Professional Documents
Culture Documents
A. Determine the business requirements for the successful development of the project. Justify your
choices.
“Most projects are designed to fix an issue, implement a new system or process, or redesign something
in the business to increase productivity. Thorough business requirements result in fully defined project
objectives, success criteria and potential risks. Developing business requirements also is the first step in
deciding on project resources, time line and budget. Business requirements answer the “what” and not
the “how” questions of a project. Use basic business oriented language in your requirements document.
Have enough detail to answer questions that come up, but not too much that your approvers won’t
bother reading. Where possible, create an “executive summary” followed by more thorough detail of
the requirements. This format will appeal to a variety of readers “(Schatz, T. 2014).
What?- Implementation of New Eco-Stream on board computers on all 53 of SRT's locomotives to help
How?
Install new Eco-Steam on board computer system in locomotives in order to monitor when a
locomotive should coast, brake, accelerate, and recommenced speeds. The GPS system should be able
to predict the appropriate approaches and limit wasted fuel and reduce Co2 emissions.
The project will be completed in phases with the first phase implementing and monitoring trial
equipment to ensure the technology is compatible to the locomotives by completing one third of the 53.
(MindEdge, 2016) Eco-Trans must procure and configure all other equipment for the remaining
locomotives while the first phase of implementation is being completed. (MindEdge, 2016) All
equipment procured must be inspected prior to the installation process to identify any defective
equipment to avoid scheduling delays of equipping the remainder of the fleet.All conductors and
engineers must attend training to ensure they are comfortable in operating the equipment.The project
must be completed in its entirety within 15month schedule and within the agreed upon budget.
B. Establish who will provide the business requirements. What approach will be used to solicit the
Project manager will provide the business requirements. Business requirements are what will be
needed to implement and complete the project. So the project manager along with the subject matter
experts who can provide operation knowledge on what will need to be done will also provide the
business requirements. On the railroad anything involving the locomotive fleet should involve
transportation and also the mechanical departments. A project like this that would require taking
locomotives out of service to install the GPS system will affect customers as well so it will be
important to have sales and marketing involved to handle service delays with customers.
One way to solicit requirements from subject matter experts is to make sure to keep them involved
in the process. “The sad truth is, your project is not your Subject Matter Experts’ top priority. This is
why you need to find ways to engage them by getting them interested, so that you will be able to easily
find them when you need them. While identifying your goals in the beginning, ask them to answer
questions such as why they think this project needs to exist, how it will improve productivity or
employees’ professional lives, and which is the best way in their opinion to measure the success of the
program. This will not only help clarify the objectives, but also get your expert more involved in your
Package the BRD so it has a logical flow and is easy to follow. An example of a high-level list of
sections follows:
1. 53 trains in the Sunshine Rail Transit (SRT) fleet will have customized ECO-Stream systems. High
2. During the first phase of this project, there will be system tests to best configure the ECO-Stream
system for SRT operations. High
3. During the second phase of this project, ECO-Stream modules and equipment will be installed on the
entire SRT rail locomotive fleet. High
4. Completion of end user training will occur during the second phase of this project. Medium
5. ECO-Stream computer terminal has defects and it is critical to connecting the communication box
with the terminal. High
6. With the defective computer equipment, an alternative supplier will be considered. Medium
7. Consider additional funding to afford the costs of using an alternative supplier. High
8. Optimize resources by moving forward with installing other components in the trains while awaiting
replacement parts. High
9. Keep project on schedule without increasing costs. High
D. Explain why the format for capturing requirements is important to the overall success of the project.
Why would we consider requirements’ traceability?
Requirements must be traceable. That means for any requirement, one must be able to ascertain
its source and its realization, i.e., a reason why the requirement exists and a guarantee that the
requirement has actually been implemented. Generally, analysts construct a matrix that traces each
requirement to implementation, test cases, and sources. The source of a requirement is generally some
stakeholder but might also be a regulation or mandate.
E. Leveraging the business requirements, translate these requirements into a project schedule using
Varga developed a project schedule that consisted of seven key milestones within a fifteenth
month range. It was noted that the first four milestones were completed without a hitch,however, the
team ran into their first issue with the implementation of the fleet equipment. Varga was not able to
come up with a solid solution to this problem because she originally did not allow room for product
quality checks. Quality assurance is any systematic process of checking to see whether a product or
service being developed is meeting specified requirements. A quality assurance system is said to
increase customer confidence and a company's credibility. This process could have been added into the
schedule and this would have allowed for better communication as well as discovering earlier on that
there were defects. She than would have had more time to come up with a better solution and perhaps
not so much pressure placed upon her from her manager and the client’s project sponsor.
One additional scheduling conflict would have appeared to of been that face the the first phase of
installation was giving a four month window and only allowing one month for the final stage of the
install. However, there was a lot more work involved on the backend of the installation. I would think
the timeframes would be better suited if they were in fact revered. Allow one moth for the initial install
since its limited to 1/3 the locomotives and the 4 month window on the backend due to more
locomotives needing the equipment installed and for a chance to iron out any other issues that arise.
F. Estimate the duration of project tasks using common business knowledge, and assign resources to
Varga will have to shuffle resources around to make it work. Subject experts have
requirements about on how many hours per week they can allocate to the project and Varga is
above the allocations in some case. This may lead some of the experts to sour on the project. Frank
Hermann is unavailable in November. His material can be covered by Vin Siedek on 11/3 (5H) and
Rohan Singh (5H) on 11/17 as they as per their availability. Frank Hermann will cover 2H for Susan
Weitz on 10/27.
A. Determine the best implementation approach—agile or waterfall project—for the organization based
I would say in the case of implementing Eco-Stream in SRT's 53 locomotives the Agile method
would best be suited for the organizational structure that's in place as it allows for change.
1. The Agile methodology allows for changes to be made after the initial planning. Re-writes to the the
program, as the client decides to make changes, are expected.
2. Because the Agile methodology allows you to make changes, it’s easier to add features that will keep
you up to date with the latest developments in your industry.
3. At the end of each sprint, project priorities are evaluated. This allows clients to add their feedback so
that they ultimately get the product they desire.
4. The testing at the end of each sprint ensures that the bugs are caught and taken care of in the
development cycle. They won’t be found at the end.
5. Because the products are tested so thoroughly with Agile, the product could be launched at the
end of any cycle. As a result, it’s more likely to reach its launch date. (Hasbi, R. 2015).
For the ECO Trans project, the best methodology to use is agile.It’s efficiency with issues
during the project would help mitigate risk from parts being defective.The Eco-Trans project team is
already limited on time, and resources, agile methodology would help in quickly reassigning tasks
when the department training manager requests a demo of ECO-Stream before beginning education
(MindEdge, 2014 M6).Agile’s use of smaller teams works well with the limited resources and their
availability
B. Explain how the project schedule can be resource leveled, fast-tracked, or crashed if needed based
The project can be fast tracked by incorporating more training in the beginning rather than waiting. I
think it will be important to get engineer's engaged in the process from the offset. This way they feel a
sense of ownership over the project and it will get them talking and collaborating ideas. Also, this will
provide engineer's with more knowledge of the equipment and a chance to share some of that with co-
workers who may not have picked up on it as fast. I think this will streamline the process and when it is
in it's final stages it will cut down on training time and human factor errors.
Varga decides that she can use crashing to get the necessary components from an alternate
supplier. She knows that this supplier will charge more per part, especially with expedited delivery,
but she cannot think of another way to restore the terminal manufacturing schedule and meet the
C. Propose communication approaches and the frequency that should be used to keep leadership
I think it is important to communicate project status in a variety of different ways, but also equally
important no to over communicate. Finding the perfect balance of communication for your project is
essential.
Type/technique Description
References
http://www.base36.com/2012/12/agile-waterfall-methodologies-a-side-by-side-comparison/
https://elearningindustry.com/working-subject-matter-experts-ultimate-guide
http://smallbusiness.chron.com/project-management-business-requirements-4502.html