATIONOF SUCKER ROD REPLACEMENT SPE 3470

BY rescsling this curve, it would represent the of rod failures in a well indicates that re-
maintenance cost expectationof the rod string. placing only a portion of the rod string might
A generalizedmaintenance-costcurve of a eliminate the failures, Eq. 2 can be used to
sucker rod string was thus constructedin Fig. justify a partial sucke~rod string replacement.
2. The cost of the partial string and the antici-
pated fsilure interval of the new composite
The capital cost of replacing a string of string are substitutedin the equation, all
sucker rods equals the product of the replace- other variables being unchanged. This procedure
ment rods investment diminished by the salvage is mathematicallycorrect for determfig the
value of the rods replaced, times the capital optimum point to make a partial replacement;
recovery factor for the current interest rate however, since the balance of the string is not
and anticipated sucker rod string life. Annual new, the anticipatedcost savings depicted on
compoundinginterest tables were used in this Fig. 2 will be reduced somewhat.
development. Except for the effects of infla-
tion and fluctuationsof interest rate, the Direct applicationof Eq. 2 was found very
capital cost for replacement rods is constant, useful for specific unusual circumstances;how-
regardless of when the purchase is made. Thus, ever, it was judged to be impractical for
replacement cost, augmented by the initial routine field use. Means were therefore inves-
maintenance cost expectationof a new rod string tigated of compromisingthe accuracy of direct
can be considered a horizontal line as shown in solution of this equation, for a simple, more
Fig. 2. practicsl scheme for field application.

The optimum time for rod replacementis at DEVELOPMENT OF GRAPHICAL TECHNIQUE


the point when the anticipatedmaintenance cost
of a fatigued rod string equals the sum of A graphicsl method for applying the optimum
capital cost and maintenance cost of a new rod sucker-rodreplacement concept was thought most
string. This is the point of titersectionof desirable. The first step in the development
the two solid curves on Fig. 2. The generalized of a graphical technique was to simplify Eq. 2.
maintenance-coste-ur-rewas d@icated as a Eq. 3 was developed, as shown in the Appendix,
dashed line with its beginning shifted to this ------
by assigning average numeric values to seve~-d
intersection. The dashed line, therefore, rep- of the variables of Eq. 2. It was assumed that
resents the total cost of installationand wells are out of service an average of 16 hours
maintenance of a replacement sucker rod string. per rcxifailure. In the area studied this
The area between the maintenance-costcurve and appeared to be the most probable downtime
the dashed line curve represents the savings period. It was SJ.SOassumed that no expense
accruing from replacing a rod string at the reduction results from a well being out of
optimum time. service due to a rod failure. There is slways
some cost reduction; however, in most practical
OPTIMUM SUCKER-RODREPLACEMENTEQUATION situationsthe error introducedby this assump-
tion is insignificant. The initial failure
The optimum sucker-rodreplacement equation frequency expectationof a new rod string was
(Eq. 2) is derived in the Appendix from the assumed to be l/21+failures per month (a failure
basis establishedin the preceding paragraph. interval of 24 months per failure). A net
The mathematical expressionrepresentingthe interest of 0.875 was assumed, and an interest
optimum replacementpoint was solved for the rate of 8.o percent was used. The salvage value
time interval.between rod failures (the recip- of replaced rods was ignored in developing the
rocal of failure frequency) to facilitate field graphical technique. This is normally a small
application. Variables consideredin this percentage of new rod string price.
development include the price and anticipated
economic life of a replacementrod string, Grouping of Wells for Analysis
interest rate, average well-servicingcost for
rod failures, average number of hours of down- Our midcontinent area operationswere
ttie per rod failure, oil producing rate of the analyzed, and wells having similar producing
well, price of oil and net interest. Other characteristicswere grouped for additional
factors consideredwere occasional failures cf study. Wells in these groups were approximately
natirod strings and reduction of operating costs the same depth and completed in the same forma-
while a well is out of service due to a rod - .
tions. tianyof these groiipa .-..4
.+.A nr
.oLLD&w..=.+ ~arge
failure. Examples of this latter item are pro- unitized secondary recovery projects and others
duction taxes, salt-waterdisposal expenses and encompassedan entire field.
electric power.
Of the independentvariables of Eq. 3, oil
It is common field practice to occasionally producing rate is the most significant. Average
replace only a portion of a rod string, partic- values of the remaining variables were, there-
ularly for tapered rod strings. If the location fore, determined for each group of wells.
SPE -..
3/!470 MASTON L. POWERS

Average rod strings were ascertained. This producing rate were tinenprepared for each of
required determining average pump depths and the five producing areas. These are illustrated
average rod taper designs. With this data, in Figs. 4 and 5. Three curves were required to
average rod replacement costs were computed fox represent Ol&homa fields and one curve each
each group. Well servictiginvoices were then represents Kansas and Illinois Basin fields.
analyzed, and average well servicing costs for The area curves were compared to the individual
rod failures were calculated for each group of well group curves and were found to approxi-
wells. Average sucker rod lives were estimated mately coincide with the average of the group
These ranged from 4 to 7 years. Some lightly curves. Substitutingthe five area curves for
Ioaded rod strings will last considerably the more numerous group curves obviously re-
longer than ? years; however, these do not suited ti tine10ss of some acciti=acy;
howwr,
represent the wells for which this optimization this was outweighed by making this technique
will have the most value. Finally, the average more readily applied in the field.
crude oil price for each group was computed.
Table 1 is a tabulation of averaged variable Use of Area Curves
data for 11 of the well groups.
Use of the area rod-replacementcurves is
Group Failure Interval Vs Producing very simple. Since the ordinate of the curves
Rate Curves representsthe failure interval at the optimum
replacementpoint, one merely selects the
The average values of the variables for appropriate curve and reads the failure intervsl
each group of wells were substitutedinto Eq. 3 correspondingto the producing rate of a well.
Values for failure intervel (at the opttium This is then compared to the rcxifailure
replacementpoint) were thus calculatedfor history of the well. If the-observedfailure
various oil producing rates. From this data interval is less than the interval obtained
graphs of failure intervel (M) vs oil producing from the curve, the rod string should be re-
rate (Q) were prepared for each well group. placed when the next failure occurs.
Fig. 3 is a semple curve for Group 1. The
curve for each group was a line of minute ExtendinR Graphical Methods to
curvature. Since costs for complete rod string Partial String Replacement
were substitutedin Eq. 3, these curves apply
only to full string replacement. Application of the graphical method, as
described in the previous paragraph, cen be
The graphs representingthe various groups made only for decisions concerning the replace-
were compared end it was observed that many ment of complete rod strings. Means of exLend-
nearly coincided. This occurred because many ing this method to partial rod string replace-
circumstanceswere similar; and where there ment decisions were, therefore, explored. It
were significantdifferences they tended to was desired to keep calculationsas simple as
compensate. For example, a deep well is more possible to facilitate field application. A
costly to service than a shallow well; however, multiplying factor to correct the optimum point
a replacement rod string also costs more. Thes failure interval for a full rod string to a
can be seen to be compensatingfactors in Eq. 3 partisl string failure interval was the approach
taken. The partial replacementfactor (ratio of
The curves for the various well groups did ftiure interval for a partial replacementto
not pass through the origin, but rather had the failure interval for a complete replacement
p~~itive ~m.t.ercept.s
of the vertical axis. At at the optimum replacementpoint) can be com-
the intercept fsilure frequency, rod replacement puted from Eq. ~, found in tne Appendix. From
can be justified on the basis of reduced well Eq. 4 it cen be seen that the partial replace-
servickg expense without regauxito oil pro- ment factor for a given fractional replacement
ducing rate. is influencedby both oil producing rate and
,,. ‘.A1.. ,.h.me + A.++fi to = ~~&_u~@
me four ‘WiiiUUAca ~AAad.e.Aw.&.
area.

The similarity of the graphs of many well Fartiai replacementfactors a“erewnputed


groups indicated that the fields studied could and tabulated for each of the five areas at
be representedby considerablyfewer curves, various oil producing rates and for various
covering more inclusive areas. The well groups fractional replacements. From this data, plots
were thus compiled into five producing areas, of partial replacementfactor vs percent re-
and the variable data was averaged for each placement were prepared for each of the five
area. This data is tabulated in Table 2. The producing areas for an oil producing rate of
data was then substitutedinto Eq. 3, and value 20 BOPD. This rate is most representativeof
d ~,~recal-111~+.d
of failuz-e~-~terv .-.— . . . .
for VariOUS the wells to which this method was applied.
producing rates, as was done with the well Except for Area 2, these curves fall within the
groups. Graphs of failure titerval vs oil narrow envelope shown in Fig. 6. This envelope
OPTIMIZATIONOF SUI ER ROD REPLACMIMNT Srli347(

was approximatelybisected by the curve for sufficientlydamaged that failures persist.


Area 3. The curve for Area 2 fell somewhat
above the other curves. The narrowness of the Coupling breaks and unscrewed rods should
envelope indicates that the characteristicarea not be regarded as failures in sucke~rod
-~..l.fi ~-n+ r-lapici~p-~e
~-cpLatie-A. --- These two t+ypesof
variables do not significantlyaffect the par-
tial replacement factor. ‘RIus,separate partiti failures are a result of improper rod makeup
replacement factor data were not provided for practices. Instances of unscrewed rods can be
each of the five producing areas. prevented by proper makeup. If application of
proper makeup does not remedy coupling breaks,
Because the Area 3 curve approximately the couplings can be replaced on the used rod
bisected the Fig. 6 curve envelope, this area string. Pin failures are also a result of
was considered representativeof all.fields improper rod makeup practices. However, if
studied. Curves of partial.replacementfactor applying proper makeup does not abate chronic
vs percent replacement for various producing pin breaks in a well, they should be counted as
rates were prepared for this area. These curve: rod failures (just as body breaks) in making
are presented h Fig. 7. The wide envelope sucke~rod replacementdecisions. This type
these curves present gdicates that oil pro- of behavior can result from prior makeup
ducing rate has a much greater influence on practices that have damaged the pins so that
partial replacement factor than the characte~ they are the weakest link in the sucker rod
istic area variables. Fig. 7 was therefore chain.
used for determiningpartial replacementfactor[
in all areas. Sucker-rod failure history must be avsil-
able to utilize the optimum replacementtech-
Application of the graphical method to a nique. To assure the availabilityof failure
well for which a partial rod string replac~ data, we have initiated a computer prepared
ment is being contemplatedcan now be made. monthly Well Servicing SummqY report. Copies
The partial replacement factor (P), correspond- of this report are sent to everyone responsible
nl3,-I
ing to the percent replacement and oil producin~ for rlakmg rod ZWya=.e..,”...man+. dori .si nns
------------ , This rod
rate of the studied well, is selected from Fig. failure history must be analyzed to determine
7. The failure interval (M), corresponding the current rod failure interval of a well. No
to the oil producing rate of the well, is next significancecan be placed on one rod failure;
obtained from the appropriatearea curve on Fig and isolated singular rod failures (greaterthan
4 or Fig. 5. The product, M’ = MP, is then 1 year apart) should be ignored in determ~
computed and this prcduct is compared to the failure interval. Two rod failures do not
rod failure history of the well, as in the case necessarily reflect the failure frequency that
of a complete rod string replacementdecision. should be expected. At least three, but not
more than four, failures are needed to determine
To be mathematicallycorrect, the quantity the failure interval and make a sound replace-
7..----+1?
‘:percentrepLaGeLjLGJIU~rk~ered +1-1+.n
u..” WC.
.-~. 7, ment decision.
should be the percent of total rod string cost
rather than percent of total rod string length. It has been observed from practical appli-
For tapered rod strings these will normally be cation of the optimizationtechnique that
different numbers. Use of percent of rod partial rod string replacementscan normally
string length is recommended,however, for be justified by the time sufficientdata is
routine field application. The refinement of available to identify a failure problem. Excep-
calculatingpercent of cost would not usually tions to this trend occur at low oil producing
be justified. rates, in deep wells and for high percentage
replacements.
FIELD APPLICATION OF OPTIMIZATIONTECHNIQUE
ACKNOWLEDGMENT
It must be emphasized that the foregoing
developmentpertains to replacementdecisions I would like to express my appreciationto
for fatigued sucker rods. If a specific Contfientsl Oil Co. for permission to prepare
problem is causing rod failures in a well, this and present tJnispaper. The assistame of?. ?’.
problem should first be resolved. If such em- Ndcker is gratefully aclmowledged.
ditions as excessive rod stress, pump stickinge
fluid pounding, severe corrosion, or improper NOMENCLATURE
rod makeup are present, there is no assurance
that a new rod string will perform any better A= price of replacementrod string (less
than the one in use. The technique developed salvage value of replaced rods), dollar
in this paper should be applied only if a B= price of oil, dol.lars/bbl
mechanical condition cannot be identified as c = average well-servichg cost per rod fail-
the cause of rod failures or if a problem is ure, dollars
discovered and corrected and the rods have been F= fraction of rods to be replaced,
dimensionless
G=net interest
H=average downtime per rod failure, hours
i=interest rate, percent
j= anticipated economic life of a rod
string, years
M= time interval between rod failures at
economic replacementpoint (for a com-
plete rod string), months
M’ = time interval between rod failures at Q
M
c+w&=Q- .“” (A-1)
economic replac~ent petit (for a par- [ 1
tial rod string), months
N= anticipated time interval between rod Solved for (M), Eq. (1) becomes:
failures of a new rod string, months
P= partial replacementfactor, dimensionless &l
Q= oil prcducing rate, B/D 12N C + 24
Ri-j . capital recovery factor at (i) interest M= [ J .. (A-2)
rate and (j) interest periods
A..-A.
-.A.k7
UV* fiP
v= variable operating cost, Uutiti-=z ..
oil

Simplified @ timum ReplacementEquation

1. Mood, A. M. and Graybil.1,F. A.: Intro- Assumptions made were as follows: G=


duction to the Theory of Statistics,2nd 0.875, H =-16 hours, i = 8 percent, N = 24
cd., McGraw-Hill Book Cp., New York (1963). months and V = O. Eq. 2 becomes
2. ‘IImesen,H. G. and Fabrycky, W. J.: En.gi-
neeri.n.g
Economy, 3rd cd., Prentice-Hall, 24(12C + 705)
‘= 24AR8-j +12c+7QB ““”” (A-3)
Inc., Englewood Cliffs, N.J. (1964).
3. Bull., API, lWIL, 1st cd., American
~oleum Institute, Dallas (1967). Partial Replacement Factor Equation

APPENDIX Partial replacementfactor (p) was defined


ss M’/M. It was assumed that N = 24 for a
Development of Equations compositerod string. !l’hus~Eq. 3 can be
applied. Using Eq. 3 this ratio becomes
Optimum Sucker Rod ReplacementEquation
24~8-j + 12C + 7QB
P . . . . (A-4)
Basis of optimization: annual capital cost = ~R8_j + lzc + 7QB .
TABLE 1 - TABULATIONOF WELL GROUP VARIABLE DATA

Avg. Depth
Ss!2!I! (Feet) & & & &
1 4,500 2,359 3.00 180 6

2 4,400 2,288 3.20 210 6

3 3,100 1,562 2.84 150 6

4 8,800 4,576 3.25 215 6

5 7,200 3,744 3.30 185 7

6 5,200 2,704 3.30 160 7

7 4,900 2,548 3.25 160 7

8 3,100 1,562 3.30 95 5

9 3,600 1,814 3.34 100 5

10 3,700 1,865 3.17 110 5

11 2,700 1,400 3.27 140 4

TABLE 2 - TABULATIONOF PRODUCINGAREA VARIABLE DATA

Avg. Depth
Area (Feet) .& & & &
1. Okla. (1) 4,500 2,359 3.00 180 6

2. Okla. (2) 8,,000 4,160 3.30 200 6

3. Okla. (3) 5,100 2,652 3,30 160 7

4. Kansas 3,300 1,665 3.30 100 5

5. 111. Basin 2,800 1,400 3.27 140 4


/

Fig. 1 - Generalized sucker rod failure


frequency curve.

oPTIMUM

CAPITALCOST
-—..-. .- / I ~
OF REPLACEMLNi

OIL PRODUCINGR;TE (&)- BBL./&;


TIME
Fig. 3 - Well Group 1 failure interval
Fig. 2 - Generalized operating cost curve vs producing rate.
of ~ ~uc~e~ ~~~ ~frir!cj.
olLPRODUCING
RATE(Q)- BBL./DAy olL PRODUCINGRm (d- BBL./DAy
.~i”,!3. ~ . Fa~~Ure!~t~rval vs producing Fig. 5 - Failure interval vs producing
rate curves - Kansas and
rate curves - Oklahoma areas.
Illinois basin.

I
\ An
-r”
Qrmn
““m “

o
0 20 40 60 80 1~
PERCENT REPLACEMENT

Fig. 7 - Partial replacement


Fig. 6 - Envelope of partial
factor curves for various
replacement factor curves
uroducing rates, avera9e of
for various producing areas
all areas.
at 20 bbl/Day oil producin9
rate.

You might also like