Professional Documents
Culture Documents
radFE13E PDF
radFE13E PDF
ABSTRACT
INTRODUCTION
During initial excavation for construction of the soil nail wall system, a
poorly graded sand with trace silt (SP) was encountered. This material provided
insufficient standup time to permit soil nail wall construction resulting in excessive
caving as noted immediately upon excavation (Figure 3).
Figure 3. Poorly graded sand condition encountered during initial excavation for
soil nail wall construction
In the end, stabilization using sodium silicate based chemical grouting of the
excavation face along the full height of support was the selected method of
treatment. Grouting offered numerous advantages including the ability to excavate
the grouted soil layer on the original alignment using conventional excavation
methods and the ability to adjust the treatment procedures for varying ground
conditions including performing multiples injections, if required. Grouting also
provided the added benefits of serving as both temporary underpinning of the
existing structure and as an additional movement reduction measure.
A sodium silicate based grouting program using a two (2) row system of tube-
a-manchette (TAM) grout pipes and needles were positioned on three (3) foot center
to center spacing along the alignment to chemically stabilize a theoretical three (3)
foot wide soil block (Figure 5). The preliminary concept was to install the TAM
pipes at 5 degree batter just in front of the abutment footing. However, this geometry
would result in much of the assumed grout influence zone at top of the wall being
installed on the outside face of the excavation. Due to concerns with the possibility
of “pulling” the grout body out from under the footing during excavation of the upper
portion of the wall, small 25 mm (1 in.) diameter grout needles were utilized to grout
the upper 2.13 m (7 ft) of grout wall construction. This would ensure that a better
concentration of the grout injected would be present in the upper portion of the cut.
Figure 6. Grout needles through abutment footing with header system attached
After completion of the grouting program, the soil nail wall construction
resumed and was installed to full depth. The effectiveness of the chemical grouting
was confirmed during excavation with significant increases in the excavation face
stability noted at all soil nail levels (Figure 7).
Figure 7. Excavation first and second tier of soil nails after chemical grouting
The wall was excavated in 1.22 m (4 ft) vertical lifts with a 101 mm (4 in.)
temporary shotcrete facing placed prior to nail installation. Due to the permanent
nature of the wall, geocomposite drainage board was installed on 1.22 m (4 ft) center
spacing the full depth of the wall and integrated into a toe drainage structure at base
of the wall to prevent hydrostatic buildup. Nails consisting of #32M (#10) epoxy
coated thread bars, over-sized for additional corrosion protection, were installed to a
depth of 12.2 m (40 ft) using rotary-percussive duplex drilling methods (Figure 8).
Both proof and verification nail tests were performed to confirm the required bond
capacity was achieved. The upper two rows of nails were pre-tensioned with a
calibrated torque wrench to 17.8 kN (4 kips) to limit movement during construction.
Careful attention to wall verticality during construction was made to ensure that the
wall did not encroach into future roadway construction (Figure 9). It should be
specifically noted that the chemical grouted soil assisted in this endeavor and
permitted a very uniform shotcrete facing to be constructed.
CONCLUSION
Unanticipated poorly graded sand provided insufficient face stability for soil
nail construction which the contractor was able to overcome through the use of
sodium silicate based chemical grouting. Chemical grouting using TAM grouting
methods provided flexibility in construction by permitting changes in mix design to
suit actual ground conditions encountered as well as permitting construction in
limited access conditions. The effectiveness could be assessed both during and after
grouting prior to soil nail wall construction with supplementary grout injections
performed as required. Additional benefits of grouting prior to soil nail wall
construction included temporary underpinning of the abutment as well as assistance
in maintaining verticality and permitting longer stretches of shotcrete runs during
soil nail construction.
ACKNOWLEDGEMENTS
The project was successful in large part due to the group efforts of the project
team including representatives from the NJDOT, the soil nail wall designer Gannett
Fleming, and the general contractor Union Paving. It was with input and ideas from
all parties that appropriate solutions to the problems encountered were implemented
in a timely manner.